Emami Infrastructure Inspection EMAMI

Limited Pre Pouring inspection No- SAF


checklist FM-17

Project Site:-
Name of the Contractor:-
Ser Description Yes No NA Remarks
No
A BELOW THE FLOOR
1. Are all support given to the shuttering for slab of
adequate strength and properly fixed and braced
2. Are all Props rests on the ground firmly?
3. Are all Props pin in place
4. Are all Props braced with ledger with pipe and tied by
coupler?
5. Are all props straight?
6. Are bottom of props not on the any slope?
7. Are all legs of tripod on the firm ground?
8. Are wall tie pins in place correctly and well in
position?
9. Is there provision of usage wooden pieces, stone
pieces etc as distance pieces?
10. Are edges of the slab properly barricaded?
Are an Adequate illumination has been ensured?
B ABOVE THE FLOOR
11. Are edges of the slab properly barricaded?
12. Has vertical Rebar (20mm) been inserted at every
2mtrs minimum for edge protection?
13. Are all loose materials removed from the slab?
14. Do all props start from the next lower slab for the
Edge protection?
15. Is condition of cable of vibrator to be used while
casting good connected to the ELCB?
16. Are there any damage/ joint in the cable?
17. Are the safety belt, Gumboot, etc available for the
workers engaged in the casting?
18. Is lighting arrangement proper?
19. Are walk way challis provided to walk on
reinforcement while casting good?
C SURROUNDING AREA
20. Is approach to the Slab unobstructed and proper?
21. Is the width of a working platform properly maintained
according to usage?
22. Are opening in working platform kept safely covered/
fenced?
23. Is there a provision of handrails?

Page 1 of 2
24. Is there a provision of anchoring full body harness?
25. Are all the workers have been explained safe work
procedures?
26. Are ladder providing access to the Slab securely
fixed top and bottom?
27. Are all the materials stored on the working platform
secured?
28. Are walkway/ aisles and workplaces cleared of loose
materials
29. Are route of the Concrete Pipe line clear, Is it
supported at enough places using proper stands, and
Is it properly clamped?
30. Is Walky-Talky available for the communication
between Pump Operator and person on the Slab/
32. Is good approach for the transit miller to the concrete
pump proper?
33. Is ball catcher available to clear the blocked line.
34. Is the stopper for the ball there in the place?
35. Are work area inspected prior starting to the job?
36. Are safety nets provided wherever required

Checked by Confirmed by Verified by


Section Incharge Safety Officer Safety
officer
(Contractor) (Contractor) (EMAMI)
Name: Name: Name:
Designation: Designation: Designation:
Signature: signature: Signature:
Date: Date: Date:

Page 2 of 2