Documente Academic
Documente Profesional
Documente Cultură
By Colin Genge
propped open when the enclosure is added, only 15 percent of the agent would
in use. This practice impairs the clean have to be lost before the equipment loses
agent systems ability to put the fire its protection, since the standard requires
out. A better solution is an automatic that the final concentration at the end of
Figure 8: As agent is lost, air continually mixes
door release mechanism that will close the hold time at the top of the protected
with the agent to provide the same concentration
the doors whenever the first alarm equipment be not less than 85 percent
everywhere in the enclosure.
sounds. Choose a mechanism that will of the design concentration. The latest
close the door when it is de-energized so version of the NFPA 2001 standard uses
an integration formula that increases the positive and/or negative pressures, creating
it is fail-safe. a need to be vented in either direction or
4. )F A FALSE CEILING IS SPECIlED REQUIRE hold time prediction somewhat, but it
is still extremely important to add this both depending on the agent and the
air sealing of lower leaks first until humidity.
the specified hold time is reached additional agent otherwise the enclosure
will fail the hold time after only 15 s !LL 026S SHOULD BE INSPECTED ANNUALLY TO
and then seal leaks above the false confirm they will open according to their
CEILING UP TO THE PEAK PRESSURE LIMIT percent of the total weight of agent is lost.
6. )F NO MIXING WILL OCCUR KEEP THE specifications and to verify that the vent
The air leakage determination will path to the outdoors has not been
require measuring upper and lower leaks height of the protected equipment to
A MINIMUM If the equipment height accidently restricted which is quite
SEPARATELY AS DESCRIBED IN SECTION # common as evidenced by the sign shown
AND SHOWN IN &IGURE EXCEEDS PERCENT OF ENCLOSURE HEIGHT
continual mixing may be the only way to in Figure 9.
5. Increase the initial concentration of
agent an additional 15 percent over ensure a reasonable retention time.
design concentration if continual
MIXING WILL OCCUR TO ENSURE A LONG Pressure Relief Vent (PRV) Tips
ENOUGH HOLD TIME If air handlers If PRVs must be installed, there are several
continue to run during the hold time, guidelines to follow to optimize their
then continual mixing is certain but performance:
even equipment cooling fans or thermal s )NSTALL VENTS AS HIGH AS POSSIBLE SO THAT
effects can be sufficient to cause continual the lighter air, not the denser agent, is
mixing. Increasing the gap between vented.
the initial and final concentration in s 6ENTS SHOULD OPEN AT PRESSURES NO LOWER Figure 9: The sign says DO NOT
the continual mixing case has the same than 50 Pa to ensure they dont open OBSTRUCT because it is very likely the vent
effect as making the room taller in the unintentionally under normal HVAC path will be obstructed, thus the vent path must
descending interface case. For non-mixing pressures and no higher than 100 Pa so the be checked regularly.
cases, the agent is allowed to drain out pressure is vented early enough to prevent
until it hits the protected equipment it from building up. Peak Pressure Evaluation Tips
WHICH IS TYPICALLY AT TO PERCENT OF s %NSURE THE CORRECT DIRECTION FOR VENTING PRVs that are designed to open at a certain
the enclosure height allowing 40 to 25 with the PRV is specified. Inert agent pressure must be tested prior to and/or
percent of the agent, respectively, to run discharges always create positive pressures after installation to verify they open at the
out before the equipment is no longer and therefore must be vented out of the prescribed pressure. 125 Pa is the pressure
protected. If additional agent were not enclosure, but halocarbons may create generally used to test PRVs because it is
Table 1: Comparison of hold time and peak pressure calculations for three different clean agents in a 2,200-cubic-foot enclosure
representative of the peak pressures that Pa is determined, the vanes must be locked in the flow direction that will occur during
may be encountered. This pressure can be in that position while the damper leakage discharge. There are dual-acting PRVs that
imposed upon the damper in a test box, or area is tested. If installed in a test box will open in both directions, but their free
the entire enclosure can be pressurized, or a where there are no bias pressures, it can be vent area differs with respect to direction so
temporary pressure box can be constructed tested in the direction of intended venting. they must be tested in both directions to see
around the damper for testing purposes. A If installed in the enclosure, it should be how open they are at 125 Pa.
large flow at a fairly high pressure will be tested in both directions to compensate for
required to test these vents in their open any bias pressures and to achieve a more Reduced Need for Air Sealing and
position, so consider testing them in a test accurate test due to increasing the amount Relief Vents
box. Once the position at test pressure of 125 of data collected. Ensure the PRV is tested The 2008 and new 2012 editions of NFPA
References
1. National Fire Protection Association. NFPA 2001,
2012 Edition, Standard on Clean Agent Fire
Extinguishing Systems. Quincy, Mass.: 2012.
2. 2OBIN -, &ORSSELL %7 3HARMA 6 0APER
HOTWC 2005; NIST SP 984-3, Pressure Dynamics
of Clean Agent Discharges. Available at: http://fire.
NISTGOVBFRLPUBSlRE0$&FPDF
3. Genge C. Paper 18; HOTWC 2005; NIST SP
984-3, Preventing Excessive Enclosures Pressures
During Clean Agent Discharges. Available at:
http://fire.nist.gov/bfrlpubs/fire05/PDF/f05059.pdf Colin Genge is the founder and owner of Retrotec Ltd., a Canadian
company founded in 1980 that does research and design of air leakage
2012 by Colin Genge, all rights reserved. standards and equipment. He is also the owner of Retrotec Inc., a US
company founded in 1990 that is the worlds largest manufacturer of air
leakage measurement systems with customers in over sixty countries.