Documente Academic
Documente Profesional
Documente Cultură
Document ID SP-2148
Security Unrestricted
Discipline IM&T
Owner IT CFDH
th
Issue Date 25 March 2013
Version 1.0
Keywords: This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part
of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any
form by any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent
of the owner.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 2 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
i Document Authorisation
Authorised For Issue March 2013
ii Revision History
The following table lists the four most recent revisions to this document. Details of all revisions prior to
these are held on file by the issuing department.
Version No. Date Author Checked Scope / Remarks
N/A
Page 4 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
TABLE OF CONTENTS
i Document Authorisation ................................................................................................... 3
ii Revision History ............................................................................................................... 3
iii Related Business Processes............................................................................................ 3
iv Related Corporate Management Framework (CMF) Documents .................................... 3
1. Introduction ....................................................................................................................... 6
2. Main Requirements .......................................................................................................... 7
3. Definition and abbreviations ............................................................................................. 7
A. PART ONE FOC SPECIFICATIONS INCLUDING ACCESSORIES ............................... 9
1. Quality systems .............................................................................................................. 10
2. Cable construction .......................................................................................................... 10
3. General requirements ..................................................................................................... 12
4. Core Configuration ......................................................................................................... 13
5. Cable performance requirements ................................................................................... 16
6. Design testing ................................................................................................................. 20
7. Routine Tests ................................................................................................................. 21
8. Bidding requirements ..................................................................................................... 22
9. Manufacturers test results ............................................................................................. 22
10. Acceptance Test ............................................................................................................. 22
11. Instalation methology ..................................................................................................... 23
12. Packaging ....................................................................................................................... 23
13. Fiber Optic Cable Accessories ....................................................................................... 24
14. Accessories for ADSS .................................................................................................... 31
B. PART TWO FOC INSTALLATION STANDARDS .......................................................... 34
1. Purpose .......................................................................................................................... 35
2. Priority ............................................................................................................................ 35
3. Access to the site ........................................................................................................... 35
4. Safety regulations ........................................................................................................... 35
5. General guidlines ........................................................................................................... 36
6. Installation methods ....................................................................................................... 36
7. Design ............................................................................................................................ 37
8. Installation ...................................................................................................................... 39
9. Direct buried FOC/HDPE Duct ....................................................................................... 46
10. Installation of FOC above ground along the pipe line .................................................... 51
11. Aerial cable installlation (ADSS)..................................................................................... 51
12. Acceptance tests ............................................................................................................ 62
13. Drawing and documents................................................................................................. 65
14. Appendicies .................................................................................................................... 67
Page 5 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
1. Introduction
1.1 Purpose
This document is a guide to the material, design, installation and testing of different types of fiber optic
cables including buried, ducted (blown, pulling) and All Dielectric Self Supporting (ADSS). This
Guideline does not cover the installation of in-building. It supersedes the existing SP 2002, 2004,
1265 and 1266. The new SP2148 becomes the single document for all FOC material and installation
specification.
This specification shall be corresponding with one or more of the referenced SPs and international
standards to complete the COMPANY requirement for installation works. However, it remains the
contractors responsibility to ensure the complete installation of FOC.
The Contractor shall fully comply with all the requirements in these specifications.
This document is divided into two parts. The first part one A is Material specifications and key
accessories, while the second part two B is guide for installation and testing of different types of fiber
optic cables.
1.2 Scope
This document is a PDO generic specification for polyethylene sheathed optical cables. It describes
the construction, performance, acceptance criteria of polyethylene sheathed armoured optical cables
(herein after called PSA), and polyethylene sheathed dielectric optical cables (herein after called PSD)
and All Dielectric Self Supporting (herein after called ADSS).
For PSA cable, applications include pulling/blowing into ducts and direct burial by blowing or by
trench & backfill method. PSA designs should be well protected against attack by rodents & termites
and have excellent crush & impact resistance.
For PSD cable, deployments are limited to duct installation by pulling or blowing.
The ADSS fiber optic cable shall be suitable for installation along the route of the 33kV and 132kV
overhead lines. Where the route of the OHL does not correspond with the desired route of the fiber
optic cable, the cable shall be deployed in underground rout using HDPE ducts.
The cables described herein have a stranded loose buffer tube construction that is designed so that
no net axial fibre strain occurs at maximum pulling tension.
The ADSS Fibre Optic Cable shall be supplied from approved local manufacturer. The manufacturer
shall assure that cables provided to PDO meet the requirements set forth in this specification
The supplier shall be responsible for the insurance of the cable and associated accessories from the
place of manufacture to the location designated by PDO..
Page 6 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
2. Main Requirements
For any project, the Contractor shall consider all the requirements including design, supply,
installations and testing of any FOC in HDPE duct, buried and ADSS. Any deviation to the
specification shall be approved by the IT CFDH.
The entire FOC work shall be conducted by an approved Company Telecommunications contractor.
All requirements of this specification shall apply except where the manufacturers standards are
more stringent, than the latter shall apply. If a standard becomes old and a latest issue of the same
standard is available then the latest issue shall be followed.
Compliance with these specifications for modifications or extension work to existing facilities may
not always be possible; in such cases the Company's written instructions shall be obtained to
indicate whether a deviation is acceptable.
If the Contractor has any concern about the applicable specification for a particular project, the
Contractor shall bring the concern or question to the attention of the Company for clarification or
resolution. The company's decision shall be final and binding.
Page 7 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
For the purposes of this document, the following abbreviations shall apply:
AC Alternating Current
ADSS All Dielectric Self Supporting
ASTM American Society for Testing and Materials
BS British Standard
CCITT Committee Consultative International Telegraphy and Telephony
Db Decibel
DC Direct Current
DEP Design and Engineering Practice
ERD Engineering Reference Document
FAT Factory Acceptance Test
FOC Fiber Optic Cable
GHz Gigahertz
HDPE High Density polyethylene
HV High Voltage
IEC International Electrotechnical Committee
ISO International Standards Organization
ITU-T International Telecommunications Union Telecommunications
IT-CFDH Information Technology - Corporate Functional Discipline Head
Kbit/s Kilobits per second
LAN Local Area Network
LLDPE Linear low density polyethylene
m (m/s) Meter (Meter per second)
MBL Minimum breaking load
MDPE Medium density polyethylene
OHL Overhead Line
OLTE Optical line Terminating Equipment
OTDR Optical Time Domain Reflectometer
PE Poly ethylene
PMD Polarization Mode Dispersion
PSA Polyethylene Sheathed Armoured Optical Cable
PSD Polyethylene Sheathed Dielectric Optical Cable
SAT Site Acceptance Test
SP PDO Specification Practices
UV Ultra Violet
Page 8 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 9 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
1. Quality systems
The factory where the cable manufacturing takes place must be registered to ISO-9001 and have
been registered for a period of at least 2 years.
2. Cable construction
The required cable shall comprise of the following components listed radially from the centre.
- A central strength & anti-buckling member shall be made of GRP.
- Superabsorbent polymer yarns wrapped around the central member (or superabsorbent polymer
binders suitably located elsewhere in the cable structure)
- SZ stranded loose buffer tube containing optical fibres and a thixotropic filling compound.
- Optionally, filler rods may be used in lower fibre count cables to keep the structure round.
- A layer of aramid yarn that is engineered to provide the required level of tensile strength.
- A superabsorbent polymer tape wrapped around the aramid yarn
- One or two ripcords
- A PE inner sheath
- A corrugated steel armour tape (PSA only)
- A PE outer sheath (PSA only)
FRP Rod
Water Blocking Yarn
Buffer Tubes & Fibers
Ripcord
Water Blocking Tape
High molecular weight PE sheath
Page 10 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
FRP Rod
Dielectric Strength
Yarn
Water Blocking
Tape
Ripcords (2)
Corrugated Steel
Tape
High Molecular Weight PE Sheaths
(2)
FRP Rod
Water Blocking Yarn
Stranded Core
The required cable shall comprise of the following components listed radially from the centre.
- A central strength & anti-buckling member made of 2.5 mm FRP.
- Super-absorbent polymer yarns wrapped around the central member (or super-absorbent
polymer binders suitably located elsewhere in the cable structure)
- SZ stranded loose buffer tube containing optical fibers and a thixotropic filling compound.
- Optionally, filler rods may be used in lower fiber count cables to keep the structure round.
- A super absorbent polymer water blocking tape.
- A ripcord for the PE inner sheath.
- An LLDPE or MDPE inner sheath with printing.
Page 11 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
- A layer of water blocked aramid yarn that is engineered to provide the required level of tensile
strength for the project span, sag and loading conditions.
- A ripcord for the PE outer sheath.
- An MDPE or track-resistant PE outer sheath (only for 132kV lines)
The cable must be circular in cross-section and free from pinholes, joints, repairs and other defects.
Materials used in the construction of the cable shall not affect the physical or optical properties of the
fiber and shall be compatible with each other.
3. General requirements
The cables shall not be leftovers from another project without the written permission of PDO.
The fiber and stranded loose tubes shall be colour coded as specified below to provide easy
identification at either cable end.
3.1.2 ADSS
A 2.5 mm FRP rod is placed in the centre of the optical cable core. It must serve dual function, acting
as a tensile strength element and as an anti-buckling member.
The central member must be free of imperfections that degrade its performance and must be stiff
enough to prevent the cable from kinking at its minimum bend radius. Ultimate tensile strength of the
cable shall not be less than 42kN.
Page 12 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
3.2.2 ADSS
Each buffer tube in the finished cable is distinguishable from the others by means of colour coding
as follows:
4. Core Configuration
Page 13 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
4.1.3 ADSS
Page 14 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
4.5.2 ADSS
The sheath must be made of Telecommunications grade LLDPE or MDPE. The inner sheath
thickness should be nominally 1.0 mm or otherwise to meet the required cable mechanical and
environmental performance characteristics.
4.6.2 ADSS
The strength yarns for ADSS cables shall be water blocked aramid yarns.
4.7.2 ADSS
The sheath must be made of MDPE or track resistant polyethylene depending on the electrical
potential at the ADSS attachment point. 33KV system cables shall use MDPE sheathed cables and
132KV system shall use track resistant sheathed (Outer sheath) cables. For MDPE, the nominal
outer sheath thickness shall be 1.8 mm. For track resistant polyethylene, the sheath thickness
should be engineered to meet project requirements.
The track resistant sheath shall be tested in accordance with BS5604 and IEC587 and the cable
supplier must provide evidence of compliance.
Page 15 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
The average thickness of any cross-section shall not be less than 90% of the specified thickness.
The minimum spot thickness shall not be less than 80% of the specified thickness.
4.8.2 ADSS
The inner sheath shall be marked with the following:
Companys Name: PDO
Type of fiber Optic Cable and the fiber count: (for example: ADSS 33KV or 132KV - 24 f)
The manufacturers name:
The year of manufacture:
Meter marks at a one-meter interval with arrowhead indicating upward direction of meter markings.
Parameter Requirements
Maximum pulling tension (MPT) 3500N for PSA
2700N for PSD
Minimum bend radius, no load 10 times the cable outside diameter
Minimum bend radius at maximum pulling 15 times the cable outside diameter
tension
Compressive Load 5000N/10 cm for PSA
2500N/10 cm for PSD
Impact Load 25Nm for PSA
15 Nm for PSD
PARAMETER SPECIFICATION
Maximum Pulling Tension (MPT) 2700N
Operating Temperature -40 to +70C
Crush Resistance 2500 N/10cm
Page 16 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
5.1.3 ADSS
Parameter Requirement
Page 17 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
5.2 Optical Performance of Cable for G.652D 9/125 Single Mode fiber
Parameter Requirement
Attenuation variation with wavelength (1285-1330 nm) < 0.1 dB/km
Attenuation at water peak 2.1 dB/km
Attenuation with bending (100 turns on a 75 mm diameter 0.1dB at 1550 nm
mandrel)
Attenuation coefficient at 1310 nm 0.38 dB/km
Attenuation coefficient at 1550 nm 0.25 dB/km
Optical point discontinuities at 1310 and 1550 nm < 0.1 dB
Chromatic dispersion between 1285 and 1330 nm 3.5 ps/nmkm
Chromatic dispersion at 1550 nm 18 ps/nmkm
Cable cut-off wavelength 1260 nm
PMD Coefficient 0.5 ps/km
Parameter Requirement
Attenuation coefficient at 850 nm 3.0 dB/km
Attenuation coefficient at 1300 nm 0.7 dB/km
Optical point discontinuities at 1310 and 1550 nm < 0.1 dB
Bandwidth Distance Product at 850 nm 160 MHzkm
Bandwidth Distance Product at 1300 nm 500 MHzkm
Parameter Requirement
Operating Temperature -20 to +70 C
Allowable change in attenuation at temperature extremes 0.05 dB/km
Installation Temperature -20 to +55 C
Storage Temperature -20 to +70 C
5.4.2 ADSS
2
Wind pressure (velocity) at everyday conditions 39N/m (@ 2.8 m/s)
2
Max wind pressure (velocity), q 709N/m (@ 34 m/s)
Max wind gust, v 34 m/s
Operating Temperature 0 to +70 C
Allowable change in attenuation at temperature 0.05 dB/km
extremes
Installation Temperature 0 to +55 C
Storage Temperature 0 to +70 C
Page 19 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Parameter Requirement
Fibre Type G.652D Compliant Single mode fibre made
from VAD (Vapour-phase Axial Deposition)
performs.
Mode field diameter at 1310 nm 9.3 0.5 m
(Petermann II definition)
Mode field concentricity error 1.0 m
Cladding diameter 125 2 m
Cladding non-circularity 2%
Coating diameter 245 10 m
2
Proof test 1% strain (equivalent to 0.7 GN/m )
Parameter Requirement
Core diameter 62.5 3 m
Numerical aperture 0.275 0.015
Cladding diameter 125 2 m
Cladding non-circularity 2%
Coating diameter 245 10 m
2
Proof test 1% strain (equivalent to 0.7 GN/m )
6. Design testing
The cable supplier must provide test reports for the IEC-794-1 series of cable tests noted below. The
tests must have been performed on an identical or similar construction to the one being offered and with
equal or higher fibre count. In the absence of pre-existing test reports, the cable supplier must perform
the tests on an actual length of cable manufactured for PDO orders and submit the type test reports to
PDO for approval.
Page 20 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
6.3 Impact
The test shall be performed per IEC-794-1-E4 according to the impact load requirements shown
above.
After impact, a permanent or temporary increase in optical attenuation value greater than 0.1 dB at
1550nm shall constitute a failure.
6.4 Bending
The cable must be subjected to a bending radius of 12 times the diameter of the cable for 4
complete turns according to IEC-794-1-E11, test method E11A.
During or after bending, a permanent or temporary increase in optical attenuation value greater
than 0.1 dB at 1550nm shall constitute failure.
6.5 Stress-Strain
The test must be carried out in accordance with IEC-794-1-E1 to determine the tensile
characteristics of the cable under load and to verify the fibre strain margin within the cable.
The maximum change in the optical attenuation at the cables rated maximum working tension shall
be no greater than 0.1 dB at 1550nm.
6.7 Torsion
The cable must be subjected to 10 twists of 180C on a 1 meter cable sample, according to IEC-
794-1-E7. A permanent or temporary increase in optical attenuation value greater than 0.1 dB at
1550nm and 0.1dB at 850nm shall constitute failure.
7. Routine Tests
The following routine tests must be performed on all individual lengths of PSD and PSA cable:
PDO has the right to call for schedules of all measurements carried out and check the test results.
Summary of certified test data shall be provided upon request.
Page 21 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
8. Bidding requirements
All Non-compliant items must be clearly identified and explained in detail. No other categories are
allowable and the use of other responses may disqualify the offer.
9.1 Inspection
During manufacture, the Company or its appointed delegate might visit the Manufacturer's shop to
verify that the cable meet the construction rules, drawings and specifications. This shall be paid by
the Company (PDO). The supplier shall inform the Company for the specified dates.
Factory Acceptance Test (FAT) for all the cables must be conducted at the presence of PDO witness
or PDO representative. The supplier shall inform PDO well in advance (not less than 4 weeks) the
date required for FAT.
Page 22 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
the Company to ensure free drum handling damages on the cable. If the tests showed any
damages on the FOC by having:
- More attenuation (optical loss) than what it specified in this document,
- Macrobends,
- Microbends, or/and
- Non-continuity in the FOC.
Then the supplier shall take full responsibility for replacing the whole affected cable drum(s) at his
own expense.
The tests shall be conducted for both850, 1300, 1310 and 1550 nm using;
- Optical Time Domain Reflectometer (OTDR).
- Light/laser source and power meter.
The output of the tests will be:
- OTDR curves and the loss details for each core.
- Attenuation (optical power loss) for each core.
In addition to the optical characteristics, the physical characteristics of the cable will be included in
the acceptance test, such as any abnormalities in construction, bulges or kinks etc.
All tests shall be conducted under the witness of the Company representative. The contractor shall
take full responsibility in case of non compliance or abnormalities found, it will be rejected PDO.
12. Packaging
The cable shall be shipped on a wooden non-returnable reel. The cables shall be supplied on
standard drums of 2 km, 4 km and 5km as specified by PDO at time or order placement.
Length tolerance is + 5% only. The length shall not be less than the specified quantity.
The reel containing the cable shall be packaged in a robust fashion so as to minimise the risk of
damage during handling and ocean shipping. When requested by PDO, the cable shall be
prepared for air shipment.
The reel shall be visibly marked to indicate the proper direction of rotation.
The inside ends (ISE) and outside ends (OSE) of the cable shall be sealed with a heat shrinkable
end cap. The ends shall be firmly fixed to the reel to prevent transit and handling damage.
The reel shall have a drum that is large enough to prevent damage to the cable and maintain an
optimal bending configuration for long term storage.
The drum shall have the following minimum information on a robust marking plate:
- Petroleum Development Oman LLC
- Name of manufacturer
- Cable type, i.e. PSD or PSA.
- Fibre count
- Fibre type
- Project name and number
- PDO purchase order number
- Cable length in meters
- Manufacturers unique cable ID #
- Month and year of cable manufacture
Page 23 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
13.1.1 Features
The Optical Fiber Joint Kit shall have the following features:
- Re-enterable
- No special tools required
- Cassette Type. Each cassette shall allow entering two types from both sides.
- Accommodate a maximum of 3 splice cassettes.
- Designed for straight and multiple branch splices on cut or uncut cable.
- Strain relief offering superior cable retention.
- Central strength member retainer.
- Integral fiber management.
- Dust and water proof.
- Each joint shall be capable of being marked with a unique identification number.
In general, the Contractor shall supply fully loaded patch panels with all the above
features, as minimum.
The approved vendors for material can be found in PDO AVME list (AVME C.4.6)
Page 25 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
connectors shall be capable of field installation on 9/125 micron fiber with 900 micron buffers
(OD).
Each connector shall be of the industry standard E-2000 or ST2 type compatible, designed for single
mode or multimode tolerances, respectively, and shall meet or exceed the applicable provisions of
EA.-455-5, 455-2A, and 455-34, and shall be capable of 100 repeated mating with a maximum loss
increase of 0.1 dB. Connectors shall incorporate a key-way design and shall have a zirconia ceramic
ferrule. Connector bodies and couplings shall be made of corrosion-resistant and oxidation-resistant
materials, such as nickel plated zinc, designed to operate in humid environments without degradation
of surface finishes.
13.4.1 Standards
HDPE Ducts shall conform to the following standards and the technical specifications:
13.4.2 Material
The raw material used for HDPE ducts shall meet the following requirements:
Page 26 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
- The raw materials used in the ducts shall be made of pure raw materials. Additives or recycled
materials shall neither be used nor added. The duct surface layers shall not have any spots.
- The raw material used for extrusion shall be dried to bring the moisture content to less than
0.1%.
- Suitable UV stabilizers shall be used for manufacture of the duct to protect against UV
degradation, when stored in open for a minimum period of 12 months.
- The raw material used in the manufacture of the duct shall be such that the service life of the
duct and all its accessories can be expected to be more than 50 years.
- The ducts shall be rolled on wooden drums so as not to conduct heat that can have effect on
ducts considering the weather in Gulf countries. The drums should be covered with wooden
planks to avoid ducts from direct sunlight and severe weather conditions.
Outer Layer: The base HDPE resin used for the outer layer of the HDPE duct shall conform to
any designation of IS-7328 or to any equivalent standard meeting the following requirements,
when tested as per IS-2530. However, the manufacturers shall furnish the designation for the
HDPE resin as per IS 7328 as applicable.
- Density : 0.940 to 0.958 g/cc at 27 C
- Melt Flow Rate (MFR) : 0.2 to 1.1 g/10 minutes at 190C & 5 Kg load
Inner Layer: The inner lubrication material shall be of friction reducing, polymeric material, which
shall be integral with HDPE layer. The lubricant materials shall have no toxic or dramatic hazards
for safe handling. In the finished HDPE duct, the co-extruded inner layer of solid permanent
lubricant shall be integral part with HDPE and shall be white in colour and clearly visible in cross-
section of duct. The inner layer of solid permanent lubricant shall be continuous all through and
shall not come out during storage, usage and throughout the life of the duct.
Tensile Strength and Elongation: The samples removed from the HDPE ducts when tested as per
IS-14151 (Part-I) shall meet the following requirements:
- 2
Tensile Strength : Min. 20 N/mm
- Elongation :Min. 350%
Page 27 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
direction and the deviation from the initial length shall be calculated and stated in percentage. The
dimensions shall not change by more than 3 per cent in the longitudinal direction.
Page 28 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 29 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 30 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
The approved vendors for material can be found in PDO AVME list (AVME C.4.6)
13.11 Manholes
The manhole shall be/have the followings:
- Ultima (GRP, Glass Reinforced Plastic) chamber 915 x 445 x 750mm.
- C/w base, cable management. Two ducts for in & out (sponge entry system).
- Ductile iron covers with a galvanised steel frame for MAF and cement covers for interior sites.
The covers shall be tested to the European standard EN124 B125.
- All covers to be locked and sand proof (i.e. sand cannot enter the chamber when closed).
- Locking should be of at least Allen key secure and sand proof. Lifting keys shall be provided
also. One lifting key among 10 manholes shall be provided.
- Base material shall have a VICAT SOFTENING RATE of 84C and drain hole.
- Internal Cable furniture
- FOC joint holder.
The Contractor shall supply C4 Industries make or equivalent specification. The Contractor shall
also provide FOC holder, internal cable holders, FOC joint enclosure and any other installation
required within the manhole.
The approved vendors for material can be found in PDO AVME list (AVME C.4.9)
tension while preserving the desired sag. They are specially designed to provide the required
holding strength while minimizing any compressive stresses that may be transferred to the optical
fiber element within the cable.
Page 32 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 33 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 34 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
1. Purpose
A guide to the design, installation and testing of different types of fiber optic cables including
buried, ducted (blown, pulling) and installation along the electrical OHL (ADSS). This Guideline
does not cover the installation of in-building.
Installation of fiber optic cables shall be governed by, but not limited to the provisions specified,
and shall be undertaken to high standards of workmanship and in a safe manner. However, it
remains the contractor responsibility to ensure the complete installation of FOC.
The Contractor shall fully comply with all the requirements in these specifications.
2. Priority
Standards shall take the following priority (in order of highest to lowest):
- The project technical specification
- This document (SP 2148)
- Other PDO documents (including ERDs, codes of practice, standards, specifications,
procedures and guidelines)
- DEPs
- Other Shell Standards
- International Standards
- Industry Standards
4. Safety regulations
Safety is the most important aspect of a fiber optic cable installation and highest priority shall be
assigned to the safety issues. These safety recommendations are meant to supplement, not to
replace, relevant local & national laws, company-specific safety practices and other codes and
regulations. Some of the key points are:
- Fire and safety regulations & laws limit the use of polyethylene-sheathed cables for indoor
applications. Local fire codes must be consulted before deployment of cables.
- To prevent eye damage, never look into the end of an optical fiber unless a power meter is
used to verify that no optical signal is present.
- All local government and end user regulations must be followed at all times.
- Testing for explosive gases and proper ventilation of underground facilities is vital.
- Capable ventilation equipment must be used according to local regulations & practices prior to
installation of OFO cables in underground facilities.
- A running ground must be used whenever there is the possibility that a voltage may be
somehow applied to the cable.
Page 35 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
- The use of compressors for cable blowing requires careful attention be paid to the
safety instruction for the compressor and all compressed air fittings.
- Although ADSS cable has a fully dielectric construction, the cable can become
conductive because of contaminants or moisture on or in the cable. It is recommended
to connect to the earth the installed ADSS cable and all ADSS cable fittings before the
cable system is touched.
- If the surface of the cable is wet, the ground clamp must be within 2 meters of either
side of the point to be touched. This applies to installation, splicing, terminating, testing
and maintenance of the cable system.
- ADSS cable should not be installed in wet weather.
- Running earth should be used where needed to eliminate the risk of electrical hazards.
- When positioning the cable near high voltage power lines, Contractor shall produce a
high intensity plot. This is used to try and position the cable at locations of minimum
field intensity.
- Clearances and separations between the line conductors and the Fiber Optic cable
shall be referred to Standards SP 1114A & SP 1114B.
- The attachment point of the ADSS cable must be carefully considered during the design
stage. The attachment point must be selected so that the electrical stresses on the
cable do not support destructive electrical surface activity and must also ensure that
there is no clashing between the ADSS cable and the phase conductors, earth wires or
other suspended cables.
- The structure installation of ADSS cable on an overhead line shall be according to SP
1114A & SP 1114B. The installation will affect the loading and load balancing conditions
on the structures. Careful engineering consideration must be given to this incremental
loading and any remedial work that might be needed (such as reinforcement of the
structures, adding guy wires, etc.).
5. General guidlines
Care must be taken when handling and installing ADSS FOC. The primary points to be
aware of are:
- Never stand on the cable or allow vehicle to drive over it.
- Cable drums shall be rolled only in the direction indicated by the arrow on the drum.
- Drums shall not be laid flat for installation or storage.
- When lifting the cable drum by crane or other lifting device, a spreader bar must be
used above the drum to avoid inward pressure on the top of the drum flanges.
- Do not allow the cable to be kinked.
- Care must be taken during all phases of handling and installation to ensure that the
minimum bending radius is not exceeded.
- The ends of the cable should be sealed with heat resistance sleeve to prevent moisture
ingress.
- Do not use gasoline as a cable cleaner. Use Polywater optical cable cleaner or other
effective orange oil based cleaner.
Sufficient skilled personnel shall be made available for supervision and technical advice.
6. Installation methods
The cable supplier must provide PDO with a detailed installation manual. It must provide
vital information with regard to safety, tensioning, equipment, sheave sizes, etc.
Page 36 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
It is preferred that the installation manual be provided in an electronic form, preferably Acrobat.
7. Design
In the design stage, the following shall is mandatory:
- Optical power loss budget shall be calculated for any FOC link.
- A pre-survey of the route shall be conducted for all types of installations.
- Problem areas shall be identified & fixed and an installation plan should be clearly defined
prior to the start of the installation.
- Catalogue Data: Catalogue data on conduit system, manholes, conduit fittings, conduit plugs,
pull rope, identification tape, and warning signs.
- Detailed bill of materials.
- Drawings indicating the routes, total layout and locations of all manholes.
- Catalogue data on all testing devices proposed for use plus certifications of accuracy,
calibration, and traceability to standards of the National Institute for Standards and Testing.
- In case of pressure blowing, detailed methodology of blowing FOC.
- In case of HDPE duct installation, detailed installation methodology of the duct.
- In case of cable pulling, pulling calculations for all conduit runs.
- In case of cable puling, a cable pulling and splicing work plan shall be submitted a minimum
of 45 days prior to the planned initiation of cable pulling. The pulling plan and pull tension
calculations may be prepared by using a software program such as Pull-Planner 2000 by
American Polywater Corporation, or equivalent. The cable pulling and splicing work plan
must be approved, a minimum of 15 days prior to pulling cable. Work plan shall include the
following:
a. Pull tension calculations
b. Calculated amount of lubrication required
c. Detailed description of pull operation methods for all conduit runs
d. Tools and equipment to be used for cable installation and testing
e. Physical location of equipment setup and type
f. Exact location of splice points
g. Safety and manual assist cable pulling operations
h. Detailed schedule for pulling and testing cables
- The name and qualifications of the supervisory personnel that will be directly responsible for
the installation of the cable and/or conduit system.
Page 37 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
System Margin dB
Equipment Degradation (ageing of Laser lifetime (Ref. 3
CCITT 956)
Design Noise 1
Operation Margin (Safety Margin) 1.5
Future Splice Margin (The system shall allow at least 10 0.1 per splice
additional joints)
The fiber optic link shall accommodate up to additional 10 joints (5 repairs) without
exceeding the error performance.
Table 2 shows the recommended parameters to be included for calculating the link losses.
Link Losses dB
Cable loss (G.652) 0.4 dB/km
Splice loss (G.652) 0.1
Connector Loss 0.5
FDF loss (Connector loss + Jumper loss) 0.75
The received optical signal shall not exceed the OLTE upper receive threshold. Optical
attenuates may be required on short sections to accomplish this.
Page 38 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
8. Installation
8.1 General
The Contractor shall determine a suitable cable installation method to ensure that all cable
installation requirements shall be met. All work shall be carried out in accordance and consistent
with the highest standards of quality and craftsmanship in the communication industry with regard
to the electrical and mechanical integrity of the connections; the finished appearance of the
installation; as well as the accuracy and completeness of the documentation.
The following guidelines and procedures shall be followed in any FOC installation:
- The Contractor shall comply with the cable manufacturer's recommended installation
procedures at all times.
- Remove wood battens just prior to installation. For pre-installation tests, use the 3 meter
inside end (routed through the flange).
- For long term storage of reels, it is advisable not to expose the reel to direct sunlight or
excessive levels of moisture.
- General precautions shall be taken before starting the cable laying. Cable shall be normally
pulled out by hand. When using a winch, tension shall be monitored by tension meter, and
the work be performed accordingly
- The cable shall be carefully inspected for jacket defects as it is removed from the reel. If
defects are noticed, the pulling operation shall be terminated immediately and the Company
Site Representative shall be notified.
- The ends of the cable should be sealed with heat resistance sleeve to prevent moisture
ingress.
- The cable shall be tested at site before starting the laying of the cable and the test results
recorded in the approved test sheet format.
- Fiber optic cable of each drum shall be installed in continuous lengths without intermediate
splices throughout the project. Cable installation personnel shall be familiar with the
manufacturer's recommended procedures including, but not limited to the following:
- Proper attachment to the cable strength elements for pulling during installation.
- Cable tensile limitations and tension monitoring procedures.
- Cable bending radius limitations.
- Cable twisting limitations.
- Under no conditions shall the FOC be left exposed or unattended.
- At termination points, such as at cabinets or end equipment/system, a five (5) meter loop
shall be provided wherever space permits. The fiber optic cable shall be coiled and secured
with cable ties. The Contractor shall ensure that the minimum bending radius of the fiber
optic cable is not compromised when preparing this stored cable slack.
- Repairs: Repair of cable jacket shall not be permitted. Jacket damage shall require removal
and re-installation of a new cable run at the Contractors expense.
- PTW procedures shall be followed for any FOC installation.
Page 39 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
8.2 Reels
Fiber optic cables are normally supplied on wooden reels. These reels must be handled
properly to assure optimum control of the cable. Prior to installation, the installation crew
must inspect the condition of the reel. If there is any evidence of reel damage, the damage
must be repaired prior to installation to avoid damage or over-tensioning of the cable. Pay
special attention to ensure there are no protruding nails or other sharp objects that can
damage the cable sheath during loading/unloading. Reels must be supported on a straight
& sturdy axle through the central (arbor) hole. Back tension pressure must NOT be applied
to the drum flange. Do not lay reels on their side during installation or storage.
- The end of the cable is then taken off the drum and directed under the obstruction. At
the other side, it is to be re-coiled onto the cable drum that has been relocated to the
other side of the obstruction. Whether the cable is re-rolled or is manually handled into
the trench stretching away on the far side of the obstruction is determined by the length
of the remaining cable.
- Distances up to 750 meters would be handled by walking the cable away for the
obstruction until the joint location is reached. Sufficient Manpower to be allocated so
that the cable does not touch the ground or is dragged along the ground. Surplus cable
is then moved along this chain of men to the joint location, and the cable is then laid into
the trench. Cable length in excess of 750 meters would normally be re-coiled onto the
drum prior to being dispensed into the trench.
Page 40 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
8.7 Communications
Communications between installation personnel is vital to assure proper cable handling.
Installation, splicing & testing crews must be equipped with radios, mobile phones, talk sets, order
wires or other communication devices during the entire installation period to avoid accidental over-
tensioning or other cable damage.
It is vital to maintain the minimum bend radius of the cable at all times to avoid catastrophic
damage to the cable components including the optical fibers.
8.10.2.2 Crossings
Maintain a minimum of 300mm separation between fiber optic and electrical cables. Install
fiber optic cable within a PVC pipe at least 3m each side of the crossing, and install
protective tiles between the power cable and the fiber optic cable at least 1m each side of
the crossing.
8.11 Splicing
In order to provide the optimum performance and reliability, any splicing of fiber optic cable
shall be by fusion splice only, no mechanical splices are permitted.
The following procedure shall be followed:
- The splicing shall be conducted by trained, authorized persons only.
- All fusion splicing equipment shall be in good working order, properly calibrated, and
meeting all industry standards and safety regulations. Cable preparation, closure
installation and splicing shall be accomplished in accordance with accepted and
approved industry standards.
- Following are important considerations for low-loss, reliable fusion splices.
a. Maintain cleanliness and temperature/humidity/dust control of the splicing area
b. Use a quality fusion splicer and maintain it according to the manufacturer
recommendations.
c. Use a quality, well-maintained cleaver that is capable of consistent, low angle
cleaves.
d. To maintain the strength of the optical fiber, the coating strippers must be able to
remove the primary and secondary coatings without scratching or damaging the
cladding glass.
Page 42 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
e. Set the fusion splicer arc settings according to local temperature, humidity and altitude
conditions.
f. Perform an arc test periodically to verify splicer performance.
- Splices shall be made in manholes and shall use re-enterable splice closures.
- The average splice loss shall be 0.1 dB or less per splice. The average splice loss is defined
as the summation of the loss as measured in both directions using an optical time domain
Reflectometer (OTDR) through the fusion splice, divided by two. No individual splice loss
measured in a single direction shall exceed 0.15 dB.
- Upon completion of the splicing operation, all waste material shall be deposited in suitable
containers, removed from the job site, and disposed of in an environmentally acceptable
manner.
- All unused couplings shall have protective dust covers. All panels shall be furnished with front
removable door or cover, Factory-terminated, tight-buffered, agamid-reinforced fiber optic
jumper assemblies or interconnect cables, standard 3.0 mm O.D, shall connect the optical
cable terminations to the patch panel couplings.
8.13 Manholes
The manhole shall be provided for the followings:
- Any FOC joint shall be housed inside the manhole.
- Manhole shall be installed at the entry/exit point of any station or site.
- Manhole shall be installed at both ends of road, wadi and Falaj crossings.
- At every change of route direction for > 30 degrees.
The following guidelines and procedures shall be followed for FOC Installation at Manholes:
- Excavate site to the depth required. Allow 150mm all around the wall for backfill and 150mm
for the base.
- Form a base (min 150 mm thick) with concrete and shall be compacted properly. The
Contractor shall neither use compacted stone nor lean dry mix concrete for the base. Check
depth with tape, allow for cover and frame. Arrange for sump and cable anchors if required.
Where anchor required, floor to be reinforced with steel mesh.
- Place the box in the excavation with frame fitted. Using a screed, level the top of the box with
the surrounds. Adjust the depth by packing material under the walls.
- Mark the position for duct entries.
- Remove box from the excavation. Cut duct entries with holesaw. If duct already in situ, see
separate instructions for method to form 'drop over' or 'build around' box.
- Replace box. Place length of duct section through cut-out holes and extending to outside of
excavation. The duct should extend inside the box by 25-50mm.
- Form a floor using mortar. Fall to sump if fitted.
- Backfill with, Type 1 stone [mixed size road stone] or lean mix, compacting frequently up to
the top of the frame. The choice of backfill material will not affect the performance of the box
and should be consistent with the preferred compaction method and local conditions. Where
Page 43 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
the excavation is less than 0.5m from the road, lean mix backfill is recommended. [Lean Mix -
use 1 cement: 10 aggregate/sand].
- Place frame and cover in position. Form a mortar haunch around the frame 100mm
wide by 75mm deep. Ensure the grouting lugs on the frame are properly bedded in the
concrete collar. The mortar can be placed under the frame to adjust the finish level.
- Manholes installed in soil areas shall be installed so that the top of the cover is at least
100 mm above the final grade level of the restored surface to prevent accumulation of
dirt, silt and debris on the top of the hand-hole cover.
- Manholes conduit entries shall be sealed with duct plugs to prevent the intrusion of
water and debris into the manholes.
- The pulling of the cable shall be hand assisted at each Manhole or hand hole. The
cable shall not be crushed, kinked or forced around a sharp corner. Sufficient slack
shall be left at each end of the cable to allow proper cable termination.
- The cable shall be looped in all manholes as noted on the plans to provide
approximately five (5) meter of extra cable in the manhole. The fiber optic cable shall
be coiled and secured with cable ties in the manhole. The Contractor shall ensure that
the minimum bending radius of the fiber optic cable is not compromised when
preparing this stored cable slack.
- For FOC Joint, cable length of ten (10) meter shall be left coiled on each side of the
joint in the manhole for future maintenance requirements.
- The cable shall be marked and labeled at each manhole and at all entry and end
points of the fiber optic cables.
- When all cables at each manhole are securely racked, unused conduits and void areas
around conduit containing cables shall be sealed.
- The area around the manhole shall be compacted.
- Upon final acceptance of the conduit/duct system all manholes shall be free of debris
and water, and be ready for cable installation.
Refer to Drawings GEN-6-2016-001 and GEN-6-2016-002 for the method and
specifications for installation of manhole on the pipeline route.
Page 44 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
8.15 Crossings
The cable shall not be cut at crossings. Cuts shall only be allowed for long crossings and subject
to the Company approval. In case the crossing is at the middle of the cable length, a cut shall be
made prior the crossing. This shall also be subject to the Company approval and accounted for in
the power budget design.
In case of road crossing, the depth of the trench shall be 1000mm. The specifications shall be
the same as shown in GEN-6-2016-004.
At crossings the cable shall be protected by HDPE duct and Steel conduit. The Contractor shall
supply and install 100 mm diameter G.I. Class C steel pipe for the road crossings. The pipe shall
extend at least 3 meters on either side of the road. The Contactor shall install the HDPE duct
inside the GI steel pipe with 5 m extension from both sides.
The HDPE duct/conduit shall be of corrugated construction with a plain internal wall of LDPE
(low-density polyethylene) and an external corrugated wall of HDPE (High Density Polyethylene).
External colour shall be blue. Manufacturing shall be according to STD. EN50086-1 and EN
50086-2-4. Conduit shall withstand 450N with maximum deflection of 5% of internal diameter and
750N with maximum deflection of 15%.
Conduit shall withstand impact test specified in EN 50086-2-4- sect. 10.3. Suitable jointing tubes
with indented rings, which mate with external corrugations, shall be utilised for all joints. Joints
shall provide a watertight seal.
During construction the ends of the conduit shall be closed to prevent foreign objects.
Upon completion the ends shall be sealed to prevent ingress of water and sand using a plug.
Sealing shall be achieved without use of glues, sealing compounds or foams. After its
installation, the conduit shall be cleaned on the inside from any kind of material (earth, stones,
etc.). A puling rope shall be provided in the conduit for future use.
At Tarmac road crossing a spare GI and HDPE duct/conduit shall be installed adjacent to the
cable conduit. Pull wire and ends sealing shall be provided.
The Contractor shall comply with and follow the FOC installation standard at Wadi crossing
shown in GEN 6 2016 003 and GEN 6 2016 003 for FOC along pipeline and FOC dedicated
route respectively.
Page 45 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
The distance to the cable is to be recorded on each marker, together with the cable depth
at each point.
Installation shall include the route markers, plates, posts and all the necessary materials
required for installation.
Refer to GEN-6-2016-005, GEN-6-2016-006, GEN-6-2016-007, GEN-6-2016-008, GEN-
6-2016-011 and GEN-6-2016-009.
Page 46 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
order to avoid damages due to ground settling after backfilling, Wherever the cable laying
is interrupted the cable shall be protected by suitable means.
For plowing, the equipment in use must be capable of maintaining even & consistent cable
tension and radii above the minimum bend radius of the cable. Particular importance should be
paid to the plow itself.
For direct burial of cables in difficult soil, a pre-rip (in the same direction as the installation) is
required to improve plowing conditions. Vibratory plowing is the preferred method to static
plowing because of its lower drawbar force.
Figure-8s shall be used for back feed pulling or other situation where removal of the cable from
the drum is needed. The size of the figure-8 should be marked with cones or other suitable
devices. The figure-8 shall be at least 5 meters long with each loop at least 2 meter minimum
diameter.
Figure 1 shows the high air speed blowing (HASB) method. In this method, the conduit is
wide-open, and high air volume (300-600 cfm) blows through it. This "wind" pushes on the
cable and advances it forward at whatever speed the pusher will support. There is no
Page 47 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
pulling force on the front end of the cable, only a mechanical pushing force at the back and
an air drag force distributed along its length.
The following are general steps required for the installation:
- The HDPE duct shall be in the range of 1075 m 1500 m drums.
- Dielectric and seamless Accessories shall be used for jointing HDPE ducts. The
jointing accessories shall withstand the pressure required to blow the cable.
- Suitable jointing tubes with indented rings, which mate with external corrugations,
shall be utilised for all joints. Joints shall provide a watertight seal.
- During construction the ends of the conduit shall be closed to prevent foreign
objects.
- Upon completion the ends shall be sealed to prevent ingress of water and sand
using a plug.
- The Telecom contractor shall provide the sealing and it shall be achieved without
use of glues, sealing compounds or foams.
- After its installation, the conduit shall be cleaned on the inside from any kind of
material (earth, stones, etc.).
- Air blowing test shall be conducted to confirm the intact of the joints and no air leaks
exist.
- The HDPE duct shall be provided in a 1000m per drum. The contractor shall advise
for any preferable change subject to PDO approval.
- After duct installation, integrity testing shall be conducted to ensure proper duct
installation.
- Using one blowing machine (Cable Jet), Up to 1500 or 2000m can be blown,
depending on quality and characteristics of the cable, ambient temperature and
profile of the trench.
The above are only general guideline. The contractor shall develop their own procedures
and submit to the Company for approval.
Page 48 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
- Clean, dry, and prove the duct. If it was not done previously, blow through a hard mandrel to
establish that the duct is not crushed. Then blow a tight fitting foam carrier through the duct
at high pressure. The foam should travel through at approximately 100 ft/sec in a clean duct.
If excess water or dirt comes from the duct, repeat the process. If necessary, dry the duct
with dry airflow.
- For high air speed machines (no missile), inject the recommended amount of lubricant and
spread it by blowing through another foam carrier. For piston type machines, majority of the
lubricant are injected in front of the missile with some placed behind it.
- Hook the blowing machine to the duct. For HASP machines, hand pushes a hundred feet or
so of cable into the duct. Close and seal the cable and air chamber on the blowing machine.
Follow the machine manufacturers instructions for all operations.
- Check all pneumatic and hydraulic hook-ups. Slowly turn up the air and watch it go.
- An after-cooler shall be sued for all pressure blowing (Cable Jet) installation, particularly
when the cable is to be installed in high ambient temperatures (such as in Oman and the
Middle East). The use of an un-cooled compressed air source can cause a dramatic increase
in the coefficient of friction between the duct and the cable sheath.
Page 49 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 50 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
- Other protective measures not specified herein may be taken during installation if it will
ensure protection of the cable.
Page 51 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 52 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 53 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
The wire mesh-pulling grip is to be used only for pulling of the ADSS cable. It is not
meant to be used to sag the cable or hold it for long periods of time under high tension.
Pulleys used during installation must be set up properly to avoid torsion damage.
Practical experience has shown that a simple support rope used to hold the pulley at an
appropriate angle to the pole or tower will serve to reduce the amount of torsion in the
cable. An example of the correct pulley setup is shown below.
Page 54 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
When a pull begins, it is essential to check for rotation of the ADSS cable by using a flag or other
visual means as shown in the following sketch.
Observe the indication as the cable is pulled, especially as it is pulled through line angle
changes. If there is a continuous twist in the cable, then the pull should be halted immediately
and the tension on the cable reduced. Efforts should then be made to reposition the pulley and
eliminate the source of the torsion.
11.4.3 Communications
Communications between installation personnel is vital to ensure proper handling of the ADSS
cable. Installation, splicing & testing crews must be equipped with radios, mobile phones, talk
sets, order wires or other communication devices during the entire installation period to avoid
accidental over-tensioning or other cable damage.
Page 55 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
11.5.2 Tensioner
Standard cable drums are not designed to withstand the force developed by braking
during high tension stringing operations. Therefore, direct tension stringing from the
cable drum at cable installation stringing tensions should not be attempted. The cable
may be pulled directly from the drum stand only when employing slack stringing methods
that allow minimal tension to be applied directly to the reel of the cable.
11.5.4 Pulleys
Pulley Groove Diameter for Tension Stringing:
Sheave diameters that are larger than those specified are acceptable, and offer some
advantages by reducing the load applied to the cable.
Pulley Parameters for Tension Stringing:
Parameter Recommendation
Radius of pulley groove At least 55% greater than the cable OD
Depth of pulley groove At least 25% greater than the cable OD
Pulley groove flare 15 to 20 from vertical
Pulley material Heat treated aluminum or aluminum alloy
Safe working load 2 times maximum loading tension of ADSS cable
Groove lining Elastomer, neoprene or urethane lining (unlined
pulleys are not recommended!)
Page 57 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
11.5.8 Tensiometer
Tensiometers (also called dynamometer) must be used to measure the tension in each
installation span. The tensiometer should be accurate and must be rated no more than
20% above the maximum installation load of the ADSS cable.
When a high degree of measurement accuracy is required, two tensiometers can be
used in series. If there is significant difference between the two, then investigations must
be made to determine if accurate measurements are possible. If the measurements are
similar, then the average of the two readings can be used.
Page 58 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Step # Recommendation
1 Mount the cable drum on a trailer or truck equipped with a drum carrier. Be
sure that the cable drum is mounted so that the cable pays off from the top of
the drum for trailers and from the bottom to the quadrant for line trucks.
2 Set the brake to minimum. The brake should apply tension to the arbor shaft,
not to the reel or cable.
3 Determine the correct attachment point for dead ends and suspensions and
pre-install the necessary attachment hardware, if desired.
4 Place pulleys at each point along the route. Position the pulleys just above or
just below the desired attachment point. The pulleys must be sized properly.
5 Dead-end terminate the cable at the first structure.
6 Drive the truck along the route and pay off the cable under minimum possible
tension. Adjust the tension periodically to compensate for the reduced weight of
the reel.
7 When moving past a structure, stop the vehicle and place the cable in the
Page 59 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
pulley. Alternatively, the cable can be laid on the ground for a number of
structures then the cable is lifted into the pulleys.
8 Repeat steps 6 & 7 until the last structure*
9 Go to the first tensioning point from the start point and tension the cable.
10 Install dead ends and suspensions according to the instructions provided by the
fitting manufacturer.
* Alternatively, the cable can be tensioned & sagged at the first tensioning point.
Ensure good communication between the vehicle driver and the person positioned near
the cable reel. Where traffic control is needed a flagman must also be able to
communicate with the other installation personnel.
Step # Recommendation
Place the cable reel on a suitable reel payoff stand or reel payoff
trailer. The cable must be supported by the arbor holes and an
1
effective back tensioning device must be present and in good working
order.
Place the tensioner in-line between the payoff stand and the first
2 structure. Feed the cable through the tensioner in the precise
manner recommended by the installation equipment manufacturer.
Determine the correct attachment point for dead ends and
3 suspensions and pre-install the necessary attachment hardware, if
desired.
Place pulleys at each point along the route. Position the pulleys just
4 above or just below the desired attachment point. The pulleys must
be sized properly.
5 Run a small pilot line through the pulleys at each support structure
Use the pilot line to pull the installation rope through the pulleys
6
starting at the planned pulling point.
Attach the ADSS cable to the wire pulling grip and the swivel link.
7
The swivel link must be used for all ADSS cable installations.
Use the puller and tensioner to pull the cable through the pulleys
according to the pull plan. Good communication between the
personnel at the puller and tensioner is absolutely vital to the success
of tension stringing. In addition, positioning of personnel at key points
8 such as road crossings, obstacles, crossing power lines, bodies of
water, pipeline crossings, etc is strongly recommended.
The puller and tensioner MUST be operated according to the
equipment manufacturer. The ADSS cable must be kept under
minimum load to complete the pull.
Once the cable is installed, each tensioning span can be sagged and
9 the support hardware installed. All hardware must be installed
according to the hardware manufacturers instructions.
Page 60 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 61 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Wherever possible the route shall follow the route of the HV cables. The fiber optic
cables shall be laid in a dedicated trench. The spacing between HV cable trench and
FOC trench shall be minimum of 1200mm.
The HDPE duct shall be no less than 3 times the diameter of the cable to be installed (it
may be assumed that a 50mm duct will be sufficient for a 15mm diameter FOC). The
HDPE pipe shall extend into the Control Rooms/buildings at each location and shall
terminate the FOC on the patch panel. Joints in the HDPE pipe shall be seamless so as
to allow the installation of the cable.
The cable joints, relevant cable rings and other underground works shall be protected
by a manhole. Suitable jointing tubes with indented rings, which mate with the external
corrugations, shall be utilized for all joints.
Page 62 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
The OTDR trace results shall demonstrate the following pass criteria at both directions at
1310nm and 1550nm wavelength:
- No Point Losses along the end to end cable stretch.
- No Micro or Macro bends.
- Average Optical Loss per Km on all the fibers shall be within the test results
achieved during drum test prior to installation.
- One Way Splice Loss AB and BA shall be less than 0.15 dB at each of the
splices.
Page 63 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
- Average Splice Loss ((AB) + (BA))/2 shall be less than 0.1 dB at each of the
splices. No other anomalies/defects developed in the Optic Fiber due to installation.
- Final Insertion loss testing from both directions at both 1310nm and 1550nm wave
length. Total end to end AB, BA and ((AB) + (BA))/2 shall be less than the
calculated Loss based on the total Fiber Length, Splices including terminations,
Connector / adaptor losses at the termination points.
Telecoms Contractor shall measure the loss of the Patch cords used for testing by
connecting the optical source and the level Meter in a back-to-back fashion prior to
conducting the test to get accurate results.
The following theoretical calculations shall be used as a guide to determine the
acceptable measurable actual loss on the fiber optic cable:
- For 1550 nm using insertion loss measurement, the total FOC loss shall be 0.25
dB/km Y km + Splice loses (0.1 dB no. of splices) + 0.2 dB (Termination losses
at both ends) + 1 dB (2 connector losses, each connector loss is 0.5 dB).
- For 1310 nm using insertion loss measurement, the total FOC loss shall be 0.38
dB/km Y km + Splice loses (0.1 dB no. of splices) + 0.2 dB (Termination losses
at both ends) + 1 dB (2 connector losses, each connector loss is 0.5 dB)
For example, the insertion loss measurement results for 69 km route shall be the
following:
- For 1550 nm, The total FOC loss shall be:
(0.25 dB/km 69 km)+ (0.1 dB 9) + 0.2 dB + 1dB = 10.85 dB. Hence the total loss
of the route shall be not more than 10.85 dB.
- For 1310 nm, The total FOC loss shall be:
(0.38 dB/km 35 km)+ (0.1 dB 9) + 0.2 dB + 1dB = 15.4 dB. Hence the total loss
of the route shall be not more than 15.4 dB.
The Contractor shall replace any fiber optic cable in which any fiber (core) does not
meet with the above criteria, for both OTDR and Insertion loss, at contractor own
expense.
In addition, although the total measurable actual loss on the FOC found to be less than
the calculated one, the contractor will not be free from the responsibility of microbends
and macrobends. The contractor shall repair the damage caused by the macrobends
and microbends even though the measurable loss is less than the calculated loss, as
mentioned in this section.
Page 64 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Page 65 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
If connectors exist in the cable under test, then two traces shall be recorded. One trace
shall record the fiber loss (dB) and average attenuation (dB/km) of the entire cable
segment under test, including connectors. The second trace shall display a magnified
view of the connector regions, revealing the connector losses (dB). All connector losses
shall be measured using the 5-point splice loss measurement technique.
Page 66 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
In accordance with SP-1131, as-Built drawings shall utilise the contract drawings as the basis
for the final status of the installation. Also shall records all deviation, deletions and additions
with respect to the original scope and
14. Appendicies
Page 67 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Poles
Are all poles structurally sound and can accept the cable tensions?
Clearances
Will all clearances meet NESC code (line/line, electrical stress, ground)?
Installation Equipment
Is equipment available to load cable onto trailer or payout?
Is the cable drum trailer/cable payout shaft appropriate for the reel arbor
hole?
Is the cable drum trailer/cable payout large enough for the cable?
Does the cable drum trailer/cable payout have a brake?
Are all bucket trucks (if used) in working order?
Is equipment available to drill holes into poles for hardware?
Is a chain hoist available?
Are all pulleys/sheaves greater than 12" in diameter (dead end pulleys 20")?
Is a method available to pull the rope/cable?
Is a dynamometer available and accurate?
Is equipment available to provide cable back tension control?
Tools
Are the following tools available?
Temporary Tensioning Grip
Formed Wire Installation Tools (FIT)
Cable
Has the cable undergone a satisfactory incoming inspection by OTDR?
Page 68 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Hardware
Is all hardware available and inspected?
Dead Ends
Tangents
Suspensions
Tower Guide Clamps
Splice Boxes
Vibration Dampers
Bolts, Nuts, Washers
Crew Training
Has crew training been performed
Page 69 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
1310
1
1550
10
11
Page 70 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
Cable type before splice (from A) Cable type after splice (from A)
1310 nm 1550 nm
Fibre Measured value Splice atten. Measured value Splice atten.
Site A Site B
No. from (dBx100) Average from (dBx100) Average
A B (dB) A B (dB)
10
11
12
Page 71 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: March. 2013
SP User-Comment Form
If you find something that is incorrect, ambiguous or could be improved in this document,
write your comments and suggestions and send to Document Control Section (DCS). They
will review and then send to CFDH. In case there is requirement for inquiry DCS or CFDH
will get in touch with you.
SP Details Title Issue Date:
Number:
Comments:
Suggestions:
Comments:
Page 72 SP-2148 - Specification for Fiber Optic Cable and Installation Printed 20/08/2014
Standards
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.