Estimate for proposed residential building Chennai

GROUND FLOOR
Sl.No. Specification UNIT QTY RATE

1 EARTH WORK
a. Earth work excavation up to 6' depth Cft 2,565.00 3.25

b. digging of bore holes for soil stabilization Rft 480.00 10.00

2 FILLING
a. Supplying and filling with rier sand Cft 7,423.80 9.00

b. ffilling bore holes with lime and sand mix 2 : 1 Sft 254.34 23.00

3 Plain Cement Concrete (pcc)


a. PCCC 1: 4: 8 with 40mm ( 1 1/2" down graded metal) Cft 78,000.00 35.00

b. Sand lime bed in 2 : 1 Cft 189.92 27.00

4 RCC Works:- including reinforement and centering


a. Footings with RCC 1: 1 1/2 : 3 up to ground floor Cft 467.75 60.00

b. Columns in ground floor in 1 : 1 1/2 : 3 Cft 240.00 80.00

5 RCC work including reinforcement and centering


a. For Plinth beams in 1 : 2 : 4 Cft 327.94 85.00
b. For lintel beams in 1 : 2 : 4 Cft 30.19 85.00
c. for sunshade in 1: 2 : 4 Sq..ft 66.00 70.00
d. for beams in 1 : 2 : 4 Cft 357.75 85.00
e. For roof slabs in 1: 2 : 4 Sq.ft 1,377.42 70.00
f. For loft slabs in 1: 2 : 4 Sq.ft 106.00 70.00

6 BRICK WORK : with cement mortar 1 : 5 for 9" thick walls


in first class brick
a. Up to ground floor Cft 2,214.00 45.00

7 BRICK WORK:- with cement mortar 1 : 4 for 4 1/2" thick walls


in first class brick with 8mm rod at 4 layer intervel
a. In ground floor Sq.ft. 1,250.85 26.00

8 Flooring:-
a. Flooring with ceramic tiles in 1: 3 cement mortar 13404.00 Sq.ft 1,117.00 48.00

9 Plastering:-
a. 1 : 4 cement mortar 1m5mm thick for internal walls
and finished to smooth including scaffolding if necessary
Sq.ft 3,768.90 9.00

b. 1: 5 cement mortar 15mm thick for external walls


including scaffolding Sq.ft 2,568.04 9.00

c. 1: 3 cement mortar 12mm thick for ceiling including


scaffolding Sq.ft 1,333.50 10.00

10 Paintings
a. Painting all inner walls with 1 coat primer and 2 coat
cement paint Sq.ft 3,768.90 3.50

b. (a) painting all exterior walls with 1 coat primer and


2 coat exterior emulsion Sq.ft 2,610.03 8.00

c. (a) painting all ceilings with 1 coat primer and 2 coat


cement paint Sq.ft 1,333.50 1.50

11 Joinery: - (without polishing or painting)


a. Supplying and fixing of teak wood door in cluding door frame cft 2.92 2200.00

b. Supplying and fixing of padac wood door including frame Sq.ft 157.50 100.00

c. Supplying and fixing of padac wood window Sq.ft 115.50 120.00


d. Supplying and fixing of ventilators and A/C frame Sq.ft 21.00 100.00

12 Steel joinery
a. Supplying and fixing of MS flat grill work in windows Kg 346.50 38.00

13 Anti Termite
a. Providing and applying of GE silicon sealent around
perimeter of windows at 3 mm thick Sq.ft 1,218.06 3.00
TOTAL
14 Rates for plumbing and pipe line excluding fittings 15% of civil work

15 Rates for electrical work in laying of conduits and wiring


excluding switches and fittings 15% of civil work

FIRST FLOOR
Sl.No. Specification UNIT QTY RATE

1 RCC works:- including reinforement and centering


a. columns in first floor in 1: 1 1/2 : 3 Cft 125.00 85.00

2 RCC work including reinforcement and centering


a. for lintel beams in 1: 2 : 4 Cft 40.98 85.00
b. For sunshade in 1 : 2 : 4 Sq.ft 150.00 70.00
c. for beams in 1: 2 : 4 Cft 215.00 85.00
d. For roof slabs in 1 : 2 : 4 Sq.ft 1,125.00 70.00
e. for loft slabs in 1 : 2 : 4 Sq.ft 101.00 70.00

3 Brick work:- with cement mortar 1: 5 for 9" thick walls in


first class brick
a. First floor to 2 nd floor Cft 1,350.00 48.00

4 Brick work: with cement mortar 1:4 for 4 1/2" thick walls in
first class brick, with 8mm rod at 4 layer intervel
a. In first floor Sq.ft 1,325.00 27.00

5 Flooring:-
a. flooring with marble slabs using 1:3 cement mortar and
pointing with white cement Sq.ft 1,012.00 115.00

6 Plastering
a. 1 : 4 cement mortar 20mm thick for internal walls and
finished to smootoh including scaffolding if necessary Sq.ft 1,655.00 9.00

b. 1:5 cement mortar 20mm thick for external walls including


scaffolding Sq.ft. 1,690.00 9.00

c. 1 : 3 cement mortar 12mm thick for ceiling including


scaffolding Sq.ft. 1,482.03 10.00

7 Paintings
a. Painting all inner walls with acrylic silk putty and
interior emulsion Sq.ft. 1,325.00 8.00
b. (a) painting all exterior walls with 3 coat exterior emulsion Sq.ft. 1,465.00 8.00
c (a) painting all ceiling with 1 coat primer and 2 coat cement
Paintings Sq.ft. 1,124.00 1.50

8 Weathering Course
Pressed clay tile in 1:3 mix glove oil 5% by weight of cement
over 125mm layer of BJC lime concrete composed of 1 cum of
pure slaked lime of 25mm with 45 angle finish slope (6" to 4")( Sq.ft. 1,012.00 25.00

9 Plaster bands:-
a. Running of plaster band of 3/4" projection and 3" wide all
around the exterior in 1:3 mix Rft 750.00 8.00

b. running of 25mm wide and 5mm thick grooves in 1:3 MIX Rft 650.00 6.00

10 Tiles
a. Supplying and laying of mangalore tile for sloped roof
in 1: 3 mix Sq.ft 215.00 25.00

11 Joinery (without polishing or painting


a. Supplying and fixing of teak wood door including door frame cft 2.92 2200.00

b. Supplying and fixing of padac wood door inclduing frame Sq.ft 165.50 100.00

c. Supplying and fixing of padac wood window Sq.ft 165.00 120.00

d. Supplying and fixing of ventilators and A/C frames Sq.ft 145.00 100.00

12 Steel Joinery
a. Supplying and fixing of MS flat grill work in windows Kg 147.00 38.00

13 providing overhead tank of 11431 litres capacity with 9" outer


wall in 1 : 3 plaster ltrs 8,950.00 3.50

14 providing of sump of capacity 12000 litres capacity with rcc


walls being water prooofing (including excavation rate) ltrs 8,750.00 3.50

15 providing of septic tank in RCC for a capacity of 10000 litres


without choke pit. Including excavation rate ltrs 8,755.00 3.50

16 Laying of paving bloocks in car parking area mention rate in


required slope Sq.ft 145.00 35.00

17 providing of compound wall in 9" brick wall with plinth beam and
piles at regul;ar intervel including plastering and painting in
supercem Rft 20.25 120.00

18 providing and fixing of steel gate Sq.ft 75.00 38.00

19 Rates for plumbing and pipe line excluding fittings 10% of civil work

20 Rates for electrical work in laying of conduits and wiring 10% of civil work
excluding switches and fittings
AMOUNT

8,336.25

4,800.00

66,814.20

5,849.82

2,730,000.00

5,127.84

28,065.00

19,200.00

27,874.90
2,566.15
4,620.00
30,408.75
96,419.40
7,420.00

99,630.00

32,522.10

53,616.00
33,920.10

23,112.32

13,335.00

13,191.15

20,880.20

2,000.25

6,413.00

15,750.00

13,860.00
2,100.00

13,167.00

3,654.18
3,384,653.61
102,293.44

102,293.44
3,589,240.49

AMOUNT

10,625.00

3,483.30
10,500.00
18,275.00
78,750.00
7,070.00

64,800.00

35,775.00

116,380.00

14,895.00

15,210.00

14,820.25

10,600.00
11,720.00

1,686.00

25,300.00

6,000.00

3,900.00

5,375.00
6,413.00

16,550.00

19,800.00

14,500.00

5,586.00

31,325.00

30,625.00

30,642.50

5,075.00

2,430.00

2,850.00
620,961.05

62,096.11

62,096.11
745,153.26