EXCAVATION WORKS
1. Excavation permit
Prior starting Excavation works. D.C.I has been granted by the authorities.
2. Existing services
3. Shoring system
4. Dewatering system
5. Safety
i. Ambulance 999
ii. Fire Brigade 999
iii. Police 999
iv. Electricity 4677601 or 4677602
v. Hamad General Hospital 4393333
vi. Project Manager 5545746
vii. Site Engineer 5217456
viii. General Foreman 5330138
6. Supervision
Site Engineer and General Foreman for assuring that work is on going as per the
drawings/specification and approved Method Statement.
-2-
8. Materials to be used
9. Method Statement
A General Description
Taking into consideration of all the above, Excavation Works to start from the
existing Ground Level upto the required level of each face. The excavation work
is divided into 6 phases as described below.
B Phase one
C Phase two
D Phase three
E Phase four
* Level upto
Geometrical Qty to be excavated and kept
in place till the completion of the piling works.
F Phase five
G Phase six
19x19x0.988 = 357m3
* CQJ-02/Exca-SK05/01/02/04
showing the plan trenches location
* CQJ-02/Exca-SK06/01/02/04
showing profile section through the plot and
the trench depth and location
* CQJ-02/Exca-SK07/01/02/04
showing the phases place S. Ramp to be removed
at the completion of Excavation/Piling works
N.B.
1. On completion of Piling works all excavated material kept in place to be
carted away progressively.
2. Disturbed layer (if any) to be removed carefully prior Blinding works to start
and filled (if needed) with concrete Grade 15.