Sunteți pe pagina 1din 6

Clean Agent Enclosure Design for NFP

By Colin Genge

The Clean Agent Discharge Under-prediction of Peak Pressure


Clean agent fire suppression systems are used It is common practice for peak pressure
in enclosures where a sprinkler system would calculations to be done for inert agents but
cause damage to sensitive contents such as not for halocarbon agents and that is a big
computer servers, paper files, or historical problem since they can produce as much peak
artifacts. Upon fire detection the compressed pressure as inert agents. Peak Pressure varies
clean agent, which can be a halocarbon or an over time depending on the ratio between the
inert gas, is released into the enclosure causing leakage rate and the volume of the enclosure
a peak pressure of around 5 to 25 pounds per (leak to volume ratio, or LVR). In a typical
square foot to occur for a fraction of a second. halocarbon agent discharge, as shown in
The actual magnitude depends on total Figure 3, the peak pressure increases with Figure 3: Typical halocarbon discharge showing
enclosure leakage area. Once the enclosure is enclosure tightness since tightness determines peak pressure increasing with enclosure tightness
totally flooded, the agent will begin to leak out the increasing hold times shown in the legend. (longer hold times).
at a rate that primarily depends upon leakage Formulae for calculating peak pressure may be
area in the lower part of the enclosure. The provided by agent manufacturers. Although pressure formulae previously used to predict
distribution of the remaining agent will either peak pressure is referred to by the NFPA 2001 pressure values during enclosure design and
be constant throughout the enclosure due to standard, the standard does not yet provide testing. These facts include:
continual mixing or will establish an interface guidance on how it is to be calculated. 1. Existing inert agent formulae under-predict
with air above and agent below that descends A five-year research projectcarried out peak pressure.
over time as agent leaks out as shown in Figure to provide a validated prediction model for 2. Under certain conditions, halocarbon
2. Until 1988, enclosures protected by clean peak pressure based on LVR and involving agents can produce as much peak pressure
agents used full discharge tests to determine the author and many of the industry as inert agents.
the hold time, but since then door fans have manufacturers (including Fike, 3M, Ansul, 3. Peak pressures from halocarbons are
been used to measure the leakage area which is Kidde Fenwal, Chemetron, Retrotec)has extremely dependent upon humidity.
then entered into formulae found in Annex C uncovered many important facts about clean Results of the project were published in the
of NFPA 2001 to predict the hold time. agent discharge pressures and the peak Fire Suppression Systems Association (FSSA)

Figure 2: Graphical representation of the NFPA 2001, 2012 Edition,


Annex C clean agent standard model for descending interface where 100
percent agent leaks out the bottom of the enclosure causing 100 percent air
to be drawn in above the interface to replace the lost volume.
Figure 1: The clean agent expands, causing cooling which condenses
moisture to form a fog.

[ 12 ] FIREWATCH! December 2012


A 2001, 2012 Edition
Pressure Relief Vent (PRV) Area Guide. pressure limit which will, in turn, dictate Optimizing Peak Pressure and Hold Time
Sufficient data was gathered to more the minimum allowable leakage area for the Performance
accurately predict the peak pressure for all enclosure. This leakage area can be provided Clean agent discharges can produce damaging
agents. Figure 4 shows the new curve (in white) by unintentional enclosure leakage and/or the peak enclosure pressures that increase as total
developed for inert agent peak pressure versus area of any dampers that will be open during enclosure leakage area decreases. Simply
LVR. Notice how the existing formulae (dashed the discharge period. The enclosure integrity providing a lot of enclosure leakage area to
lines) all under-predict the peak pressure procedure in Annex C has also been changed solve the peak pressure problem creates another
expected at a given LVR over the typical peak to require the measurement of two leakage problem because hold times decrease as the
pressure values from 250 to 500 Pa. Figure 5 area values, one used for the calculation of the leakage area increases. One solution is to add
shows the results of testing of peak pressures hold time and another used for evaluating a PRV that will provide increased leakage
versus LVR for all tested inert agents in the peak pressure during discharge. These to reduce the peak enclosure pressure only
research. values must be measured after the enclosure during discharge; the enclosure can then be
has been completed. The new leakage area made tight to provide the specified hold time.
measurement is now necessary to fulfill the Another solution is to carefully consider the
new requirement in Section 5.1.2.2 (10) that design parameters that affect peak pressure and
states an estimate of the maximum positive hold time so that both requirements are met
pressure and the maximum negative pressure without using PRVs. Even if this design effort
during the clean agent discharge must be made. still results in the need for PRVs, optimizing
3ECTION  STATES h)F THE DEVELOPED PRESSURES the enclosure will increase the level of fire
present a threat to the structural strength of protection and possibly allow the use of smaller
the enclosure, venting shall be provided to PRVs since more passive protection will be
prevent excessive pressures. Clearly it would built in.
Figure 4: Peak pressure is a function of LVR be extremely bad news to find out that a Ironically, many inert agent protected
(leakage to volume ratio). Existing formulae completed enclosure needed to have a pressure enclosures have PRVs installed where they are
all under-predict at typical peak pressure values relief vent (PRV) installed a few days before not needed while other enclosures (protected by
(250 to 500 Pa). occupancy, but fortunately the designer can both inert and halocarbon agents) need PRVs
run calculations in advance using the new peak but they are not installed. This situation
pressure equations that have come out of the can be resolved by using the new enclosure
research project to determine whether or not a integrity evaluation procedure from Annex C of
PRV is likely to be needed and alter the design NFPA 2001 along with the new peak pressure
using the tips presented later in this article. formulae. Adding PRVs is costly, sometimes
It is no longer sufficient to simply specify a impossible, and often a source of unwanted risk
PRV of the correct size; its leakage rate must also since they may fail to open and could damage
be measured after installation to ensure the vent the enclosure.
both opens at the correct pressure and has a large Understanding the factors that affect the
enough leakage path outdoors to prevent the peak relationship between peak pressure and hold
pressure from exceeding the specified enclosure time will allow for designs without PRVs
Figure 5: Peak Pressure curves for all tested pressure limit. The 2008 edition requires this new that easily pass both criteria. Invariably, a
inert agents. second measurement which can be done using few simple changes to the enclosure will
the same Annex C enclosure integrity procedure dramatically improve the suppression systems
but with different set-up conditions. The same performance and also save the installer from
A Second Leakage Area Must Now Be door fan equipment can often be used, but users having to resolve difficult design problems in
Measured may find they need higher fan output to test at 50 a last-minute panic when the enclosure fails
NFPA 2001, 2012 Edition, Section 5.1.2.2 Pa instead of the previous 10 Pa and need to test one or more of the acceptance criteria which
(28) now requires a specified enclosure with the PRVs open. typically occurs just prior to occupancy.

December 2012 FIREWATCH! [s ]


Maximum Allowable
Wall Type
Pressure (psf)
Selection of Specified Enclosure 2x4 stud @ 16 OC 13
Pressure Limit 2x6 stud @ 16 OC 32
Formulae have been used for over a decade to 2x8 stud @ 16 OC 56
predict peak pressures and to size PRVs for 2x10 stud @ 16 OC 90
thousands of enclosures without damaging 6 masonry reinforced 41
those enclosures. Since the five-year research 8 masonry reinforced 57
project showed that the actual peak pressures 10 masonry reinforced 74
exceeded those predicted by the previously Figure 6: Wall 12 masonry reinforced 91
used formulae by at least 100 percent, and strength versus 4 concrete reinforced 59
many of those enclosures were discharge maximum 6 concrete reinforced 89
tested with inert agents, it is safe to say that allowable pressure
8 concrete reinforced 120
a wide range of enclosures handled 500 Pa of in pounds per
4 concrete unreinforced 29
peak pressure with ease. This has also been square foot for
walls of different 6 concrete unreinforced 66
verified with the use of a high output fan to
construction type.2 8 concrete unreinforced 117
pressurize enclosures where we have noticed
no effects at 500 Pa. We can therefore
assume that a double-sided wall, securely personnel will actually be because much leakage test, with PRVs closed, is performed
fastened on the top and bottom, will handle longer hold times are required for remote to ensure adequate retention time.
500 Pa and that 500 Pa can be used as a sites or those with heavy fuel loads while
specified enclosure pressure limit, which much shorter hold times can be considered 1. Specify sealing of the walls to the
is the maximum pressure the enclosure can FOR SMALL ENCLOSURES THAT ARE MANNED  UPPER SLAB Extending walls to the
be subjected to without damage. If in doubt, Reducing this hold time to 6 minutes for upper slab and sealing them airtight is
test a wall section under the chosen specified a small 1,250-cubic-foot enclosure and to the only defense against fire and smoke
enclosure pressure limit using a high- 3 minutes for a 350-cubic-foot enclosure entering from outside the enclosure.
pressure door fan. would solve one of the most costly and Refer to C.1.2.1 (2) in NFPA 2001
While thicker walls can take more pernicious problems that installers face, which states enclosures absent of
pressure as shown in Figure 6, false ceilings where getting these enclosures tight enough any containing barriers above the false
can only take about 50 Pa so they must be to pass the 10-minute requirement becomes ceiling, are not within the scope of
protected from pressures higher than that virtually impossible. Annex C meaning the enclosure will
with vented tiles. Ensure the false ceiling be difficult to test and verify.
has at least 5 percent open area to prevent it Enclosure Design Tips 2. 0LACE NOZZLES TO mOOD THE ENTIRE
from being dislodged as the discharge vents The following design tips have the potential ENCLOSURE WITH AGENT The higher the
upwards. to do one or more of the following: initially flooded height, the leakier the
% reduce installation costs enclosure can be, producing less peak
Selecting an Appropriate Hold Time % reduce risk of damage created by pressure but yielding longer hold times.
After a typical 10-second discharge for discharge pressures Typically, the small savings generated
halocarbons or 60 seconds for inert agents, % ease maintenance by flooding only to the bottom of a
the hold time begins. Even though this % improve fire protection false ceiling are more than offset by
time has almost always been specified as % reduce the risk of smoke damage the increased air sealing costs needed
10 minutes, there was no specific NFPA to ensure adequate hold time and may
requirement until the 2008 edition when The tips are meant to be considered during also force the inclusion of PRVs more
the words a minimum period of 10 minutes the design phase. The installed performance often. If a false ceiling is needed, specify
or for a time period to allow for response of the PRVs must be checked during nozzles above the ceiling; thats how
by trained personnel were added to section installation to ensure they open at the correct virtually all systems are designed in
5.6. Is 10 minutes always the correct hold pressure, in the correct direction, and that Europe.
time? The designer must consider what the the free vent area of the entire vent path falls 3. Use an automatic door closing
time period to allow for response by trained within the specification. A very different SYSTEM Doors often get wedged or

[ 14 ] FIREWATCH! December 2012


Figure 7: One door fan depressurizes the room while the second depressurizes above the ceiling so the
pressure across the ceiling is zero, allowing the lower fan to measure the room leaks separate from
above ceiling leaks.

propped open when the enclosure is added, only 15 percent of the agent would
in use. This practice impairs the clean have to be lost before the equipment loses
agent systems ability to put the fire its protection, since the standard requires
out. A better solution is an automatic that the final concentration at the end of
Figure 8: As agent is lost, air continually mixes
door release mechanism that will close the hold time at the top of the protected
with the agent to provide the same concentration
the doors whenever the first alarm equipment be not less than 85 percent
everywhere in the enclosure.
sounds. Choose a mechanism that will of the design concentration. The latest
close the door when it is de-energized so version of the NFPA 2001 standard uses
an integration formula that increases the positive and/or negative pressures, creating
it is fail-safe. a need to be vented in either direction or
4. )F A FALSE CEILING IS SPECIlED REQUIRE hold time prediction somewhat, but it
is still extremely important to add this both depending on the agent and the
air sealing of lower leaks first until humidity.
the specified hold time is reached additional agent otherwise the enclosure
will fail the hold time after only 15 s !LL 026S SHOULD BE INSPECTED ANNUALLY TO
and then seal leaks above the false confirm they will open according to their
CEILING UP TO THE PEAK PRESSURE LIMIT percent of the total weight of agent is lost.
6. )F NO MIXING WILL OCCUR KEEP THE specifications and to verify that the vent
The air leakage determination will path to the outdoors has not been
require measuring upper and lower leaks height of the protected equipment to
A MINIMUM If the equipment height accidently restricted which is quite
SEPARATELY AS DESCRIBED IN SECTION # common as evidenced by the sign shown
AND SHOWN IN &IGURE  EXCEEDS  PERCENT OF ENCLOSURE HEIGHT
continual mixing may be the only way to in Figure 9.
5. Increase the initial concentration of
agent an additional 15 percent over ensure a reasonable retention time.
design concentration if continual
MIXING WILL OCCUR TO ENSURE A LONG Pressure Relief Vent (PRV) Tips
ENOUGH HOLD TIME If air handlers If PRVs must be installed, there are several
continue to run during the hold time, guidelines to follow to optimize their
then continual mixing is certain but performance:
even equipment cooling fans or thermal s )NSTALL VENTS AS HIGH AS POSSIBLE SO THAT
effects can be sufficient to cause continual the lighter air, not the denser agent, is
mixing. Increasing the gap between vented.
the initial and final concentration in s 6ENTS SHOULD OPEN AT PRESSURES NO LOWER Figure 9: The sign says DO NOT
the continual mixing case has the same than 50 Pa to ensure they dont open OBSTRUCT because it is very likely the vent
effect as making the room taller in the unintentionally under normal HVAC path will be obstructed, thus the vent path must
descending interface case. For non-mixing pressures and no higher than 100 Pa so the be checked regularly.
cases, the agent is allowed to drain out pressure is vented early enough to prevent
until it hits the protected equipment it from building up. Peak Pressure Evaluation Tips
WHICH IS TYPICALLY AT  TO  PERCENT OF s %NSURE THE CORRECT DIRECTION FOR VENTING PRVs that are designed to open at a certain
the enclosure height allowing 40 to 25 with the PRV is specified. Inert agent pressure must be tested prior to and/or
percent of the agent, respectively, to run discharges always create positive pressures after installation to verify they open at the
out before the equipment is no longer and therefore must be vented out of the prescribed pressure. 125 Pa is the pressure
protected. If additional agent were not enclosure, but halocarbons may create generally used to test PRVs because it is

December 2012 FIREWATCH! [ 15 ]


AGENT CONCENTRATION
LEAKAGE
MIN. HEIGHT
OLD NFPA HOLD TIME | NEW NFPA HOLD TIME |
AREA PEAK PRESSURE PEAK PRESSURE
ALL FAIL ALL PASS
DuPont FM-200
7% 29 sq in 8.5 ft 9.3 min. 382 Pa 10.4 min. 247 Pa
3M Novec 1230 4.5% 43 sq in 7.5 ft 9.7 min. 319 Pa 10.4 min. 217 Pa
Argon 40% 166 sq in 7.0 ft 7.3 min. 373 Pa 10.3 min. 247 Pa

Table 1: Comparison of hold time and peak pressure calculations for three different clean agents in a 2,200-cubic-foot enclosure

representative of the peak pressures that Pa is determined, the vanes must be locked in the flow direction that will occur during
may be encountered. This pressure can be in that position while the damper leakage discharge. There are dual-acting PRVs that
imposed upon the damper in a test box, or area is tested. If installed in a test box will open in both directions, but their free
the entire enclosure can be pressurized, or a where there are no bias pressures, it can be vent area differs with respect to direction so
temporary pressure box can be constructed tested in the direction of intended venting. they must be tested in both directions to see
around the damper for testing purposes. A If installed in the enclosure, it should be how open they are at 125 Pa.
large flow at a fairly high pressure will be tested in both directions to compensate for
required to test these vents in their open any bias pressures and to achieve a more Reduced Need for Air Sealing and
position, so consider testing them in a test accurate test due to increasing the amount Relief Vents
box. Once the position at test pressure of 125 of data collected. Ensure the PRV is tested The 2008 and new 2012 editions of NFPA

[ 16 ] FIREWATCH! December 2012


The 2008 and new
2012 editions of NFPA
2001 reduce the need for air
sealing and relief vents.

2001 reduce the need for air sealing and


relief vents. In many cases, the slightly more
complex procedure proposed by Retrotec
that was accepted into the enclosure integrity
procedure of NFPA 2001 will identify when
enclosures will perform better than the older
more conservative formula dictated. This
means 10 to 40 percent less air-sealing to be
performed and pressure relief vents will have
to be installed a lot less often, saving money
on both counts.
The example in Table 1 of a 2,200-cubic-
foot enclosure, 10-feet high and protected
with three popular agents, shows how the
new standards test procedure yields both
longer retention times and lower peak
pressures. In the example, the old formulae
would fail both the hold time requirement of
10 minutes and a 250 Pa peak pressure limit
in each case but pass it in each case with the
new formulae. The old formulae assumed a
square root relationship between pressure and
flow, represented by a 0.5 exponent whereas
most tight enclosures have exponents closer
to 0.65.

References
1. National Fire Protection Association. NFPA 2001,
2012 Edition, Standard on Clean Agent Fire
Extinguishing Systems. Quincy, Mass.: 2012.
2. 2OBIN -, &ORSSELL %7 3HARMA 6 0APER 
HOTWC 2005; NIST SP 984-3, Pressure Dynamics
of Clean Agent Discharges. Available at: http://fire.
NISTGOVBFRLPUBSlRE0$&FPDF
3. Genge C. Paper 18; HOTWC 2005; NIST SP
984-3, Preventing Excessive Enclosures Pressures
During Clean Agent Discharges. Available at:
http://fire.nist.gov/bfrlpubs/fire05/PDF/f05059.pdf Colin Genge is the founder and owner of Retrotec Ltd., a Canadian
company founded in 1980 that does research and design of air leakage
2012 by Colin Genge, all rights reserved. standards and equipment. He is also the owner of Retrotec Inc., a US
company founded in 1990 that is the worlds largest manufacturer of air
leakage measurement systems with customers in over sixty countries.

December 2012 FIREWATCH! [ 17 ]

S-ar putea să vă placă și