Sunteți pe pagina 1din 9

Bidding for

HVAC / F.A / F.F Works

NOV. 11, 2016

Grati CCPP (Peaker) Extension Project 450MW


0. CONTENTS

1. PROJECT SUMMARY

2. PLOT PLAN

3. PROJECT MILESTONE

4. SITE ARRANGEMENT PLAN

5. SCOPE OF WORK

6. GUIDELINE FOR BIDDING


1. PROJECT SUMMARY

1) Summary 2) Location
Item Description

Client P.T PLN (Persero) Jakarta Site

Contract
EPC Lump Sum Turn Key
Type About 730km

Grati CCPP(Peaker) Extension Project 450MW Consortium


Contractor
Samsung C&T Corporation
(Consortium
Lotte Engineering & Construction
Member)
P.T Hutama Karya

Project Total 26 months from June 24, 2016


Period (Warranty : 12 months after T.O.C)

500MW Combine Cycle Power Plant


Capacity (5 hr operation/day, Peaking Plant)
GTG/HRSG/STG (2:2:1), 500kV Connections

Located at Pasuruan, East Java, Indonesia


Location
(75km from Surabaya East)

Fuel Natural Gas

Remark
2. PLOT PLAN

69 45. Gas Turbine Building


73 46. Intermediate Tower
54
52 47. Fuel Gas Area

51 58 74 48. GTG Fin Fan Cooler

77 49. Steam Turbine Building


67 49
50. HRSG

53 51. Workshop Building

52. Make-up Water Tank

53. Central Control Building


50
48 54. CW intake Structure
63
B-I B-II
45 58. Desalination Plant
47 61 61. GTG Transformer

62. Continuous Emission Monitoring

System
46
63. By-Pass Stack

67. Circulating Water Discharge Pipe

69. CW Discharge Structure

82 73. CW Intake Desal. & Chlorination

Elec. Building

74. Electro Chlorination Area

77. Circulating Water Supply Pipe

82. 500kV AIS


3. PROJECT MILESTONE

26M (Project Period) 12M (Warranty Period)

Electrical Power Initial Firing Synchronization


Effective Date Receiving Synchronization for GTG For STG
of Contract
C.O.D 1 F.A.C
C.O.D 3 (T.O.C)
C.O.D 2

15.5M
1st Inspection
16.5M
17.5M
GT #1 : 18M / GT #2 : 19M
23M

No. Key Milestone Month Date Remark


1 Contract Effective - Jun. 24, 2016

2 COD #1 for GTG #1 18M Dec. 24, 2017

3 COD #2 for GTG #2 19M Jan. 24, 2018

4 COD #3 for STG 26M Aug. 24, 2018


4. SITE ARRANGEMENT PLAN

LAYDOWN AREA

Temporary Facility

Fence
Access (Heavy Equipment)

Batch Plant

Access (Labor)
5. SCOPE OF WORK

1) Scope of work R : Responsibility, S : Support

No. Description Consortium Bidder Remark

Equipment such AHU, Condensing Unit and Bulk Material such as Pipe,
1 R
Cable etc including associated parts, Accessories and consumable parts

2 All material for Fire Alarm and Fire Fighting Works R

Transportation from temporary storage area to working area including


3 R
Loading and unloading

4 Area / Space for Office, Laydown, Storage, and etc R

5 Office, Warehouse, Work Shop, Utilities for construction works R

6 T.A.B R

Supply of materials, installation of temporary piping, valve, strainer, sil


7 R
encer, etc. for test and flushing

8 All permit related with the HVAC, Fire Alarm and Fire Fighting Work R
6. GUIDELINE FOR BIDDING

1) Terms of Payment
No. Description Amount Bond Remark

1) Advance Payment Bond, 15%


1 Advance Payment 15 % of Subcontract Price
2) Performance Bond, 10%

2 Monthly Progress Payment 75 % of Subcontract Price

1) 10 % of Subcontract Price, 1) Warranty Bond, 10%, 12 Months


3 Retention 2) From Initial Acceptance Date after 2) After issue of Certificate of Final
receiving Warranty Bond Acceptance

4 Liquidated Damage Max 10 %, 0.1 % / each day delayed

2) Guideline for Submission of Documents


No. Description Details Remark
duly stamped and
1 Bid Form Refer to our format and fill up the blank
signed by
authorized
2 Quotation for BOQ BOQ in excel file shall be submitted. (do not change the given BOQ form)
personnel
3 CBE Sheet Refer to our format and fill up the blank
1) Major Material Information (AHU, Air conditioner, Piping and fitting, fire alarm
system, cables, and etc) : manufacturer, specification, catalogue and
delivery confirmation letter
4 Technical Document 2) Work organization chart
3) Detailed construction schedule
4) Manpower mobilization schedule
5) Construction equipment mobilization schedule
5 Deviation Sheet(if any)
6. GUIDELINE FOR BIDDING

3) Guideline for Submission of Quotation


No. Description Details Remark

1 Bid closing date on or before 16:00, November 28, 2016 in Indonesian local time. By E-Mail

1) Commercial Queries
-. Attn. : H.G Kim (seankim@lottenc.com, +62-812-3352-6621)
2) Technical Queries
2 Communication
-. Attn. : M.S Lee (topos412@lottenc.com, +62-812-1899-3195)
-. C.C : H.G Kim (seankim@lottenc.com, +62-812-3352-6621)
M.K Yoon (mkyoon87@lottenc.com, +62-813-3394-7245)

1) Attn. : H.G Kim (seankim@lottenc.com, +62-812-3352-6621)


3 Submission of Quotation
2) C.C : Y.S Yoon (ysyoon@lottenc.com)