Can Tho Bridge Vietnam

Post-tensioning for Vietnams longest-spanning cable-stayed bridge

Can Tho Bridge crosses the River Hau and is seen here from the Vinh Long bank.

With a 550m main span, Can Tho over the final river-based hurdle to
Bridge is the longest-spanning cable link the region with the southern
stayed bridge in Vietnam and capital, Ho Chi Minh City.
indeed the whole of South-East Asia.
The bridge over the River Hau is part Previously, 13 ferries had to be used
of a project including approach roads to carry 60,000 motorcycles, 8,000
and smaller bridges that carries the vehicles and 80,000 people every
four-lane National Highway No 1 day between the banks of the River
Hau, which is the largest tributary of
the Mekong River. Opening of the
Scope of works performed bridge to traffic has reduced travel
times by an estimated 30 minutes,
Design and fabrication of two thus dramatically improving traffic
form traveller pairs flows to the southern provinces.
Segmental construction of the
reinforced concrete main bridge Vietnams Prime Minister Nguyen
girder including the bearings and Tan Dung officially opened the
pier tables bridge on 24th April, praising it as a
Supply of PT anchorages significant catalyst for socio-
Rental of PT equipment economic development in the Cuu
ID 1897

Long (Mekong) delta region. The form traveller pairs were


Supply of PT ducting designed and fabricated by VSL.
VSL had been appointed by TKN OWNER
Joint Operation - a joint venture of My Tuan Project Management Unit
Taisei, Kajima and Nippon Steel - to
design and fabricate two form ENGINEER
traveller pairs and construct the Nippon Koei-Chodai
two 30m-long concrete pier tables
together with a total of 140 concrete MAIN CONTRACTOR
segments for the main girder, Taisei Kajima Nippon Steel Joint
working from the two pylons. The Operation (TKN)
box girder comprised a four-cell box
section with a width of 26m and VSL ENTITY
maximum depth of 2.7m. Each VSL Vietnam Limited
segment was 4m in length with a
volume of 80m 3 of concrete. The 8m VSL COMPLETION DATE
spacing between stays along the 27th June 2009
entire length of the girder required
the installation of guide
Stressing of post-tensioning bar

Casting of a side span closure segment


This was achieved while maintaining
high quality standards.

There was good coordination with


the main contractor in constructing
the concrete-steel interfaces of the
mid-span steel girder. Work involved
the construction of tapered approach
segments incorporating curved
stress bars and longitudinal post-
tensioning. This was followed by the
lifting and alignment of the first steel
segments on each side together with
associated concrete stitch and
stressing work carried out from
inside the steel box sections.

Off-site work on the form travellers


Tandem lowering of the bottom form pipes and blisters in every second began in October 2006, while on-site
of a form traveller work to the main girder started in
segment.
Diaphragms were constructed at December 2006. All VSL segment
each stay set using 12m 3 of concrete works were substantially complete by
following the main segment casting. 27th June 2009, following which the
main contractor launched and
A longitudinal system of CT stress secured the steel segments forming
bars ran the full length of the the 220m mid-span section of the
concrete girder and was made main girder. All road furnishings and
continuous by the use of staggered other finishing works required for the
connections. Post-tensioning was main girder and the approach
also installed transversely in the top bridges were also carried out and the
slab, in the diaphragms and full scope of the work package was
Finishing works to a 4m-long segment
longitudinally for continuity at pier completed in February 2010.
tables and connections with side
spans and the first steel girder
sections of the mid-span. VSL
installed a total of 160t of CT bar and
230t of strands in the structure.

Production levels achieved by VSL


exceeded expectations with cycle
times as little as 12 days for a pair of