Documente Academic
Documente Profesional
Documente Cultură
0
1
FORWARD
(S.K.DHARGUPTA)
CHIEF POWER & UTILITIES MANAGER
GUWAHATI REFINERY
IOC GUWAHATI
CONTENTS
1
2
2
3
These two parameters (i.e. voltage and frequency) most be perfectly steady
in rated value with in tolerable limit of variation for proper operation of any
power system.
3
4
THE TPS SHALL ENSURE SUPPLY OF POWER, STEAM, AIR & WATER AS FOLLOWS UNDER
NORMAL CONDITION.
1. WATER IS COMING FROM INTAKE PUMP HOUSE THROUGH INTAKE PUMPS IN OUR SYSTEM.
2. CIRCULATION WATER SHALL BE SUPPLIED TO PROCESS UNITS THROUGH COOLING WATER
PUMPS (18-PM-01A/B/C ) AS PER FOLLOWING PRESSURE & TEMPERATURE :-
PRESSURE: - 2.0 KG/CM ----- 2.5 KG/CM TEMPERATURE:- 29DEG.C ------ 33DEG.C
AIR
INSTRUMENT AIR: - MOISTURE FREE DRY AIR AT 5.8KG/CM ---- 6.4KG/CM AND AT AMBIENT
TEMPC. SHALL BE SUPPLIED THROUGH OUR AIR COMPRESSORS (13KM-01A/B/C ).
SERVICE AIR: - SHALL BE SUPPLIED AT 6.0KG/CM ----7.0KG/CM UNDER NORMAL CONDITIONS.
HOWEVER AS PER PLANT REQUIREMENTS DUE COMPRESSOR MAINT, SERVICE AIR MAY NOT BE
AVAILABLE FOR SHORT DURATION.
3. DEFINITIONS OF EQUIPMENTS
4
5
ALTERNATORS
TRANSFORMERS
Transformers are the devices, which step up or step down the voltage as per the
requirement. Transformers are the static apparatus for transferring power from one circuit
to another without change of frequency. In Guwahati refinery all the power transformers
are utilized for step down the voltage. Only DG sets transformers are utilized for step up
the voltage. Based on the utilities, transformers are divided into following categories:
* STEP UP TRANSFORMER: Transformers used to step up the voltage. At
Guwahati refinery, DG power is generated at 415 Volts. 415V DG voltage is stepped up
to 6.3 KV to match our generation voltage to transfer power to our system.
* STEP DOWN TRANSFORMERS: Transformers used to step down the voltage. At
Guwahati Refinery, most of our utilities/motors are operating at 433 Volts; therefore
generated power is step down from 6.3KV to 433 Volts.
* AUTO TRANSFORMERS: Used for HT motors starting. Autotransformer reduces
the line currents of the HT motor.
* UNIT STEP TRANSFORMERS: Utilized at GR for Lighting purposes e.g. 433/433
Volts transformers.
* INSTRUMENT TRANSFORMERS: It is a step down transformers, normally used
to step down the voltage from 433/230V, 433/110V or 230/110V.
* POTENTIAL TRANSFORMERS: It is used for metering and protection of line/
phase voltages.
* CURRENT TRANSFORMERS: It is used for metering and protection of the line
currents.
SWITCHGEARS
It houses such equipment, which locates the fault on the system and isolate the faulty part
from the healthy section. It contains Circuit Breakers, relays, switches, fuses & others
control devices.
5
6
Generated Electrical power from a power station is a complex power. This complex
power is the components of Reactive & Active power:
Complex Power (KVA) = Active Power (KW) + Reactive Power (KVAr)
Active Power (KW) is also called as real power as it actually does the work. Active
power is developed by steam input to turbine. Reactive power is also called as imaginary
power. Reactive power is induced from Excitation of the Generator.
HP LP
G
E
SIDE SIDE X
B3 E C
I
V N
B4 M
H
GOVERNOR E
B5 A CW INLET
C
D O
E N
COOLING
B6 R D
E TOWER
N N
R
B7 V CW OUTLET
CONDENSATE
PUMPS
DM
TANK
TO UNITS DEARATOR
BOILER FEED PUMPS
6
7
3) Heat : Calorie is the unit of heat..It is the amount of heat required to raise
the temperature of 1gm of water through 1C. Kilocalorie is commonly
been used.
RELATIONSHIP
In AC circuit, there is a phase difference ' between voltage and current. The term
cos is called the power factor of the circuit
I
I Sin or
. Apparent Power Reactive power
V
I cos or
Active power
In others words power factor (Cos ) = Active power (kW) / Apparent power (kWA)
From the above power triangle, followings are conclusive:
7
8
1. Smaller the Reactive power component, higher is the power factor of the
circuit.
2. Higher the Active power component, Higher the power factor.
P = 3 V L I L Cos
I L = P / ( 3 VL Cos )
From the above it is clear that for fixed power & voltage Load current is inversely
Proportional to power factor. The disadvantages listed below due to low power factor
1)
LARGE KVA RATING OF EQUIPMENT. Low power factor results in higher
KVA rating (KVA = KW/ Cos ).
2) LARGER CONDUCTOR . Lower the power factor, more current the conductor
to carry. To transmit more current, larger x- sectional area conductors are required .
3) LARGER LINE (COPPER) LOSSES. Losses = I R. Higher current mote
losses.
4) POOR VOLTAGE REGULATION.
CAUSES OF LOW POWER FACTOR. Major contribution of the lower power factor
is
Due to induction motors operates at lower power factor.
* Static Capacitors
* Synchronous condenser
* Phase advancers.
a) UNDERGROUND CABLES
However, their major drawback is that it has greater installation cost and introduce
insulation problem at higher voltage compared to equivalent overhead lines.
8
9
* Cores or conductor
* Insulation
* Metallic sheath
* Bedding
* Armoring
* Serving
b) SWITCHES
Switches are the devices, which is used to open or closed the Electrical circuit in a
convenient way. It can be used under full load or no load conditions but it can not
Interrupt the fault currents.
When the contacts of a switch are opened, an arc is produced in air between the
contacts. This is particularly true for circuit of high voltage or large current
capacity. The switches may be ( I ) Air switches ( II ) Oil switches. The contacts of
air break switch are opened in air that of the latter are opened in oil.
c) ISOLATORS
d) FUSES
Fuses are installed in series to the circuit to be protected. The fuse consists of a
short piece of wire or thin strip, which melts when excessive current flows through
it for sufficient time.
Always installed the proper size, type & capacity fuses in the circuit . For motor
circuit, select the fuse rating as per the chart.
Always use the HRC fuses. Never use wire in place HRC fuse. Here is the list of
fuse selection for different capacities of DOL motors.
9
10
e) CIRCUIT BREAKER
10
11
(I) Oil circuit breakers: Oil circuit breaker employs some insulating oil for ARC
extinction. Application :- (a) 6.3 KV generation buses Siemens section.
(b) Non essential Bus breakers
(c) 12-02 sub station breakers
(d) Intake sub station breakers
(II) Air blast circuit breakers: This type of breakers high-pressure air blast is used for
extinguishing the ARC.
Application: - All LT breakers are Air circuit breakers at Guwahati
Refinery
(III) Vacuum circuit breakers : Vacuum circuit breakers in which Vacuum is used for
ARC extinction.
Application: - (a) All HT breakers of New sub-station (Make Siemens)
(b) Some breakers at TPS HT section (Make Siemens)
OPERATING PRINCIPLE
A circuit breaker essentially consists of fixed and moving contacts, called poles. Under
normal conditions, breaker contacts remain unchanged. When tripping coil get the
energy, breaker is tripped to isolate the live part from the fault (meaning thereby open
the breaker contacts). Breaker can also be tripped manually.
11
12
* Check the Current carrying parts, clean if carbon deposition with strong and dry
fabric.
* Check the oil level in the oil chamber. Get it filled, if level is low.
* Check Mechanical tripping and closing of the breaker.
* Check and clean the breaker chamber.
* Check the panel space heater & and maintain the temperature ~ 35 Deg C.
* Check the Vacuum in bottles after detaching lower poles hinging from lower poles.
* Check the breaker auxiliary contracts. Elevate the depressed contact pin.
f) RELAYS
12
13
DEFINITION: A protective relay is a device that detects the fault and initiates the
operation of the circuit breaker to isolate the defective element from the rest of the
system.
BUS BAR
CIRCUIT TRIP
CONTROL
BREAKER COIL SUPPLY
RELAY
RELAY
C.T COIL
FAULT
The above sketch is the general arrangement of relay circuit with protection to open the
circuit breaker. From the above figure, it can be seen that when a fault occurs at
mentioned F on the system, the current flowing in the line increases enormous value.
This causes heavy current flow in to the relay coil, causing the relay to operate by closing
its contacts.
When the relay contact is made through, control supply to breaker trip coil gets through.
Trip coil in such cases after getting the energy; operate the circuit breaker to open the
faulty portion of supply system.
Basic relays : Most of the relays installed in old system are basic relays. They work on
the principal of (i) Electromagnetic attraction & (ii) Electromagnetic induction.
13
14
Numerical Relays : Basic relays have low speed, less sensitivity & reliability reduces
in due course of time. One of the other major drawbacks of basic relays is that they
have the plug setting multiplier in steps of 0.25. Whereas numerical relays have the
setting range in plug setting multiplier of 0.1. Minimum setting on the over current
Electromagnetic relays is 0.25 whereas Numerical relays can be set at 0.1. Followings
are the Numerical relays installed at Guwahati Refinery:
Micom P-121
Micom P-147
g) BATTERY BANK
For example capacity of each battery bank 220V. TPS main battery charger is 600A/H.
It means 100A current can be delivered by battery for 6 hours.
OR
Battery can supply 50 amps X 12 hours.
At Guwahati Refinery, we monitor the physical condition of batteries e.g. condition of:
h) BATTERY CHARGER
14
15
battery connected to the out put, the charger will supply sufficient current to maintain
the battery at full charge regardless of variations in line or load within its rating.
LIST OF GR CHARGERS
All the battery chargers are provided with two modes of operation viz. Boost & Float
battery charger. Charger in Float or Trickle mode is the normal operation of the charger.
Put charger in Boost mode of operation once in three months, if batteries are not
employed in Boost mode or charger is not put in Boost mode.
METERING
INDICATIONS ALARMS
INDICATING LED
15
16
LOAD
AC =
MAINS
RECTIFIER
CONVERTS
AC TO DC
BATTERY
BANK
This feature enables the charger to detect the need of the battery for charge and
automatically Boost it to full capacity. Charger returns to the float mode after
completely charging the battery. This feature is optional. At GR this feature is not
available.
Normal operation of the charger is in float mode. Switch over of charger from Trickle
to Boost mode or vise-versa can be accomplished manually.
To change the charger into Boost mode, just press the push button marked Boost on
the chargers front panel.
Falling of the Boost current below the set value (or ~ to float current), bring the charger
back to Float by pressing push button marked Float on the charger front panel.
The 3-ph full wave bridge rectifier provide a variable DC voltages at in output
DO S
16
17
DO NOT S
17
18
J) UPS
18
19
At Guwahati Refinery we have Tata Libert make UPS systems. The block diagram of
UPS system is :
INPUT MAINTENANCE
MCCB BY-PASS SW
SVR
ST SW
ISOLATOR
INPUT
MCCB
L
O
RECTIFIER INVERTER
A
D
INPUT OUTPUT
ON/OFF ON/OFF
SWITCH SWITCH
BATTERY
BANK
Mimic Indications
Control switches
&
19
20
MIMIC INDICATIONS
Six LEDs are mounted on a single line diagram to represent the various UPS power
paths
These leds, which are annotated in figure shows the current UPS operational status and
should to interpreted as below
LS3 LS5
This LED illuminates when the input isolator is closed, the input supply is within 20%
of nominal voltage, and the rectifier is operative.
This LED glows when the battery circuit breaker is closed and the voltage is with in
UPS operating range.
This LED glows when the static bypass supply is within 10% of its nominal voltage
(and the static bypass isolator is closed)
20
21
This LED glows when the inverter is operating and its output is within a preset
acceptable voltage window.
This LED glows when the output isolator is closed and the load is connected to the
Inverter via static switch.
This LED glows when the output isolator is closed and the load is connected to the
Inverter via static switch.
CONTROL SWITCHES
Seven tactical switches are located on the operation panel, together with an emergency
stop push button, which is fitted with a safety cover to prevent inadvertent operation.
When this switch is pressed, the lower line of the LCD display shows the output line to
line voltages on all three phases. For single phase, it shows phase to neutral voltage.
When this switch is pressed, the lower line of the LCD display shows the output
frequency
When this switch is pressed, the lower line of the LCD display shows the output line
(And neutral) currents for 3 phases. For single phase it shows phase current only.
When this switch is pressed, the lower line of the LCD display shows the battery
voltage
And current. Note that a discharging current is symbolized by a preceding minus (-).
Pressing this switch cancels the audible alarm. The alarm led and messages will remain
active if a detected fault condition is still present.
21
22
Pressing this switch turns OFF the inverter and causes the load to be transferred to the
static bypass supply.
SWITCH S7 Inverter ON
Pressing this switch activates the inverter and caused the load to be transferred to the
inverter side of the static switch after the inverter voltage had time to stabilized.
When the emergency stop is pressed it disables the static switch block entirely (so
removing load power). It also disables the rectifier and inverter, and trips the battery
circuit breaker. Under normal circumstances it does not remove UPS input power
since this is applied through a manually controlled isolator, however, if the UPS input
power is connected via a circuit breaker having an electrical trip facility the
emergency stop signal can be used to drive the external circuit breakers trip circuit.
There are two LEDs contained within the switch panel area:
LS7 - Alarm
This led accompanies the audible alarm warning when any alarm condition is initiated.
The audible warning can be cancelled by reset switch (S5) but LS7 will only extinguish
after the alarmed condition has reverted to normal.
This green led situated near the inverter ON switch illuminates when the inverter is
selected
ON.
k) POWER TRANSFORMER
22
23
l) AUTO TRANSFORMER
AUXILIARIES 0F TRANSFORMER
* BUCHOLZ RELAY : The relay serves as main protection for any minor or major
faults that may develop inside the transformer. Such fault always result in generation of
gases which causes the operation of mercury switches giving signal for audible alarm or
isolate the transformer from the network or both.
23
24
Switch on the cooling equipment when winding attains a preset high temperature
and
Switch it off when the temperature drops by an established differential
(transformers with forced cooling are not existing in Guwahati Refinery).
* BUSHING AND CABLE SEALING BOX : Low and High voltage leads are
taken out of the transformer tank to enable to make cable connections through
Bushings. The bushing is a structure carrying a conductor through a partition in the tank
and insulating the conductor from partition.
24
25
packed with silica gel dissident, which dries the air effectively. A freshly regenerated
gel dries the air unto (-) 35 Deg C.
* BASIC FORMULA
Example: Calculate the primary and secondary side rated current of 6.3 / 0.433KV,
2.5 MVA power transformer.
I L = 229.11A
II) To calculate secondary current on 0.433KV side (apply the above formula)
2500KVA = 3 0.433 IL (primary side Line current in A)
I L = 3333.53 A
IMPORTANT NOTES:
When transformer is switched ON, phenomena at the initial charging which last
within few microseconds take place. During the switching ON power transformer
draws as high as 8 to 10 times to rated current called transformer inrush current. For
example, when 2.5 MVA power transformers is switch ON, it may draw line current
from mains at 6.3 KV from 1832.88 A to 2291 A. (Reference Alstom Relay Manual).
In all the sub station, Electrical power buses are provided with two incomers and one
bus coupler (expect 12/06 HT bus wherein two incomers without bus coupler is
25
26
installed and is in operation). Both incomers ON with Bus coupler OFF in Auto
are normal operation of the sub-station. Followings checks will be done to maintain
the sub-station healthy:
Both incomers ON , bus coupler OFF in auto mode in all the sub-stations.
No relay is operated. If any relay is found operated / or flag is dropped, intimate to
the Electrical Engineer and subsequently in consultation with SELE (M)/ ELE (T),
reset the relay / flag.
Observe the body temperature of the switchgear of individual panel by touching, it
should not be hot. If found hot intimate to Electrical Engineer and subsequently in
consultation with SELE (M)/ ELE (T), change the feeder and get it attended by
Elect Maint.
Control supply of the sub-station is available.
Maximum allowable transformer winding temperature, is 55 deg C above ambient.
Normal operating winding temperature is ~ 50 deg C as our power transformers are
operating at ~35% to 60% load. Any increase in temperature above 50 deg C
indicates some abnormality, under the circumstances transformer should be
attended.
Maintain the transformer oil level between 45% to 60% in conservator.
Check date of testing, validity date & inspection due date mentioned on a tag and
attached on fire extinguishers provided in sub-stations. The fire extinguishers will
be checked before expire.
In HT-201 Bus, keep Auto / Manual switch in Manual position if single TG is
in operation and in Auto position when Two TGs are in operation. Whereas in all
cases PCC-301, PCC-302 & PCC-303 should be kept in Auto
Keep the cables entries sealed & cable entry to be observed and arrenge to seal, if
found damaged.
Keep the cable trenches covered with RCC slabs outside the sub-station and with
checkered MS plates inside the sub-station building.
Sub-station pressurization system always to kept in operation.
Get the chemical & paste control measures being used in the sub-
station/switchgears room for lizard and rat control.
Keep the sub-station lighting up to date. Replace all the fused tube light fixtures.
Check the DC lighting as per schedule & replace the faulty circuit (if found) or
fused lamps.
Keep the transformer yards clean and free from vegetation. Revise the grabbles
inside the transformer yards with 1.5 inch sizes.
Keep the silica gel breather fresh.
Always lock the transformer yards with master key
26
27
be taken for proper changeover. Do the followings while changing over or taking back
both the incomers:
While changing over incomer i.e. Isolating one incomer and closing the bus coupler (in
general)
Note down the current load incomer II, the running incomer.
Close the up stream breaker of dead incomer I with up strem breaker TNC
switch.
Insert the down stream breaker in to service position of incomer I
See that the voltage meter of Incomer-I (Line PT) is showing the voltage.
Check all the three phase voltages of Incomer-I, after selecting voltmeter selector
switch to ensure that all the three poles are close properly.
Now close the downstream breaker of Incomer-I by TNC switch.
Note down the current on each Incomer i.e. Incomer-I & II and also check that load
must be shared equally by both Incomers.
Now switch off (open) the bus coupler breaker by bus coupler TNC switch.
Report the same to ECR stating that the changeover is completed.
27
28
selected in auto position, when upstrem breaker is tripped and line voltage is not
available. In normal condition, keep both the incomers ON and Bus coupler OFF in
AUTO, in this condition, if the incomer is tripped from upstream, bus coupler will close
automatically.
The objective is to close the bus coupler and open Incomer I. Do the followings:
Now the object is to close the Incomer-I & open the bus coupler. Do the following:
* Incomer I : ON
* Incomer II : ON
* Bus Coupler : ON
28
29
29
30
HT SWITCHGEAR
CONTACTOR PURPOSE
3. ALL THE HT MOTORS, IN GENERAL ARE DESIGNATED FOR 2 HOT AND 3 COLD
STARTS.
6. KEEP HT-201 BUS COUPLER IN AUTO POSITION WHEN BOTH TGS ARE IN
OPERATION.
KEEP BUS COUPLER SWITCH IN INDEPENDENT MODE WHEN SINGLE
TG IN OPERATION
30
31
In the case of change over of running TG, AVR from Auto to Manual mode then
immediately inform to electrical testing, SRSM and shift in charge of all units to be
informed not to start the HT motor and change over of any equipment should be done
with the clearance of TPS operation.
In case of system earth fault alarm all the outgoing feeders to be checked and faulty feeder to be
identified and to be isolated immediately.
In case of sudden load thrown off due to tripping of running Unit/HT section frequency and voltage of
system will rise. In that case it is to be controlled manually immediately.
4. D.G. TRIPPING:
In case of DG set tripping, check the system load, if running TGs cannot take the load,
1. Load shed the non-essential load (Colony, ETP, OM&S and INTAKE Pumps),
Watch the frequency, if frequency has downward trend, ask the PNE of HDT to reduce the
load. Watch the system frequency it is O.K. than no further load shedding is required. If
frequency still has a falling trend, CDU may be load shaded.
31
32
The status of the Microprocessor based scheme is seen in the Monitor at ECR.
32
TG TRIPPING Boiler 3,4,6,7 Boiler 5,6,7 run
OPERATING CONDITION
TG 3/4 & 5 run
TG 3& run (or) Boiler 33 (or) Boiler
Boiler 3,4,6&7 are Boiler 3,4,5&6/7
running are running
4 run 5,6,7 run 3,4,5,6/7 run
BO IL E R 3/4 T RIP w h en
BO IL E R 3/4 T RIP w h en
T G 5 T RIP CO NDIT IO N
I II III IV V
BO IL E R 5 T RIP
L O AD IN T P H
L O AD IN M W
T G 3/4 T RIP
T G 3/4 T RIP
CO NDIT IO N
CO NDIT IO N
ru n n in g
ru n n in g
S .No .
2 OM&S 0.6 6.4 0.6 0.6 0.6 0.6 6.4 0.6 6.4 4 0.6 6.4
3 CISF 0.15 0.6 0.15 0.15 0.15 0.15 0.6 0.15 0.6 0.15 0.6
Coke
4 0.7 2.8 0.7 0.7 0.7 0.7 2.8 0.7 2.8 0.7 2.8
Cutting
5 Intake 0.5 2 0.5 0.5 0.5 0.5 2 0.5 2
7 WGC 0.6 2.8 0.6 0.6 0.6 0.6 2.8 0.6 2.8
8 12-02 s/s 0.6 2.8 0.6 0.6 0.6 0.6 2.8 0.6 2.8
9 ISOSIV 0.5 2 0.5 0.5 0.5 0.5 2 0.5 2
10 CDU 0.8 10 0.8 0.8 0.8 0.8 10 0.8 10
11 ETP 1 6 1 1 1 6
12 HDT 2.5 10 2.5 2.5 2.5 10
15 CT 0.6 2.4
12.95 65.4 5.45 8.95 8.95 8.95 49.4 5.45 33.4 4 1.95 11.8
PLUS OM&S ONLY
PLUS OM&S PLUS OM&S
AND ETP OM&S
STEAM STEAM
STEAM STEAM
Boiler 3,4,5,6/7 run (or) Boiler 3,4,6&7 run (or) Boiler 5,6,7 run
OPERATING CONDITION
w hichever is applicable
B O IL E R 3 / 4 & 5
B O IL E R 5 & 6 /7
CASCADE TRIPPING FOR BOILERS
B O IL E R 6 & 7
B O IL E R 3 & 4
L O A D IN T P H
L O A D IN M W
S .N o .
7 WGC 0.6 2.8 0.6 2.8 0.6 2.8 0.6 2.8 0.6 2.8
8 12-02 s/s 0.6 2.8 0.6 2.8 0.6 2.8 0.6 2.8 0.6 2.8
9 ISOSIV 0.5 2 0.5 2 0.5 2 0.5 2 0.5 2
10 CDU 0.8 10 0.8 10 0.8 10 0.8 10 0.8 10
11 ETP 1 6 1 6 1 6 1 6
12 HDT 2.5 10 2.5 10 2.5 10 2.5 10
1 Colony 0.50
2 CISF 0.15
3 OM&S Feeder-2 0.30
4 LRU Compressor Group-1 2.70 MW 49.00hz:0.5s 0.50
5 Coke cutting 0.70
NE Panel
6 0.55
(Intake-1 + OM&S-1)
7 Intake-2 0.25
8 WGC Group-2 4.85 MW (2.15+2.70) 0.60
9 ISOSIV 48.75hz:0.75s 0.50
10 CDU 0.80
11 ETP Group-3 8.35 MW (3.5+2.15+2.70)MW 1.00
12 HDT 48.50hz:1.0s 2.50
Group-4 10.55 MW
13 INDMAX 2.20
(2.2+3.5+2.15+2.70)MW 48.25hz:1.25s
14 DCU Group-5 12.35 MW 1.20
15 Cooling Tower (1.8+2.2+3.5+2.15+2.7) MW 48.00hz:1.5s 0.60
Total Load Shedding 12.35 MW
TOTAL L OA D S HE D
50. 00
12.35 MW
34
35
1. CHECKS & CONFIRMS THAT THE ISOLATION OF THE EQUIPMENT IS ASKED BY THE
OWNER LINE CLEARANCE FROM (OWNER: PRODUCTION IN CASE OF UNIT &
OPERATION IN CASE OF TPS).
3. PREPARE THE ISOLATION PERMIT AND NOTE DOWN IN DETAIL ALL PTECAUTIONS
TAKEN IN THE LOG BOOK AS WELL AS IN THE ISOLATION BOOK (REGISTER)
INCLUDING SL NO & DATE. & ISOLATE EQUIPMENT FROM THE SORCE SIDE
6. RACK OUT THE BREAKER FROM ITS SERVICE POSITION TO ISOLATING POSITION.
LOCK THE BREAKER AT ISOLATING POSITION. TAKE OUT THE KEY. (TAKE OUT
POWER FUSES IN CASE OF SWITCH FUSE MODULE)
7. TAKE OUT ORIGINAL LINE CLEARANCE WITH COPY & KEYS /FUSES. KEEP IN THE
LINE CLEARANCE & FUSE KEEPING RACK. HAND OVER THE KEY TO THE OWNER
(e.g. PRODUCTION / TPS OPERATION)
9. CHECK & ENSURE THAT LINE CLEARANCES SHOULD BE ISSUED TO ALL CONCERN
AGENCIES WHOSOVER PERFORM THE JOB EVEN ON ALREADY LINE CLEARANCE
ISSUED EQUIPMENT.
35
36
36
37
1. CHECKS & CONFIRMS THAT THE ISOLATION OF THE EQUIPMENT IS ASKED BY THE
OWNER IN THE LINE CLEARANCE FROM (OWNER: PRODUCTION IN CASE OF UNIT &
OPERATION IN CASE OF TPS).
2. INDENTIFY THE ISOLATION SOURCE CHECK THAT THE EQUIPMENT IS NOT IN OPERATION.
3. PREPARE THE ISOLATION PERMIT AND NOTE DOWN IN DETAIL ALL PTECAUTIONS TAKEN IN
THE LOG BOOK AS WELL AS IN THE ISOLATION BOOK (REGISTER) INCLUDING SL NO &
DATE. & ISOLATE EQUIPMENT FROM THE SORCE SIDE
4. PUT THE MEN AT WORK TAG ON THE PANEL AS WELL AS ON THE EQUIPMENT UNDER
MAINTENANCE / LINE CLEARANCE.
5. RACK OUT THE BREAKER FROM ITS SERVICE POSITION TO ISOLATING POSITION. LOCK
THE BREAKER AT ISOLATING POSITION. TAKE OUT THE KEY. IF APPLICABLE.
6. TAKE OUT ORIGINAL LINE CLEARANCE WITH COPY & KEYS /FUSES. KEEP IN THE LINE
CLEARANCE & FUSE KEEPING RACK. HAND OVER THE KEY TO THE OWNER (e.g.
PRODUCTION)
.
7. TEST THE EQUIPMENT BY GIVING ON COMMAND FOR COMPLETE ISOLATION.
9. CHECK & ENSURE THAT LINE CLEARANCES SHOULD BE ISSUED TO ALL CONCERN
AGENCIES WHOSOVER PERFORM THE JOB EVEN ON ALREADY LINE CLEARANCE
ISSUED EQUIPMENT
*** NOTE: ELECTRICAL AUTHORISED PERSON MUST CARRY OUT ALL THE ACTIVITIES. ***
37
38
SR NO: - DESCRIPTIONS
38
39
2. POWER TAKEN FROM ASEB ON BUS I & II ( 6.3 KV) ECR (OPTR)
39
40
1. RESET GEN LOCK OUT RELAY (86A), UNIT LOCK OUT RELAY
(86B) AND TRIPPING RELAY (86AX) ECR OPTR
10. CHECK GEN FLD BRK & EXCITER FLD BRK AS BELOW
40
41
c) SWITCH OFF GEN FIELD BREAKER & THEN EXCITER FIELD BRK
SHOULD TRIP. ECR OPTR
c) FIELD UNDER VOLTAGE RELAY (81-1, 81-2) & THEIR TIMERS. ECR OPTR
*************************
41
42
2. INFORM TURBINE OPERATOR THAT TG IS GOING TO BE SYN WITH ASEB ELE (ECR)
3. CHECK THAT OLTC ( ON LOAD TAP CHANGER) IS OPERATING FROM ECR) ECR (OPTR)
4. INSERT THE SYNCHRONISING KEY INTO ASEB SYN KEY SEC I, ASEB
33/6.3KV SEC I SOCKET OF THE 6.3KV SIDE CONTROL KEY OF 33KV
TRANSFORMER OF THE PERTICULAR SECTION (PRESENTLY TR I SIDE) ECR (OPTR)
11. IF REQUIRED VOLTAGE CAN ALSO BE ADJUST WITH ONLC ECR (OPTR)
12. INFORM THE PANEL OPTRS OF THE TURBINE THAT THE SYSTEM HAS BEEN
SYNCHRONISED WITH ASEB ELE (ECR)
13. REDUCE LOAD ON TURBO GENERATOR AND IMPORT THE POWER FROM
ASEB AS REQUIRED. ECR (OPTR)
42
43
1) CHECK THAT NO LINE CLEARANCE IS PENDING TO ANY AGENCY FOR ANY OF THE
BREAKERS (PANEL NO. 10 & 42 IN GEN BUS SEC I & II AND NO. 6 AT NE BUS).
2) RACK-IN TO ANY OF THE BREAKERS TO ITS SERVICE POSITION & LOCK THE BREAKER
AT SERVICE POSITION (PANEL NO 10 IN GEN BUS SEC I, PANEL NO 42 IN GEN BUS SEC
II FOR SYNCHRONIZING DGS WITH GUWAHATI REFINERY SYSTEM OR PANEL NO. 6 AT
NE BUS FOR SYNCHRONIZATION WITH ASEB).
3. SWITCH ON THE DC CONTROL SUPPLY & AC SUPPLY OF THE SELECTED BREAKER (AS
PER POINT NO. 2).
4. RESET ALL THE OPERATED RELAYS.
5. ENSURE THAT THE SPRING OF THE BREAKER IS CHARGED.
6 CHECK AND ENSURE THAT NO DG BREAKER IS CLOSED.
7. CHECK AND ENSURE THAT DG CONTROL PANEL MAIN ISOLATING BREAKER (4.0 MVA, 6.3 /
0.415 KV) AT LT SIDE IS OFF.
8. NOW CLOSE THE BREAKER IN SERVICE POSITION (PANEL NO 10. IN GEN BUS SEC- I,
PANEL NO 42 IN GEN BUS SEC II FOR SYNCHRONIZING DG S WITH GUWAHATI
REFINERY SYSTEM OR PANEL NO 6 AT NE BUS FOR SYNCHRONIZING WITH ASEB).
2. SYNCHRONAZATION PROCEDURE
43
44
5) SCROLL THE MANUE ON DG PCC, AND BRING IT TO BUS FREQUENCY & ANGLE MANUE.
CLOSE THE DG BREAKER FROM DG PCC WHEN ** APPEARS AHEAD OF ANGLE.
6) NOW LOAD THE DG BY ADJUSTING REGULATOR VOLRAGE SLOWLY & SLEADILY IN
CONTROL PANEL AS PER DEMAND OF LOAD ON THE DG.
7) IF THE RAGULATOR VOLTAGE IN CONTROL PANEL IS ADJUSTED BEFORE ACTION AT SL.(5)
& (6), DG WILL GENERATE POWER UP TO PRESET LOAD IN 120 SECONDS.
44
45
1. CAUTION
a) RED SWITCHES AND RED PUSH BUTTONS AFFECT SYSTEM OPERATE ONLY
WHEN SURE ABOUT IT.
b) BLAKE SWITCH AND BLACK PUSH BUTTON PERFORM MONITORING THE SYSTEM.
2. STARTING MODULE I / II
a) CLOSE CONTROL SUPPLY SWITCH (S3) ON THE MODULE (INSIDE).
a) CHECK GREEN LIGHT INDICATIONS OF CB1, CB2, AND CB3.
c) CLOSE CB1 SWITCH AND SEE RED LIGHT INDICATION ON CB1. OBSERVE FOR 10 TO
15 SECONDS AND SEE THAT DC AND AC OUT PUT VOLTAGE RAISE GRADUALLY.
d) CLOSE BATTERY CIRCUIT BREAKER CBB AND SEE RED LIGHT LAMP INDICATION ON
MODULE MIMIC CHECK BATTERY CHARGING CURRENT ON (M5)
e) CLOSE OUT PUT CIRCUIT BREAKER CB1 AND SEE RED LAMP INDICATION ON OF
MODULE MIMIC.
45
46
46
47
47
48
48
49
.
4. IF ALL THE THREE TGS (TG-3, 4 & 5) ARE IN OPERATION
UNDER THIS CONDITION AUTO LOAD SHEDDING WILL NOT TAKE PLACE
DURING TRIPPING OF ANY ONE TG.
KEEP THE SELECTION SWITCH FOR TG-3, 4 & 5 ON AND OTHER SWITCHES OFF.
SWITCHES OF TG-3, TG-4 & TG-5 SHOULD BE KEPT ON.
PUT AUTO-MANUAL SWITCH IN MANUAL MODE
IF TG-3 OR TG-4 TRIPS NO LOAD SHEDDING IS REQUIRED.
HOWEVER IF TG-5 TRIPS MANUAL LOAD SHEDDING GROUP-1 CAN BE
OPERATED BY PRESSING COMMON BUTTON AND GROUP-1 BUTTON
SIMULATANEOUSLY.
SWITCH OF TG (WHICH HAS TRIPPED) SHOULD BE PUT OFF.
SELECT BALANCE TWO TGS IN OPERATION BY SWITCHING ON EITHER TG-3/4
&5 OR TG3&4 AS THE CASE MAY BE AND SWITCH OTHER TWO-SELECTION
SWITCH OFF.
PUT THE AUTO MANUAL SWITCH IN AUTO POSITION.
BEFORE PUTTING THE LOAD SHEDDING SWITCH IN AUTO MODE, PLEASE
ENSURE ALL THE SWITCH POSITIONS ARE IN CORRECT POSITION AS PER
SYSTEM REQUIREMENT.
49
50
SWITCH ON THE SELECTION SWITCH FOR BOILER 5, 6 & 7 & ENSURE OTHER
SELECTION SWITCHES ARE OFF.
SWITCH ON BOILER 5, BOILER-6 & BOILER-7 AND ENSURE THAT BOILER 4 &
BOILER-3 SWITCHES ARE OFF.
PUT AUTO MANUAL LOAD SHEDDING SWITCH IN AUTO MODE.
AS SOON AS ANYONE BOILER TRIPS AUTO LOAD SHEDDING WILL TAKE
PLACE.
AFTER ADJUSTING LOAD ON RUNNING TWO BOILERS, SWITCH OFF THE
TRIPPED BOILER SELECTION SWITCH OFF AND ADVISE THE ELECTRICAL
CONTROL ROOM TO RESET PLC.
PLEASE NOTE THAT LOAD SHEDDING PLC CAN BE RESET ONLY FROM
ELECTRICAL CONTROL ROOM.
SWITCH ON THE SELECTION SWITCH FOR BOILER 3,4,6 & 7 & ENSURE
BOILER-5 SELECTION SWITCHES IS OFF.
SWITCH ON BOILER 3, BOILER-4, BOILER-6 & BOILER-7 AND ENSURE THAT
THE IDLE BOILER SWITCH IS OFF.
PUT AUTO MANUAL LOAD SHEDDING SWITCH IN AUTO MODE.
AS SOON AS ANYONE BOILER TRIPS AUTO LOAD SHEDDING WILL TAKE
PLACE.
50
51
WHEN AT A TIME TWO BOILERS TRIPS, AUTO LOAD SHEDDING WILL TAKE
PLACE AS PER REQUIREMENT.
PLEASE NOTE THAT PLC LOAD SHEDDING CAN BE RESET ONLY AFTER
PUTTING THE TRIPPED BOILERS SWITCHES IN OFF POSITION.
IN ADDITION TO AUTO LOAD SHEDDING, THE OM&S STEAM AND THE ETP
STEAM CAN ALSO BE SHEDDED BY INDIVIDULA SWITCHES PROVIDED ON
LOAD SHEDDING PANEL.
S.C.GHOSH.
ELE (TPS)
51