As there are a number of items to talk about in this topic and I have discussed most of them
before, I will introduce most items in the form of a question and then immediately give the
answer.
The Project Manager does most of their reviewing progress in the Controlling a Stage
process.
During the stage, the Project Manager will hand out work in Work Packages to Team
Managers or directly to the Team Members in the case of a small project. What two
management products do you think the Project Manager uses as input to check on how well
the Work Packages are progressing and, therefore, to see how the stage is progressing?
They use the Checkpoint Reports, which come from the Team Manager or team members,
and they use the Quality Register to see that intended Quality responsible persons have
As you can now see, the Quality Register acts an important extra check for the Project
Manager, as perhaps the Team Manager was not 100% open in the Checkpoint Reports.
Question: Which Management Products does the Project Manager use to keep track of how
the project is doing (e.g., where do they keep informal notes, issues, check on product
The Project Manager uses the Daily Log, Issue Register, Product Status Account, Quality
Question: What do you think the Project Manager uses the Daily Log for?
This is the place to record any informal information about the project (e.g., news, telephone
calls, meetings, small issues, reminders, observations, tolerance levels and other such
information.) The Daily Log is similar to a Daily Journal for the Project Manager.
Question: What does the Project Manager use the Issues Register for?
The Issues Register contains all formal issues raised during the project, which could be:
Request for Change: This happens when the clients notice something that was not in the
original requirement but now wants this included (so it becomes a Request for Change)
Off-Specification: This happens when the supplier may not be able to complete something
Problems and Concerns: This is the place to note any other comments, problems and
concerns (for example, there is train strike on the same day as our expected demonstration
for the major stakeholders, or the cost of a major component we need for the project has
Question: What does the Project Manager use the Product Status Account for?
At certain times during the project the Project Manager will want to check that all products
created so far in the project (1) are in the right place, (2) are the correct version, (3) have the
correct identification codes attached, (4) are distributed correctly, (5) have the correct status,
and so on
Let me give an example to explain how important this is. Consider that you are organizing an
event and send out a communication 20 days beforehand that the location has changed to a
new conference center due to the demand. But you are using an older registration list and
Product Status Accounting could also show that some products have not been updated
according to the plan. For example, one product was supposed to be approved 2 weeks
earlier but has still not been approved. Product Status Accounting makes sure that the right
products are in the right place and that the products are in line with the Project Plan.
Question: What does the Project Manager use the Quality Register for?
The Quality Register is a record of all planned and executed Quality activities. Therefore the
Project Manager can see if all planned Quality activities are in line with the plan and if results
What does the Project Manager use the Risk Register for?
The Risk Register is a record of all identified risks and the Project Manager should review it
as part of the Reviewing a Stage status in Controlling a Stage. Risk levels can change during
the project. The Project Manager therefore needs to be vigilant during the project as far as
Risk is concerned.
One of the principles in PRINCE2 is that the project team learns from experience. Lessons
have to be sought, recorded and actioned during the project. PRINCE2 uses the word
sought to ensure that everyone in the project checks for previous lessons. Any useful
experiences are then recorded into a Lessons Log. Lessons can be about anything that
These include how best to communicate, how to deal with a supplier, how certain documents
should be tailored for this kind of project and which product specialists to get help from when
doing the product breakdown structure. The Project Manager continues to add new lessons
The Lessons Learned report is used to document lessons that might be of value to future
projects. If a lesson is of value only to the current project, then it should not be included in
the Lessons Learned report. A Lessons Learned report has to be created at the end of the
project during the Closing a Project Process. In larger projects, a Lessons Learned report
might be created during the project, for example, during the Managing a Stage Boundary
Process.
PRINCE2 Reports used to Report Progress
What report does the Team Manager use to report to the Project Manager and when is the
frequency decided?
The Team Manager uses the Checkpoint Report to report to the Project Manager.
Information on the progress of the work done compared to the agreed Team Plan is also
included in it.
The Project Manager will agree on the frequency for these reports with the Team Manager
What 3 reports are used by the Project Manager to report to the Project Board and when is
1. Highlight Report
The Highlight Report is used by the Project Manager to report on the status of the current
stage compared to the Stage Plan. The important word here is highlight as a 1- to 2-page
The Highlight Report allows the Project Board to manage by exception between each stage
end, as they are aware of the tolerances agreed with the Project Manager in the Stage Plan,
so the Highlight Report should report the current status of tolerances of Time, Cost, Quality,
Strategy and this can be updated during the Managing a Stage Boundary Process.
The End Stage Report is created by the Project Manager towards the end of the stage and
The End Project Report is produced by the Project Manager towards the end of the project
during the Closing a Project Process and is used by the Project Board to evaluate the project
This is quite easy to understand and you will see that it is linked to the principle Manage by
Exception. The best way to explain this is with a question, i.e., When is an exception raised
and by whom?
An exception is raised when an agreed tolerance is exceeded or is forecast to be. You raise
The Work Package tolerances are agreed between the Team Manager and the Project
Manager when the Team Manager accepts the Work Package. If the Team Manager
exceeds or has been forecast to exceed a tolerance, then they raise an issue (not an
exception).
They just tell the Project Manager, and the Project Manager enters the issue in the Issues
Register and starts to create an Issue Report if the issue needs to be handled formally. The
Stage Tolerances are agreed between the Project Board and Project Manager. If the stage is
forecast to go out of tolerance, then the Project Manager creates an Exception Report to
capture and analyze why, and then to provide this information to the Project Board.
The Exception Report can include a number of options with usually one recommend option.
Project Tolerances are set between the Corporate or Program Management and Project
Board. If project tolerances are forecast to be exceeded, then the Project Board will advise
the Corporate or Program Management and can provide an Exception Plan to show how the
They make decisions on the Exception Plan when Project Tolerances are forecast to be
What are the responsibilities of the Senior User and Senior Supplier?
Ensuring that progress remains consistent from a user and supplier point of view
Producing Highlight Reports, End Stage Reports, Lessons Learned reports & End Project
Reports
Producing Exception Reports for the Project Board when the stage-level tolerances are
forecast to be exceeded
Notifying the Project Manager of any forecast deviation from the Work Package tolerances.
Verifying the Business Case against external events and project progress
Confirming stage and project progress against agreed tolerances in case the Project
Maintaining the Quality Register on behalf of the Project Manager. (Check that everything is