Documente Academic
Documente Profesional
Documente Cultură
Presentation prepared by
Raymond Wong
January 2010
Purpose of site formation is for:
Forming of land by cutting & leveling of an
uneven, sloppy or congested area.
Accommodate building/s or other facilities
which will be placed within the area.
Form the land to the required orientation,
shape or levels in order to accommodate such
facilities.
Provide the required back-up facilities including
access roadways, drainage and other related
services, both temporary or permanent in
nature.
What works are usually involved in site
formation projects in Hong Kong
Clearance of the site including the removal of
buildings or unwanted structures, shrubs and
trees, surface soil and debris.
Excavation by cutting into slope or other land
area to get the required/extra land
Leveling of the land by necessary cutting or
filling to get a piece of flat or terraced land.
Stabilize natural or new slope within the site.
Construct retaining wall (as part of the slope
stabilization or trimming to terraced land).
Forming of access road and drainage system
Previous old buildings
being demolished
New plantation
Public
Road
Site Boundary
Scraping machine so
designed with a blade to
scrape and level large
area of land
Bulldozer machine
blade
Excavation by cutting into slope or other land
area to get the required/extra land
Leveling of the land by necessary cutting or
filling to get a piece of flat or terraced land.
Stabilize natural
or new slope
within the site.
Construct retaining wall (as part of the slope stabilization
or trimming to terraced land).
Forming of access road and drainage system
Some site formation project cases
as an introduction to start our lecture
A site formation project in Ap Lei Chau, Aberdeen, Hong Kong
The site as seen in 2008
A residential development project at Ap Lei Chau
Choi Wan area in 2000
Choi Wan area in 2007
Choi Wan area in 2008
See also following
photos
Area B
Area C
Area A at Junction of
Clear Water Bay Road
and Anderson Road
Area B west slope
near Shun Lee Estate
Area B west slope
near Shun Lee Estate
KCRC Kowloon
Tong Station
Stage 2 work
construction of the
basement
Complicated site
environment of Festival
Walk
MTR tunnels running across
the site
diaphragm wall, bore-pile
foundation, site formation and
basement excavation almost
worked at the same time
Approximate profile
of slope before site
formation
Diaphragm wall
panel tie back using
ground anchor
Case example
Formation for the South China
Sport Association extension facility
Site formation
Extension to South
China Sport Association
The preserved
tree grow in
healthy condition
along the re-
aligned road side
Case example CityU Academic Building 3
Works in the project include:
1. Cut-back and level the site along the existing access roadway by about
30m
2. Cut and stabilize the newly formed slope including necessary
temporary surface treatment and other retaining structures.
3. Provide surface and sub-soil drainage on the newly formed slope.
4. Construct the new foundation in average 2m bore-pile for the future
building.
5. Substructure of the future building including cutting into slope for
locating the foundation rafts or caps.
6. Other safety and environmental protection provisions as required.
The site as seen in 2005
The site as seen in 2009
Early stage of site as seen in June 2008
(contract commenced in November 2007)
First stage of
slopework being
completed with
temporary surface
treatment using
planting of grass
2nd stage of
cutting as well as
forming a
temporary
accessway for
working machines
Machine (reverse
circulation drill)
for the forming of
the bore-pile as
foundation for the
future building
Lower
portion of
slope being
removed
Previous
retaining
wall to be
demolition
Approx.
slope
profile
before site
formation
Tree to be
preserved
Toe of
slope
stabilized
using soil
nail
Lok Man
Sun Chuen
Case example
Private Residential Development project in Ma Tau Wai
Site formation to provide
land for the construction of
a public housing estate
(Lok Man Sun Chuen,
completed in early 1970s)
Condition of site
in mid 1960s
Condition of site in 2006
The Site
Transfer plate
constructed in
sections
podium
Podium construction
using top-down approach
Ground level
Bore-pile for
residential tower