Documente Academic
Documente Profesional
Documente Cultură
ABSTRACT
A paper called Global Experience with Soft Ground and Weak Rock Tunneling under Very High
Groundwater Heads was presented at the North American Tunneling 2006 conference (Holzhuser et.al
2006). It summarized global experience with earth pressure balance (EPB) and slurry shield tunneling on
nine projects that encountered groundwater heads ranging from 6 to 11 bar. Since then, additional
projects have been completed with groundwater heads ranging from 7 to 15 bar. Of these, the high
pressure tunneling experience on the Lake Mead Intake No. 3 project in Nevada and on the Eurasia
Tunnel (Istanbul Strait Crossing) had the greatest lengths of tunneling at face pressure over 7 bar.
Experience with sustained pressurized face tunneling at groundwater heads over 7 bar and risk
management observations are the focus of this paper.
INTRODUCTION
High groundwater head, particularly at 7 bar or more, is a major challenge when tunnelling in high
permeability ground and on drives long enough to require cutter changes. It has a strong impact on
design and operation of Tunnel Boring Machines (TBMs) in order to protect the main bearing from
contamination, prevent excessive groundwater inflow, ensure face stability and enable access to the
cutterhead and excavation chamber for maintenance.
During the past 20 years, TBM manufacturers and suppliers have made tremendous improvements
that allow tunneling at groundwater pressures to 17 bar or more. The most significant risk with high
pressure tunneling is generally that of excavation chamber access and potentially the cutterhead for
cutter changes, cutterhead repairs and TBM maintenance.
Hyperbaric interventions are possible and safety variances have been approved for saturation dive
interventions at pressures as high as 17 bar (Lake Mead Intake No. 3). While high pressure hyperbaric
intervention equipment is available and safety approvals can be obtained at many locations, few
contractors consider the cost and risk of hyperbaric interventions over 7 bar to be acceptable as the
primary means of excavation chamber access.
Experience with high pressure tunneling prior to 2006 was summarized in a paper entitled Global
Experience with Soft Ground and Weak Rock Tunneling under Very High Groundwater Heads
(Holzhuser et.al 2006). That paper provided information on 9 projects: South Bay Ocean Outfall, San
Diego; Channel Tunnel (French Side), France; Storebaelt Tunnel, Denmark; 4th Elbe Tunnel, Germany;
Wesertunnel, Germany; Westerschelde Tunnel, Netherlands; St. Petersburg Red Line, Russia; Nara
Prefecture Water Conveyance Tunnel, Japan; and Tokyo Wan Aqua Line Tunnel, Japan see Table 1.
1
Table 1. Summary of data from selected projects with high pressure tunneling and interventions (modified from Holzhuser et.al 2006)
2
Since then, over 15 projects have had TBMs designed to allow tunneling at groundwater pressures
at 7 bar or more including: Brightwater Central BT3, Seattle (8 bar); Brightwater Central BT3C, Seattle
(7.3 bar); Arrowhead Tunnels, California (22 bar standstill, <5 bar tunneling); Shanghai, China (7 bar);
Nanjing, China (7 bar); Lee Tunnel, London (8 bar); Hallandsas, Sweden (13 bar); Katzenberg Tunnel,
Germany (9 bar); Croydon Cable Tunnel, London (8 bar); Alaskan Way, Seattle (7 bar EPB tunneling, 10
bar emergency); Melen 7 Bosporus Crossing Tunnel, Turkey (13.5 bar standstill, 4 bar EPB); LMI- 3,
Nevada (17 bar); and Eurasia Tunnel -Istanbul Strait Crossing, Turkey (12 bar). Anagnostou 2014
provides a discussion of risks and tunneling for several of these projects.
Of the more recent projects, two tunnel projects had the longest lengths bored at face pressures of
7 bar or more: Lake Mead Intake No. 3 having ~ 2310 m or 52 percent of the total tunnel; and Eurasia
Tunnel having ~2300 m or 69 percent of the total. Data and experience with pressurized face tunneling
on these projects are also summarized in Table 1 and are discussed in more detail below.
3
Figure 1. Lake Mead Intake No. 3 alignment alternatives considered (MW-Hill TM-4)
4
phase decision to locate the tunnel along Alignment 3 to reduce tunneling and intervention risks was
compromised by the corridor option and resulting starter tunnel inundations, abandonment and
realignment.
5
Figure 3. Geologic profile along actual alignment, TBM mode and excavation chamber pressure
After advancing the TBM to Ring 234 or Station 18+65 ft, a distance of 430m without cutter changes,
TBM parameters indicated a significant cutter wear and need to inspect and change worn cutters
(Nickerson et.al 2015a and 2015b). The face pressure was reduced to assess if a free air intervention
was possible, but indicated potential inflows of over 2000 m3/h (500 l/s or 8800 gpm). VTC elected to
complete a cutter change intervention after grouting from the TBM rather than by a saturation diving
intervention. This decision was partly due to a helium shortage resulting in an inadequate supply of tri-
mix gas, but was mostly due to saturation dive risk concerns. The highest pressure saturation dive
intervention to date (2012) had been 8 bar on the Westerschelde Tunnel in Germany (Holzhuser et.al
2006). The potential health and safety impacts a full 14 bar intervention were considerable. The risks of
trapping workers in the excavation chamber if a blow-in or face instability occurred during a partial
pressure intervention were considered unacceptable (Nickerson et.al 2015a and 2015b).
An extensive grouting campaign was implemented to reduce heading inflows to a manageable level
- Nickerson et.al 2014 and in Nickerson et.al 2015a and 2015b. After 4-1/2 months of grouting and two
TBM advances into the grouted zone, the heading inflows at free air were reduced temporarily to 220
m3/h (61 l/s or 965 gpm) - a reduction of about 90 percent. TBM slurry line repairs and perimeter cutter
changes were initiated, but heading inflows progressively increased during the first two days to over 450
m3/h (125 l/s or 2,000 gpm). After 14 additional days of similar high inflows, a partial face collapse
occurred and cutter changes were stopped before the center cutters had been changed. The high
seepage pressures from 14 bar of head had caused progressive erosion of fines and grout in rock joints
resulting in a very high hydraulic gradient near the cutterhead and eventually face instability. High
seepage pressures associated with high groundwater heads makes grouting to complete a free air
6
intervention less reliable than if the same grouting effort were completed at lower hydrostatic pressure.
This risk should be recognized when planning and managing grouted ground interventions at high heads.
VTC pressurized the face back to nearly 14 bar then advanced the TBM out of the unstable grouted
zone. Soon they found metal fragments at the separation plant an indication that the center cutters
were breaking. Fortunately, a heading pump test found an isolated zone of lower permeability rock that
allowed atmospheric access at inflows of about 950 m3/h (~264 l/s or 4180 gpm). VTC proceeded with
an atmospheric intervention without grouting. Within two days the inflow rates had increased to
approximately 1000 m3/h (278 l/s or 4400 gpm) and ranged from that value to 1090 m3/h (303 l/s or
4800 gpm). After access was achieved and inspections completed, severe abrasion damage was found at
the center cutters, center cutter housings and portions of adjacent cutterhead (Nickerson et.al 2015a
and 2015b). A repair cavern had to be mined and the high inflows channeled around it. Fortunately, the
face remained stable for the 47 days required to finish repair the cutters, housings and cutterhead.
In summary, the decision to grout and complete a free air intervention took 222 days (32 weeks) to
complete during which the TBM had advanced only 35m (114 ft). In high permeability, high head
ground, grouting to complete a free air excavation chamber intervention for cutter and cutterhead
repairs is often an expensive and time-consuming operation that should be compared to the cost and
risks for both hyperbaric interventions and surface grouted safe zones that the TBM could bore into.
High pressure tunneling continued through the Upper Plate rocks until June 17, 2013 when the TBM
had finally bored into the Tertiary Muddy Creek formation. After mining about 15m into the low
permeability Muddy Creek, open mode tunneling was initiated (Figure 3). Generally stable face
conditions and low inflows of 10-35 m3/h (3-10 l/s or 44-154 gpm) were encountered during open mode
tunneling in the Muddy Creek. The contractor found that when heading inflows exceeded about 23 m3/h
(6 l/s or 100 gpm) muck spillage at the screw conveyor discharge onto the belt conveyor created an
excessive mess and unsafe work conditions. When these conditions developed, they generally switched
back to slurry shield tunneling at low face pressure (Figure 3).
High pressure tunneling was resumed around Station 80+70 (ring 1247) as a precaution for
tunneling below the Las Vegas Wash. High pressure tunneling was continued until around Station
136+88 (ring 2204) on October 21, 2014 before resuming open mode tunneling. High pressure slurry
tunneling was resumed on October 30, 2014 at Station 142+56 (ring 2298) due to decreasing cover and
proximity to the Callville basalt formation (Figure 3).
High pressure tunneling (around 7-9 bar or 1-2 bar below lake pressure) resumed until the tremie
concrete surrounding the Intake Structure was encountered. The TBM proceeded into the tremie
concrete with a cover of only 3.7 m (12 ft) at full lake pressure (8.8 bar). Breakthrough into the flooded
Intake Structure successfully occurred on December 10, 2014 (Nickerson et.al 2015a and 2015b).
None of the many, but generally small fault zones encountered from entry into the Muddy Creek
formation through breakthrough into the Intake Structure presented any problems for TBM advance.
These faults had no influence on tunneling except where the fault zone and adjacent rock had high
enough permeability to cause excessively sloppy conditions within the TBM when advancing in open
mode resulting in a need to convert to slurry mix-shield mode.
In summary, 2310 m or 52 percent of the Lake Mead Intake No. 3 intake tunnel was bored at face
pressures of 7 bar or more. Approximately 1300 m or 30% of the tunnel was bored at face pressures of
12 bar or more, which was a world record. The intake tunnel was successfully completed through
extremely faulted, very poor quality, faulted Precambrian hard rock under 14 bar of hydrostatic pressure
7
and through lower permeability, weak sedimentary rock having buried ridges of volcanics and
Precambrian rock.
EURASIA TUNNEL
Tunnel and TBM
Eurasia Tunnel consisted of a 3,340 m long bore using a 13.66 m outside diameter Herrenknecht slurry
mixshield TBM see data summary in Table 1. Precast concrete segmental rings with a 12.0 m ID were
installed for the lining (Clark et.al 2015 and Zlatanic et.al 2015). The tunnel was bored below the
Istanbul Strait in Turkey at maximum depth of 106 m below the sea Figures 4-5. The tunnel was
advanced through inter-layered siltstones/mudstones and sandstones of the Trakya Formation and a
zone of soft ground soils.
8
The TBM was designed for maximum face (excavation chamber) pressure of 12 bar (Bappler 2012).
Actual measured faced pressures ranged from 3 to 10.8 bar Figure 5 (Burger 2015). Approximately
2300 m or 69 percent of the drive was completed at face pressure over 7 bar.
The TBM cutterhead had six man accessible spokes with and special lock systems to allow disc cutter
changes under atmospheric conditions (Bappler 2012). The spoke access allowed the 19-inch disc
cutters to be changed without hyperbaric interventions or grouting. In addition the TBM was equipped
with a disc cutter rotation monitoring system (DCRM) to determine when disc cutters needed changing.
In addition, wear detector bars were placed on the cutterhead. This combination of cutter and
cutterhead wear monitoring with atmospheric access for cutter changes helped to keep the cutterhead
in good condition and avoid the center cutter, cutter housing and cutterhead wear problem experienced
on Lake Mead Intake No. 3. While spoke access solved the disc cutter intervention challenge, it did not
preclude the need for saturation dive interventions for scraper cutter changes and other excavation
chamber maintenance work.
9
quality faulted rock conditions were handled by the TBMs without serious impacts such as face collapse,
squeezing and stuck advances.
TBM manufacturers have developed equipment that can handle very high pressures, however this
equipment requires maintenance and repairs when components wear or break. The biggest challenges
for tunneling in poor quality, high head ground do not appear to be TBM advance, but instead how to
create suitable, safe conditions for access to the excavation chamber and cutterhead for maintenance
and repairs.
Options for facilitating access to the excavation chamber and cutterhead include:
Hyperbaric interventions with compressed air up to 4 or 4.5 bar and mixed gas saturation diving
at higher pressures.
Spoke cutter access for larger TBMs (>12-13 m diameter) this only provides disc cutter change
access and does not provide access to change other cutters and complete maintenance work.
Grouting from the TBM heading to create a lower permeability zone suitable to reduce inflows
to a manageable, safe level.
Pre-excavation grouting from the surface to create a lower permeability safe zones.
Closer spaced, more thorough subsurface investigations (borings and water pressure tests) to
identify suitable natural or more readily grouted safe zones for interventions.
Saturation dive interventions can be very expensive and risky. North American contractors are
generally more reluctant than global contractors to utilize hyperbaric interventions as the primary
method of access. Even if not used as the primary means for interventions, hyperbaric intervention
capability should still be required for backup.
Grouting is an option to consider for primary access, but grouting is often unreliable and can be very
expensive, particularly from a TBM. The uncertainties of grouting effectiveness must be managed.
Based on the experience to date, more funding and effort should be given to more extensive
subsurface exploration programs that are designed to find and characterize natural low permeability
safe zones for potential interventions. More extensive subsurface investigation programs may save
considerable expense during tunneling from use of hyperbaric or grouted interventions.
REFERENCES
Anagnostou, G. 2014. Some Critical Aspects of Subaqueous Tunnelling. Muir Wood Lecture 2014. ITA-
AITES, 20p.
Anon. 2012. Eurasia Tunnel, The most advanced transportation infrastructure connecting the
continents. Republic of Turkey. 9p
Bppler, K. 2014. Constant Demand on Very Large Tunnel Boring Machine Diameters for the
Construction of Todays Infrastructure Systems. In: Proceedings of 2014 North American Tunneling
Conference. SME, Littleton, Colorado, USA. N2014.19. 160-165.
Burger, W. 2015. Chamber Interventions and High Pressure TBM Operation, In: Ozdemir (ed.)
Presentations and Proceedings of 2015 Tunneling Short Course, September 14-17, 2015, Colorado
School of Mines. 27p.
Carl, V. 2015. Istanbul Strait Road Tube Crossing Project S-762, Hyperbaric Work - Project Report,
Nordseetaucher GmbH. 7p.
10
Clark, G., Castelli, R., Richards, D., Toan, T., Arolu, B. & Gnen, O. 2015. Elements of the Istanbul
Strait Highway Tunnel. In: Proceedings of 2015 Rapid Excavation and Tunneling Conference. SME,
Littleton, Colorado, USA. R2015.19. 223-239.
Holzhuser, J., Hunt, S. W., Mayer, C. 2006. Global Experience with Soft Ground and Weak Rock
Tunneling under Very High Groundwater Heads. In: Ozdemir (ed.), North American Tunneling 2014,
Taylor & Francis Group, London. 277-289.
Hunt, S.W., Smith, E. & Moonin, E. 2015. Characterizing and Baselining Faults for Tunneling. In
Proceedings of 2015 Rapid Excavation and Tunneling Conference, SME, R2015.49. 600-615.
McDonald, J. & Burger, W. 2009. Lake Mead TBM designed for the extreme, Tunnel Talk, Nov 2009, 3p.
McDonald, J.A., Hurt, J. & Moonin, E. 2010. Lake Mead Intake No. 3. In Proceedings of 2010 World
Tunnelling Congress, ITA, W2010.54. 8p.
Nickerson, J., Ceccato, R., Bono, R., Cimiotti, C. & Fioravanti, P. 2014, Lake Mead - Intake Tunnel No. 3,
Pre-excavation grouting challenges using a high pressure slurry TBM. Geotechnical News, September
2014, 32-38.
Nickerson J., Bono, R., Cimiotti C. & Moonin E. 2015a. Lake Mead Intake No. 3 - TBM Tunneling at high
pressures. In Proceedings of 2015 World Tunnelling Congress, ITA, Session 4.36, W2015.233. 12p.
Nickerson J., Bono, R., Cimiotti C. & Moonin E. 2015b. Lake Mead Intake No. 3TBM Tunneling at High
Pressures; In Proceedings of 2015 Rapid Excavation and Tunneling Conference, SME, R2015.77. 936-
946.
Wallis, S. 2015 Bosphorus Eurasia highway TBM breaks through, TunnelTalk, 22 Aug 2015. 3p.
Zlatanic, S., Ozturk, M. & Munfah, N. 2015. Istanbul Strait Road Tube Crossing Project Uses Good
Practices to Manage Risks. In: World Tunnelling Congress 2015. ITA, No. 1.60, W2015.60. 19p.
11