ID Task Name Duration Start Finish M1 M2 M3 M4 M5 M6 M7 M8 M9

W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36
0 RoxasSubstation 230days Tue13/12/16 Sun30/07/17
1 ProjectStart 0days Tue13/12/16 Tue13/12/16 13/12
2 Mobilization 9days Tue13/12/16 Wed21/12/16
3 Constructionof50MVAPowerTransformer 14days Thu22/12/16 Wed04/01/17

4 ConstructionofAFrameFoundation 28days Thu22/12/16 Wed18/01/17


5 ConstructionofHFrameFoundation 33days Thu22/12/16 Mon23/01/17
6 ConstructionofPCB,DS,SA,PT,CT 21days Thu22/12/16 Wed11/01/17
Foundation
7 SupplyandInstallationofSteelStructure 90days Tue24/01/17 Sun23/04/17
8 Grading 14days Tue24/01/17 Mon06/02/17
9 GroundLevellingandGravelBedding 14days Tue07/02/17 Mon20/02/17
10 ConstructionofPerimeterFence 180days Thu22/12/16 Mon19/06/17
11 ConstructionofConcreteRoad&Pavement 16days Tue11/04/17 Wed26/04/17
12 ConstructionofDrainageSystem 49days Tue21/02/17 Mon10/04/17
13 ConstructionofCableTrench 125days Tue21/02/17 Sun25/06/17
14 ConstructionofConcreteDuctbank& 26days Tue21/02/17 Sat18/03/17
Pedestal
15 ConstructionofPowerhouse&GuardHouse 130days Thu22/12/16 Sun30/04/17
16 InstallationofElectrucalEquipment 7days Mon24/04/17 Sun30/04/17
(Substation)
17 SuppleandDeliveryofMVSG 150days Wed01/02/17 Fri30/06/17
18 InstallationofMVSG 14days Mon01/05/17 Sun14/05/17
19 SupplyandInstallationofGroundingSystem 60days Tue21/02/17 Fri21/04/17

20 SupplyandInstallationofSwitchyard 14days Sat22/04/17 Fri05/05/17


OverheadConductorsandHardwares
21 Assemblyof50MVAPowerTransformerand 14days Thu05/01/17 Wed18/01/17
OilFilling
22 PowerandControlCablesandAccessories 14days Sat01/07/17 Fri14/07/17
23 LightingandPowerSystem 18days Mon10/07/17 Thu27/07/17
24 KalawStationProjectStart 0days Mon06/03/17 Mon06/03/17 06/03
25 SiteDevelopmentatKalawStation 7days Mon06/03/17 Sun12/03/17
26 ConstructionofAFrameFoundation 21days Mon13/03/17 Sun02/04/17
27 ConstructionofHFrameFoundation 21days Mon13/03/17 Sun02/04/17
28 ConstructionofPCB,DS,SA,PT,CT 30days Mon13/03/17 Tue11/04/17
Foundation
29 ConstructionofCHBPerimeterFence 60days Mon13/03/17 Thu11/05/17
30 GroundLevellingandGravelBedding 14days Wed12/04/17 Tue25/04/17
31 DrainageSystem 30days Wed26/04/17 Thu25/05/17
32 DemolitionofExistingPerimeterWall 14days Fri12/05/17 Thu25/05/17
33 PaintingofCHBPerimterFence 21days Fri12/05/17 Thu01/06/17
34 HaulingandDisposalofDebris 1day Fri02/06/17 Fri02/06/17
35
36 TestingandCommisioning 3days Fri28/07/17 Sun30/07/17
37 ProjectFinish 0days Sun30/07/17 Sun30/07/17 30/07

Split Rolled Up Progress Deliverable Duration Inactive Split Start-only Deadline

Project: Roxas Substation Group By Summary Rolled Up Milestone Dependency Start Duration-only Finish-only Progress
Date: Wed 08/03/17 Rolled Up Task Deliverable Start Dependency Finish Manual Summary Rollup External Tasks Manual Progress

Rolled Up Split Deliverable Finish Dependency Duration Manual Summary External Milestone

Page 1