GRUNDFOS INSTRUCTIONS

DSS dosing skid station


Installation and operating instructions
English (GB) Installation and operating instructions
English (GB)

Original installation and operating instructions. 2. Safety information


Non-observance of the safety instructions may have dangerous
CONTENTS consequences for the staff, the environment and the product and
Page may result in the loss of any claims for damages.
1. General information 2 Should you require further information, please contact Grundfos.
2. Safety information 2 2.1 Target group
2.1 Target group 2
2.2 Symbols used in this document 2 These installation and operating instructions contain general
2.3 Safety-related symbols on the product 3 instructions that must be observed during installation, startup,
2.4 Safety instructions for the user 3 operation and maintenance of the product. The responsible staff
2.5 Unauthorised changes 3 must read these installation and operating instructions prior to
2.6 Safety of the system in the event of product failure any work at the product. These installation and operating
3
instructions must be available at the installation location at all
2.7 Working with chemicals 3
times.
3. Product introduction 3
3.1 Certificates 3 2.1.1 Qualification and training of staff
3.2 Intended use 3 The staff responsible for the installation, startup, operation and
3.3 Improper use 3 maintenance must be qualified for these tasks. Areas of
3.4 Product overview 4 responsibility, levels of authority and the supervision of the staff
4. Technical data 4 must be precisely defined by the operating company.
If necessary, the staff must be trained.
5. Transport and storage 4
6. Installation 5 2.1.2 Obligations of the operating company
6.1 Hydraulic connection 5 Observe the local safety regulations.
6.2 Electrical connection 5 Instruct the operating staff.
7. Startup 5 Provide the stipulated safety equipment and personal
7.1 Calibration 5 protective equipment.
8. Operation 5 Arrange regular maintenance.
9. Maintenance 6
2.1.3 Obligations of the user
9.1 Safety instructions 6
9.2 Maintenance intervals 6 Read this manual thoroughly before putting the product into
operation.
10. Long-term shutdown 6
Observe the recognised health and safety regulations as well
11. Disposal 6
as the accident prevention regulations.
Wear protective equipment in accordance with national health
Warning
and safety regulations when working at the system and
Prior to installation, read these installation and handling chemicals.
operating instructions. Installation and operation
must comply with local regulations and accepted 2.2 Symbols used in this document
codes of good practice.
Warning
Warning If these safety instructions are not observed,
Read the installation and operating instructions it may result in personal injury.
of the components used.
If these safety instructions are not observed,
Caution it may result in malfunction or damage to the
1. General information
equipment.
These installation and operating instructions apply to Grundfos
DSS (dosing skid station) systems equipped with Grundfos Notes or instructions that make the job easier
dosing pumps. Note
and ensure safe operation.
The proper functioning of a DSS system depends on the following
points:
correct operation
regular maintenance
regular control of the dosing performance
provision of the necessary resources and spare parts.

2
2.3 Safety-related symbols on the product 3. Product introduction

English (GB)
The DSS systems consist of one or more dosing pumps mounted
Symbol Description in a cabinet together with optional equipment. See section
3.4 Product overview.
Indication of universally dangerous spot. The DSS systems are always designed as customer-specified
products. A drawing of the DSS system including product number,
In case of emergency and prior to all maintenance specified materials and components is supplied with the DSS
work and repairs, take the mains plug out of the system. Make sure to keep this drawing together with the
mains supply. installation and operating instructions as it gives important
specifications as to the proper use of the DSS system.
The product complies with electrical safety class II.
3.1 Certificates
The DSS systems can be designed for different applications and
Connection for deaeration hose at dosing head.
with a wide range of components. The EC directives with which it
If the deaeration hose is not correctly connected,
complies and the requirements for certification are described in
danger will arise due to possible leakage of dosing
the specification of each DSS system. Required certificates are
medium.
delivered as separate documents.
All signs and symbols on the product must be observed and kept
legible. 3.2 Intended use
The DSS systems are intended for dosing certain liquid dosing
2.4 Safety instructions for the user media according to an agreement with the customer.
Warning The operating safety of the DSS systems is only ensured, if it
is used for the specified application and media, and in
Observe the local regulations for work safety.
accordance with the values mentioned in section 4. Technical
Observe the safety data sheets of the supplier of data. The specified limit values must not be exceeded.
chemicals.
The DSS systems may only be operated by technical staff in
All work on the DSS systems must be carried out accordance with the installation and operating instructions.
by authorised and qualified staff.
Modifications to the DSS system are only permitted with the
Wear protective clothing when working on the consent of the manufacturer. Original spare parts and
DSS systems. accessories approved by the manufacturer are safe to use.
2.5 Unauthorised changes Warning
No changes of the DSS systems are allowed without prior Any usage other than that described here is not
consent of or agreement with the supplier. intended. Grundfos accepts no liability for any
Use only original accessories and original spare parts. Use of injuries or damage resulting from improper use.
other parts or modification of the DSS systems can result in
malfunction of the product. 3.3 Improper use
The DSS systems are not intended for dosing explosive,
2.6 Safety of the system in the event of product failure gaseous, highly viscous, solid media, or media containing
Use appropriate monitoring and control devices in order to ensure abrasive or long-fibred particles.
the overall safety of the system in case the product fails. The DSS systems are not intended for operation in other
conditions than specified in the agreement with the customer
Warning or described in section 4. Technical data.
Danger of personal injury due to contact with
chemicals. Warning
Make sure that leaking chemicals do not cause Any improper use can lead to personal injury and
personal injury or damage to property. damage to the equipment.
We recommend installation of leakage
monitoring solutions and drip trays. Observe the freezing and boiling points of the
Note dosing medium at operating pressure.
2.7 Working with chemicals Observe the temperatures specified.
Warning The operational safety of the product is only guaranteed, if it is
used in accordance with section 3.2 Intended use.
Danger of personal injury due to contact with
chemicals. The product must not be used for media that are not specified
in the agreement between Grundfos and customer.
Wear the stipulated personal protective
equipment (protective clothing, goggles, The product must not be used in potentially explosive areas.
respirator etc.) when handling chemicals. The product must not be used in food-processing systems.
Observe the chemicals manufacturer's safety The product must not be used if it is damaged.
data sheets and safety instructions of the The product must not be used after improper repair.
chemicals used. The product must not be used after unauthorised modification.
Make sure that parts in contact with the
chemicals are resistant to the chemicals under
the specific operating conditions.
Caution
Should you have questions regarding the
material resistance of the product to specific
chemicals, please contact Grundfos.

3
3.4 Product overview 4. Technical data
English (GB)

9 10 11 12 13 14 15 16 The values stated in the technical data of the


components must be observed.
Caution
For the entire system, the value of the component
with the most limited value applies.

The dosing medium must be in liquid state.


Caution Observe the freezing point of your dosing
medium.
Refer to the installation and operating instructions of the dosing
pump and characteristic of the dosing medium.

5. Transport and storage

TM05 9510 3913


Transport the DSS system carefully and only at
Caution temperatures above 5 C.
8 7 6 5 4 3 2 1
Risk of breakage.

Fig. 1 Example of a DSS system The DSS system is tested for tightness in the
Note factory. Some residual water may still be present
in the fittings and pipes.
Pos. Description
Check the DSS system for transportation damage or missing
1 Manual vacuum pump (suction aid) parts.
2 Suction-side isolating valve Store the DSS system in a sheltered place at temperatures
3 Suction-side pulsation damper between 5 and 45 C.
4 Dosing pump
5 Suction-side isolating valve for dosing pump
6 Dosing pump (standby)
7 Suction-side isolating valve for dosing pump (standby)
8 Drip tray
9 Drain/flush valve
10 Safety valve for dosing pump (standby)
Discharge-side isolating valve for dosing pump
11
(standby)
12 Safety valve for dosing pump
13 Discharge-side isolating valve for dosing pump
14 Discharge-side pulsation damper
15 Pressure-loading valve
16 Discharge-side isolating valve

4
6. Installation 7. Startup

English (GB)
Warning Warning
Make sure that the room where the DSS system is Some chemicals react with water, which can lead
installed has sufficient ventilation. to explosions. If the dosing medium can react
with water, the DSS system must be flushed with
a medium compatible with both water and the
Warning dosing medium first, to remove remaining water
Protect the DSS system against unauthorised in the DSS system.
access.
Prior to startup, flush all tanks and pipes.
The dosing medium must be in liquid state. Caution An initial test can be made with water if the
Caution Observe the freezing point of your dosing dosing medium is compatible with water.
medium.
The DSS system is tested for tightness in the
Keep the DSS system freely accessible for Note factory. Some residual water may still be present
Note operation and maintenance. in the fittings and pipes.
Provide sufficient lighting. 1. Retighten all threaded joints.
6.1 Hydraulic connection 2. Check the tightness of the entire DSS system and all pipes.
3. Check the electrical wiring and the power supply.
Mount the DSS system with a support on a wall, or on a suitable
steel frame, depending on its weight. 4. For dosing pumps with three-phase motors, additionally check
the direction of rotation and the setting of the motor
Keep the minimum diameter of the suction and discharge lines
protection.
(see provided drawing). Too small diameters may cause damage
to the DSS system and the dosing pump. 5. Install the suction line with foot valve in the dosing tank.
Depending on the viscosity and density of the dosing medium, the Install the suction line with a continuous upward slope
number of valves and fittings, and the length of the pipes, an towards the dosing pump.
increase of the diameter may be required. 6. Make sure that the valve at the flush connection is closed.
The discharge line is dimensioned in such a way that pressure 7. Open the isolating valves for the dosing pump.
peaks during the discharge stroke do not exceed the pressure 8. Vent the pump.
limit of the pump. Procedure for venting a pump via the flush connection:
The suction line is dimensioned in such a way that the minimum Open the valve at the flush connection by turning it left.
pressure during the suction stroke of the pump does not fall Flush liquid pressure: maximum 0.5 bar above the operating
below the vapour pressure of the dosing medium. pressure.
Install the suction line with a continuous upward slope towards Close the valve at the flush connection by turning it right.
the dosing pump.
Disconnect the hose from the flush connection.
If this is not possible, use a manual vacuum pump (suction
9. Check the proper interaction of all accessories such as
aid).
leakage detection, level switch, alarm relay, with the controller
If the DSS system has a water flush connection, connect it to of the installation.
the water supply only during flushing.
10. Make sure that the valve at the flush connection is closed.
Observe possible siphoning effects.
7.1 Calibration
6.2 Electrical connection
Calibration must be done with the dosing medium. For details on
calibration, see installation and operating instructions of the
Warning
dosing pump.
Observe the local regulations when connecting
the DSS system to the power supply.
8. Operation
Cables must comply with EN 60204-1 to meet the operating In normal operation, the DSS system operates independently.
requirements and withstand external influences. Do not close the isolating valves on the discharge side of the
The electrical components must be secured against short pump during normal operation.
circuit and overload in accordance with EN 60204-1. Otherwise the safety valve will open.
DSS systems installed outdoors must be sheltered to allow Keep all isolating valves closed, that are not in the line
trouble-free operation. between the dosing medium inlet and the injection point, e.g.
Exceptions are DSS systems equipped with an IP65 outdoor valves (pos. 7, 10, 11) of standby pump (pos. 6) and drain/
cabinet with integrated heating. flush valve (pos. 9). See fig. 1.
Do not close or block the vent hole of the dosing tank.
Do not contaminate the dosing tank.

5
9. Maintenance 10. Long-term shutdown
English (GB)

9.1 Safety instructions Warning


Some chemicals react with water, which can lead
Warning to explosions. If the dosing medium can react
Cleaning and maintenance must only be carried with water, the DSS system must be flushed with
out by authorised and qualified staff. a medium compatible with the dosing medium.
Wear the stipulated personal protective 1. Flush the dosing tank, lines, pipes, connections and pumps.
equipment (protective clothing, goggles,
The flushing can be done with water if the dosing medium is
respirator etc.) when handling chemicals.
compatible with water.
Observe the chemicals manufacturer's safety
In case of danger of frost, remove remaining liquid from
data sheets and safety instructions of the
tanks, lines and connections with compressed air.
chemicals used.
2. Disconnect the DSS system from the power supply.
Warning
Shut down the entire installation before starting
11. Disposal
any work on the system components and lines. This product or parts of it must be disposed of in an
Before starting maintenance work, disconnect environmentally sound way. Use appropriate waste collection
the DSS system from the power supply. services. If this is not possible, contact the nearest Grundfos
company or service workshop.
Before starting maintenance work, depressurise
the discharge line.
Drain and flush dosing head, valves and pipes.
Subject to alterations.
Warning
Safety devices, which have been deactivated
during maintenance, must be activated again
immediately after maintenance.

Store important spare parts close to the DSS


Note
system.

9.2 Maintenance intervals


9.2.1 Daily checks
Inspect the tightness visually.
9.2.2 Regular checks
Regular checks must be carried out weekly or monthly,
depending on the type of dosing pump and dosing medium.
See the installation and operating instructions of the dosing pump
and characteristic of the dosing medium.
Check the dosing performance.
Check the strainer and the foot valve,
clean the strainer, if necessary.
Maintain the dosing pump,
see installation and operating instructions of the dosing
pump.
Maintain the pressure loading valve,
see installation and operating instructions of the pressure
loading valve.
Check all accessories such as leakage indication, level switch,
alarm relay for their proper functioning.
9.2.3 Annual checks
Check the entire installation,
replace gaskets, O-rings, diaphragms and other wear parts,
if necessary.

After maintenance, check the proper functioning


Note
and tightness of the entire installation.

6
Argentina Denmark Korea Slovakia

Grundfos companies
Bombas GRUNDFOS de Argentina S.A. GRUNDFOS DK A/S GRUNDFOS Pumps Korea Ltd. GRUNDFOS s.r.o.
Ruta Panamericana km. 37.500 Centro Martin Bachs Vej 3 6th Floor, Aju Building 679-5 Prievozsk 4D
Industrial Garin DK-8850 Bjerringbro Yeoksam-dong, Kangnam-ku, 135-916 821 09 BRATISLAVA
1619 - Garin Pcia. de B.A. Tlf.: +45-87 50 50 50 Seoul, Korea Phona: +421 2 5020 1426
Phone: +54-3327 414 444 Telefax: +45-87 50 51 51 Phone: +82-2-5317 600 sk.grundfos.com
Telefax: +54-3327 411 111 E-mail: info_GDK@grundfos.com Telefax: +82-2-5633 725
www.grundfos.com/DK
Slovenia
Australia Latvia GRUNDFOS d.o.o.
GRUNDFOS Pumps Pty. Ltd. Estonia SIA GRUNDFOS Pumps Latvia landrova 8b, SI-1231 Ljubljana-rnue
P.O. Box 2040 GRUNDFOS Pumps Eesti O Deglava biznesa centrs Phone: +386 1 568 0610
Regency Park Peterburi tee 92G Augusta Deglava iel 60, LV-1035, Rga, Telefax: +386 1 568 0619
South Australia 5942 11415 Tallinn Tlr.: + 371 714 9640, 7 149 641 E-mail: slovenia@grundfos.si
Phone: +61-8-8461-4611 Tel: + 372 606 1690 Fakss: + 371 914 9646
Telefax: +61-8-8340 0155 Fax: + 372 606 1691
South Africa
Lithuania Grundfos (PTY) Ltd.
Austria Finland GRUNDFOS Pumps UAB Corner Mountjoy and George Allen Roads
GRUNDFOS Pumpen Vertrieb Ges.m.b.H. OY GRUNDFOS Pumput AB Smolensko g. 6 Wilbart Ext. 2
Grundfosstrae 2 Mestarintie 11 LT-03201 Vilnius Bedfordview 2008
A-5082 Grdig/Salzburg FIN-01730 Vantaa Tel: + 370 52 395 430 Phone: (+27) 11 579 4800
Tel.: +43-6246-883-0 Phone: +358-(0)207 889 900 Fax: + 370 52 395 431 Fax: (+27) 11 455 6066
Telefax: +43-6246-883-30 Telefax: +358-(0)207 889 550 E-mail: lsmart@grundfos.com
Malaysia
Belgium France GRUNDFOS Pumps Sdn. Bhd. Spain
N.V. GRUNDFOS Bellux S.A. Pompes GRUNDFOS Distribution S.A. 7 Jalan Peguam U1/25 Bombas GRUNDFOS Espaa S.A.
Boomsesteenweg 81-83 Parc dActivits de Chesnes Glenmarie Industrial Park Camino de la Fuentecilla, s/n
B-2630 Aartselaar 57, rue de Malacombe 40150 Shah Alam E-28110 Algete (Madrid)
Tl.: +32-3-870 7300 F-38290 St. Quentin Fallavier (Lyon) Selangor Tel.: +34-91-848 8800
Tlcopie: +32-3-870 7301 Tl.: +33-4 74 82 15 15 Phone: +60-3-5569 2922 Telefax: +34-91-628 0465
Tlcopie: +33-4 74 94 10 51 Telefax: +60-3-5569 2866
Belarus Sweden
Germany Mexico GRUNDFOS AB
GRUNDFOS Water Treatment GmbH Bombas GRUNDFOS de Mxico S.A. de (Box 333) Lunnagrdsgatan 6
220125, Reetzstrae 85 C.V. 431 24 Mlndal
. , 11, . 56 D-76327 Pfinztal (Sllingen) Boulevard TLC No. 15 Tel.: +46 31 332 23 000
.: +7 (375 17) 286 39 72, 286 39 73 Tel.: +49 7240 61-0 Parque Industrial Stiva Aeropuerto Telefax: +46 31-331 94 60
: +7 (375 17) 286 39 71 Telefax: +49 7240 61-177 Apodaca, N.L. 66600
E-mail: minsk@grundfos.com E-mail: gwt@grundfos.com Phone: +52-81-8144 4000
Switzerland
Telefax: +52-81-8144 4010 GRUNDFOS ALLDOS International AG
Bosnia/Herzegovina Germany Schnmattstrae 4
GRUNDFOS Sarajevo GRUNDFOS GMBH Netherlands CH-4153 Reinach
Trg Heroja 16, Schlterstr. 33 GRUNDFOS Netherlands Tel.: +41-61-717 5555
BiH-71000 Sarajevo 40699 Erkrath Veluwezoom 35 Telefax: +41-61-717 5500
Phone: +387 33 713 290 Tel.: +49-(0) 211 929 69-0 1326 AE Almere E-mail: grundfosalldos-CH@grundfos.com
Telefax: +387 33 659 079 Telefax: +49-(0) 211 929 69-3799 Postbus 22015
e-mail: grundfos@bih.net.ba E-mail: infoservice@grundfos.de 1302 CA ALMERE
Switzerland
Service in Deutschland: Tel.: +31-88-478 6336 GRUNDFOS Pumpen AG
Brazil E-mail: kundendienst@grundfos.de Telefax: +31-88-478 6332 Bruggacherstrasse 10
BOMBAS GRUNDFOS DO BRASIL E-mail: info_gnl@grundfos.com CH-8117 Fllanden/ZH
Av. Humberto de Alencar Castelo Branco, Greece Tel.: +41-44-806 8111
630 GRUNDFOS Hellas A.E.B.E. New Zealand Telefax: +41-44-806 8115
CEP 09850 - 300 20th km. Athinon-Markopoulou Av. GRUNDFOS Pumps NZ Ltd.
So Bernardo do Campo - SP P.O. Box 71 17 Beatrice Tinsley Crescent
Taiwan
Phone: +55-11 4393 5533 GR-19002 Peania North Harbour Industrial Estate GRUNDFOS Pumps (Taiwan) Ltd.
Telefax: +55-11 4343 5015 Phone: +0030-210-66 83 400 Albany, Auckland 7 Floor, 219 Min-Chuan Road
Telefax: +0030-210-66 46 273 Phone: +64-9-415 3240 Taichung, Taiwan, R.O.C.
Bulgaria Telefax: +64-9-415 3250 Phone: +886-4-2305 0868
Grundfos Bulgaria EOOD Hong Kong Telefax: +886-4-2305 0878
Slatina District GRUNDFOS Pumps (Hong Kong) Ltd. Norway
Iztochna Tangenta street no. 100 Unit 1, Ground floor GRUNDFOS Pumper A/S
Thailand
BG - 1592 Sofia Siu Wai Industrial Centre Strmsveien 344 GRUNDFOS (Thailand) Ltd.
Tel. +359 2 49 22 200 29-33 Wing Hong Street & Postboks 235, Leirdal 92 Chaloem Phrakiat Rama 9 Road,
Fax. +359 2 49 22 201 68 King Lam Street, Cheung Sha Wan N-1011 Oslo Dokmai, Pravej, Bangkok 10250
email: bulgaria@grundfos.bg Kowloon Tlf.: +47-22 90 47 00 Phone: +66-2-725 8999
Phone: +852-27861706 / 27861741 Telefax: +47-22 32 21 50 Telefax: +66-2-725 8998
Canada Telefax: +852-27858664
GRUNDFOS Canada Inc. Poland Turkey
2941 Brighton Road Hungary GRUNDFOS Pompy Sp. z o.o. GRUNDFOS POMPA San. ve Tic. Ltd. Sti.
Oakville, Ontario GRUNDFOS Hungria Kft. ul. Klonowa 23 Gebze Organize Sanayi Blgesi
L6H 6C9 Park u. 8 Baranowo k. Poznania Ihsan dede Caddesi,
Phone: +1-905 829 9533 H-2045 Trkblint, PL-62-081 Przemierowo 2. yol 200. Sokak No. 204
Telefax: +1-905 829 9512 Phone: +36-23 511 110 Tel: (+48-61) 650 13 00 41490 Gebze/ Kocaeli
Telefax: +36-23 511 111 Fax: (+48-61) 650 13 50 Phone: +90 - 262-679 7979
China Telefax: +90 - 262-679 7905
Grundfos Alldos India Portugal E-mail: satis@grundfos.com
Dosing & Disinfection GRUNDFOS Pumps India Private Limited Bombas GRUNDFOS Portugal, S.A.
ALLDOS (Shanghai) Water Technology 118 Old Mahabalipuram Road Rua Calvet de Magalhes, 241
Ukraine
Co. Ltd. Thoraipakkam Apartado 1079
West Unit, 1 Floor, No. 2 Building (T 4-2) Chennai 600 097 P-2770-153 Pao de Arcos , 103
278 Jinhu Road, Jin Qiao Export Phone: +91-44 4596 6800 Tel.: +351-21-440 76 00 . , 03131,
Processing Zone Telefax: +351-21-440 76 90 : (+38 044) 237 04 00
Pudong New Area
Indonesia .: (+38 044) 237 04 01
Shanghai, 201206 PT GRUNDFOS Pompa Romania E-mail: ukraine@grundfos.com
Phone: +86 21 5055 1012 Jl. Rawa Sumur III, Blok III / CC-1 GRUNDFOS Pompe Romnia SRL
Kawasan Industri, Pulogadung Bd. Biruintei, nr 103
United Arab Emirates
Telefax: +86 21 5032 0596 GRUNDFOS Gulf Distribution
E-mail: grundfosalldos-CN@grundfos.com Jakarta 13930 Pantelimon county Ilfov
Phone: +62-21-460 6909 Phone: +40 21 200 4100 P.O. Box 16768
China Telefax: +62-21-460 6910 / 460 6901 Telefax: +40 21 200 4101 Jebel Ali Free Zone
GRUNDFOS Pumps (Shanghai) Co. Ltd. E-mail: romania@grundfos.ro Dubai
50/F Maxdo Centre No. 8 Xing Yi Rd.
Ireland Phone: +971-4- 8815 166
Hongqiao Development Zone GRUNDFOS (Ireland) Ltd. Russia Telefax: +971-4-8815 136
Shanghai 200336 Unit A, Merrywell Business Park
Ballymount Road Lower , 109544 , .
United Kingdom
PRC GRUNDFOS Pumps Ltd.
Phone: +86-21 6122 5222 Dublin 12 39
Phone: +353-1-4089 800 . (+7) 495 737 30 00, 564 88 00 Grovebury Road
Telefax: +86-21 6122 5333 Leighton Buzzard/Beds. LU7 4TL
Telefax: +353-1-4089 830 (+7) 495 737 75 36, 564 88 11
Croatia E-mail grundfos.moscow@grundfos.com Phone: +44-1525-850000
GRUNDFOS CROATIA d.o.o.
Italy Telefax: +44-1525-850011
Cebini 37, Buzin GRUNDFOS Pompe Italia S.r.l. Serbia
Via Gran Sasso 4 GRUNDFOS Predstavnitvo Beograd
U.S.A.
HR-10010 Zagreb GRUNDFOS Pumps Corporation
Phone: +385 1 6595 400 I-20060 Truccazzano (Milano) Dr. Milutina Ivkovia 2a/29
Tel.: +39-02-95838112 YU-11000 Beograd 17100 West 118th Terrace
Telefax: +385 1 6595 499 Olathe, Kansas 66061
www.hr.grundfos.com Telefax: +39-02-95309290 / 95838461 Phone: +381 11 26 47 877 / 11 26 47 496
Telefax: +381 11 26 48 340 Phone: +1-913-227-3400
Czech Republic Japan Telefax: +1-913-227-3500
GRUNDFOS s.r.o. GRUNDFOS Pumps K.K. Singapore
Gotanda Metalion Bldg. 5F, GRUNDFOS (Singapore) Pte. Ltd.
Uzbekistan
apkovskho 21 Grundfos Tashkent, Uzbekistan The
779 00 Olomouc 5-21-15, Higashi-gotanda 25 Jalan Tukang
Shiagawa-ku, Tokyo, Singapore 619264 Representative Office of Grundfos
Phone: +420-585-716 111 Kazakhstan in Uzbekistan
Telefax: +420-585-716 299 141-0022 Japan Phone: +65-6681 9688
Phone: +81 35 448 1391 Telefax: +65-6681 9689 38a, Oybek street, Tashkent
Telefax: +81 35 448 9619 : (+998) 71 150 3290 / 71 150
3291
: (+998) 71 150 3292

Addresses revised 21.05.2014


ECM: 1144761
98537151 0215

www.grundfos.com
The name Grundfos, the Grundfos logo, and be think innovate are registered trademarks owned by Grundfos Holding A/S or Grundfos A/S, Denmark. All rights reserved worldwide. Copyright Grundfos Holding A/S

S-ar putea să vă placă și