Working

Task Name Start Date End date Status Duration %Completed days

Team formation 22-12-2016 04-01-2017 completed 14 100% 13

Meeting and
administration 22-12-2016 12-22-16 Completed 1 100% 1

Team Selection 23-12-2016 12-24-16 Completed 2 100% 2

Task distribution 25-12-2016 12-27-16 Completed 3 100% 2


Registration for
event 28-12-2016 12-28-16 Completed 1 100% 1

Gokart study 29-12-2016 12-31-17 Completed 3 100% 3


Market analysis 01-01-2017 03-01-2017 Completed 3 100% 3

Weekly meeting 04-01-2017 04-01-2017 Completed 1 100% 1

Study of Design 05-01-2017 10-01-2017 In Progress 6 90% 5

Design study 05-01-2017 06-01-2017 In Progress 2 80% 2


Analysis
problems in
design 07-01-2017 09-01-2017 In Progress 3 95% 2

Weekly meeting 10-01-2017 10-01-2017 Completed 1 100% 1

Study of consern
departments 11-01-2017 19-01-2017 In Progress 9 95% 8

Study of engine
and transmission 11-01-2017 11-01-2017 In Progress 1 95% 1
Study of
designing of
steering 12-01-2017 13-01-2017 In Progress 2 90% 2
Study and
designing of
braking 14-01-2017 16-01-2017 In Progress 3 90% 2
Preparation of
final design 17-01-2017 18-01-2017 Completed 2 100% 2

Weekly meeting 19-01-2017 19-01-2017 Completed 1 100% 1


Dynamic
event(Task-1) 20-01-2017 21-01-2017 Completed 2 100% 2
Meeting with
administration 20-01-2017 20-01-2017 Completed 1 100% 1

Weekly meeting 21-01-2017 21-01-2017 Completed 1 100% 1


Dynamic
event(Task-2) 22-01-2017 25-01-2017 Completed 4 99% 4

Selection of
required tools
and components 22-01-2017 22-01-2017 In Progress 1 99% 1
Verification of
parts 23-01-2017 23-01-2017 Completed 1 100% 1

Material testing 24-01-2017 24-01-2017 Completed 1 100% 1

Weekly meeting 25-01-2017 25-01-2017 Completed 1 100% 1


Dynamic
event(Task-3) 26-01-2017 02-02-2017 Completed 8 100% 7
Fabrication of
chassis 26-01-2017 02-02-2017 Completed 8 100% 7
Preparation for
report
submission 03-02-2017 05-02-2017 Completed 3 100% 3
Preparation of
design report 03-02-2017 03-02-2017 Completed 1 100% 1
Preparation of
cost report and
gantt chart 04-02-2017 05-02-2017 Completed 2 100% 2
Dynamic event
(Task-4) 06-02-2017 25-02-2017 Not started 20 0% 19
Assembly of
different
components 06-02-2017 13-02-2017 Not started 8 0% 8
Installation of
safety
equipments 14-02-2017 14-02-2017 Not started 1 0% 1

Body works and


final finishing 15-02-2017 20-02-2017 Not started 6 0% 5
Test drive and
correction of
errors(if any) 21-02-2017 25-02-2017 Not started 5 0% 5
Days Days
Complete Remaining

12-22-16 12-29-16 1-5-17 1-12-17 1-19-17


1 0
Team formation
Meeting and administration
1 0
Team Selection

2 0 Task distribution
Registration for event
2 0 Gokart study
Market analysis
1 0
Weekly meeting
3 0 Study of Design
3 0 Design study
Analysis problems in design
1 0
Weekly meeting
Study of consern departments
5 0
Study of engine and transmission
2 0 Study of designing of steering
Study and designing of braking
Preparation of final design
2 0
Weekly meeting

1 0 Dynamic event(Task-1)
Meeting with administration
Weekly meeting
8 0 Dynamic event(Task-2)
Selection of required tools and components

1 0 Verification of parts
Material testing
Weekly meeting
2 0 Dynamic event(Task-3)
Fabrication of chassis
Preparation for report submission
2 0
Preparation of design report
2 0 Preparation of cost report and gantt chart
Dynamic event (Task-4)
1 0
Assembly of different components
Installation of safety equipments
2 0
Body works and final finishing
1 0 Test drive and correction of errors(if any)

1 0
4 0

1 0

1 0

1 0

1 0

7 0

7 0

3 0

1 0

2 0

0 20

0 8

0 1

0 6

0 5
1-19-17 1-26-17 2-2-17 2-9-17 2-16-17 2-23-17 3-2-17