Documente Academic
Documente Profesional
Documente Cultură
Whereas the Parliament of India has set out to provide a practical regime of right to
information for citizens to secure access to information under the control of public authorities,
in order to promote transparency and accountability in the working of every public authority,
and whereas the attached publication of the Bureau of Indian Standards is of particular interest
to the public, particularly disadvantaged communities and those engaged in the pursuit of
education and knowledge, the attached public safety standard is made available to promote the
timely dissemination of this information in an accurate manner to the public.
1 +, 1 + 01 ' 5
Mazdoor Kisan Shakti Sangathan Jawaharlal Nehru
The Right to Information, The Right to Live Step Out From the Old to the New
! $ ' +-
Satyanarayan Gangaram Pitroda
Invent a New India Using Knowledge
! > 0 B
BharthariNtiatakam
Knowledge is such a treasure which cannot be stolen
IS 15883 (Part 1) : 2009
Indian Standard
CONSTRUCTION PROJECT
MANAGEMENT - GUIDELINES
PART 1 GENERAL
ICS 03.100.40
BIS 2009
FOREWORD
This Indian Standard (Part I) was adopted by the Bureau of Indian Standards. after the draft finalized by the
Construction Management (Including Safety in Construction) Sectional Committee had been approved by the
Civil Engineering Division Council.
A construction project is an endeavour undertaken by a project team on behalf of owner/client to create a built
facility suited to the defined functional objectives. From inception to commissioning. the project goes through
various distinct stages leading to progressive achievement of project objectives. Each stage involves specific
inputs, processes (both technical and managerial) and deliverables. Typically. the life cycle of a project from
commencement to completion involves the following stages :
a) Project Appraisal- Inception, feasibility and strategic planning;
b) Project Development - Project brief development. planning and design, finalization of proposals.
procurement strategy. construction documentation including tender drawings. working drawings.
specifications. cost estimates. bills of quantities. procurement documents;
c) Planning/or Construction - Sequencing of project components. planning tools. resource planning and
time cost trade-off:
d) Tender Action - Open competitive bidding/pre-qualification of agencies. issue of tender documents.
evaluation of bids, negotiation if required and award of work ;
e) Construction - Execution. monitoring. control. work acceptance; and
f) Commissioning and Handing Over - Contractual closeout, financial closeout, defect liability
commencement, facility handing over.
The distinct features of a construction project include the temporary nature of the organizations involved. the
evolutionary process of project deliverables during project development stages and the unique output of the built
facility. As a result of these features. unless there is efficient and effective project management, a construction
project is faced with challenges of uncertainties leading to time over-runs. cost over-runs. changes in project
parameters, loss of quality and inability to meet the functional objectives. While technical soundness of a proposal
is an important aspect of a construction project. the management aspects. which involve techno-legal. financial
and other issues , have also a significant role in the success of a project. Therefore, management functions and
technical processes in a construction project need to be integrated towards achieving project objectives. Top
management commitment plays an important role in harmoniously achieving these project objectives. In some of
the public sector projects, it may be necessary to share relevant information with public at large through appropriate
means .
This standard is intended to provide a general overview of construction project management and information
regarding the applicable tools and techniques. It gives brief guidelines on various construction project management
functions and formulation of other parts of this standard to cover detailed guidelines on each of these management
functions may be taken up subsequently . Users of this standard are encouraged to employ suitable construction
management software as an aid to implement provisions of this standard.
The guidelines may be applicable in general to all construction projects. However, for smaller projects. the
applicability of various provisions may be decided appropriately by the parties concerned.
The composition of the Committee responsible for formulation of this standard is given in Annex A.
For the purpose of decid ing whether a particular requirement of this standard is complied with, the final value,
observed or calculated . expressing the result of a test or analysis, shall be rounded off in accordance with IS 2 : 1960
'Rules for rounding off numerical values irevisedv . The number of significant places retained in the rounded off
value should be the same as that of the specified value in this standard.
IS 15883 (Part 1) : ZOO9
Indian Standard
CONSTRUCTION PROJECT
MANAGEMENT - GUIDELINES
PART 1 GENERAL
r--
-'
-e
en
~
e, !Z 15~
z
0
e,
!j ~g >=
u
...uc ti& ~~
-c
II:
W !!l w-' w
I- 0
-,w
i~ 0
w
f~
Z
~o
...J
a..
II:
e, a..u ...w
~
0 I
(J
if.
I
I
I
I
I
I
I
L.~::
TIME -
2
IS 15883 (Part 1) ; 2009
Owner/client orhls
representative
1
Project
Manager
.1
Consultants
NOJ'E - As the scope of this standard covers activities starting Peer review/proof checking of the drawings/designs/
from pre-construction stage , the project appraisal stage has not
estimates shall be done in case of important projects,
been covered here .
depending upon their complexity and sensitivity.
Under each of the above stage s. the relevant Environment impact analysis and social impact analysis
construction management function guidelines given shall be done in applicable cases.
in 6 should be employed for achieving the intended
objectives. 5.1.2 Planning for Construction
The following aspects shall be considered:
5.1 Pre-construction
a) Sequencing of project components,
5.1.1 Project Development
b) Planning tools:
This will involve: I) Work breakdown structures (WBS),
a) Formalization of design brief; 2) Bar charts, and
b) Site survey and soil investigation; 3) Network techniques and scheduling.
c) Hazard risk vulnerability analysis; c) Resource planning , and
d) Alternative concept designs with costing and d) Time cost trade-off.
finalization; 5.1.2.1 Sequencing ofproject components
e) Preliminary designs and drawings;
Methodology of construction shall be detailed before
f) Development of design of each discipline and
the start of the project. Sequencing of project
their integration;
components shall be done on the basis of methodology
g) Obtaining statutory approvals; adopted and availability of resources. This shall be
h) Decision on construction methodology; reviewed during the progress of the project and revised,
j) Preliminary cost estimates; if necessary.
k) Detailed design of each discipline; 5.1.2.2 Planning tools
m) Construction working drawings and related
specifications with integration of engineering The planning tools describ ed below may be employed
inputs of all concerned disciplines; for effective management of a construction project:
n) Detailed cost estimate; a) Work Breakdown Structure (WBS) - The
p) Detailed specifications and billof quantities; and WBS shall identify the total scope of works
q) Tender documents. involved in the project and shall form the basis
3
IS 15883 (part 1) : 2009
for the development of detailed project For details on network preparation and analysis,
schedule. Through WBS, the project shall be reference shall be made to IS 14580 (Part 1) and
sub-divided into major sub-divisions (work IS 14580 (Part 2). Network schedule shall be prepared
packages) and each major sub-division shall for all disciplines and they shall be integrated into a
be further sub-divided into additional levels Master Control Schedule.
as required up to the level of activities that 5.1.2.3 Resource planning
could form the basis for monitoring and
control of project performance in terms of This shall involve the following:
time, cost and quality parameters. WBS shall a) Resource Allocation - The feasibility of the
provide activity listing with associated cost network shall be checked with respect to
account codes for the preparation of project manpower, equipment, other resources
schedule either by bar charts or by network required at the site.
diagramming methods. b) Resource Levelling - It shall be done by re-
b) Bar Chart - Bar chart is the simplest form allocating the slack resources from non-critical
of project scheduling and used for small and path to critical path activity in order to obtain
complex projects and in preliminary planning a reduction of time or by shifting the activities
and tender stages of major projects. A typical within the floats available with them, to obtain
bar chart form of project schedule depicts the an optimum uniform resource requirements.
various activities on a calendar time scale in
c) Resource Schedule - Schedule of following
the form of bars in their relative positions with
resource requirements with respect to time
start and finish dates and length of bar
indicating probable activity duration. Linked shall be prepared on the basis of network
bars represent the interdependencies between developed and kept in the database for project
the activities. Bar chart type of schedule shall control purposes:
be used to comprehend, summarize and I) Technology,
display the results of complex project network 2) Manpower:
analysis and further monitoring and i) Technical staff,
controlling process.
ii) Skilled labour, and
c) Network Techniques and Scheduling
iii) Unskilled labour,
1) Network Diagramming Methods -
3) Machinery,
Network based project schedule shall be
used for major and complex projects. In 4) Materials, and
this method, the network of project 5) Cash flow.
activities identified through WBS is Resource schedule shall be prepared
developed incorporating their logical
separately for client, consultant and
relationships and interdependencies. The
construction agency.
two available approaches for network
diagramming techniques are Arrow 5.1.2.4 Time cost trade-off
Diagramming Method (ADM) and
Time cost trade-off analysis shall be done to obtain a
Precedence Diagramming Method
minimum total cost of the project within the specified
(PDM).
time. This shall be done taking into consideration direct
2) Network Analysis and Scheduling - The
cost and indirect cost of the project.
project network incorporating the activity
durations and logical relationships shall 5.1.3 Tender Action
be analyzed with forward and backward
5.1.3.1 Preparation of tender documents
pass schedule calculations to establish
early and late start and finish time of The bill of quantities, specifications, drawings and
activities with their available floats, conditions of contract should be prepared on the basis
critical activities, critical path and overall of design and details finalized in project proposal
project duration. The project schedule is development stage (see 5.1.1) keeping in view the
prepared in terms of calendar dates of construction project delivery model selected. The
start and finish of activities with available format, terminologies and terms and conditions should
floats. The network schedule shall also be as per the standard engineering practices. In case of
be presented in the fonn of linked bar any special item or condition, the same shall be
chart or in tabular fonnat. described clearly to avoid any ambiguity.
4
IS 15883 (Part 1) : 2009
5.3 Commissioning and Handing Over Scope monitoring and change control are critical to
the construction stage in order to control time and cost
After the project is complete as per specifications and over-runs. The work breakdown structure of the project
designs, project commissioning and handing over stage shall be the basic tool for defining the scope baseline.
follows. It shall need the compliance of the following: Scope control should aim to identify factors influencing
a) Clearing of site, scope change, determ ine the impact of scope changes
b) Removal of all defects at the time of and establish the system for scope change approval
completion and during defect liability period, and revision of scope baseline. Accordingly, a detailed
scope management plan should be drawn to lay down
c) Preparation of list of inventories,
all the necessary practices including technical and
d) Certification and settlement of construction organizational interfaces.
agency's final bills for payment,
e) Obtaining completion certificate from local 6.2 Procurement Management
government bodies/departments, Procurement management includes processes for
f) Preparation of maintenance manual, purchase of materials. equipment. products, soliciting
g) Performance compliance verification of built services of consultants and engaging agencies for
facility, execution of works under a contract. Project
h) Handing over all other required documents procurement processes, which depend on type of
to the client/owner. project delivery model include identification of
5
IS 15883 (Part l) : 2009
procurement needs. preparation for procurement. scope and identifying and listing of the activities in
sol iciting proposals. selection of suppliers/consultants/ the work packages. For the qu antum of work involved
works contractors. administering of contract. contract in the activities, the activity durations are estimated
management and closure of contract. Project manager based on the standard productivity norms for different
, ; charged with the responsibility to help structure and trades of work. Past-documented experience and
I evelop contract to suit the specific needs of the project. expertise should also be used for determination of the
As contract. which is an output of project procurement activity durations with the construction technology
management processes. is a legal document, the adopted and manpower and equipment resources used.
procurement processes should follow detailed Based on the construction methodology proposed with
pro cedures with adequate review and stakeholder the consideration of project specific constraints. the
appraisal opportunities. sequencing and interdependencies of the act ivities are
determined and the graph ical representation of
One of the fundamental issues in construction projects ,
activities in the form of network should be prepared.
managed through project managers, is to determine
The network thus prepared should be analyzed to
what needs may be met by procuring products, services
develop the project schedule with information on early
and works from external agencies and what should be
and late start and finishing of activities with their
accomplished by the project team. This decision is best
available floats and the cr itical path/critical activities
arrived at the earlier stages of the project (so that the
opportunities of procurement initiation at earlier stages on the network. Incorporating the calendar dates, the
is not lost) and reviewed at each of the subsequent life baseline schedule may be finalized with the
cycle stages of the project. Such decisions should draw incorporation of milestones for subsequent schedule
inputs from the time. cost . quality and scope monitoring and control processes.
management processes. Various procurement routes During the construction stage. schedule monitoring
should be analyzed on their suitabil ity to both time involves methods of tracking and comparing the actual
and co st criteria of project. As a strategy for schedule with the baseline schedule and schedule
procurement, a project procurement management plan control activities should ensure to remove deficiencies
should be developed to document: contract types to be and slippages corrected to acceptable levels.
used ; procurement documents; coordination of
procurement with schedules ; constraints and Project scheduling and monitoring is adynamic process
assumptions; risk mitigation activities (performance and periodic schedule updating should be done for
bonds. insurances. etc) ; and pre -qual ification of effective monitoring and control process. In the
suppliers. In addition. specifications, quality standards , process, the status of each activity should be examined.
performance data at work locations, etc. which are part For completed activities, actual durations utilized, are
of project scope statement. should be described . incorporated ; and for activities in progress, balance to
Inventory management plays an important role in the complete revised durations and estimated finish dates
procurement management process. are determined and incorporated. If the actual schedule
lags behind the baseline schedule, various options
Provision of establishment of suitable dispute redressal
should be considered to control and bring back the
system should be inbu ilt to take care of any disputes
that may arise . schedule to acceptable levels. The possible control
actions, which may be considered are : possible
6.3 Time Management reduction in activity duration of future activities with
alternate technology options . increasing the resources,
lime management aims to complete the project within
alteration in the construction logic and activity
the stipulated time period . Time management
sequencing, etc.
essentially involves the following processes:
a) Defining project scope in the form of work 6.4 Cost Management
breakdown structure to generate activity The objective of the project cost management is to
identification and listing,
en sure that the project is completed w ithin the
h) Activity duration estimating, authorized budget. The major processes involved in
c) Activity sequencing with interactivity the co st management are: resource planning, cost
dependencies, est imation. cost budgeting/cost planning and cost
d) Project schedule development. and monitoring and control. The resource planning involves
e) Project sched ule control. determination of various types of resources, such as
appropriate technology, workforce, materials,
Work breakdown structure should be used as a tool to equipments and infrastructure facilities, their quantum
prep are the project sc hedule by defining the project and their requirements during different stages of the
6
IS 15883 (Part 1): 2009
project. Preliminary cost estimate with defined scope they arc: directed towards overall quality . Quality
of work is required for obtaining the project sanction . management during construction stag~ assumes that
Detailed item wise cost estimates with bill of quantities the design and specifications comprchc ns ively
and specifications should he made for tendering and incorporate requirements of users and other
subsequent project execution. The type of contract stakeholders . Prior to selling OUI for the construction.
adopted such as item rate, percentage rate, lump sum the client should completely understand the
and cost plus, influences the cost management strategy. implications of changes to the design and specifications
during the construction stage, which may affect quality.
Most of the cost optimization techniques through value
management studies arc achieved during the Although quality is an all-encompassing concept which
pre -construction stage of the project. Value also has hearing on time and cost aspects , the specific
management is a useful technique for application in cost scope of quality management may be limited 10 irs key
management. It is a systematic multi-disciplinary effort functions of quality planning, quality assurance and
directed towards analyzing the functions of project or quality control. Quality planning refer, to the
item for the purpose of achieving the best value at the identification of relevant quality st andards and
lowest overall life cycle project cost, It is an established determining how 10 satisfy them. Quality ;)S~urancc
technique for determining value based decisions rather activities include consistent evaluation of project
than cost reduction based on change in specifications . performance to provide confidence lhat the project
Suitability of construction techniques, selection of satisfies the relevant quality standards. (.)ualitycontrol
equipments for specific purposes, considering monitors project results related til the compliance to
alternative materials and other design changes are some quality standards and identifying means 10 eliminate
of the areas of application of value engineering . non-conformity.
During construction stage, the efforts are more on On-site operations constitute most of the construction
control mode for adherence to the budgeted cosl. For processes. Scope of quality management for on-site
the purpose of cost control during execution, the time operations may he categorized broadly in three drstinct
based cost baseline of the project which forms the basis stages. In the 'receiving stage', materials and supplies
for the measurement and monitoring of cost are inspected and tested for conformance to the
performance. should be generated. The cost baseline speci fied standards. During , in-process stag e '.
is generated by allocating the overall cost estimate to materials and supplies arc processed 10 form project
individual project activities based on the project product components wherein process control ensures
schedule . Using the cost baseline, the cost control, conformance to the specified standards. In the 'final
which comprises the following , should he exercised : stage', inspections and tests monitor the functional and
physical performance of the product/service to ensure
a) Periodical cost reporting,
that they satisfy the requirements.
b) Comparison of the actual cost against the
planned cost, Planning being an integral part of the quality
c) Obtaining early warning for corrective management, may also consider efficient sire layout
actions, and its management for on-site operations. In addition
to time and cost implications of the site management,
d) Control and monitoring cost chanres,
the quality performance improves by efficient
e) Forecasting of final cost at completion based
organization of activities by way of providing adequate
on cost trend and cost changes, and
and appropriate conditions for the work processes. Site
f) Modification of the cost baseline for management needs to consider construction technology
authorized cost changes and preparation of constraints with reference to aspects related to space
revised estimates. availability such as permanent services, access to site,
temporary services, location of material stores, stacking
6.5 Quality Management
" and storage areas and plants, fencing and other
Quality management in construction aims to achieve temporary structures.
required functional and physical characteristics of a
The various organizations connected with the project
constructed facility through management actions
should have their own quality management systems,
including planning, direction and control. Quality is
the key determinant of requirements which is expressed 6.6 Risk Management
through drawings and specifications. Main function of
quality management is to achieve quality objective of Project risks have an impact on the project objectives
satisfying requirements through performance and need a planned response . Project risk management
evaluation of construction processes and ensure that processes ensure proper planning, identification,
7
IS 15883 (Part 1) : 2009
analysis. monitoring and control to the best interest of a) Providing benchmark against which to
the project. measure or compare progress and costs. like
time network schedules. cost estimates.
Risk management planning processes develop an material and labour schedules. specifications.
approach to risk management activities which include working drawings.
planning. execution and monitoring . A risk
b) Providing an organized and efficient means
management plan should define lead and support role
of mea suring. collecting. verifying and
responsibilities of project team in relation to
reflecting the progress and status of operations
management. budgeting. risk responsive scheduling.
on the project with respect to progress. cost.
classification of risk activities based on risk break-down
structure and explanation of probability and impact for resource s and qual ity.
risk context. c) Providing an organized . accurate and efficient
means of con verting the data from operations
Risk response planning determines actions required for into information.
reducing impact of risks. Risk responses are established
d) Reporti ng the correct and necessary
and assigned to appropriate project participants.
information in the required format and at the
Suitable risk mitigation measures should be evolved
required level of detail to managers at all
for identified risks.
levels and to the supervisors.
6.7lnlormation and Communication Management e) Identifying and isolating the most important
and critical information at various stages to
For information and communication management.
be communicated to the managers and
Management Information System (MIS) is used as an
supervisors for taking decisions.
important tool for systemized approach to furnish
information. It comprises a system that collects. stores. f) Communicating the information to the
sorts and analyzes data to generate and communicate managers and supervisors in time so that
information. It may be a combination of manual and decisions may be taken at the right time .
computerized systems. Total MIS configuration of the construction project
At the construction stage of a project. there are many may be divided into the following modules:
agencies involved like client. architect. engineer, a) Planning and scheduling module.
project manager, various consultants. material
b) Cost control and accounting module.
suppliers, construction agencies and sub-contractors.
Each agency is divided into top level management c) Trend and forecast module.
taking policy decisions, middle level management d) Project administrative and financial module.
monitoring the project and lower level management e) Historical and documentation module.
involved in day to day operations of the project.
All modules should be interlinked in flow of
Each level of management requires information of information and generation of reports.
varying details. at different periodicities and in different
formats. Project progress information flows from lower For large public projects. suitable mechanism may be
level to the top level management and policy decisions established for communication of relevant information
flow from top level to the lower level management. to public at large.
MIS integrates the work and information flow within 6.8 Human Resource Management
each agency and flow of information between different
All construction projects involve large number of
agencies.
skilled/unskilled persons. Human resources in a project
In construction stage of the projects. the information should be adequately qualified.trained and competent.
~ay be in the form of data reflecting status of project
Quality of construction work depends on the quality
~n terms of actual execution time for each activity. cost
of labour resource. For skilled and unskilled labour.
Incurred, resources used. quality control. material
the requirement for technical knowledge. skill and
management. bills. organization management and other
general awareness are varied for different con struction
ad~inistrative aspects like disputes that may come up.
processes. Labour is required to understand their
This data should beanalyzed to understand the overall
respective responsibilities especially towards the
progress achieved and to update schedules of the
project. work . Therefore. construction management practices
sh?uld ~~phasize on development of competence of
Basic objectives of MIS of a construction project may this cr itical human resource through training
be summarized as: programmes.
8
IS 15883 <Part 1) : 2009
The crit ical activities should be identified from the j) Effective post accident management including
po int of view of technological innovations. corrective measures to avoid repetition ofsuch
workmanship and environmental conditions which accidents.
determine labour behaviour and performance. In each
Safety Officer shall be appointed in accordance with
construction project. there are certain work related
the concerned provisions of the Building and Dthu
peculiarities wh ich call for job specific orientation .
Construction Workus (Regulation ofEmployment and
There should be a clearly defined competence
Conditions of Service) Act. 1996. Safety officer who
requirement for the workmen. As far as possible. a
is posted at a medium to major construction site shall:
formal training or a certified course undertaken should
be a preferred selection criterion for the workers. A a) look after the safety of the personnel. safe
periodic review of the performance may be made to handling of materials and machinery, safe
establish the nature of tra ining required and methods work practices and standard operating
for imparting training. There is a need to address the procedures;
motivational aspects, for better performance. b) be responsible for compliance of all statutory
obligations of the employer in regard to safety
6.9 Health, Safety and Environment Management
of personnel and structures;
6.9.1 Health management issues include looking into c) guide and assist the site managers/engineers
the risk factors to health of construction personnel and to make their sites safe and accident free;
providing hygiene conditions at construction sites and d) train personnel in construction safety. conduct
methods of their man agement. It includes managing, safety surveys and design suitable documents
a) occupational/physical health hazards. for recording and promoting safety on sites
and in the construction industry; and
b) short term as well as long-term ill effects of
the activities and the working environment e) arrange for safety briefing for all the persons
of the construction sites. entering the construction area .
c) provision of personal protective equipment 6.9.3 Environment management issues include the
required for specific health hazards. and following:
d) laying down of construction hygiene control a) Minimizing adverse environmental impact of
methods. activities, products and services.
6.9.2 Safety management issues include managing b) Limiting any adverse impact within the laws/
work processes, equipment and material handling at prescribed norms and their monitoring.
site for striving to achieve zero accident status at site. c) Safety of environment while working with
For prevention and management of accidents, a proper hazardous materials and maintaining material
organizational and administrative mechanism is safe ty data sheets.
requ ired. Following steps should be taken for achieving d) Management of disposal of waste from the
the same: construction sites .
a) Laying down of safety regulations or e) Considering posiuve environmental
mandatory prescriptions concerning different contribution particularly after completion of
work processes. construction.
b) Standardization of work processes and f) Mechanism to review concerns of interested
management actions. parties.
c) Regular and stipulated inspection of works
6.10 Integration Management
and machinery/equipments for enforcement
of mandatory regulations. Integration management aims to provide processes
d) Providing education and training to workers necessary for coordination amongst various
on safety issu es. organizations and their teams involved. It ensures that
e) Publicity and appeal to develop safety various organizational teams perform in an integrated
consciousness. manner, with their actions coordinated to the mutual
interests towards the project. Integrated management
f) Insurance of built facilities. construction
processes provide opportunities for resolving conflicts
personnel and third party.
and competing interests through appropriate trade-offs.
g) Regular safety audit of construction sites . Integration is necessary where processes interact,
h) Effective post accident action including especially when process responsibilities belong to
accident analysis and reporting. different organizational groups . Such process
9
IS 15883 (Part I) : 2009
interactions need organizational interfaces to be defined organizational groups; the rescheduling may affect
and resolved at an overall level. coordination amongst performing groups in the down-
stream processes and activ ities.
Integration management may also be required for
specific situations when impact of one management 6.11 Other Management Issues
functions is a cause for concern for other management
functions . For example, if there is a time delay in With the steady increase in global population and the
performing a particular construction process, it may rapid depletion of natural resources, the project
often have impact on the cost aspects of nor only that manager may have 10 address various other issues such
process but other processes involving other as energy management and sustainabiJity.
ANNEXA
(Foreword)
COMMITfEE COMPosmON
Construction Management (Including Safely in Construction) Sectional Committee, CEO 29
OfNanizutioll Representativeis)
In personal capacily (103. Cham" SadaII. ViWpllri. SHRI P. KJusIlHAN (CIuJimuur)
N~ /HUll)
10
IS 15883 (Part 1) : 2009
Orgunizuti on Rtp"Unlalivt(1)
Larsen and Toubro LId. ECC Group. Chennai Stw M. P. NAloo
SIftl P. R. SURI'.NtlltA BAW (Alltmalt)
M. N. Dastur &: Company (P) Limited. Kolkata SHRI S. K. GUHA
Stw D. M. KApOll1l (Alltrnalt)
Military Engineer Service s. Engineer.in-in-C1liefs Branch. SHRI J. B. SHAIlMA
Anny Headquarters. New Delhi SIW J. BHATTACHAlUI (Alltntalt)
National Buildings Construction Corporation Limited. SHill ANITAIIHA BASU
New Delhi SHill S. K. GANIIHIIl (Alltrnalt)
National Highways Authority of India. New Delhi SHRI H. C. AII".A
National Institute of Construction Managcment and Research, SHill ANI!. AOAIlWAl
Mumbai
Ninnan Viluis Anusandhan Sansthan. C1lattisgarb SHill SANlf.loV KASUWAI.
SHIU ANARJf.t.-r SINGH (AlltnIQlt)
Planning Commission. Ncw Delhi SHIll SHATltUGHAN LAL
Rajiv Gandhi Rural Housing Corporation Ltd. Bangalorc SIW N. S. MAHAOCVA PIIASAO
School of Planning and Architecture (Department of Building OIl V. THIIlUVf.Nu""AN
Engineering and Managcment). New Delhi SHRI V. K. PAUl. (Alltmalt)
Shelter Consulting Engineers. Noida SHRI MAlllIl KUNAIl MrrrAi.
Spectral Services Consultants Pvt Ltd. Ncw Delhi SHill SANI>I!EI' G'lfJ.
SHIU B. S. GUIAn (Alltmalt)
The Institution of Engineers (India). Kolkala LTGEH HARI UNIVAI. (Retd)
81S Directorate General SHRI A. K. SAINI. Scientist 'F' &: Head (Civ Engg)
[Representing Director General (Ex-oJ1icioJ\
ftltmMr Secretaries
SHIll SAHIAY PANT
Scientist E &: Director (Civ Engg). BIS
SHIll S. AIlUN KUMAIl
Scientist B (Civ Engg). BIS
New Delhi
Delhi Tourism and Transportation Devclopment Corporation . SHIU JOSE KURJAN
New Delhi
School of Planning and Architecture (Department of Building OIl V. THIIlUVDlOAOAW
Engineering and Management). New Delhi SHRJ V. K. PAUL (AllmlOlt)
11
Bureau of Indian Standards
BIS is a statutory ins titutio n establi shed under the Bureau of In dian Standa rds Ac t, 1986 to promote
harmonious development of the act ivitie s of standardization , mark ing and quality certification of goods
and attending to connected matters in the country.
Cop yright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of BIS . This does not preclude the free use , in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations .
Enqu iries relating to copyright be addressed to the Director (Publications), BIS.
This Indian Standard has been developed from Doc No. : CED 29 (7562 ).
Eastern 1/14 C.I.T. Scheme VII M, V. I. P. Road , Kankurgachi 23378499, 2337 8561
KOLKATA 700054 { 23378626,23379120