Sunteți pe pagina 1din 26

Earth work in foundation trenches up to 1.

5 m depth and 60 m lead including protecting and


maintaining the trench.
Considering 1000 cft. work
1. Mason 0.5 No. @ Tk. 500.00 each
2. Ordinary labour 10 Nos. @ Tk. 300.00 each
3. Skilled labour 2.5 Nos. @ Tk. 400.00 each
4. For lay-out:
i) Head mason 0.25 No. @ Tk. 550.00 each
ii) Lime for marking 0.5 kg @ Tk. 60.00 Per kg
iii) Bamboo for spikes 5 rft. @ Tk. 10.00 Per rft.
5. Tools and plant, sundries etc. L.S.
Total
Contractor's profit 10.00%
Overhead expenses 3.00%

VAT 0.00%

Grand total

Rate per cft.


Extra rate for each additional 1 meter depth exceeding 1.5 meter
Considering 1000 cft. work
1. Mason 0.125 No. @ Tk. 500.00 each
2. Ordinary labour 3 Nos. @ Tk. 300.00 each
Total
Contractor's profit 10.00%
Overhead expenses 3.00%

VAT 0.00%

Grand total

Rate per cft.

Total Rate /cft


= Tk. 250.00
= Tk. 3,000.00
= Tk. 1,000.00

= Tk. 137.50
= Tk. 30.00
= Tk. 50.00
= Tk. 100.00
= Tk. 4,567.50
= Tk. 456.75
= Tk. 137.03
Tk. 5,161.28
= Tk. -

= Tk. 5,161.28

= Tk. 5.16

= Tk. 62.50
= Tk. 900.00
= Tk. 962.50
= Tk. 96.25
= Tk. 28.88
Tk. 1,087.63
= Tk. -

= Tk. 1,087.63

= Tk. 1.09

= Tk. 6.25
One layer brick flat soling in foundation or in floor.
Considering 100 sft of work
1. Bricks 350 Nos. @ 7.00 Per Nos.
2. Fine sand (with wastage) 5.25 cft. @ 10.00 Per cft.
3. Labor Charge 100 sft @ 3.00 each
6. Local carriage, sundries, T & P etc. L.S.
Total
Contractor's profit 10.00%
Overhead expenses 3.00%

VAT 0.00%

Grand total

Rate per sft.


= 2,450.00
= 52.50
= 300.00
= 80.00
= 2,882.50
= 288.25
= 86.48
3,257.23
= -

= 3,257.23

= 32.57
CC Casting (Cement : Sand: Brick chips= 1:3:6) with brick chips & 100% local sand of F.M. 1.2
consider 100 cft work
1 Bricks for 90 cft chips(with wastage) 780 nos @ 7
2 Sand ( Local, F.M = 1.2, with wastage) 46 cft @ 20
3 Cement (ordinary portland) 12 bag @ 410

4 breaking chips incl. screening, stacking, wetting, 90 cft @ 7

5 Labour costing ( Material loading,RCC Casting, Curing ) 100 cft @ 20


i) Labour costing (Shuttering) 100 cft @ 15
ii) Shuttering material 100 cft @ 14
iii) Mixture machine, pump, local carriage, sundries, T & P etc.
Subtotal
Contractors profit 5.00 %
Overhead 3.00 %

Grand Total

Rate per cft


Shuttering material
For a footing base size 8 ftx 8ft
Casting volume of cc work (8.5 ftx8.5 ftx 3in)
18.0625 cft

Shuttering material
2.10 cft
2.42 cft 15% for wastage, nail, wires
1016.31 tk 420Tk/cft with carriage
254.078125 Tk using 4 times

Material Cost /cft= 14.07 Tk

Shuttering Labour
For a footing base size 8 ftx 8ft
Casting volume of cc work (8.5 ftx8.5 ftx 3in)
18.0625 cft

Shuttering labor charge


17.00 sft
272.00 tk Tk 16 /sft labour charge

labour Cost /cft= 15.06 Tk


and of F.M. 1.2

tk per nos 5460


tk per cft 920
tk per bag 4920

tk per cft 630

tk per cft 2000


tk per cft 1500
Tk/cft 1400
1000
= 17830.00
= 891.5
= 534.9

= 19256.40

= 192.56
RCC Casting for footings : ( Cement : sand : Stone Chips=1 : 1.5 : 3 )
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35
4 Labour costing ( RCC Casting , Material loading, curing) 100 cft @ 20
5 Labour costing ( Shuttering) 100 cft @ 10.5
6. Shuttering material cost 100 cft @ 8.5
7. Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 4
Subtotal
Contractors pro 8.00 %
Overhead 3.00 %

VAT
Grand Total

Rate per cft

Shuttering material
For a footing base size 8 ftx 8ft
Casting volume of RCC work (8 ftx8 ftx 12in)
64 cft

Shuttering material
5.26 cft
2209.38 tk 420Tk/cft with carriage
552.34 Tk using 4 times

Material Cost /cft= 8.63 Tk

Shuttering Labour
For a footing base size 8 ftx 8ft
Casting volume of RCC work (8 ftx8 ftx 12in)
64 cft

Shuttering labor charge


Shuttering Area= 42.50 sft
Shuttering labour cost/footing= 680.00 tk Tk 16 /sft labour charge

labour Cost /cft= 10.63 Tk


tk per bag 9020
Tk per cft 6670
Tk per cft 6440
tk per cft 1575
tk per cft 2000
tk per cft 1050
tk per cft 850
tk per cft 400
= 28005.00
= 2240.4
= 840.15
31085.55
= 0.00 %
= 31085.55

= 310.86

cft with carriage

sft labour charge


RCC Casting for Column, beam & Stair Base: Cement : sand : Stone Chips=1 : 1.5 : 3 ( for Ground floor)
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410 tk per bag
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145 Tk per cft
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140 Tk per cft
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35 tk per cft
4 Labour costing ( RCC Casting , Material loading, curing) 100 cft @ 20 tk per cft
5 Labour costing ( Shuttering) 100 cft @ 28.80 tk per cft
6. Shuttering material cost 100 cft @ 39.84 tk per cft
7. Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 3.5 tk per cft
Subtotal =
Contractors profit 8.00 % =
Overhead 2.50 % =

VAT =
Grand Total =

Rate per cft =

RCC Casting for Column, beam & Stair Base: Cement : sand : Stone Chips=1 : 1.5 : 3 ( for 1st floor)
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410 tk per bag
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145 Tk per cft
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140 Tk per cft
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35 tk per cft
4 Labour costing ( RCC Casting , Material loading, curing) 100 cft @ 20 tk per cft
5 Labour costing ( Shuttering) 100 cft @ 28.8 tk per cft
6. Shuttering material cost 100 cft @ 39.84 tk per cft
7. Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 5 tk per cft
Subtotal =
Contractors profit 8.00 % =
Overhead 2.50 % =

VAT =
Grand Total =

Rate per cft =

Shuttering material
For a column size 15 in x 15 in x10 ft
Casting volume of RCC work (15 in x 15 in x10 ft)
27.78 cft

Shuttering material
Wood 7.40 cft
3106.25 tk 420Tk/cft with carriage
776.56 Tk using 4 times

Bamboo 132 ft
3.77 nos bamboo
1320 Tk
330 Using 4 times
Material Cost /cft= 39.84 Tk

Shuttering Labour
For a column size 15 in x 15 in x10 ft
Casting volume of RCC work (15 in x 15 in x10 ft)
27.78 cft

Shuttering labor charge


Shuttering Area= 50.00 sft
Shuttering labour cost/footing= 800.00 tk Tk 16 /sft labour charge

labour Cost /cft= 28.80 Tk


9020
6670
6440
1575
2000
2880
3983.625
350
32918.63
2633.49
822.965625
36375.08
0.00 %
36375.08

363.75

9020
6670
6440
1575
2000
2880
3984
500
33069.00
2645.52
826.725
36541.25
0.00 %
36541.25

365.41
RCC Casting for Ground Floor (Cement : Sand : Brick Chips=1 : 2 : 4)

consider 100 cft work


1 Cement (ordinary portland) 18 bag @ 410
2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 20
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 1.92
6 Shuttering material cost 100 cft @ 2.26
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 5
Subtotal
Contractors profit 10.00 %
Overhead 3.00 %

Grand Total

Rate per cft


Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering material
Wood 20.86 cft
8760.94 tk 420Tk/cft with carriage
2190.23 Tk using 4 times

Bamboo 252 ft
7.20 nos bamboo
2520 Tk 350/ each
630 Using 4 times
Material Cost /cft= 2.26 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering labor charge


Shuttering Area= 150.00 sft
Shuttering labour cost/footing= 2400.00 tk Tk 16 /sft labour charge

labour Cost /cft= 1.92 Tk


tk per bag 7380
tk per nos 5530
tk per cft 630
tk per cft 480
tk per cft 840
tk per cft 2000
tk per cft 192
Tk/cft 226
Tk/cft 500
= 17778
= 1778
= 533
20089
= 20089

= 201
RCC Casting for 1st Floor (Cement : Sand : Brick Chips=1 : 2 : 4)

consider 100 cft work


1 Cement (ordinary portland) 18 bag @ 410
2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 22
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 1.92
6 Shuttering material cost 100 cft @ 2.48
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 7.5
Subtotal
Contractors profit 10.00 %
Overhead 3.00 %

Grand Total

Rate per cft

Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering material
Wood 10.92 cft
4587.73 tk 420Tk/cft with carriage
1146.93 Tk using 4 times

Bamboo 780 ft
22.29 nos bamboo
7800 Tk 350/ each
1950 Using 4 times
Material Cost /cft= 2.48 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering labor charge


Shuttering Area= 150.00 sft
Shuttering labour cost/footing= 2400.00 tk Tk 16 /sft labour charge

labour Cost /cft= 1.92 Tk


tk per bag 7380
tk per nos 5530
tk per cft 630
tk per cft 480
tk per cft 840
tk per cft 2200
tk per cft 192
Tk/cft 248
Tk/cft 750
= 18250
= 1825
= 547
20622
= 20622

= 206
RCC Casting for 2nd Floor (Cement : Sand : Brick Chips=1 : 2 : 4)

consider 100 cft work


1 Cement (ordinary portland) 18 bag @ 410
2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 24
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 1.92
6 Shuttering material cost 100 cft @ 2.48
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 10
Subtotal
Contractors profit 10.00 %
Overhead 3.00 %

Grand Total

Rate per cft

Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering material
Wood 10.92 cft
4587.73 tk 420Tk/cft with carriage
1146.93 Tk using 4 times

Bamboo 780 ft
22.29 nos bamboo
7800 Tk 350/ each
1950 Using 4 times
Material Cost /cft= 2.48 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering labor charge


Shuttering Area= 150.00 sft
Shuttering labour cost/footing= 2400.00 tk Tk 16 /sft labour charge

labour Cost /cft= 1.92 Tk


tk per bag 7380
tk per nos 5530
tk per cft 630
tk per cft 480
tk per cft 840
tk per cft 2400
tk per cft 192
Tk/cft 248
Tk/cft 1000
= 18700
= 1870
= 561
21131
= 21131

= 211
Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar (GF)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00
iii) G.I. wire 1 kg @ Tk. 95.00
2 Cost of labour 50 kg Tk. 5.00

3 Unloading, Equipment charge, Utility 50 Kg @ Tk. 1.25

Contractor's profit
Overhead expenses

Rate per Kg
Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar (1st Fl)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00
iii) G.I. wire 1 kg @ Tk. 95.00
2 Cost of labour 50 kg Tk. 5.50

3 Unloading, Equipment charge, Utility 50 Kg @ Tk. 2.00

Contractor's profit
Overhead expenses

Rate per Kg

Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar ( 2nd Fl
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00
iii) G.I. wire 1 kg @ Tk. 95.00
2 Cost of labour 50 kg Tk. 6.00

3 Unloading, Equipment charge, Utility 50 Kg @ Tk. 3.00

Contractor's profit
Overhead expenses
72.5 / 60 grade deformed bar (GF)

Per kg. = Tk. 3,050.00


Per kg. = Tk. 95.00
Per kg. = Tk. 250.00

Per kg. Tk. 62.50

Total = Tk. 3,457.50


10.00% = Tk. 345.75
3.00% = Tk. 103.73
Tk. 3,906.98
Grand total = Tk. 3,906.98
Rate per Kg = Tk. 78.14
.5 / 60 grade deformed bar (1st Fl)

Per kg. = Tk. 3,050.00


Per kg. = Tk. 95.00
Per kg. = Tk. 275.00

Per kg. Tk. 100.00

Total = Tk. 3,520.00


10.00% = Tk. 352.00
3.00% = Tk. 105.60
Tk. 3,977.60
Grand total = Tk. 3,977.60
Rate per Kg = Tk. 79.55

5 / 60 grade deformed bar ( 2nd Fl)

Per kg. = Tk. 3,050.00


Per kg. = Tk. 95.00
Per kg. = Tk. 300.00

Per kg. Tk. 150.00

Total = Tk. 3,595.00


10.00% = Tk. 359.50
3.00% = Tk. 107.85
Tk. 4,062.35
Grand total = Tk. 4,062.35
Rate per Kg = Tk. 81.25
125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure (GF)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00
3. Cement (portland) 1.75 bags @ 410.00
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00
5. Labour (Brick work) 100 sft. @ 10.00
6. Scaffolding material & labour charge 25 sft. @ 12.00
7. Local carriage, storage & sundries etc. L.S.
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =

Grand total =

Rate per sft. =

125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure ( for 1st floor)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00
3. Cement (portland) 1.75 bags @ 410.00
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00
5. Labour (Brick work) 100 sft. @ 11.00
6. Scaffolding material & labour charge 25 sft. @ 13.00
7. Local carriage, storage & sundries etc. L.S.
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =

Grand total =

Rate per sft. =

125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure ( for 2nd floor)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00
3. Cement (portland) 1.75 bags @ 410.00
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00
5. Labour (Brick work) 100 sft. @ 12.00
6. Scaffolding material & labour charge 25 sft. @ 14.00
7. Local carriage, storage & sundries etc. L.S.
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =

Grand total =

Rate per sft. =


Tk per nos 3,600.00
Tk per cft 360.00
Tk per bag 717.50
Tk per nos 480.00
Tk per sft 1,000.00
Tk per sft 300.00
200.00
6,657.50
665.75
199.73
7,522.98

7,522.98

75.23

oor)

Tk per nos 3,600.00


Tk per cft 360.00
Tk per bag 717.50
Tk per nos 480.00
Tk per sft 1,100.00
Tk per sft 325.00
250.00
6,832.50
683.25
204.98
7,720.73

7,720.73

77.21

loor)

Tk per nos 3,600.00


Tk per cft 360.00
Tk per bag 717.50
Tk per nos 480.00
Tk per sft 1,200.00
Tk per sft 350.00
350.00
7,057.50
705.75
211.73
7,974.98

7,974.98

79.75
10 inch Brick Work (1:3:6)
Considering 100 cft. of work:
1. Bricks ( With Wastage) 1152 Nos. @ 7.5 Per Nos.
2. Sand (F.M 1.2) in/c wastage 46 cft. @ 20 Per cft.
3. Cement (portland) 6 bags @ 410 Per bag

4. Labour cost ( Soaking bricks, scraning sand) 1152 Nos. @ each


1
5. Labour cost ( brick work) 100 cft. @ 12 each
6 Scaffolding material & labour charge 25 sft. @ 12 Per sft.
7 Local carriage, sundries, T & P etc. L.S.
Total
Contractor's profit 10.00%
Overhead expenses 3.00%

Grand total

Rate per cft.

10 inch Brick Work (1:6) ( for 1st floor)


Considering 100 cft. of work:
1. Bricks ( With Wastage) 1152 Nos. @ 8.5 Per Nos.
2. Sand (F.M 1.2) in/c wastage 46 cft. @ 20 Per cft.
3. Cement (portland) 6 bags @ 460 Per bag

4. Labour cost ( Soaking & carrying, scraning sand) 1152 Nos. @ each
0.5
5. Labour cost ( brick work) 100 cft. @ 13.5 each

6 Scaffolding material & labour charge 25 sft. @ 11 Per sft.

7 Local carriage, sundries, T & P etc. L.S.


Total
Contractor's profit 10.00%
Overhead expenses 3.00%

Grand total

Rate per cft.


= 8,640.00
= 920.00
= 2,460.00

= 1,152.00

= 1,200.00
= 300.00
= 100.00
= 14,772.00
= 1,477.20
= 443.16
16,692.36

= 16,692.36

= 166.92

= 9,792.00
= 920.00
= 2,760.00

= 576.00

= 1,350.00

= 275.00

= 150.00
= 15,823.00
= 1,582.30
= 474.69
17,879.99

= 17,879.99

= 178.80
RCC Casting for Lintel, Sun Shade and Drop Slab (1:2:4)

consider 100 cft work

1 Cement (ordinary portland) 18 bag @ 410


2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 20
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 94
6 Shuttering material cost 100 cft @ 107
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 10
Subtotal
Contractors profit 10.00 %
Overhead 3.00 %

Grand Total

Rate per cft

Shuttering material
For a lintle size 20 ft x 10 in x5 in
Casting volume of RCC work (20 ft x 10 in x5 in)
6.94 cft

Shuttering material
Wood 5.76 cft
2417.19 tk 420Tk/cft with carriage
604.30 Tk using 4 times

Bamboo 56 ft
1.60 nos bamboo
560 Tk 350/ each
140 Using 4 times
Material Cost /cft= 107.18 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
6.94 cft

Shuttering labor charge


Shuttering Area= 40.83 sft
Shuttering labour cost/footing= 653.33 tk Tk 16 /sft labour charge

labour Cost /cft= 94.08 Tk


tk per bag 7380
tk per nos 5530
tk per cft 630
tk per cft 480
tk per cft 840
tk per cft 2000
tk per cft 9408
Tk/cft 10718
Tk/cft 1000
= 37986
= 3799
= 1140
42924
= 42924

= 429

with carriage

labour charge

S-ar putea să vă placă și