1. To study the foster HVDC generator, Ferranti HVAC generators
Procedure:
Study about the control panel and method of operation of the high voltage
generators. Adjust the gap setting of the plate-plate gap from 0.5cm to
4.5cm in steps of 0.5cm and obtain the breakdown voltage for positive DC
high voltages.
Repeat the experiment for negative DC and AC high voltages. Follow the
same procedure for plate-plate and sphere-sphere gaps. Note down the
atmospheric pressure and temperature.
Discussion:
1. HV lab arrangement with diagrams.
- When the object starts to spark, the system will trip the circuit through
an earth conductor, so the circuit will disconnect without continuing. This
operation provides safety to the equipments.
- We have to stand away from the experiment setup while supplying the
high voltage.
In the practical we applied only the AC voltage. But for the information I
can say one of high voltage lab equipments is HAEFLEY High Voltage equipment.
This HV equipment can be used in multiple applications in high voltage
technology and used in generation of High Voltage Direct Current (HVDC), High
Voltage Alternating Current (HVAC) and Impulse voltage.
- The high rated resistor is used to control (reduce) the current flowing in
the circuit. If not high current flow may harmful to the equipments and not
desirable to do the practical.
5. for a given pair of electrode discuss the factors that affect the
breakdown voltage of air.