Documente Academic
Documente Profesional
Documente Cultură
TYPES OF SIPHON;
TYPE-I ;-
In this type, the sides of the aqueduct are earthen banks
with complete earthen slopes. The length of the culvert
through which the drainage the water has to pass under
the canal should not only be sufficient to accommodate
the water section of the canal but also the earthen banks
of the canal with aqueduct slopes
TYPE-II ;-
In this type, the canal continuous in its earthen section
over the drainage, but the outer slopes of the canal
DRAINAGE SYPHON
TYPE-III ;-
In this type, earthen section of the canal is discontinuous
and the canal water is carried in a masonry or a concrete
though. The canal is generally flumed in this case, so as
to find economy in the construction. The culvert length or
width of aqueduct is maximum in type-I and minimum in
type-III. An intermediate value exists in type-III.
2. PERFORMANCE:
As far as possible, the structure having an open channel
flow should be preferred to the structure having a pipe
flow. Therefore, an aqueduct should be preferred to a
syphon aqueduct. Likewise, a super-passage should be
preferred to a canal siphon. In the case of a syphon
aqueduct and a canal syphon, silting problems usually
occur at the crossing. Moreover, in the case of a canal
syphon, there is considerable loss of command due to
loss of head in the canal. The performance of inlet-outlet
structures is not good and should be avoided.
3. PROVISION OF ROAD:
An aqueduct is better than a super-passage because in
the former, a road bridge can easily be provided along
with the canal trough at a small extra cost, whereas in
the latter, a separate road bridge is required.
4. SIZE OF DRAINAGE:
When the drainage is of small size, a syphon aqueduct
will be preferred to an aqueduct as the latter involves
high banks and long approaches. However, if the
DRAINAGE SYPHON
5. COST OF EARTHWORK:
The type of cross-drainage work which does not involve a
large quantity of earthwork of the canal should be
preferred.
6. FOUNDATION:
The type of cross-drainage work should be selected
depending upon the foundation available at the site of
work.
7. MATERIAL OF CONSTRUCTION:
Suitable types of material of construction in sufficient
quantity should be available near the site for the type of
cross-drainage work selected. Moreover, the soil in
sufficient quantity should be available for constructing
the canal banks if the structure requires long and high
canal banks.
8. COST OF CONSTRUCTION:
The cost of construction of cross-drainage work should
not be excessive. The overall cost of the canal banks and
the cross-drainage work, including maintenance cost,
should be a minimum.
DRAINAGE SYPHON
DATA-REQUIREMENT
SOLUTION
DRAINAGE SYPHON
=240 N/mm
span
d
Modification factor = permissible ratio
= 1.4 20 = 28
4000
required
28
d
=142.85 mm.
required
D=d +cover+dia of bar/2
10
2
=142.85+15+ (assume 10 # bar)
=162.85 mm.
Assume an overall depth =170 mm.
Self weight/dead load = D 1 unit weight of RCC
=0.17 1 25
2
=4.25 KN/m
2
=19.96 KN/m
Factored Load=19.96 1.5
2
=29.94 KN/m
W L2
8
Maximum moment =
29.94 4 2
8
=
=59.88 KNm.
W L
2
Maximum shear =
29.94 2
2
=
=59.88 KN.
=2.66
DRAINAGE SYPHON
4.6 M u
1 1
fck bd 2
t 50
fy
f ck
p
4.6 59.88 10 6
1 1
20 1000 150 2
415
20
=50
=0.910
pt b d
streq uired 100
A =
0.910 1000 150
100
=
2
=1365 mm
Provide 10 mm bar
pt b dia 2
4
Astrequired
So spacing =
0.910 1000 10 2
4
1365
=
= 50 mm.
Provide 10 mm# 50 mm c/c
Half of the bars are bent up
0.1L =0.1 4000
= 400 mm
DRAINAGE SYPHON
=204 mm
2
= 0.94
From IS code
0.75 0.56
1.00 0.62
By interpolation
0.62 0.56
1.00 0.94
1.00 0.75
0.56 +
c 2
=0.5744 N/mm
For 170 mm thick slab
c
K =1.26 0.57
DRAINAGE SYPHON
=0.72
59.88 10 3
1000 170
Actual shear =
=0.352 < 0.72 (Safe)
CHECK FOR DEVELOPMENT LENGTH
0
Consider L = 8 # for continuing bars
st 785.4mm 2
A .
1 st u max
Assume, Mu =0.87 fy A (d-0.42 x )
xu xu max
=0.48 d
150
=0.48 =72 mm.
u1 415 785.4 150 0.42 72 10 6
M =0.87
=33.96 KN.m
u 59.88
V KN
M u1
L0 Ld
Vu
1.3
33.96 10 6
1.3 8
59.88 103
i.e. # 47
39 # 737.27
# 18.90 mm . (O.K.)
100 1570.8
t
1000 150
p
=1.04
1365
Service stress =0.58 415 1570.8
2
=209.16 N/mm
Modification Factor=1.42
span
1.42
Permissible d ratio= 20
=28.4
span 4000
Actual d ratio = 150
=26.66<28.4 (O.K.)
CHECK FOR CRACKING
Maximum spacing permitted for main reinforcement =3
160
=480 mm or 300 mm, i.e. 300 mm
Actual spacing =170 mm (O.K.)
Maximum spacing permitted for secondary reinforcement
160
=5 =800 mm or 450 mm, i.e. 450 mm
Actual spacing = 240 mm .. (O.K.)
For trying the bent up bars at top, provide 8 mm # @ 240
mm c/c.
DRAINAGE SYPHON
CONCLUSION
References
Irrigation Engineering
DRAINAGE SYPHON
By Prof N N Basak
Tata Mcgraw-Hill
Khanna Publishers
For Designing
By Prof. H. J saha
Internet Websites
http://www.uap-bd.edu/