Sunteți pe pagina 1din 1

22 CHAPTER TWO

able to hold the owner or architect/engineer accountable for Summary


the acts or knowledge of that apparent agent.
The doctrine of apparent authority does not apply to The foregoing provisions can best be summarized in the
public agency owners, as statutes shield them from liability following four guidelines:
for the acts of anyone other than the actual designated agent. 1. Establish actual authority in the contract with a specific
Private organizations can protect themselves by contractu- individual. Do not designate a position, job title, or
ally designating an individual with authority to act for them group of individuals.
and disclaiming responsibility for the acts of anyone else.
2. Disclaim any apparent authority and establish admin-
This is not totally foolproof, however, as the contractual
istrative procedures consistent with the disclaimer
disclaimer can be constructively waived by a persistent pat-
language.
tern of conduct that is inconsistent with the terms of the
contract. A similar result may occur through ratification. An 3. Do not give designated representatives the right to
owner or a contractor may, by its conduct, ratify the unau- further delegate their authority.
thorized actions of a person at the job site. The most com- 4. When granting limited authority, state objective guide-
mon form of ratification is silence or acquiescence. In other lines to delineate the scope of that authority.
words, if an owner or a contractor sits by silently while one
of its people takes charge at the job site, it will be difficult
later to argue that the individual lacked authority to make a
WHY HAVE AN INSPECTOR?
particular decision or issue a particular directive. It is not enough to leave the assurance of quality workman-
ship and materials entirely in the hands of the contractor. The
Delegation of Authority architect/engineer or other design firm that was responsible
for the determination of site conditions and for the prepara-
Once actual authority has been conferred on an agent, such as tion of the plans and specifications should be retained during
a Resident Project Representative, it is possible to allow that the construction phase to provide field administration and
agent to delegate his or her authority, say, to one of the inspec- quality assurance for the owner, the safety of the public, and
tors. It is sometimes common to grant certain authority to a the professional reputation of both the design firm and the
specific individual or his or her designated representative. contractor. Many architects and engineers seem to believe
The phrase or designated representative may create that if their design is adequate and the plans and specifica-
problems, however. Other companies may not be able to tions are carefully prepared, the field construction will take
determine whether there has been an effective delegation of care of itself. Experience has proven this to be far from true.
authority. The option of delegating authority also increases Although a design firm acting as the agent of the
the likelihood of creating the appearance of authority. It is owner during the construction phase of a project does not
then inconsistent with any disclaimer of apparent authority. guarantee the work of the contractor, nor does such agent
Actual authority may be delegated even by a public in any way relieve the contractor of any responsibilities
agency. As an example, an excavation contractor was oblig- under the terms of the construction contract, the design
ated to follow the directives of a resident inspector because firm, through its field inspection forces, must endeavor to
the government contracting officer had delegated on-site guard the owner against defects and deficiencies in the
authorities to the inspector (Appeal of Stannard Construction work. When, in the judgment of the designer, the plans
Co., Inc., ENG BCA No. 4767 [May 17, 1984]).1 and specifications are not being followed properly and
the design firm has been unable to obtain compliance by
Limited Authority the contractor, the owner should be notified so that
It is also possible to grant limited authority to an agent. This appropriate measures can be taken. Inspection should be
can be done in order to give the Resident Project Repre- performed during the progress of the work; inspection
sentative certain responsibilities and authority without after completion defeats the purpose of providing quality
allowing that representative to make fundamental contract control and assurance on the job, as many potential diffi-
changes, changes in time or cost, or to waive legal rights. culties must be detected during construction; otherwise,
This arrangement is preferable to naming an authorized they may be permanently covered. The result would be a
individual in the home office or his or her designated latent defect that may not be discovered for years; then,
representative. when it is discovered, it may be too late, as it may have
To be effective, a grant of limited authority must include been instrumental in contributing to a structural failure or
clear, objective contractual limitations on the scope of the other disaster.
agents authority. For instance, a Resident Project Represen- Often, the word supervision has been used in the past in
tative might be given the authority to approve changed or connection with field inspection. It is a legally risky term,
extra workup to a stated dollar amount. and as such, its use has long been discouraged by all techni-
cal and professional societies of the construction industry.
1See Construction Claims Monthly, Sept. 1984, p. 5, Business Publishers In the case of U.S. Home Corp. v. George W. Kennedy
Inc., 2601 University Blvd. West, Silver Spring, MD 20910-3928. Construction Co. [610 F. Supp. 759 (D.C.III.) 1985] a federal

S-ar putea să vă placă și