Sunteți pe pagina 1din 15

Int J Adv Manuf Technol

DOI 10.1007/s00170-016-9306-9

ORIGINAL ARTICLE

Production process improvement of buildings prefabricated


steel frames using value stream mapping
Gholamreza Heravi 1 & Mohammad Firoozi 1

Received: 5 February 2016 / Accepted: 9 August 2016


# Springer-Verlag London 2016

Abstract The ultimate goal of lean philosophy is to eliminate Keywords Lean production . Production process . Value
or decrease wastes and deliver value to the customer. After stream mapping . Simulation . Prefabricated steel frames
successful implementation of lean principles to the
manufacturing sector, researchers have been trying to apply
lean principles to the construction sector. However, construc- 1 Introduction
tion is completely different from manufacturing. Prefabricated
and industrialized buildings bear a striking resemblance to Lean means getting the right thing to the right place, at the
manufacturing due to completing most processes in the facto- right time, and in the right quantity while minimizing waste
ry environment. This paper uses value stream mapping (VSM) and being flexible and open to change [1]. Waste is defined as
as a lean technique in the production phase of Pprefabricated any process step/activity that does not add value in the final
steel frames (PSFs) in a case study. The case includes con- product delivered to the end consumers [2]. Lean production
struction of three 16-story residential buildings made of PSFs principles include specifying the value by a product, identify-
with bolt and nut connections in Iran. The production process- ing the value stream, making the production flow, acting at the
es are investigated, and the current state of the production line pull of the customer, as well as pursing perfection [3]. In this
is examined. The VSM uses elaboration of maps to identify regard, lean production principles have been used in various
the current state of production, diagnose wastes and their root industrial sectors as one way of positioning operating efficien-
causes, and finally, propose improvements in the future state. cies toward leading value indicators of operational excellency
To investigate the productivity of the production line and im- [4]. The mentioned production principles are considered as an
plement lean principles, discrete event simulation (DES) was effective management tool since they focus on eliminating
carried out. After identifying and reducing some of the wastes wastes and delivering value to the customers. As a result, lean
in the current state, the future state was modeled. The results thinking concepts have gained a lot of attention in terms of
showed 34 % reduction in the lead time of production and identifying and removing waste [5].
16 % reduction of costs. These results support the hypothesis The process of delivering a constructed facility in construc-
that lean principles can be successfully applied to industrial- tion industry is similar to that of making a product in the
ized and prefabricated construction. manufacturing industry. The two industries have the same
goal of generating a product that meets the clients require-
ments within the shortest time and at the lowest cost [6].
However, the construction industry differs significantly from
* Gholamreza Heravi manufacturing in three aspects namely onsite production, one
heravi@ut.ac.ir
of a kind projects and complexity [7]. In this regard, applying
Mohammad Firoozi
lean principles to construction is difficult even with respect to
mohfiroozi@ut.ac.ir modified lean principles since the lean journey started in the
production line of an automobile company. But, lean princi-
1
School of Civil Engineering, College of Engineering, University of ples can be applied more easily to industrialized and
Tehran, 16 Azar Ave, P.O. Box: 11155-4563, Tehran, Iran prefabricated buildings (i.e., using modularity in
Int J Adv Manuf Technol

construction), since they consist of sections manufactured and sales changes were responded rapidly. By restructuring
offsite in production lines. work packages, the number of handovers was reduced and
The use of modularity in the specific industry of construc- total lead time was further decreased to 50 % of that of the
tion can be traced back to wooden houses in Northern Europe. current state.
However, the real turning point seems to have originated in Sing et al. [13] reviewed and classified literature on VSM
Japan [8]. To provide fast and affordable housing, construc- in four categories of conceptual work, empirical/modeling
tion of industrialized and prefabricated home-building pro- work, case studies, and survey articles. In their study, they
jects have been high on the agenda in the developing country applied the VSM in a small manufacturing Indian industry
of Iran in recent years. In this research, the production line of to reduce lead time, processing time, work in process inven-
PSFs, as a widely used modular and prefabrication method, is tory, and manpower requirement at individual stations. Yu
examined. The reason for choosing steel frames is that they et al. [14] examined one of the leading industrialized building
are frequently used in prefabricated building projects in Iran manufacturers in the USA for 6 months. Value stream map-
due to the fact that no other building systems can outweigh ping was implemented to the production line along with two
steel frames when it comes to economy, flexibility, and speed other lean techniques namely, standardized work and five S
of construction. Moreover, Firoozi and Heravi [9] indicated (sort, straighten, standardize, shine, and sustain). The applica-
that PSFs create more wastes compared with other prefabrica- tion resulted in improved labor efficiency by 10 %, reduction
tion methods used in Irans industrialized building projects of labor costs by 18 %, and increase in number of customer
like insulated concrete forms (ICF) or light cold-formed steel orders by 50 %. Tabanli and Ertay [15] used the VSM in the
frames (LSF). shop floor of an automotive supplier company and, as a part of
The purpose of this research is to examine the production the study, generated a current value stream map and a future
phase of PSFs and to improve the efficiency of the production value stream map, which contained the recommended revi-
line. To improve the efficiency, the VSM is implemented in sions for the company. To evaluate the return of the invest-
the production phase of the PSFs in a construction project. ment, they established performance metrics and made a
The project included three 16-story residential buildings made benefit-cost analysis. They gained better inventory manage-
of PSFs with bolt and nut connections in Iran. VSM is de- ment to reduce the inventory levels within the production
scribed as a technique used for the diagnosis, implementation, system.
and maintenance of a lean approach. Its main function is to Forno et al. [10] investigated the main difficulties and lim-
identify opportunities for improvement through elimination of itations encountered during the development of current state
waste [10]. To estimate the impact of the method implemen- maps, analyzed associated causes, and pointed out guidelines
tation, a discrete event simulation (DES) is employed. to facilitate the use of VSM to map processes. They criticized
Eventually, the results that highlight the reduction of costs some ways in which VSM has been used and claimed that this
and time of delivering the project are discussed. tool can lead to mistakes that can cause problems instead of
benefits. They asserted that the biggest difficulty is in under-
standing and classifying problems identified in the studies
2 Literature review researched, because they were not always clearly presented.
Their study suggested future works for improving the use of
Numerous papers have been published on application of VSM VSM for mapping processes. In a case study by Rosenbaum
in various domains including health care, food industry, fi- et al. [16], the VSM was implemented as a green-lean ap-
nance, manufacturing, software development, engineering, proach in the construction of a hospital to improve its envi-
and service industries [2]. But, there has been little research ronmental and production performance during the structural
studying the application of VSM in construction projects or concrete work stage. In this research, the current state indicat-
their related sectors. Pasqualini and Zawislak [11] applied the ed that only 33 % of the cycle times were value added. The
VSM to the masonry stage of construction projects in Brazil. researchers recommended some lean tools such as FIFO lane,
Their study resulted in reduction of 25 days in the total lead work standardization, and value stream synchronization to
time of the masonry which allowed decreasing of the final tackle root causes of wastes to reduce waiting times and in-
deadline of the project. Yu et al. [12] developed a lean model ventories. To decrease wastes of materials, a waste manage-
for house construction by VSM. The model presented four ment approach was recommended to recycle some wastes and
main features namely: synchronized first in/first out (FIFO) use other wastes in projects like soil stabilization, drainage
lane-based flow, production leveling at pacemaker, work construction, and backfilling.
restructuring, and improved operation reliability. Compared Andrade et al. [17] applied the concepts of VSM in an auto-
with the current state, the future state showed a considerable parts company in Sao Paulo. By mapping the current and
improvement in overall performance. With a stable product future states, they eliminated waste and reduced lead time.
flow, the capacity of each task was synchronized to Takt time Simulations were made using current and future states to
Int J Adv Manuf Technol

support the suggested improvements. The results showed that air and noise pollution at the construction site; and less
VSM combined with simulation is a good alternative in the residual stress in the structural elements.
decision-making for change in production processes. Atieh Unfortunately, not all advantages are achieved because of
et al. [5] implemented the VSM toward improving implementing traditional management approach in the indus-
manufacturing processes in a company in Jordan. They trialized buildings which results in several wastes in construc-
employed a DES model to accurately estimate the impact of tion processes. To eliminate the wastes, after visiting several
the method implementation. The results of the simulation was project sites, production line of a steel factory, and
then used to identify all the possible primary and secondary interviewing experts, 23 most common wastes were identi-
bottlenecks using multiple approaches such as utilization fied. Table 1 shows the identified wastes within the seven
method, waiting time method, and scenario-based method. categories defined by Ohno [20] namely: (1) overproduction,
An improving algorithm is then utilized to systematically sug- producing an item before it is needed; (2) waiting and idle
gest changes aiming to relieve the system and produce a better time; (3) transportation, excessive movement, and handling
manufacturing lead time and/or increase its throughput taking of an item; (4) inventory, excess inventory, increasing lead
into consideration feasibility. Helleno et al. [18] applied the time, and consuming floor space; (5) motion, unnecessary
VSM and DES as decision-making tools to direct the manage- movement of labor, materials, and equipment; (6) over pro-
ment investment in the best option among the available sce- cessing or unnecessary processing of an item; and (7) defects
narios in manufacturing cell part of a Brazils metal industry. or quality defects.
The results showed the efficiency of VSM and DES integra- To eliminate or at least decrease wastes in the pro-
tion as decision-making tools. duction line, VSM is widely used as a lean construction
technique. This technique graphically shows the pro-
cesses required to make a product, starting from deliv-
ery of raw materials to shipping finished goods to the
3 Implementing VSM on industrialized customer. Value stream mapping is the simple process
and prefabricated home building of directly observing the flows of information and ma-
terials as they now occur, summarizing them visually,
In general, two strategies including product and process ap- and then envisioning a future state with much better
proach have been used for industrialized construction. The performance [21]. The first step of the VSM is to define
product approach aims to decrease onsite construction ac- a particular product or product family as the target for
tivities by changing buildings into products. In other words, improvement. The following step is to develop current
the processes performed at the project site are reduced as few state VSM for the targeted process with the prospect of
as possible. On the other hand, the process approach focuses reaching an efficient version in the future to become
on applying a manufacturing management model to the cur- lean. In order to achieve this, the value that each activ-
rent construction processes. Simply put, a new management ity in the current state adds to the final product is de-
approach is applied to the existing construction processes termined. Then all non-value-added activities are re-
which consists of both onsite and offsite activities [14]. moved to determine the future state. This future state
Furthermore, the extent of industrialization is expected to rise map then becomes the basis for making the required
with the emergence of building information modeling (BIM), changes to the system [2].
advanced information technology (IT), and automation tech- The map of the current state is used to simply show how the
nology [19]. Thus, using industrialized and prefabricated production is currently operating. Its analysis, based on the
buildings as a product approach and at the same time applying lean principles, is what actually allows identifying wastes
lean principles to increase efficiency through repetition as a and proposing improvement actions for a production line
process approach are perfectly justified. which generates the shortest lead time, highest quality, and
One of the methods, used by many construction com- the lowest costs. The map of the future state is a drawing of
panies in industrialized and prefabricated buildings in an ideal state of production, the best way it could operate
Iran, is PSFs with bolt and nut connections. In this based on the current state analysis. The proposed improve-
method, after the design phase, columns and girders ments show where the wastes are and how they can be elim-
are fabricated in the factory, transported to the construc- inated or reduced.
tion site, and finally installed using bolt and nut or To draw the future state map, the following eight key ques-
sometimes welding connections. The advantages of this tions should be answered [22]:
method include, but are not limited to: faster fabrication
and installation; fewer defects due to high accuracy of & What is the Takt time (Takt time is how often one part or
fabrication; fewer wastes of materials, equipment, and product is produced, based on rate of sales to meet cus-
labor; less occupied space of the construction site; less tomer demands)?
Int J Adv Manuf Technol

Table 1 The identified wastes in


Irans prefabricated steel frame Main groups The identified wastes
projects
Overproduction Early production of elements (columns and girders) before use
Additional costs due to keeping the elements in the store
Idle funds due to keeping the elements in the store
Waiting and idle time Waiting for repairing the equipment
Waiting for the fabricated elements at the project site
Waiting for funds provided by the client
Waiting for approval of the new maps
Waiting for inspection of fabricated elements
Waiting for sending the fabricated elements to the project site
Transportation Unnecessary transportation of equipment
Unnecessary transportation of materials
Inventory Materials in excess of planned requirements
Elements undergoing inspection
Motion Unnecessary movements of equipment due to inappropriate site layout
Unnecessary movements of materials due to inappropriate site layout
Unnecessary movements of staff due to inappropriate site layout
Over processing Use of equipment with higher capacities than required
Use of materials with higher qualities than required (thicker plates)
Unnecessary processes leading to wastes of materials and equipment
(e.g., application of paints with greater thickness than required)
Defects Defects in fabrication due to errors in design
Defects in fabrication due to non-conformance with maps
Defects in cutting the plates and causing scrap
Defects and rework caused by changes in maps
Defects and accidents caused by ignoring safety measures

& Will finished goods be built to replenish a supermarket, or 4 Case study


will they be built and directly shipped to clients?
& Where can continuous flow of processes be utilized? Aransage Company is in charge of fabricating and erecting
& Is there a need for a supermarket pull system within the steel structures and metal deck floors of three buildings of a
value stream? residential complex consisted of 14 buildings in Tehran. Each
& What single point in the production chain will be used to building is 16 stories tall. The production line of the
schedule production? Companys steel factory included ten production processes
& How will the production be leveled at the pacemaker from supply of materials to hauling the fabricated elements
process? as follows: (1) supplying the steel plates; (2) cutting the steel
& What increment of work will be consistently released from plates; (3) drilling the plates for nuts and bolts; (4) initial
the pacemaker process (pitch)? assembly of the main plates and stiffeners; (5) submerged
& What process improvements will be needed? arc welding (SAW) of columns in three phases; (6) final
welding by metal active gas welding (MAG); (7) cleaning
Value stream mapping offers the following advantages [23]: the fabricated elements by shot blasting and sand blasting;
(8) welding the connections by metal active gas welding
& It forms the basis for lean production implementation; (MAG); (9) painting the elements (columns and girders);
& It relates the manufacturing process internal to the facility and (10) hauling the elements.
to the whole supply chain; Each buildings steel frame weighed approximately
& It displays both the product flow and the information flow; 1900 tons. The steel frames were erected in five stages and
& It links products planning and demand forecast to each stage consisted of almost three metal deck sheet floors.
production scheduling and to flow shop control; and After examining the shop drawings, 36 box-shaped columns
& It includes information related to production time and in- and 180 girders were considered. While the elements were
ventory levels. made of different sections, for simplicity, the sections shown
Int J Adv Manuf Technol

Table 2 Dimensions of structural elements of each stage Table 4 Percentage of accepted elements after inspection

Structural elements Dimensions of required Number of plates No Process Columns (%) Girders (%)
plates (mm)
1 Accepting the initial welding 80 90
Columns 30*2000*6000 72 2 Accepting the final welding 85 95
Column connections 20*2000*6000 36 3 Accepting the paint 90 97
Flanges of girders 20*2000*6000 45
Webs of girders 8*2000*6000 45
Girder connections 30*2000*6000 15
Although, Table 3 demonstrates the number of required
resources for every process, according to site visits and
interviewing experts in the production line, there were
in Table 2 are considered as the most frequently used sections 12 skillful workers, 12 common workers, 10 common
(the dimensions and number of steel plates required by every welders, 10 skillful welders, and 4 painters available
stage for each structural element are shown in Table 2). and allocated in the production line which calls for
The approximate weight of each column and girder were movement of these resources between stations. For ev-
considered 6.60 and 0.75 tons for each stage, respectively (the ery welder, a welding rectifier was provided. Thus, 20
total weight of the steel frames is about 1918 tons). rectifiers would be needed. Also, for submerged welding
It was assumed that the staff worked in a daily work shift of of columns, a submerged welding machine was needed.
8 h. The required human resources for each process are shown In total, three submerged welding machines, which
in Table 3. would be repaired after every 200 h, were considered
It should be noted that two kinds of skillful and for the case.
common workers and welders were considered to avoid The fabricated elements of some processes were inspected
excessive movements of the staff between processes. at the factory by the designers company. Some tests like

Table 3 The required human resources for each process

Process Common welder Skillful welder Common worker Skillful worker Painter

Cutting the major plates of columns 4


Initial assembly of columns 4 2 2
Modifying the welding of columns 2
Submerged arc welding of columns 2 2
Final welding of columns 3 2
Modifying the welding of columns 1
Cleaning the columns 3
Cutting the minor plates of columns (connections) 3
Welding columns connections 3 2
Painting columns 3
Modifying the paint of columns 1
Cutting the major plates of girders 4
Initial welding of girders 1 1
Modifying the welding of girders 1
Final welding of girders 1 1
Modifying the welding of girders 1
Cleaning the girders 1
Cutting the minor plates of girders (connections) 2
Welding girders connections 1 1
Painting girders 1
Modifying the paint of girders 1
Hauling the elements 2
Total 10 10 18 14 6
Int J Adv Manuf Technol

ultrasonic test, penetration test, and visual tests were conduct- & Daily production rate for girders: 180/60 = 3
ed. Table 4 shows the percentage of accepted elements after (girders per day)
inspection.
To calculate the lead time for every process, the number of
inventories should be divided by the daily production rate. In
4.1 The current state map reality, this cannot be true because the human resources are
moved between stations by the production manager whenever
The current state map of the processes to produce the steel possible to avoid being idle. If some processes are parallel, the
frames of one stage were developed using the data gathered greater lead time would be considered.
and the aforementioned assumptions. The current state map To investigate the productivity of the production line, com-
shows which processes produce the most inventories, the puter simulation was carried out by DES software Arena 13.5.
value-added time, as well as non-value-added time. In the shop floor simulation, different flows of discrete entities
According to the approved project scheduling, the client circulate in a model composed of different processes, which
demanded that the elements be prepared for erection at the will have an effect on the speed of flow, its nature or its ad-
job site in 2 months. Since there were 36 columns and 180 vance within the model. These flows can represent logical or
girders, the daily production rate would be as follows: physical entities. A physical entity is a physical object, for
example, a product, which can be modified by physical pro-
& Daily production rate for columns: 36/60 = 0.60 cesses such as a machine or workstation. A logical entity is
(columns per day) modified by control processes to make decisions for creating

Fig. 1 The current model of production after 30 days


Int J Adv Manuf Technol

and routing physical entities and/or launching, sizing, or Since there are 36 columns and 180 girders, on average, 3
booking shop orders on physical processes [24]. Therefore, girders and 0.60 column should be fabricated to meet the
different stages of steel fabrication at the factory were deadline. To calculate the lead time for every process, the
modeled by Arena using real data gathered by site visits and number of inventories should be divided by the daily produc-
interviewing experts in the production line. The data included tion rate which is 0.6 for columns and 3 for girders (the time-
the processes, cycle times of processes, and available re- line underneath the current state map shows the lead time for
sources for every process. After developing the model, it every station). In reality, this cannot be true because the hu-
was run for 30 days or 240 h to find out the current state of man resources are moved between stations by the production
the production line. Figure 1 shows the simulated model of the manager and this assumption to calculate the lead times is
fabrication phase after 240 h in the software environment. extremely approximate. Therefore, the lead time for fabrica-
Basically, computer simulation can precisely calculate the tion of the 1st stage is the summation of lead times for every
number of inventories, total lead time, as well as costs. station. Because 30 days have passed since the fabrication
Therefore, the number of inventories and the lead time for started, as shown in Fig. 2, the total lead time will be
every station were calculated by using the software reports. 107.66 days (8.33 + 20 + 15 + 4.33 + 26.67 + 3.33 + 30).
Figure 2 shows the current state map of the production line On the other hand, by modeling the processes and using com-
which consists of stations, inventories, and lead times for ev- puter simulation with respect to available resources (Fig. 1),
ery station in the production line after 30 days. simulation has been replicated for five times since there are
As shown in Fig. 2, the current state map shows that some five stages of steel frames in every building. Figure 3 shows
stations like initial assembly of columns and girders and sub- the simulation properties like number of replications, time
merged welding produce a larger number of inventories, units, etc., in the current mode of production.
which is not desirable in lean production. The client wants After running the developed model for five replications, the
the first stage of steel frames to be completed after 60 days. total lead time of fabrication is 695, 674, 681, 718, and 630 h,

Fig. 2 The current state map of the production line


Int J Adv Manuf Technol

Fig. 3 Simulation properties of


the current model

respectively. The average of these numbers indicates that the There are often spots in the value stream where continuous
fabrication is completed by 680 h (85 days). Obviously, the flow is not possible and batching is necessary. There can be
current state of the production line will not meet the 60 day several reasons for this including [22]:
deadline.
To calculate the total costs of resources for the current & Some processes are designed to operate at very fast or
production line, the busy and idle hourly costs of each re- slow cycle times and need to change over to service mul-
source has been introduced to the software. With regard to tiple product families.
the specified rates, the software calculates busy costs when & Some processes such as those at suppliers are far away and
the resource is seized and calculates idle costs when the re- shipping one piece at a time is not realistic.
source is released. In this regard, the total busy and idle costs & Some processes have too many lead times or are unreli-
of resources are shown in Fig. 4. By adding costs of each able to couple directly to other processes in a continuous
resource, the total cost of production in the current mode is flow.
obtained which is equal to $152,554. The total cost of fabri-
cating 1 kg of steel frames is calculated by dividing 152,554 Also, while having no inventory may be beneficial with
by approximately 380,000 kg for every stage which is $0.41. regard to decreasing inventory holding costs, it can result in
production downtime if sufficient buffer stock is not avail-
able to shield against upstream variability in the manufactur-
4.2 The future state map ing process. As a result, it is essential that manufacturing firms
not ignore the cost tradeoffs which exist between holding
After identifying the stations producing the most wastes, inventory and process downtime [25].
the current state map should be modified and the future A supermarket pull system is composed of two processes,
state map be developed to eliminate or decrease wastes. namely the supplying and customer process. Figure 5 shows
As it was mentioned above, some stations produce the relationship between these two processes:
a large number of inventories. To tackle this problem, Simply put, the upstream process should not produce the
some supermarket pull systems are provided to avoid product unless the downstream is ready to receive it.
inventories and achieve continuous flow of the To draw the future state map and improve productivity of
production. the production line, several supermarkets should be placed in
Int J Adv Manuf Technol

Fig. 4 Total costs of resources for the current production line

the system to speed up the slow stations and slow down the girders should not exceed 30/day. Once the supermarkets are
fast ones to achieve a continuous flow. In the supermarkets, full, the human resources can go to the adjacent stations to
the number of columns should not exceed 6/day and that of speed things up and reduce inventories. The future state map is

Fig. 5 The supermarket pull


system
Int J Adv Manuf Technol

Fig. 6 The lean model of production after 30 days

developed using computer simulation. Figure 6 shows the By comparing costs in the lean and current production,
developed model with the above mentioned supermarkets af- total busy costs are almost the same. However, total idle cost
ter 240 h in the software environment. in the current mode is remarkably greater than idle cost of the
Figure 7 shows the future state map of the produc- lean mode which shows efficient use of resources in the pro-
tion line. The number of inventories greatly decreases duction line in the lean mode.
by controlling the speed of production through placing
ten supermarkets in the production line. 4.3 Results and discussion
It is worth mentioning that achieving a continuous flow
with no inventories is impossible with regard to the nature of Mapping the future state shows improvements in the produc-
steel frame production with long cycle times, complicated tion line in both time and costs of the project. Table 5 shows
processes, and heavy products. The simulation of production the summary of the results obtained by simulation.
line indicates that the production process is completed by According to Table 5, after applying VSM via computer
56 days. simulation, the total fabrication time of one stage reduces from
The total cost of resources for the lean production line is 85 to 56 days, which shows 34 % of improvement. In addi-
equal to $128,415 (Fig. 8). Also, the total cost of fabricating tion, the total cost of fabrication decreases by 16 %.
1 kg of steel frames in the Lean mode is calculated by dividing To calculate the amount of reduction in the time of con-
$128,415 by approximately 380,000 kg for every stage which structing the whole project, the line of balance (LOB) tech-
is $0.34. nique and critical path method (CPM) were used. If CPM is
Int J Adv Manuf Technol

Fig. 7 The future state (lean) map of the production line

used to schedule the construction of one buildings structure, should be performed with similar rates without any gaps
the structure which is fabricated and erected in five stages will (i.e., wasted time) between the end of one activity and the
complete in 220 days. The precedence relationships for the beginning of another. Fabrication of steel frames for the three
current production line are shown in Table 6. buildings, as three units of the entire project, cannot be per-
As the fabrication reduces from 85 to 56 days, the sched- formed simultaneously, since the under-studied factory does
uling should be modified in the lean mode which changes the not have the capacity to handle fabricating steel frames for
duration of fabrication from 220 to 151 days. Thus, the pre- three buildings at the same time. Foundations or other activi-
cedence relationships will be modified as shown in Table 7. ties can begin simultaneously, but if so, they will remain idle
The LOB technique is used to evaluate the construction of for a period of time, waiting for incomplete tasks to be com-
one and then three under contract buildings. The LOB tech- pleted which contradicts the principles of both LOB and lean
nique is effective in repetitive construction project scheduling construction which both emphasize continuity of work and
[26]. Construction of repetitive projects is normally carried efficient use of resources. In this regard, the first building will
out by sequencing discrete activities, which are identical in complete by 443 days and the three buildings by 703 days
each repetitive segment (unit). By arranging work to proceed (Fig. 9). The time gap between starting fabrication and erec-
continuously and sequentially from the first to the last unit for tion in Fig. 9 is due to the LOB principle of ensuring continu-
the entire project, the LOB technique links repetitive cycles of ity of work from start to finish. In this case, the succeeding
work together to form an overall schedule. This technique activity (erection) that has a faster rate of progress than its
plots repetitive activities as diagonal lines on an X-Y graph immediately preceding activity (fabrication) needs to be de-
with time on the horizontal axis and location on the vertical layed sufficiently to prevent interference with the preceding
axis. The slopes of the lines are the production rates (the rates activity (fabrication) in the future. In this regard, it will be
of progress) of the activities. To ensure continuity of work scheduled from the finish date of the last units (3rd build-
from start to finish, all similar activities in different units ings) fabrication activity. Since erection of the last
Int J Adv Manuf Technol

Fig. 8 Total costs of resources for the lean production line

building begins 85 days after its fabrication according to the the 1st building will be obtained, which are days 205 and 364,
simulated model, erection of the 3rd building would start and respectively, in comparison with days 1 and 220 as start and
finish on days 525 and 684, respectively. If we go backward finish time of fabrication activity. Since ceiling is again
from the 3rd building to the 1st one with respect to the dura- faster than erection and each ceiling starts 50 days after start
tion of each activity, the start and finish time of the erection of

Table 5 Improvement in the time


and cost of production Time or cost Current Lean Improvement (%)

Total time of fabricating a stage (days) 85 56 34


Busy cost of resources ($) 110,608 110,523 0.10
Idle cost of resources ($) 41,946 17,892 57
Total cost of fabricating a stage ($) 152,554 128,415 16
Cost of fabricating a kilogram of steel frames ($) 0.41 0.34 16
Int J Adv Manuf Technol

Table 6 The precedence


relationships in current No Work package Precedence Completion time Completion time
production of one building of three buildings

1 Excavation 30 90
2 Foundation 1FS 60 180
3 Fabrication 1SS 220 660
4 Erection 3SS + 85, 2FS 160 480
5 Ceiling 4SS + 50 130 390

Table 7 The precedence


relationships in lean production No Work package Precedence Completion time Completion time
of one building of three buildings

1 Excavation 30 90
2 Foundation 1FS 60 180
3 Fabrication 1SS 151 453
4 Erection 3SS + 56, 2FS 160 480
5 Ceiling 4SS + 50 130 390

Fig. 9 The whole project schedule with the current production line

time of erection, by the same way the ceiling of the 3rd build- precedence relationships and according to the simulated model,
ing will start and finish on days 574 and 703, respectively. which is 56 days after the start day of the 1st buildings fabrica-
If lean construction is applied to the production line of the tion. If we go forward from the 1st building to the 3rd one with
factory, the first building will complete by 294 days and the three respect to the duration of each activity, the start and finish time of
buildings by 554 days, which shows considerable improvement the erection of the 3rd building will be obtained, which are days
(Fig. 10). In this case, the succeeding activity (erection) that has a 376 and 535, respectively; in comparison with days 303 and 453
slower rate of progress than its immediately preceding activity as start and finish time of fabrication activity. Since ceiling is
(fabrication) needs to start as soon as possible depending on again faster than erection and each ceiling starts 50 days after

Fig. 10 The whole project schedule with the lean production line
Int J Adv Manuf Technol

start time of erection, by the same way the ceiling of the 3rd 4. Salem R, Musharavati F, Hamouda AM, Al-Khalifa KN (2016) An
empirical study on lean awareness and potential for lean
building will start and finish on days 425 and 554, respectively.
implementations in Qatar industries. Int J Adv Manuf Technol 82:
As shown in Figs. 9 and 10, the durations of excavation, 16071625
foundation, erection, and ceiling stages do not change since it 5. Atieh AM, Kaylani H, Almuhtady A, Al-Tamimi O (2015)
is assumed that the required resources remain the same for both A value stream mapping and simulation hybrid approach:
application to glass industry. Int J Adv Manuf Technol
current and lean productions. The only difference is the duration
DOI. doi:10.1007/s00170-015-7805-8
of the fabrication stage which affects the ceiling and erecting. 6. Mao X, Zhang X (2008) Construction process reengineering by
integrating lean principles and computer simulation techniques. J
Constr Eng Manag 134(5):371381
7. Koskela L (2002) The theory of project management: explanation
5 Conclusions to novel methods. Proc. Int Group for Lean Construction 10th
Annual
8. Pero MP, Stlein M, Cigolini R (2015) Linking product modular-
In this research, the PSFs, as one of the most common ity to supply chain integration in the construction and shipbuilding
prefabricated building systems in Iran, were investigated. industries. Int J Prod Econ 170(B):602615
Some common wastes in PSF projects were identified. To 9. Firoozi M, Heravi G. (2013) A lean approach to industrialized and
examine the wastes more closely, the VSM was used to elim- modular homebuilding: identification and assessment of wastes in
mass-housing projects. Proc. 4th construction specialty Conf.,
inate or decrease some of the identified wastes in a case study. Canadian Society for Civil Engineering (CSCE). Montral, QC,
The case included construction of three 16-story residential Canada.
buildings made of PSFs with bolt and nut connections in Iran. 10. Forno AJD, Pereira FA, Forcellini FA, Kipper LM (2014) Value
The production phase of the case study at a steel factory was stream mapping: a study about the problems and challenges found
in the literature from the past 15 years about application of lean
examined. The production processes were investigated, and tools. Int J Adv Manuf Technol 72:779790
the current state of the production line was evaluated. 11. Pasqualini F, Zawislak PA (2005) Value stream mapping in con-
The processes required to bring steel frames from raw ma- struction: a case study in a Brazilian construction company. Proc. of
terials to columns and girders were identified, and for each 13th Annual Conf. of Int. Group for Lean Construction, Sydney,
Australia, pp. 117125.
process, the required resources were also extracted. After 12. Yu H, Tweed T, Al-Hussein M, Nasseri R (2009) Development of
mapping the current state and using DES by Arena 13.5, the lean model for house construction using value stream mapping. J
stations producing the most wastes and their inventories were Constr Eng Manag 135(8):782790
determined. The future and ideal state map was modeled by 13. Singh B, Garg SK, Sharma SK (2011) Value stream mapping: lit-
erature review and implications for Indian industry. Int J Adv
DES. In the future state, the supermarket pull system was Manuf Technol 53:799809
applied to encourage Just in Time as the most important 14. Yu H, Al-Hussein M, Al-Jibouri S, Telyas A (2013) Lean transfor-
lean objective. Results of the VSM application to the produc- mation in a modular building company: a case for implementation.
tion line demonstrated 34 % reduction of time and 16 % de- J Manag Eng 29(1):103111
15. Tabanli RM, Ertay T (2013) Value stream mapping and benefitcost
crease in costs. In addition, saving time in the fabrication
analysis application for value visibility of a pilot project on RFID
phase of steel frames in the factory, affected the erection phase investment integrated to a manual production control systema
at the project site. In other words, if CPM and LOB methods case study. Int J Adv Manuf Technol 66:9871002
are used to determine the impacts of the improved or lean 16. Rosenbaum S, Toledo M, Gonzlez V (2014) Improving environ-
mental and production performance in construction projects using
production line on the whole project, the total completion time
value-stream mapping: case study. J Constr Eng Manag 140(2):
for the structure of each building will decrease from 443 to 04013045
294 days. The results of this research can be used by project 17. Andrade PF, Pereira VG, Del Conte EG (2015) Value stream map-
managers to determine the effects of a lean production line on ping and lean simulation: a case study in automotive company. Int J
Adv Manuf Technol DOI. doi:10.1007/s00170-015-7972-7
the project through simulation along with scheduling methods
18. Helleno AL, Pimentel CA, Ferro R, Santos PF, Oliveira MC, Simon
such as CPM or LOB. AT (2015) Integrating value stream mapping and discrete events
simulation as decision making tools in operation management. Int
J Adv Manuf Technol 80:10591066
19. OConnor J, OBrien W, Choi J (2014) Critical success factors and
enablers for optimum and maximum industrial modularization. J
References Constr Eng Manag 140(6):04014012
20. Ohno T (1988) Toyota production system. Productivity Press, New
York
1. Womack JP, Jones DT (2005) Lean consumption. Harvard Bus Rev 21. Jones D, Womack J (2003) Seeing the wholemapping the extend-
83(3):5869 ed value stream. The Lean Enterprise Institute, Brookline, USA
2. Tyagi S, Vadrevu S (2015) Immersive virtual reality to vindicate the 22. Rother M, Shook J (1999) Learning to see: value stream mapping to
application of value stream mapping in an US-based SME. Int J create value and eliminate MUDA. Lean Enterprise Institute.
Adv Manuf Technol 81:12591272 23. Braglia M, Carmignani G, Zammori F (2006) A new value stream
3. Womack JP, Jones DT (1996) Lean thinking: banish waste and mapping approach for complex production systems. Intl J
create wealth in your corporation. Simon & Schuster, New York Production Research 44(1819):39293952
Int J Adv Manuf Technol

24. El Haouzi H, Thomas A, Petin JF (2008) Contribution to reusability 25. Melouk SH, Freeman NK, Miller D, Dunning M (2013) Simulation
and modularity of manufacturing systems simulation models: ap- optimization-based decision support tool for steel manufacturing.
plication to distributed control simulation within DFT context. Int J Int J Prod Econ 141(1):269276
Prod Econ 112(1):4861 26. Uher TE (2003) Programming and scheduling techniques.
University of New South Wales Press Ltd (UNSW Press Ltd),
Sydney

S-ar putea să vă placă și