Guarantee Technical Parameters

Sr.N
Performance Parameter Test Method
o.
GTP Approval will be as per MSEDCL/MSETCL
Standards.
Following Items are included
i)ACSS 0.4 Zebra HTLS Conductor
ii)Columns and Structure
Approved GTP
iii) Suspension Type Polymeric Insulator
1 Document from
iv)60+3M D/C Tower
MSETCL
v)Earthing Pit Material
vi) Clamps and Connector
vii) Earth Wire
viii) Bus Post Insulator
ix) 0.2 ACSR Zebra Conductor
Approved List of
Material Supply should be from
2 Vendors from
MSETCL/MSEDCL Approved Vendor Only
MSETCL/MSEDCL
Test Certificates from
All Material Shall Comply with Valid Test MSETCL/MSEDCL
3
Certificates and Manuals. Approved Testing
Centers
Test must be conducted as per As per Norms guided
4
MSETCL/MSECL Test Standards by MSETCL/MSEDCL
Inspection report to be submitted prior to
5 -
Dispatch.
Successful Charging & Commissioning of
6 -
Equipment
Performance Guarantee parameters for LD Clause
Sr.N L/D
Performance Parameter Clause
o. Weightage
GTP Approval will be as per
MSEDCL/MSETCL Standards.
Following Items are included
i)ACSS 0.4 Zebra HTLS
Conductor LD will be applicable, if
ii)Columns and Structure supplier fails to produce
1 25 %
iii) Suspension Type Polymeric Approval GTP as per PG
Insulator Parameters
iv)60+3M D/C Tower
v)Earthing Pit Material
vi) Clamps and Connector
vii) Earth Wire
LD will be applicable, if
Material Supply should be
supplier fails to produce
2 from MSETCL/MSEDCL 25 %
Approval as per PG
Approved Vendor Only
Parameters
LD will be applicable, if
All Material Shall Comply with
supplier fails to produce
3 Valid Test Certificates and 20 %
Approval GTP as per PG
Manuals.
Parameters
LD will be applicable, if
Test must be conducted as per supplier fails to produce
4 15 %
MSETCL/MSECL Test Standards Test Certificates as per
PG Parameters
LD will be applicable, if
Inspection report to be supplier fails to produce
5 5%
submitted prior to Dispatch. Inspection report as per
PG Parameters
LD will be applicable, if
Successful Charging &
6 10 % issues arises during
Commissioning of Equipment
Charging Process.
Total
100 %
Remarks

1. The LD % will be decided at the time of Commercial Negotiation.


2. Percentage of LD mentioned in the above table means % of the
maximum LD for Non fulfillment of Guarantee Figures Fixed in the
Contract.
3. Penalty against rejection of any performance parameter will be decided
at the time of Commercial Negotiation.