Sunteți pe pagina 1din 86

Project: Geotech Inv.

Work for C/O ROB in replacement of existing level crossings


in Bihar.
Job No. : 3363-09 Sheet No.

ROB AT CH. KM. 119 AT NH-30

DANAPUR-ARA SECTION (ECR)

[LC NO. 48A/3T]


Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

ROB AT CH. KM. 119 AT NH-30

1. SOIL PROFILE & PROPERTIES:


The subsoils in general are of good quality. The subsoil is characterized by a medium to stiff
clayey silt layer appears at top followed by a very stiff to hard clayey silt layer. Underlying the
above a dense to very dense silty sand layer is encountered and that continued up to the
terminating depth of all the boreholes.

The generalized profile of the site is shown in Fig.2. On the above basis the layer wise
descriptions are presented below.

1.1. STRATUM I:
The soil in this layer is characterised by medium to stiff yellowish/ brownish grey clayey silt /
silty clay with fine sand mixture. Kankar and black spots have been observed in this layer.
The average N value of this layer is 08. The average soil properties of this layer revealed
from routine laboratory test on UDS collected from this layer are presented below.
Bulk Density, gms/cc 1.97 Specific gravity 2.51
Dry Density, gms/cc 1.59 Natural Water Content, % 24
Liquid limit % 36 Void ratio 0.710
Plastic limit % 21 GRAIN SIZE
TRSH-UU: Sand % 10
Cohesion kg/sqcm 0.57 Silt % 79
Friction angle 00 Clay % 11
1.2. STRATUM II:
The soil in this layer is composed of very stiff to hard yellowish / brownish grey clayey silt /
silty clay with fine sand mixture. Kankar and calcareous nodules have been observed in the
layer. The average N value of this layer is 27. The "UDS" that could be collected from this
layer show the following average properties.
Bulk Density, gms/cc 2.03 Specific gravity 2.70
Dry Density, gms/cc 1.65 Natural Water Content, % 23
Liquid limit % 39 Void ratio 0.593
Plastic limit % 17 GRAIN SIZE
TRSH-UU: Sand % 20
Cohesion kg/sqcm 1.17 Silt % 69
Friction angle 00 Clay % 11
N

CLIENT: CONSULTANT : DWG. NO.


SCALE :-
MINISTRY OF ROAD TRANSPORT & HIGHWAYS (MORT&H) BORE HOLE LOCATIONAL PLAN
N.T.S CET/3363/P5/LC-48A/3T/PR/BH_01
GOVERNMENT OF INDIA

C.E. TESTING COMPANY PVT. LTD. DRAWN BY CHEEKED BY APPROVED BY REV.


PROJECT: CONSULTANCY SERVICES FOR PREPARATION OF PROJECT REPORT PROJECT NAME:-
( An ISO 9001 , 14001 & OHSAS 18001 Certified Company )
MKD. DESCRIPTION CHKD. APPRD. DATE:- COMPRISING,DETAILED SURVEY/INVESTIGATION, ALIGNMENT OPTION, PREPARATION OF
PROPOSED ROB AT LC NO - 48A/3T ON KM 119 OF NH-30 124-A, N.S.C. Bose Road , Kolkata - 700092.
MAY,2015 GENERAL ARRANGEMENT DRAWING AND ENGINEERING REPORT FOR CONSTRUCTION OF R0
P.Das D. Pal K. Datta
REVISIONS PROPOSED ROB & THEIR APPROACHES IN REPLACEMENT OF EXISTING LEVEL CROSSINGS.
Geotechnical Inv work for ROB replacing Level Crossing at Ch: NH-30/119km. (Lcno. 48A/3T)
3363_09 JRC

To PATNA To SASARAM

BH-01 BH-02
BH-05
R.L.=57.63M R.L.=57.74M BH-03 BH-04
R.L.=56.93M
00.00 00.00 R.L.=56.41M R.L.=56.35M
57 00.00 57
U1 0.43/0(UU) 00.00 00.00
BH-06
56 N=4 N=4 56
15/80/15 I R.L.=54.18M
55 N=7 55
U1 0.63/0(UU) S.W.L.=2.1M N=4 N=5
N=4 S.W.L.=2.9M 00.00
54 N=5 0.54/0(UU) 54
0.25/0(UU) 08/85/07 CI U1 0.60/0(UU)
U2 U1 S.W.L.=3.4M 0.50/0(UU) N=8
53 07/80/13 U1 53
06/89/05 N=5 N=9 18/77/05
Medium to Stiff, N=9 yellowish grey / brownish grey, Silty clay / Clayey silt. 11/79/10 S.W.L.=1.9M N=5
52 N=8 52
Observed U2 kankars & black spots. 5.00 N=17
51 N=10 N=9 N=9 U1 0.85/0(UU) 51
0.56/0(UU) U2 0.81/0(UU) N=14
U3 0.62/0(UU) U2 0.78/0(UU) I 0.45/0(UU) N=18 15/78/07
50 N=10 10/73/17 U2 08/81/11 50
06/85/09 8.00 N=20 N=13 N=10
08/83/09 08/75/17 5.00
49 7.50 N=24 49
U3 1.59/0(UU) N=16
N=8 N=23
48 N=28 N=11 U2 1.26/0(UU) 48
0.48/0(UU) 26/55/19 U3 0.87/0(UU)
U4 1.12/0(UU)
CI 0.74/0(UU) N=20 N=30 06/77/17
47 Stiff to very stiff to Hard, yellowish U3 U3 II 47
N=10 15/71/14 N=28 N=14 07/73/20
II N=24 grey/ brownish grey, clayey silt / 08/72/20 06/76/18
46 N=34 46
U4 (Slip)silty clay. Observed kankars and N=25
N=11 N=30 11.00
45 calc. nodules. N=17 U3 45
N=28 28/72 U4 N=33 1.06/0(UU)
U5 (Slip) U4 0.79/0(UU) N=30 1.20/0(UU)
44 1.19/0(UU) U4 44
N=13 14.00 N=34 23/77 N=25 14/69/17 06/74/20
N=37 39/51/10 06/85/09
43 14.50 You are using N=36 43
U5 (Slip) CI N=29
N=18 09/91 14.00 N=40 14.50
42 N=39 88/12
ZwCAD 2007 Trial Version N=23 42/47/11 U4 1.84/0(UU) 42
U5 (Slip) N=41
U6 (Slip)
41 III Please U5
contact U5 (Slip)
(Slip) WWW.ZwCAD.COM for detailed information N=39 06/74/20 41
N=18 02/98
N=40 N=44 81/19 N=32 89/11
40 14.00 N=44 17/68/15 40
U6 (Slip) N=39
N=22 N=50 17.00
39 N=44 N=36 87/13 U5 (Slip) 39
U6 (Slip)
U6 (Slip) U6 (Slip) N=54
III N=43
38 N=27 27/73 87/13 38
N=45 91/09 N=38 88/12 N=36
37 N=50 86/14 37
21.00 N=48
N=40 N=50 SM-SP 89/11
36 N=48 N=48 U6 (Slip) 36
N=55 N=52
35 N=42 U7 (Slip) 35
Dense to Very dense, N=50
yellowish brown /brownish N=46 grey, reddish brown, N=53
silty sand. Observed kankars.
34 N=58 34
REDUCED LEVEL(M)

N=53 87/13
N=48 93/07

REDUCED LEVEL(M)
33 N=57 90/10 N=43 91/09 N=52 03/93/04 33
N=54 91/09
32 N=54 32
N=51 N=48 40/55/05
N=58 N=46
31 N=62 31
N=62 92/08
N=58 90/10 N=57 86/14
30 N=64 90/10 N=52 30
DS-17 93/07 N=60 89/11
29 N=62 29
N=61 97/03 N=52
N=79 06/86/08 N=56 87/13
28 N=60 28
N=81 91/09 N=54
30.45m N=83 93/07 30.45 N=60
27 08/85/07 N=59 27
30.45 N=67 N=59
N=74 10/81/09 N=60
90/10
26 30.45 30.45 88/12 26
25 N=69 25
24 N=65
88/12 24
30.45
23 23
U means UDS
22 N means `N' value 22
21 C / values 21
FIG.2. GENERALISED SOIL PROFILE. Sand/Silt/Clay %
Sand/(Silt+Clay) %
Gravel/Sand/(Silt+Clay) %
Project : Geotech Inv. Work for C/O ROB in replacement of existing level
crossings in Bihar.
Job No. 3363-09

CORRECTION FOR STANDARD PENETRATION TEST VALUES

Bore Starting Ending Average Field 'N' Cor. 'N' for Ovp. Reduced Stratum Computed
Hole Depth Depth Depth Values & Dilatancy Level Phi in
No: (M) (M) (M) (if reqd) (M) Degrees

BH01 1.45 1.90 1.68 4 04 55.96 I


BH01 3.00 3.45 3.23 4 04 54.41 I
BH01 5.50 5.95 5.73 8 08 51.91 I
BH01 7.45 7.90 7.68 10 10 49.96 I
BH01 9.00 9.45 9.23 8 08 48.41 I
BH01 10.45 10.90 10.68 10 10 46.96 I
BH01 12.00 12.45 12.23 11 11 45.41 I
BH01 13.60 14.05 13.83 13 13 43.81 I
BH01 15.00 15.45 15.23 18 18 42.41 II
BH01 16.60 17.05 16.83 18 18 40.81 II
BH01 18.00 18.45 18.23 22 22 39.41 II
BH01 19.50 19.95 19.73 27 27 37.91 II
BH01 21.00 21.45 21.23 40 23 36.41 III 35
BH01 22.50 22.95 22.73 42 23 34.91 III 35
BH01 24.00 24.45 24.23 48 25 33.41 III 35
BH01 25.50 25.95 25.73 51 25 31.91 III 36
BH01 27.00 27.45 27.23 58 27 30.41 III 36
BH01 28.50 28.95 28.73 61 28 28.91 III 36
BH01 30.10 30.55 30.33 83 35 27.31 III 38

BH02 1.50 1.95 1.73 4 04 56.02 I


BH02 3.45 3.90 3.68 5 05 54.07 I
BH02 5.00 5.45 5.23 9 09 52.52 I
BH02 6.45 6.90 6.68 10 10 51.07 I
BH02 8.00 8.45 8.23 20 20 49.52 II
BH02 9.45 9.90 9.68 28 28 48.07 II
BH02 11.00 11.45 11.23 24 24 46.52 II
BH02 12.60 13.05 12.83 28 28 44.92 II
BH02 14.00 14.45 14.23 37 23 43.52 III 35
BH02 15.60 16.05 15.83 39 24 41.92 III 35
BH02 17.00 17.45 17.23 40 24 40.52 III 35
BH02 18.60 19.05 18.83 44 25 38.92 III 35
BH02 20.00 20.45 20.23 45 25 37.52 III 35
BH02 21.50 21.95 21.73 48 25 36.02 III 36
BH02 23.00 23.45 23.23 58 29 34.52 III 37
BH02 24.50 24.95 24.73 57 28 33.02 III 36
BH02 26.00 26.45 26.23 58 28 31.52 III 36
BH02 27.50 27.95 27.73 62 28 30.02 III 37
BH02 29.00 29.45 29.23 79 34 28.52 III 38
BH02 30.00 30.45 30.23 81 34 27.52 III 38

BH03 1.50 1.95 1.73 4 04 54.69 I


BH03 3.45 3.90 3.68 5 05 52.74 I
BH03 5.00 5.45 5.23 9 09 51.19 I
BH03 6.45 6.90 6.68 13 13 49.74 I
BH03 8.00 8.45 8.23 23 23 48.19 II
BH03 9.45 9.90 9.68 28 28 46.74 II
Project : Geotech Inv. Work for C/O ROB in replacement of existing level
crossings in Bihar.
Job No. 3363-09

CORRECTION FOR STANDARD PENETRATION TEST VALUES

Bore Starting Ending Average Field 'N' Cor. 'N' for Ovp. Reduced Stratum Computed
Hole Depth Depth Depth Values & Dilatancy Level Phi in
No: (M) (M) (M) (if reqd) (M) Degrees

BH03 11.00 11.45 11.23 30 30 45.19 II


BH03 12.45 12.90 12.68 34 34 43.74 II
BH03 14.00 14.45 14.23 40 40 42.19 II
BH03 15.60 16.05 15.83 44 26 40.59 III 36
BH03 17.00 17.45 17.23 50 28 39.19 III 36
BH03 18.60 19.05 18.83 38 23 37.59 III 35
BH03 20.00 20.45 20.23 50 27 36.19 III 36
BH03 21.50 21.95 21.73 46 25 34.69 III 35
BH03 23.00 23.45 23.23 43 23 33.19 III 35
BH03 24.50 24.95 24.73 48 25 31.69 III 35
BH03 26.00 26.45 26.23 57 27 30.19 III 36
BH03 27.50 27.95 27.73 52 25 28.69 III 36
BH03 29.00 29.45 29.23 60 27 27.19 III 36
BH03 30.00 30.45 30.23 74 32 26.19 III 37

BH04 1.50 1.95 1.73 5 05 54.63 I


BH04 3.45 3.90 3.68 9 09 52.68 I
BH04 5.00 5.45 5.23 9 09 51.13 I
BH04 6.45 6.90 6.68 10 10 49.68 I
BH04 8.00 8.45 8.23 11 11 48.13 I
BH04 9.45 9.90 9.68 14 14 46.68 I
BH04 11.00 11.45 11.23 17 17 45.13 II
BH04 12.45 12.90 12.68 25 25 43.68 II
BH04 14.00 14.45 14.23 23 23 42.13 II
BH04 15.60 16.05 15.83 32 32 40.53 II
BH04 17.00 17.45 17.23 36 36 39.13 II
BH04 18.60 19.05 18.83 36 21 37.53 III 34
BH04 20.00 20.45 20.23 48 26 36.13 III 36
BH04 21.60 22.05 21.83 53 27 34.53 III 36
BH04 23.00 23.45 23.23 52 26 33.13 III 36
BH04 24.50 24.95 24.73 46 24 31.63 III 35
BH04 26.00 26.45 26.23 52 25 30.13 III 36
BH04 27.50 27.95 27.73 56 26 28.63 III 36
BH04 29.00 29.45 29.23 59 27 27.13 III 36
BH04 30.00 30.45 30.23 60 27 26.13 III 36

BH05 1.50 1.95 1.73 5 05 55.21 I


BH05 3.45 3.90 3.68 8 08 53.26 I
BH05 5.00 5.45 5.23 17 17 51.71 II
BH05 6.45 6.90 6.68 18 18 50.26 II
BH05 8.00 8.45 8.23 16 16 48.71 II
BH05 9.45 9.90 9.68 20 20 47.26 II
BH05 11.00 11.45 11.23 25 25 45.71 II
BH05 12.45 12.90 12.68 30 30 44.26 II
BH05 14.00 14.45 14.23 29 29 42.71 II
BH05 15.60 16.05 15.83 39 24 41.11 III 35
BH05 17.00 17.45 17.23 39 23 39.71 III 35
Project : Geotech Inv. Work for C/O ROB in replacement of existing level
crossings in Bihar.
Job No. 3363-09

CORRECTION FOR STANDARD PENETRATION TEST VALUES

Bore Starting Ending Average Field 'N' Cor. 'N' for Ovp. Reduced Stratum Computed
Hole Depth Depth Depth Values & Dilatancy Level Phi in
No: (M) (M) (M) (if reqd) (M) Degrees

BH05 18.60 19.05 18.83 54 29 38.11 III 37


BH05 20.00 20.45 20.23 48 26 36.71 III 36
BH05 21.50 21.95 21.73 55 28 35.21 III 36
BH05 23.00 23.45 23.23 53 27 33.71 III 36
BH05 24.50 24.95 24.73 54 27 32.21 III 36
BH05 26.00 26.45 26.23 62 29 30.71 III 37
BH05 27.50 27.95 27.73 62 28 29.21 III 36
BH05 29.00 29.45 29.23 54 25 27.71 III 36
BH05 30.00 30.45 30.23 67 29 26.71 III 37

BH06 1.50 1.95 1.73 5 05 52.46 I


BH06 3.45 3.90 3.68 14 14 50.51 I
BH06 5.00 5.45 5.23 24 24 48.96 II
BH06 6.45 6.90 6.68 30 30 47.51 II
BH06 8.00 8.45 8.23 34 34 45.96 II
BH06 9.45 9.90 9.68 33 33 44.51 II
BH06 11.00 11.45 11.23 36 36 42.96 II
BH06 12.45 12.90 12.68 41 41 41.51 II
BH06 14.00 14.45 14.23 44 27 39.96 III 36
BH06 15.60 16.05 15.83 43 26 38.36 III 36
BH06 17.00 17.45 17.23 50 28 36.96 III 36
BH06 18.60 19.05 18.83 52 28 35.36 III 36
BH06 20.00 20.45 20.23 58 30 33.96 III 37
BH06 21.50 21.95 21.73 54 28 32.46 III 36
BH06 23.00 23.45 23.23 62 30 30.96 III 37
BH06 24.50 24.95 24.73 60 29 29.46 III 37
BH06 26.00 26.45 26.23 60 28 27.96 III 37
BH06 27.50 27.95 27.73 54 26 26.46 III 36
BH06 29.00 29.45 29.23 69 30 24.96 III 37
BH06 30.00 30.45 30.23 65 29 23.96 III 37
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

CORRECTED 'N' VALUES


5 10 15 20 25 30 35 40
0.00

2.00

BH01
4.00
BH02
BH03
6.00 BH04

8.00

10.00

12.00

14.00
DEPTH (M)

16.00

18.00

20.00

22.00

24.00

26.00

28.00

30.00

32.00
FIG. 3. CORRECTED 'N' Vs DEPTH PLOT
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

CORRECTED 'N' VALUES


5 10 15 20 25 30 35 40 45
0.00

2.00 BH05
BH06
4.00

6.00

8.00

10.00

12.00

14.00
DEPTH (M)

16.00

18.00

20.00

22.00

24.00

26.00

28.00

30.00

32.00
FIG. 3. CORRECTED 'N' Vs DEPTH PLOT
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

1.3. STRATUM III:


Underlying the above we have a sand layer characterized by dense to very dense reddish
brown/ yellowish brown/ brownish grey silty sand and that continued upto the terminating
depth of all the boreholes. Kankar and gravel have been observed in the layer. The average
corrected N value of this layer is 54. No UDS could be collected from this layer. Grain size
analysis of some SPT samples show the following average properties.
Specific gravity 2.68
GRAIN SIZE
Gravel % 02
Sand % 88
(Silt + Clay) % 10

2. CHOICE OF FOUNDATION & FOUNDING LEVEL:


The proposed structure will be a ROB. Considering the nature of the subsoil and the type of
structures to be constructed at the present site, it is suggested to go for deep foundation in
the form of piles.

3. USE OF R.C. BORED PILE:


Bored cast in-situ piles are preferred due to availability of construction agencies, ease of
construction and less sound pollution. Such piles may be placed at a suitable depth below
EGL depending upon structural requirement. The determination of pile capacity is presented
in separate sheets.
At first, the design strength parameters are determined. Thereafter, the pile capacity values
are calculated. While determining the pile capacity, the following considerations are made.
a) Pile capacity is calculated using average strength parameters and layer
stratification as around BH-04.
b) Assumed Grade of Concrete = M35
c) Diameter of pile used = 1000 and 1200mm
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

3.1. DESIGN STRENGTH PARAMETERS:

STRATUM I:
Average "N" in this layer = 08 So, estimated cohesion from "N" value = 0.59 kg/sqcm
From Laboratory TRSH-UU test results, average C = 0.57 kg/sqcm & = 00
Considering the above Use, C = 0.50kg/sqcm & = 0
Use Adhesion factor, = 0.871

STRATUM II:
Average "N" in this layer = 27. So, estimated cohesion from "N" value = 1.12 kg/sqcm
From Laboratory TRSH-UU test results, average C = 1.17 kg/sqcm & = 0
Considering the above Use, C = 1.00kg/sqcm & = 0
Use Adhesion factor, = 0.446

STRATUM III:
Average corrected "N" in this layer = 27, corresponding Relative Density (Dr) = 60.50 %
Friction angle 1 = 25+0.15*Dr = 25+0.15*60.50 = 34.08
[Refer VNS Murthy Principle and practices of Soil Mechanics and Foundation Engineering
Chapter 9]

Relation between SPT N and Shear Strength


Widely used relationship is due to Terzagi and Peck recommending C = N/16
However, it has been seen over the years with stiffness in clay the shear strength does not increase as rapidly as proposed by Terzagi.
Our experience also shows that for clays at medium to higher depth, the above relation does not hold good.
For Static Cone Penetration Tests, the recommendations for cone factor Nk generally are
C = qc/Nk where C = Cohesion in kg/sqcm and qc = Cone resistance in Static Cone and
Nk = 17 , 21 & 27 for normally consolidated clay, partly over consolidated clay and heavily over consolidated clay respectively
[Ref. Meigh, A.C (1987) : Cone Penetration Testing Methods and Interpretation, Butterworths, London, pp-43-47]
Taveres, A.X [Penetration Testing 1988, ISOPT-1, Volume-I, J.De Ruiter Editor, pp-375-379] has shown very clearly that a better correlation can be obtained
with stiffness of the clay. From his experimental results he obtained,
Range of SPT N K = N/C
N < 10 12.50
10 < N < 20 14.20
20 < N < 30 16.25
30 < N < 40 20.00
Over the years on the basis of the laboratory test results we have been using the following relations. However, for N value greater than 40, we use C = N/27

R ela tio n b etw ee n " N " & C (k g /sq cm )


1 .5 0

1 .4 0

1 .3 0

1 .2 0

1 .1 0

1 .0 0

0 .9 0
C (Kg/sqcm)

0 .8 0

0 .7 0

0 .6 0

0 .5 0

0 .4 0

0 .3 0

0 .2 0

0 .1 0

0 .0 0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40
N V a lu e
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

EGL EGL

3.00M (Cut-Off)

8.00 M I
C= 0.50 kg/sqcm and = 0, = 0.871

16.20 t/sqm for


1200mm dia. pile

7.00 M II C= 1.00 kg/sqcm and = 0, = 0.446

C= 0.00 kg/sqcm and = 31, 0 = 1.05


7.00M III

III

3. PILE FOUNDATION DESIGN MODEL


(Based on layer stratification around BH-04
Not to scale
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

For bored cast-in-situ piles the soil get loosened during boring.
Poules(1980) suggested that = 1 3 = 34.08 - 3 = 31.08 31
Use, C = 0.00kg/sqcm & = 31.
Use Ko = 1.05 (As per IS 2911, Part 1 / Sec-2: 2010, pp-10)

Based on the above the pile capacity values are calculated by two different approaches
(From Static formula & from SPT values using Extended Method of Mayerhoff).
Now we have following sample pile capacity,

For 1000mm dia pile placed at 25m depth below EGL


a. Using static formula, Safe Pile Capacity = 392.86T
b. Using Extended Method of Mayerhoff, Safe Pile Capacity = 375.36T
So, recommended pile capacity = 380T.

4.2. DETERMINATION OF VERTICAL PILE CAPACITY:


Following the same principle, the pile capacity values for different pile diameter as well as
different founding level are calculated and following pile capacity values are recommended.
A typical sample calculation is presented in separate sheet.

Pile Pile founding Recommended


Diameter depth below Vertical Pile
(mm) EGL(M) Capacity(T)
22 245
1000 25 270
28 300
22 340
1200 25 380
28 420

4.3. LATERAL PILE CAPACITY (FOR 1200MM DIA PILE):


Use c = 0.50 kg/sqcm for lateral pile capacity calculation
Refer to IS : 2911 (Part I/Sec 2) - 2010, Appendix - C
Constant Factor, k1 = 1.80 kg/cucm corresponding to Cohesion = 0.50 kg/sqcm
Now, K = (k1/1.5) x (30/D) which is coming as 0.30 kg/cucm [D = Pile dia in cm]
Stiffness factor, R = [EI/KD]1/4
Now, I = 10.18 x 106 cm4 [for 1200mm dia pile]
E = 5000 x (fck)0.5 = 5000 x (35)0.5 = 29580 N/sqmm = 2.96 x 105 kg/sqcm
Hence, R = 537.77 cm
From Graph (Fig.4), Lf = 1.95 x R = 1048.66 cm [Assuming Fixed Head Piles]
Pile Head deflection, Y = H x Lf3 / 12EI = 0.3192mm for 1T load
So, for 12mm horizontal deflection , (i.e.1% of pile dia., as per IRC 78-2014) at cut-off level, the lateral
force(H) at the Bottom of pile cap is given by, H = 37.60T, say 37T
Now, Moment = [H x Lf/2] = [1 x 10.49/2] = 5.24t-m per T of thrust
The Reduction Factor for computation of Maximum Moment in Pile, m = 0.70
So, the corrected actual moment, M = 5.24 x 0.70 = 3.67t-m per T of thrust
SAMPLE PILE CAPACITY CALCULATION

Bottom depth of Pile = 25.00 m below EGL


Cut-off Length = 3.00 m
Diameter of Pile = 1200 mm Critical depth 15.00 D
FOS of Shaft Resistance = 2.50
FOS for End Bearing = 2.50
So, maximum Depth upto which pressure will increase = 18.00 m Maximum OVP = 16.55 t/sqm

Layer No. Top Depth Bottom Depth Eff. Depth Cohesion Adhesion Factor K0 Eff. Density Mean Pressure
(M) (M) (M) (kg/sqcm) (Degree) () (gm/cc) (t/sqm)
1 3.00 11.00 8.00 0.50 0 0.871 1.00 0.90 6.30
2 11.00 18.00 7.00 1.00 0 0.446 1.00 0.95 13.23
3 18.00 25.00 7.00 0.00 31 1.000 1.05 0.90 16.55

Layer Eff. Depth Effective z fs1 = C fs2 = K0ztan fs =fs1 +fs2 Ultimate Shaft Safe Shaft
No. (M) (t/sqm) (t/sqm) Resistance (T) Resistance (T)
1 8.00 6.30 4.35 0.00 4.35 131.33 52.53
2 7.00 13.23 4.46 0.00 4.46 117.76 47.10
3 7.00 16.55 0.00 10.44 10.44 275.54 110.22
524.63 209.85
For End Bearing
Cohesion C= 0 kg/sqcm
Friction Angle = 31
So, Nc = 57
Nq = 24.44
Eff. Ovp. Pressure=p(tip) 16.55 t/sqm
q(tip) =C.Nc+p(tip).Nq= 404.53 t/sqm
Ultimate End Bearing = 457.52 T
Safe End Bearing = 183.01 T
Safe Shaft Resistance= 209.85 T
So, Total Pile Capacity = 392.86 T
PILE CAPACITY CALCULATION FROM SPT VALUES
(Using extended method of Mayerhoff)
(Considering Borehole Stratification as around BH-04)
Bore Starting Ending Average Cor. 'N' for Ovp. Computed
Field 'N' Reduced Average
Hole Depth Depth Depth & Dilatancy Stratum Phi in
Values Level (M) "N"
No: (M) (M) (M) (if reqd) Degrees

BH04 1.50 1.95 1.73 5 05 54.63 I


BH04 3.45 3.90 3.68 9 09 52.68 I
BH04 5.00 5.45 5.23 9 09 51.13 I
BH04 6.45 6.90 6.68 10 10 49.68 I
BH04 8.00 8.45 8.23 11 11 48.13 I
BH04 9.45 9.90 9.68 14 14 46.68 I 09.67
BH04 11.00 11.45 11.23 17 17 45.13 II
BH04 12.45 12.90 12.68 25 25 43.68 II
BH04 14.00 14.45 14.23 23 23 42.13 II
BH04 15.60 16.05 15.83 32 32 40.53 II
BH04 17.00 17.45 17.23 36 36 39.13 II
BH04 18.60 19.05 18.83 36 21 37.53 III 26.60
BH04 20.00 20.45 20.23 48 26 36.13 III
BH04 21.60 22.05 21.83 53 27 34.53 III
BH04 23.00 23.45 23.23 52 26 33.13 III
BH04 24.50 24.95 24.73 46 24 31.63 III 24.75
BH04 26.00 26.45 26.23 52 25 30.13 III
BH04 27.50 27.95 27.73 56 26 28.63 III
BH04 29.00 29.45 29.23 59 27 27.13 III
BH04 30.00 30.45 30.23 60 27 26.13 III

Let us assume:
Pile Dia. = 1.20 m
Founding Depth of 25.00 m
pile from EGL=
Soil neglected upto = 3.00 m Pile length 22.00 M
Average N at Pile tip = 26
Calculation of Ultimate Shaft Resistance:
Layer From To Length Avg. Design N = 67% fs=N/3+1 SR
No (m) (m) (m) N of Avg. N (t/sqm) (T)
I 3.00 11.00 8.00 09.67 6.48 3.16 95.27
II 11.00 18.00 7.00 26.60 17.82 6.94 183.16
III 18.00 25.00 7.00 24.75 16.58 6.53 172.26
Sum = 450.69
Calculation of Ultimate End Bearing:
Use design average "N" at Pile Tip = 26
Use 67% of "N" for bored pile = 17.25
The subsoil is Silty sand at Pile tip.
Use K = 25 (a constant)
Hence, Ultimate End Bearing = 487.71 T

So, we have
Ultimate Shaft Resistance = 450.69 T
Ultimate End Bearing = 487.71 T

Use Factor of safety for SR = 2.5


Use Factor of safety for EB = 2.5

So, Safe Pile Capacity = 375.36 T


Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

Based on the above, the following lateral pile capacity values are recommended for different
pile diameters.
Grade of Pile For Fixed Head Pile
Concrete Diameter Lateral Moment Length of
(MPa) (mm) (T) (T-m/T) Fixity (m)
1000 26 3.06 8.74
35
1200 37 3.67 10.49

5. USE OF OPEN FOUNDATION:


For ancillary structures at approach, such as VUP/PUP/CUP, Retaining wall etc. it is
suggested to go for open foundation. The determination of bearing capacity around
Abutment locations are presented below.
5.1. FOUNDING LEVEL:
It is suggested to place the foundation at 1.50m below existing ground level.

GENERAL BEARING CAPACITY CALCULATION:


5.1.2. EVALUATION OF STRENGTH & DEFORMATION PARAMETERS:
FOR STRATUM - I
Average "N" in this layer = 08
Use, C = 0.50 kg/sqcm & = 0 [As calculated above]
Total soil modulus, Es = 4.4 x N = 35.20 kg/sqcm
[Ref. to History of Soil penetration testing by B. B. Broms & N. Flodin in Penetration
Testing 1988, ISPOT-1: vol.1, p 185]
Undrained Youngs modulus, Eu = K x C = 350 x 0.50 = 175 kg/sqcm
Again, 1/Es = 1/Eu + 1/Ed giving drained young's modulus, Ed = 44.06 kg/sqcm
Now, we have, Ed = Eu/3 = 58.33 kg/sqcm
[Refer to Cone Penetration Testing" by A.C.Meigh, pp. No. 53]
Considering the above, let us use Ed = 51 kg/sqcm
From Ed, mvc = 1/G.Ed =0.0231 sqcm/kg [Geological Factor, G = 0.85 & = 0.35]
Again from SPT N, mvc = 1/5N = 0.0250 sqcm/kg
[Refer to Standard Penetration Test, State-of-the-art-Report by Ivan K. Nixon in
Penetration testing 1 Edited by A.Verrujt, F.L.beringen & E.H.De Leeuw, pp. No. 11]
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

Now, let us consider the mvc value for the pressure range between 0.50 to 2.00 kg/sqcm
Sample No. 0.50 1.00kg/sqcm 1.00 2.00kg/sqcm
BH-01/UDS02 0.0127 0.0113
BH-01/UDS03 0.0287 0.0214
BH-02/UDS01 0.0216 0.0103
BH-03/UDS01 0.0095 0.0049
BH-04/UDS01 0.0101 0.0120
BH-05/UDS01 0.0059 0.0070
Average weighted mvc,
sqcm/kg over entire
pressure range
Giving more weightage to the laboratory test results,

Use mvc = [2 x 0.0124+0.025+0.0231]/4=0.0182 sqcm/kg

5.1.3. DETERMINATION OF BEARING CAPACITY:


The Net Ultimate Bearing Capacity is given as:
qnu = C.Nc.Sc.Dc + q.Nq.Sq.Dq + 0.5.B.N.S.D - q
Where,
Nc, Nq and N are bearing capacity factors,
Sc, Sq and S are shape factors,
Dc, Dq and D are depth factors,
And
C = Cohesion
q = Overburden pressure,
B = Width of foundation,
= Effective density below foundation.

For (5mx10m) Isolated Footing


Cohesion, C = 5.00 t/sqm
Using = 0 degree, the bearing capacity factors are:
Nc = 5.14
Nq = 1.00
N = 0.00
Use,
Depth of Foundation = Df = 1.5 M(Below EGL)
Width of Foundation = B = 5 M
Length of Foundation = L = 10 M
Overburden Pressure = q =1.500 (Depth) x 0.90 (Submerged density) = 1.35 t/sqm (Assuming water
table is flushing with the ground level)
The Shape factors are [ IS:6403 - 1981 ]
Sc = 1.10 Sq = 1.10 S = 0.80
The Depth factors are [ IS:6403 - 1981 ]
Dc = 1.06 Dq = 1.00 D = 1.00
Computed Net Ultimate Bearing Capacity = 30.13 t/sqm
Using a factor of safety of 2.5, Net Safe Bearing Capacity = 12.05 t/sqm

The above bearing capacity should be checked against settlement criteria and is presented
below.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

5.1.4. SETTLEMENT CALCULATION:


We use the shallow foundation based on soil stratification as around BH-01 and average
strength parameters of all boreholes. With reference to the above, the settlement is
calculated and is presented below.
Depth of Foundation = 1.50 m below EGL
Foundation Width, B = 5.00 m
Foundation Length, L = 10.00 m
Net base Pressure, P = 0.90 kg/sqcm

Strata From To Thickness of Mid depth below P Young's Mvc, G Si Sc St


(M) (M) compressible Founding level, Modulus, sqcm/kg (cm) (cm) (cm)
layer (M) (M) kg/sqcm
I 1.50 3.00 1.50 0.75 0.728 175.00 0.0182 0.85 0.62 1.69 2.31
3.00 5.00 2.00 2.50 0.480 175.00 0.0182 0.85 0.55 1.49 2.03
5.00 7.00 2.00 4.50 0.327 175.00 0.0182 0.85 0.37 1.01 1.38
7.00 10.00 3.00 7.00 0.221 175.00 0.0182 0.85 0.38 1.02 1.40
10.00 12.00 2.00 9.50 0.159 175.00 0.0182 0.85 0.18 0.49 0.67
Total = 2.11 5.70 7.81
Fox's Depth correction Factor = 0.95
Hence, corrected Total Settlement = 7.39

Use a net allowable bearing capacity of 09 t/sqm

Use of mvc value to Calculate Settlement:

In our report we have calculated the settlement of soil assuming trapezoidal distribution of stress. In case of sandy soil, we are having only immediate
settlement. Now the problem starts when the soil becomes silty clay / clayey silt.
There is no definite and particular formula to calculate settlement of this type of soil. The mv value we get from the consolidation test results includes immediate
part also. It is seen that for the present case about 26-67% of compression takes place just after application of test load. Hence, judicious use of mvc (the
consolidation part only and not the mv) should be used. Thus mv value obtained from the e-logP curves should not be used blindly.
It is seen that the settlement determined as per Clause 9.2.2.3 for computation as per IS 8009 Part-1 leads to more or less same value as calculated by us.
Moreover, for sites like the present project where we have large numbers of consolidation test results, this type of approach is very very tedious. Since, this e-
logP curve is totally undefined and can not be framed in any particular equation, it is not at all suitable for any computer programming. Thus determination of
settlement through this procedure is not feasible for a day to day work basis job.
mvc & p approach is very straight forward and the equation is similar to normal settlement calculation by theory of elasticity (mvc 1/E). We are in this field
for the last 25 years and using this approach (mvc & p) satisfactorily to calculate settlement for almost all of our Clients.

Calculation of P

Note:
1) Ei = Young's Modulus values and Gi = Geological factor
A
of the ith layer / sub layer,
B 2) Pi = Stress increment at the mid depth of the layer / sub
Ei = Young's Modulus. layer due to dispersion of the load applied at the founding
Pi = Stress increment C level using trapezoidal distribution of load (1H:2V)
at mid depth 3) Hi = Thickness of each layer / sub layer.
D 4) A thick layer is sometimes divided in to several sub layers
(like A, B, C etc.) for more accurate prediction of
E settlement.
F 5) Si(immediate) = Pi x Hi / Ei
6) Si(consolidation) = Pi x Hi x mvci x Gi
G

Hi H

Geological Factor: This is nothing but the consolidation settlement reduction factor, as given in IS 8009, Part I. This is termed as geological factor by M. J.
Tomlinson as the value is dependent on geology and pore pressure history of the soil.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

SAND CUSHION
For higher bearing capacity sand cushion/ incompressible materials (such as gravel,
crushed stone aggregates etc.) may be provided below founding level. This will reduce the
settlement and thus increasing the net allowable bearing capacity. Since the foundation is
resting on sand cushion/incompressible materials bearing capacity will not be a problem.

Let us check for


a) Settlement criteria
b) Bearing capacity at the interface of sand and virgin soil

Settlement with sand cushion: The settlement is calculated assuming no deformation of the
sand cushion (thus 1.50m to 3.50m soil settlement is neglected).
Depth of Foundation = 1.50 m below EGL
Foundation Width, B = 5.00 m
Foundation Length, L = 10.00 m
Net base Pressure, P = 1.50 kg/sqcm

Strata From To Thickness of Mid depth below P Young's Mvc, G Si Sc St


(M) (M) compressible Founding level, Modulus, sqcm/kg (cm) (cm) (cm)
layer (M) (M) kg/sqcm
I 3.50 3.50 0.00 2.00 0.893 175.00 0.0182 0.85 0.00 0.00 0.00
3.50 5.00 1.50 2.75 0.759 175.00 0.0182 0.85 0.65 1.76 2.41
5.00 7.00 2.00 4.50 0.544 175.00 0.0182 0.85 0.62 1.68 2.31
7.00 10.00 3.00 7.00 0.368 175.00 0.0182 0.85 0.63 1.71 2.34
10.00 12.00 2.00 9.50 0.265 175.00 0.0182 0.85 0.30 0.82 1.12
Total = 2.21 5.97 8.18
Fox's Depth correction Factor = 0.95
Hence, corrected Total Settlement = 7.74

Check for bearing capacity at the interface: Assuming 15 t/sqm net pressure at the founding
level, pressure at the interface of sand cushion & virgin soil = 15 x 5 x 10 / [(5+2) x (10+2)] =
8.93 t/sqm
Approximate ultimate bearing capacity of the virgin soil = 6C = 6 x 0.50 = 3.00kg/sqcm = 30
t/sqm
So, available factor of safety = 30/8.93 = 3.35 OK
Hence, use a net allowable bearing capacity of 15t/sqm for foundations placed at 1.50m
below EGL with 2m thick sand cushion below founding level.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

5.2. RECOMMENDATIONS:
Based on the above calculation, the following uniform bearing capacity values are
recommended.
Recommended Net
Depth of Allowable Bearing
Foundation
foundation below
Location Capacity (t/sqm)
EGL (M)
(S=75mm)
09
1.50
15*
BH 01
10
2.50
16*

Note :
a. S = Limiting Settlement.
b. * Provide a sand cushion/incompressible material of 2.0m thick below founding level.

6. DISCUSSION ON HIGH EMBANKMENT:

6.1. AROUND BH 01 & 06 LOCATIONS:

In this location, at the top, we have a medium to stiff silty clay layer. Considering the nature
of the subsoil, it is clear that the subsoil may fail in the following two aspects: -

1. Bearing Capacity of Stratum - I


2. Settlement Criteria.

6.1.1 BEARING CAPACITY OF STRATUM I:


(Considering the embankment portion BH- 01 only)
Use design C = 0.50 kg/sqcm & = 0 [Considering BH-04]
Approximate ultimate bearing capacity = 6*c = 6 x 0.50 = 3.00 kg/sqcm = 30.00 t/sqm
Using a factor of safety of 2.5, Net Safe Bearing Capacity = 12 t/sqm
Unit weight of soil = 1.95 t/cum
The height of the embankment that could be retained = 12/1.95 = 6.15 m ,say 6m
However about 11m high embankment is to be constructed.
This proposed 11m high embankment is likely to be constructed in 11 months. Due to
consolidation at this period, the soil will gain strength and the available factor of safety may
be of the order of 2.50 with respect to full height. So, it is required to check the virgin soil
with respect to factor of safety.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

Height of Wall = 11M


-3
Aveareg Cv = 4.614 sqcm/sec x (10 )
Assumed Effective Thickness = 21 M (i.e. Thickness of compressible layer = 10.00M with oneway drainage)
Initial Cohesion = 0.5 kg/sqcm

Time after each Cumulative Consolidatio Time % Increase in Increase in Final Applied Ultimat FOS
installment of fresh height of n Period, Factor, Completed effective cohesion Cohesion load e BC
construction, months Embankment months T stress (2.00 x (kg/sqcm) (kg/sqcm) (t/sqm) (t/sqm)
(m) % compl) (=0.26 x IES)

1 1.000 0.50 0.001 1.69 0.0339 0.0088 0.51 2.00 30.53 15.26
2 2.000 1.00 0.003 3.39 0.0678 0.0176 0.52 4.00 31.06 7.76
3 3.000 1.50 0.004 5.08 0.1017 0.0264 0.53 6.00 31.59 5.26
4 4.000 2.00 0.005 6.78 0.1356 0.0353 0.54 8.00 32.12 4.01
5 5.000 2.50 0.007 8.47 0.1695 0.0441 0.54 10.00 32.64 3.26
6 6.000 3.00 0.008 10.07 0.2014 0.0524 0.55 12.00 33.14 2.76
7 7.000 3.50 0.009 10.75 0.2149 0.0559 0.56 14.00 33.35 2.38
8 8.000 4.00 0.011 11.42 0.2285 0.0594 0.56 16.00 33.56 2.10
9 9.000 4.50 0.012 12.10 0.2420 0.0629 0.56 18.00 33.78 1.88
10 10.000 5.00 0.014 12.78 0.2556 0.0665 0.57 20.00 33.99 1.70
11 11.000 5.50 0.015 13.46 0.2692 0.0700 0.57 22.00 34.20 1.55

Hence the virgin soil is not safe from bearing capacity point of view due to construction of
proposed embankment. Hence some improvement of existing soil is required. In order to
improve the subsoil quality installation of sand drain/prefabricated vertical drain (PVD) is
suggested.

USE OF SAND DRAIN/PREFABRICATED VERTICAL DRAIN (PVD):


Installation of sand drain/PVD will accelerate the consolidation settlement to take place,
which in turn results in strength gain of subsoil. This is discussed below.
Use Sand drain diameter, d = 150 mm
Depth of drains, l = 20M
Place the drains in a square grid with a spacing of 2000 mm c/c
So, the contributing area for each drains = 2.00 x 2.00= 4.0 sqm
So, diameter of equivalent circular influence zone, D = 2.26m [(/4)*D2= 4.00, hence,
D = 2.26]
D / d = 2.26 x 1000 / 150 = 15.06
[Refer to Engineering Properties of Soils by G. A. Leonards in Foundation Engineering, Edited
by G. A. Leonards, pp no. - 175. Mc Graw-Hill Civil Engineering Series]
Time factor, Tr = (Cv x t)/D2 (Design Cv= 4.614X10-3cm2/s)
-3 2
= (4.614 x 10 x 0.50 x 30 x 24 x 3600)/(2.26 x 100) = 0.117
[Assuming 1 month time is provided for 1m height of filling after installation of sand
drains. So average consolidation time 0.50month for 1m height]
Corresponding % of complete consolidation = 38%
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

-3
Aveareg Cv = 4.614 sqcm/sec x (10 )

Initial Cohesion = 0.5 kg/sqcm


Diameter of equivalent circular influence zone= 2.26 M

Time after each Cumulative Consolidatio Time % Increase in Increase in Final Applied Ultimat FOS
installment of fresh height of n Period, Factor, Completed effective cohesion Cohesion load e BC
construction, months Embankment months T stress (2.00 x (kg/sqcm) (kg/sqcm) (t/sqm) (t/sqm)
(m) % compl) (=0.26 x IES)

1 1.000 0.50 0.117 37.86 0.7572 0.1969 0.70 2.00 41.81 20.91
2 2.000 1.00 0.234 61.39 1.2277 0.3192 0.82 4.00 49.15 12.29
3 3.000 1.50 0.351 76.01 1.5201 0.3952 0.90 6.00 53.71 8.95
4 4.000 2.00 0.468 85.09 1.7018 0.4425 0.94 8.00 56.55 7.07
5 5.000 2.50 0.585 90.74 1.8147 0.4718 0.97 10.00 58.31 5.83
6 6.000 3.00 0.702 94.24 1.8849 0.4901 0.99 12.00 59.40 4.95
7 7.000 3.50 0.820 96.42 1.9285 0.5014 1.00 14.00 60.08 4.29
8 8.000 4.00 0.937 97.78 1.9555 0.5084 1.01 16.00 60.51 3.78
9 9.000 4.50 1.054 98.62 1.9724 0.5128 1.01 18.00 60.77 3.38
10 10.000 5.00 1.171 99.14 1.9828 0.5155 1.02 20.00 60.93 3.05
11 11.000 5.50 1.288 99.47 1.9893 0.5172 1.02 22.00 61.03 2.77

6.1.2. Calculation of Post construction Settlement


Load coming from the embankment considering 11m height = 1.95 x 11 = 21.45 t/sqm
Estimated consolidation settlement = G*P*H*mvc = 0.85x2.15x15x100x0.0182 = 489 mm
Due to installation of PVD, the consolidation settlement will take place faster and post
construction settlement is calculated as follows.
Height of Filling = 11 m
Estimated consolidation settement = 498.9 mm
-3
Aveareg Cv = 4.614 sqcm/sec x (10 )
Diameter of equivalent circular influence zone= 2.26 M

Time after Cumulative height of Total Consolidation Time % consolidation Estimated Remaining
installment of PVD, Embankment Period, months Factor, Completed consolidation consolidation
(months) (m) T settlement (mm) settlement (mm)

1 1.000 10.50 2.466 99.995 45.35 0.0021


2 2.000 9.50 2.231 99.988 45.35 0.0054
3 3.000 8.50 1.996 99.969 45.35 0.0139
4 4.000 7.50 1.761 99.920 45.35 0.0361
5 5.000 6.50 1.526 99.794 45.35 0.0934
6 6.000 5.50 1.292 99.467 45.35 0.2419
7 7.000 4.50 1.057 98.619 45.35 0.6265
8 8.000 3.50 0.822 96.423 45.35 1.6225
9 9.000 2.50 0.587 90.735 45.35 4.2020
10 10.000 1.50 0.352 76.006 45.35 10.8823
11 11.000 0.50 0.117 37.861 45.35 28.1831

498.90 45.91

Similarly for layer-II the post construction settlement is about 34mm


Thus the estimated post construction settlement is of the order of 80mm and can be
accepted.
Hence provide prefabricated vertical drain of 150mm diameter with 15m length with 2000mm
c/c spacing.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

7. CHEMICAL TESTS:
Chemical tests were performed on a few soil samples for determining the pH value, Sulphate
and Chloride content. The results are given in a tabular form below:

CHEMICAL TEST RESULTS ON SOIL SAMPLE:


BH / Sample Depth pH value Sulphate as Chloride as
No. (M) SO3 % Cl %
01 / UDS-01 1.00 7.28 0.050 0.0280
04 / UDS-01 3.00 7.79 B.D.L. 0.0120
05 / UDS-01 3.00 7.50 0.050 0.0130
Note: B.D.L. = Below Detection Limit
It is seen that the values are within permissible limits (as per IS 456). So no special cement
will be required for foundation concrete. Either Ordinary Portland cement or Portland
slag cement or Portland Pozzolana cement can be used for the purpose.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

8. SUMMARY & CONCLUSIONS

Based on the field and laboratory test results and the foregoing discussion, the following are
summarised.
1. The subsoils in general are of good quality. The subsoil is characterized by a medium to
stiff clayey silt layer appears at top followed by a very stiff to hard clayey silt layer.
Underlying the above a dense to very dense silty sand layer is encountered and that
continued up to the terminating depth of all the boreholes.

2. Considering the subsoil condition it is suggested to go for deep foundation in form of pile.
Bored cast-in-situ piles are preferred due to availability of construction agencies, ease of
construction and less sound pollution.

3. The determination of vertical pile capacity for bored cast-in-situ pile is presented in the
previous section. However, the recommended pile capacity values for different pile
diameters at different founding levels are presented below. [Cut-off = 3.00M]

Pile Pile founding Recommended


Diameter depth below Vertical Pile Lateral (T) Moment Length of
(mm) EGL(M) Capacity(T) (T-m/T) Fixity(m)

22 245
1000 25 270 26 3.06 8.74
28 300
22 340
1200 25 380 37 3.67 10.49
28 420
Note: Pile load test should be conducted to ascertain the pile capacity as per IS: 2911,Part IV.

4. For the structures in approaches such as PUP, VUP, retaining wall structures, it is
suggested to go for open foundation. The determination of bearing capacity of open
foundation around abutment locations are presented in the previous section. The
recommended bearing capacity values are presented below.

Depth of Recommended Net


Foundation foundation below Allowable Bearing
Location EGL (M) Capacity (t/sqm)
09
1.50
15*
BH 01
10
2.50
16*
Note :
a. * Provide a sand cushion/incompressible material of 2.0m thick below founding level.
Project: Geotech Inv. Work for C/O ROB in replacement of existing level crossings
in Bihar.
Job No. : 3363-09 Sheet No.

5. For discussion on High embankment refer section 6

6. Chemical tests were performed on a few soil samples to determine the pH value,
Sulphate and Chloride content. It is seen that the values are within permissible limits (as
per IS 456). So no special cement will be required for foundation concrete. Either
Ordinary Portland cement or Portland slag cement or Portland Pozzolana cement
can be used for the purpose.
Res-336309 / Page 1

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %
BH01 UDS01 1.00 Brownish grey clayey silt 1.92 1.49 2.73 28 S 0.651 TRSH-UU 0.43 0 37 21 15 80 15
with sand mixture, rusty 29 T 3.0 0.510
spots and steel patch. 23 C 2.0 0.447
1.0 0.322

BH01 UDS02 4.00 Brownish grey clayey silt 1.88 1.46 2.71 28 S TRSH-UU 0.25 0 34 22 6 89 5
with sand mixture and 29 T 3.0 0.359
rusty spots. 2.0 0.235
1.0 0.149

BH01 UDS03 7.00 Reddish brown clayey 2.06 1.70 2.73 21 S 0.676 TRSH-UU 0.62 0 36 20 6 85 9
silt with traces of kankar. 21 T 3.0 0.709
23 C 2.0 0.652
1.0 0.493

BH01 UDS04 10.00 Brownish grey clayey silt 2.06 1.66 2.75 24 S TRSH-UU 0.48 0 40 20 15 71 14
with kankar. 24 T 3.0 0.588
2.0 0.447
1.0 0.395

BH01 SPT09 15.00 Brownish grey clayey silt 9 91(Silt+Clay)


with sand mixture.

BH01 SPT10 16.60 Brownish grey clayey silt 2.65 2 98(Silt+Clay)


with fine sand.

BH01 DS08 17.50 Yellowish grey clayey silt 38 16


with sand mixture.

BH01 SPT12 19.50 Brownish grey clayey silt 2.66 27 73(Silt+Clay)


with sand mixture.

BH01 SPT15 24.00 Brownish grey silty sand. 93 7(Silt+Clay)


Res-336309 / Page 2

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %
BH01 SPT17 27.00 Brownish grey silty sand. 2.66 90 10(Silt+Clay)

BH01 SPT20 30.00 Brownish grey silty sand 2.70 97 3(Silt+Clay)

BH01 SPT19 30.00 Brownish grey silty sand. 93 7(Silt+Clay)

BH02 UDS01 3.00 Brownish grey clayey silt 1.86 1.42 2.72 29 S 0.849 TRSH-UU 0.63 0 35 25 8 85 7
with sand mixture and 31 T 3.0 0.723
rusty spots. 31 C 2.0 0.633
1.0 0.532

BH02 UDS02 6.00 Brownish grey clayey silt 2.00 1.63 2.71 21 S TRSH-UU 0.56 0 40 18 10 73 17
with rusty spots. 23 T 3.0 0.672
2.0 0.531
1.0 0.465

BH02 UDS03 9.00 Brownish grey clayey silt 2.08 1.76 2.71 18 S TRSH-UU 1.59 0 36 16 26 55 19
with sand mixture and 18 T 3.0 1.659
kankar. 2.0 1.594
1.0 1.523

BH02 DS06 10.50 Yellowish grey clayey silt 38 15


with sand mixture.

BH02 SPT08 12.60 Brownish grey clayey silt 2.65 28 72(Silt+Clay)


with sand mixture.

BH02 SPT13 20.00 Brownish grey silty sand. 91 9(Silt+Clay)


Res-336309 / Page 3

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %

BH02 SPT16 24.50 Brownish grey silty sand. 2.66 90 10(Silt+Clay)

BH02 SPT18 27.50 Brownish grey silty sand. 2.66 90 10(Silt+Clay)

BH02 SPT20 30.00 Brownish grey silty sand. 91 9(Silt+Clay)

BH03 UDS01 3.00 Grayish brown clayey silt 1.95 1.49 2.71 30 S 0.769 TRSH-UU 0.54 0 35 25 7 80 13
with sand mixture. 31 T 3.0 0.701
28 C 2.0 0.542
1.0 0.391

BH03 UDS02 6.00 Brownish grey clayey silt 2.03 1.69 2.71 21 S TRSH-UU 0.78 0 38 16 8 83 9
with rusty spots. 20 T 3.0 0.812
2.0 0.788
1.0 0.742

BH03 UDS03 9.00 Brownish grey clayey silt 2.13 1.81 2.71 19 S 0.586 TRSH-UU 1.12 0 41 17 8 72 20
with traces of kankar and 18 T 3.0 1.241
sand mixture. 18 C 2.0 1.173
1.0 0.938

BH03 UDS04 12.00 Brownish grey clayey silt 2.09 1.77 2.70 17 S TRSH-UU 1.19 0 38 16 39 51 10
with rusty spots. 18 T 3.0 1.286
2.0 1.162
1.0 1.130

BH03 SPT08 12.45 Yellowish grey clayey silt 2.65 23 77(Silt+Clay)


with sand mixture.
Res-336309 / Page 4

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %

BH03 SPT09 13.50 Brownish grey silty sand 88 12(Silt+Clay)


with mica.

BH03 SPT10 15.60 Brownish grey silty sand 81 19(Silt+Clay)


with traces of mica.

BH03 SPT12 18.60 Brownish grey silty sand 2.67 88 12(Silt+Clay)

BH03 SPT15 23.00 Brownish grey silty sand. 91 9(Silt+Clay)

BH03 SPT16 24.00 Brownish grey silty sand 2.72 40 55 5(Silt+Clay)


with gravel pieces.

BH03 SPT17 26.00 Brownish grey silty sand. 86 14(Silt+Clay)

BH03 DS17 26.50 Brownish grey silty sand 93 7(Silt+Clay)

BH03 SPT18 27.00 Brownish grey silty sand 2.70 6 86 8(Silt+Clay)


with gravel.

BH03 SPT19 27.00 Brownish grey silty sand 8 85 7(Silt+Clay)


Res-336309 / Page 5

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %
BH03 SPT20 30.00 Brownish grey silty sand 2.70 10 81 9(Silt+Clay)
with gravel.

BH04 UDS01 3.00 Brownish grey clayey silt 2.00 1.65 2.75 21 S 0.705 TRSH-UU 0.50 0 37 22 11 79 10
with kankar. 22 T 3.0 0.521
22 C 2.0 0.495
1.0 0.484

BH04 UDS02 6.00 Brownish grey clayey silt 1.98 1.57 2.71 23 S TRSH-UU 0.45 0 42 18 8 75 17
with rusty spots. 26 T 3.0 0.509
2.0 0.421
1.0 0.435

BH04 UDS03 9.00 Brownish grey clayey silt 1.93 1.55 2.71 24 T TRSH-UU 0.74 0 6 76 18
with kankar. 3.0 0.778
2.0 0.739
1.0 0.703

BH04 UDS04 12.00 Brownish grey clayey silt 1.90 1.45 2.72 31 T TRSH-UU 0.79 0 6 85 9
with rusty spots. 3.0 0.878
2.0 0.770
1.0 0.722

BH04 SPT09 14.00 Yellowish brown clayey 42 47 11


silt with sand mixture.

BH04 SPT11 17.00 Brownish grey silty sand 87 13(Silt+Clay)

BH04 SPT13 20.00 Brownish grey silty sand 2.68 89 11(Silt+Clay)


Res-336309 / Page 6

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %
BH04 SPT15 23.00 Brownish grey silty sand 2.70 3 93 4(Silt+Clay)
with gravel.

BH04 SPT18 27.50 Brownish grey silty sand 87 13(Silt+Clay)

BH04 SPT20 30.00 Brownish grey silty sand 88 12(Silt+Clay)

BH05 UDS01 3.00 Brownish grey clayey silt 1.89 1.56 0.00 19 S 0.609 TRSH-UU 0.60 0 31 21 18 77 5
with sand mixture. 21 T 3.0 0.625
18 C 2.0 0.605
1.0 0.562

BH05 UDS02 6.00 Brownish grey clayey silt 2.00 1.57 2.72 27 S TRSH-UU 0.81 0 39 16 8 81 11
with sand mixture. 27 T 3.0 0.826
2.0 0.809
1.0 0.800
Res-336309 / Page 7

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %
BH05 UDS03 9.00 Brownish grey clayey silt 2.01 1.59 2.71 24 S 0.600 TRSH-UU 0.87 0 39 17 7 73 20
with sand mixture and 26 T 3.0 0.886
kankar. 22 C 2.0 0.871
1.0 0.846

BH05 UDS04 12.00 Brownish grey clayey silt 2.04 1.59 2.71 29 S TRSH-UU 1.20 0 42 16 14 69 17
with sand mixture and 28 T 3.0 1.228
kankar. 2.0 1.195
1.0 1.177

BH05 SPT10 15.60 Brownish grey silty sand 89 11(Silt+Clay)

BH05 SPT12 18.60 Brownish grey silty sand 87 13(Silt+Clay)

BH05 SPT15 23.00 Brownish grey silty sand 87 13(Silt+Clay)

BH05 SPT17 26.00 Brownish grey silty sand 92 8(Silt+Clay)

BH06 UDS01 3.00 Yellowish grey clayey silt 1.99 1.72 2.70 16 S TRSH-UU 0.85 0 32 19 15 78 7
with sand mixture. 16 T 3.0 0.873
2.0 0.848
1.0 0.829

BH06 UDS02 6.00 Yellowish grey clayey silt 1.87 1.40 2.71 32 S TRSH-UU 1.26 0 41 22 6 77 17
with kankar and sand 34 T 3.0 1.283
mixture. 2.0 1.260
1.0 1.244
Res-336309 / Page 8

Bore Sample Depth Sample Description Bulk Dry Spec. Nat. Void Strength Test Results Atter. Limits Grain Size
Hole Number M Dens. Dens. Grav. Mois. Ratio Pc/Pn Shear Cohesn Frictn LL PL SL Gravl Sand Silt Clay
gms/cc gms/cc % kg/sqcm kg/sqcm kg/sqcm Deg. % % % % % % %
BH06 UDS03 9.00 Brownish grey clayey silt 2.07 1.72 2.71 24 S TRSH-UU 1.06 0 39 16 6 74 20
with traces of kankar. 20 T 3.0 1.085
2.0 1.056
1.0 1.039

BH06 UDS04 12.00 Brownish grey clayey silt 2.10 1.77 2.72 20 S TRSH-UU 1.84 0 34 21 6 74 20
with kankar and sand 18 T 3.0 1.869
mixture. 2.0 1.838
1.0 1.815

BH06 SPT09 14.00 Yellowish brown clayey 2.71 17 68 15


silt with sand mixture.

BH06 SPT11 17.00 Brownish grey silty sand 86 14(Silt+Clay)

BH06 SPT14 21.50 Brownish grey silty sand 91 9(Silt+Clay)

BH06 SPT16 24.50 Brownish grey silty sand 89 11(Silt+Clay)

BH06 SPT18 27.50 Brownish grey silty sand 2.68 90 10(Silt+Clay)

BH06 SPT20 30.00 Brownish grey silty sand 88 12(Silt+Clay)


SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing at Ch.: NH-30/119 km. Commencement Date : 6/7/2015 Level of Ground : 57.630 M Job No : 3363_09
Bore Hole No. : 1 Location : (L.C.No.48A/3T) Completion Date : 7/7/2015 Standing Water Level : m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)
57.630 57.630 150
0.00m
57.130 0.50 0.50 DS-01

56.630 1.00 1.45 1.00 UDS-01 UU 15 80 15 1.51 2.73 0.651 28 37 21 0.43 0 7.28 0.0280 0.050

56.180 1.45 1.90 1.45 SPT-01 1.45 4

55.130 2.50 2.50 DS-02

54.630 3.00 3.45 3.00 SPT-02 3.00 4

53.630 4.00 4.45 4.00 UDS-02 UU 6 89 5 1.46 2.71 28 34 22 0.25 0

52.630 5.00 5.00 DS-03

52.130 5.50 5.95 5.50 SPT-03 5.50 8

51.130 6.50 6.50 DS-04

50.630 7.00 7.45 7.00 UDS-03 UU 6 85 9 1.69 2.73 0.676 21 36 20 0.62 0


Medium to Stiff, yellowish grey, clayey
50.180 7.45 7.90 7.45 SPT-04 7.45 10 silt / silty clay. Observed kankars.

49.130 8.50 8.50 DS-05

48.630 9.00 9.45 9.00 SPT-05 9.00 8

47.630 10.00 10.45 10.00 UDS-04 UU 15 71 14 1.66 2.75 24 40 20 0.48 0

47.180 10.45 10.90 10.45 SPT-06 10.45 10

46.130 11.50 11.50 DS-06

45.630 12.00 12.45 12.00 SPT-07 12.00 11

44.630 13.00 13.45 13.00 *UDS-05

44.030 13.60 14.05 13.60 SPT-08 13.60 13

43.130 14.50 14.50 DS-07


14.50 m
42.630 15.00 15.45 15.00 SPT-09 15.00 18 9 91(Silt+Clay)

41.630 16.00 16.45 16.00 *UDS-06


Very stiff, yellowish grey, clayey silt / /
silty clay. Observed kankars
41.030 16.60 17.05 16.60 SPT-10 16.60 18 2 98(Silt+Clay) 2.650

40.130 17.50 17.50 DS-08 38 16


SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing at Ch.: NH-30/119 km. Commencement Date : 6/7/2015 Level of Ground : 57.630 M Job No : 3363_09
Bore Hole No. : 1 Location : (L.C.No.48A/3T) Completion Date : 7/7/2015 Standing Water Level : m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)

39.630 18.00 18.45 18.00 SPT-11 18.00 22

38.630 19.00 19.00 DS-09

38.130 19.50 19.95 19.50 SPT-12 19.50 27 Very stiff, yellowish grey, clayey silt / / 27 73(Silt+Clay) 2.66
silty clay. Observed kankars
37.130 20.50 20.50 DS-10

36.630 21.00 21.45 21.00 SPT-13 21.00 40

21.00m
35.630 22.00 22.00 DS-11

35.130 22.50 22.95 22.50 SPT-14 22.50 42

34.130 23.50 23.50 DS-12

33.630 24.00 24.45 24.00 SPT-15 24.00 50 93 7(Silt+Clay)

32.630 25.00 25.00 DS-13

32.130 25.50 25.95 25.50 SPT-16 25.50 51


Dense to very dense, yellowish brown,
31.130 26.50 26.50 DS-14 silty sand.

30.630 27.00 27.45 27.00 SPT-17 27.00 58 90 10(Silt+Clay) 2.66

29.630 28.00 28.00 DS-15

29.130 28.50 28.95 28.50 SPT-18 28.50 61 97 3(Silt+Clay) 2.70

28.130 29.50 29.50 DS-16

27.630 30.00 30.45 30.00 SPT-19 30.00 83 93 7(Silt+Clay)


30.45m

Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
B.D.L. = Below Detection Limit for soil samples SO 4 content is expressed as SO3.
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing at Ch.: NH-30/119 km. Commencement Date : 4/7/2015 Level of Ground : 57.740 M Job No : 3363_09
Bore Hole No. : 2 Location : (L.C.No.48A/3T) Completion Date : 5/7/2015 Standing Water Level : m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)
57.740 57.740 150
0.00m
57.240 0.50 0.50 DS-01

56.740 1.00 1.00 DS-02

56.240 1.50 1.95 1.50 SPT-1 1.50 4


Medium, brownish grey, Silty clay
/clayey silt. Observed kankars
55.240 2.50 2.50 DS-03

54.740 3.00 3.45 3.00 UDS-01 UU 8 85 7 1.43 2.72 0.849 30 35 25 0.63 0

54.290 3.45 3.90 3.45 SPT-2 3.45 5


3.45 m
53.240 4.50 4.50 DS-4

52.740 5 5.45 5.00 SPT-3 5 9

51.740 6.00 6.45 6.00 UDS-02 UU 10 73 17 1.64 2.71 22 40 18 0.56 0


Stiff, yellowish grey, silty clay/clayey
silt. Observed kankars.
51.290 6.45 6.90 6.45 SPT-04 6.45 10

50.240 7.50 7.50 DS-5

49.740 8.00 8.45 8.00 SPT-05 8.00 20


8.00 m
48.740 9.00 9.45 9.00 UDS-3 UU 26 55 19 1.76 2.71 18 36 16 1.59 0

48.290 9.45 9.90 9.45 SPT-06 9.45 28

47.240 10.50 10.50 DS-6 38 15


Very stiff, yellowish grey, silty clay /
46.740 11.00 11.45 11.00 SPT-07 11.00 24
clayey silt. Observed kankars.
45.740 12.00 12.45 12.00 *UDS-04

45.140 12.60 13.05 12.60 SPT-8 12.60 28 28 72(Silt+Clay) 2.65

44.240 13.50 13.50 DS-7


14.00 m
43.740 14.00 14.45 14.00 SPT-9 14.00 37

42.740 15.00 15.45 15.00 *UDS-5


Dense to very dense, yellowish brown,
silty sand.
42.140 15.60 16.05 15.60 SPT-10 15.60 39

41.240 16.50 16.50 DS-8


SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing at Ch.: NH-30/119 km. Commencement Date : 4/7/2015 Level of Ground : 57.740 M Job No : 3363_09
Bore Hole No. : 2 Location : (L.C.No.48A/3T) Completion Date : 5/7/2015 Standing Water Level : m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)

40.740 17.00 17.45 17.00 SPT-11 17.00 40

39.740 18 18.45 18.00 *UDS-6

39.140 18.60 19.05 18.60 SPT-12 18.60 44

38.240 19.50 19.50 DS-9

37.740 20.00 20.45 20.00 SPT-13 20.00 45 91 9(Silt+Clay)

36.740 21.00 21.00 DS-10

36.240 21.50 21.95 21.50 SPT-14 21.50 48

35.240 22.50 22.50 DS-11

34.740 23.00 23.45 23.00 SPT-15 23.00 50

33.740 24.00 24.00 DS-12

33.240 24.50 24.95 24.50 SPT-16 24.50 57 Dense to very dense, yellowish brown, 9010(Silt+Clay) 2.66
silty sand.
32.240 25.50 25.50 DS-13

31.740 26.00 26.45 26.00 SPT-17 26.00 58

30.740 27.00 27.00 DS-14

30.240 27.50 27.95 27.50 SPT-18 27.50 64 90 10(Silt+Clay) 2.66

29.240 28.50 28.50 DS-15

28.740 29.00 29.45 29.00 SPT-19 29.00 79

27.940 29.80 29.80 DS-16

27.740 30.00 30.45 30.00 SPT-20 30.00 81 91 9(Silt+Clay)

57.740
30.45m

Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
B.D.L. = Below Detection Limit for soil samples SO 4 content is expressed as SO3.
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 3/7/2015 Level of Ground : 56.410 M Job No : 3363_09
Bore Hole No. : 3 Location : (L.C.No.48A/3T) Completion Date : 4/7/2015 Standing Water Level : 2.10 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)
56.410 54.310 150
0.00m
55.910 0.50 0.50 DS-01 Brownish grey, silty clay / clayey silt.
0.90m
55.410 1.00 1.00 DS-02

54.910 1.50 1.95 1.50 SPT-01 1.50 4

53.910 2.50 2.50 DS-03

53.410 3.00 3.45 3.00 UDS-01 UU 7 80 13 1.50 2.71 0.769 30 35 25 0.54 0

52.960 3.45 3.90 3.45 SPT-02 3.45 5 Medium to stiff, yellowish grey, silty
clay / clayey silt. Observed kankars,
51.910 4.50 4.50 DS-04 black spots.

51.410 5.00 5.45 5.00 SPT-03 5.00 9

50.410 6.00 6.45 6.00 UDS-02 UU 8 83 9 1.68 2.71 21 38 16 0.78 0

49.960 6.45 6.90 6.45 SPT-04 6.45 13

48.910 7.50 7.50 DS-05


7.50m
48.410 8.00 8.45 8.00 SPT-05 8.00 23

47.410 9.00 9.45 9.00 UDS-03 UU 8 72 20 1.80 2.71 0.586 18 41 17 1.12 0


Very stiff, yellowish grey, clayey silt.
46.960 9.45 9.90 9.45 SPT-06 9.45 28 Observed kankar, black spots etc.

45.910 10.50 10.50 DS-06

45.410 11.00 11.45 11.00 SPT-07 11.00 30


11.00m
44.410 12.00 12.45 12.00 UDS-04 UU 39 51 10 1.78 2.70 18 38 16 1.19 0

43.960 12.45 12.90 12.45 SPT-08 12.45 34 23 77(Silt+Clay) 2.65


Hard, yellowish grey, silty clay/ clayey
42.910 13.50 13.50 DS-07 silt. Observed kankars.

42.410 14.00 14.45 14.00 SPT-09 14.00 40 88 12(Silt+Clay)

41.410 15.00 15.45 15.00 *UDS-05


15.00m
40.810 15.60 16.05 15.60 SPT-10 15.60 44 81 19(Silt+Clay)
Dense to very dense, yellowish grey,
39.910 16.50 16.50 DS-08
silty sand. Observed kankars.
39.410 17.00 17.45 17.00 SPT-11 17.00 50
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 3/7/2015 Level of Ground : 56.410 M Job No : 3363_09
Bore Hole No. : 3 Location : (L.C.No.48A/3T) Completion Date : 4/7/2015 Standing Water Level : 2.10 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)

38.410 18.00 18.45 18.00 *UDS-06

37.810 18.60 19.05 18.60 SPT-12 18.60 38 88 12(Silt+Clay) 2.67

36.910 19.50 19.50 DS-09

36.410 20.00 20.45 20.00 SPT-13 20.00 50

35.410 21.00 21.00 DS-10

34.910 21.50 21.95 21.50 SPT-14 21.50 46

33.910 22.50 22.50 DS-11

33.410 23.00 23.45 23.00 SPT-15 23.00 43 91 9(Silt+Clay)

32.410 24.00 24.00 DS-12 Dense to very dense, yellowish grey,


silty sand. Observed kankars.
31.910 24.50 24.95 24.50 SPT-16 24.50 48 40 55 5(Silt+Clay) 2.72

30.910 25.50 25.50 DS-13

30.410 26.00 26.45 26.00 SPT-17 26.00 57 86 14(Silt+Clay)

29.410 27.00 27.00 DS-14 93 7(Silt+Clay)

28.910 27.50 27.95 27.50 SPT-18 27.50 52 6 86 8(Silt+Clay) 2.70

27.910 28.50 28.50 DS-15

27.410 29.00 29.45 29.00 SPT-19 29.00 60 8 85 7(Silt+Clay)

26.610 29.80 29.80 DS-16


30.00 30.45 30.00 SPT-20 30.00 74 30.45m 10 81 9(Silt+Clay) 2.70

Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
B.D.L. = Below Detection Limit for soil samples SO 4 content is expressed as SO3.
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 1/7/2015 Level of Ground : 56.350 M Job No : 3363_09
Bore Hole No. : 4 Location : (L.C.No.48A/3T) Completion Date : 2/7/2015 Standing Water Level : 3.40 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)
56.350 52.950 150
0.00m
55.850 0.50 0.50 DS-01

55.350 1.00 1.00 DS-02

54.850 1.50 1.95 1.50 SPT-01 1.50 5

53.850 2.50 2.50 DS-03

53.350 3.00 3.45 3.00 UDS-01 UU 11 79 10 1.64 2.75 0.705 22 37 22 0.50 0 7.79 0.0120 B.D.L.

52.900 3.45 3.90 3.45 SPT-02 3.45 9

51.850 4.50 4.50 DS-04

51.350 5.00 5.45 5.00 SPT-03 5.00 9


Medium to Stiff, brownish / yellowish
grey, clayey silt. Observed kankars.
50.350 6.00 6.45 6.00 UDS-02 UU 8 75 17 1.59 2.71 25 42 18 0.45 0

49.900 6.45 6.90 6.45 SPT-04 6.45 10

48.850 7.50 7.50 DS-05

48.350 8.00 8.45 8.00 SPT-05 8.00 11

47.350 9.00 9.45 9.00 UDS-03 UU 6 76 18 1.56 2.71 24 0.74 0

46.900 9.45 9.90 9.45 SPT-06 9.45 14

45.850 10.50 10.50 DS-06

45.350 11.00 11.45 11.00 SPT-07 11.00 17


11.00m
44.350 12.00 12.45 12.00 UDS-04 UU 6 85 9 1.45 2.72 31 0.79 0
Very stiff, yellowish grey, clayey silt /
43.900 12.45 12.90 12.45 SPT-08 12.45 25
silty clay. Observed kankars.
42.850 13.50 13.50 DS-07
14.00m
42.350 14.00 14.45 14.00 SPT-09 14.00 23 42 47 11

41.350 15.00 15.45 15.00 *UDS-05


Very stiff to hard, reddish brown,clayey
40.750 15.60 16.05 15.60 SPT-10 15.60 32 silt / silty clay. Observed kankars and
calc. nodules.
39.850 16.50 16.50 DS-08

39.850 16.50 16.50 DS-09


SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 1/7/2015 Level of Ground : 56.350 M Job No : 3363_09
Bore Hole No. : 4 Location : (L.C.No.48A/3T) Completion Date : 2/7/2015 Standing Water Level : 3.40 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)

39.350 17.00 17.45 17.00 SPT-11 17.00 36 87 13(Silt+Clay)

38.350 18.00 18.45 18.00 *UDS-06


18.00m
37.750 18.60 19.05 18.60 SPT-12 18.60 36

36.850 19.50 19.50 DS-10

36.850 19.50 19.50 DS-11

36.350 20.00 20.45 20.00 SPT-13 20.00 48 89 11(Silt+Clay) 2.68

35.350 21.00 21.45 21.00 *UDS-07

34.750 21.60 22.05 21.60 SPT-14 21.60 53

33.850 22.50 22.50 DS-12

33.350 23.00 23.45 23.00 SPT-15 23.00 52 3 934(Silt+Clay) 2.70

32.350 24.00 24.00 DS-13


Dense to very dense, reddish brown,
silty sand. Observed kankars.
31.850 24.50 24.95 24.50 SPT-16 24.50 46

30.850 25.50 25.50 DS-14

30.350 26.00 26.45 26.00 SPT-17 26.00 52

29.350 27.00 27.00 DS-15

28.850 27.50 27.95 27.50 SPT-18 27.50 56 87 13(Silt+Clay)

27.850 28.50 28.50 DS-16

27.350 29.00 29.45 29.00 SPT-19 29.00 59

26.550
29.80 29.80 DS-17
26.350 30.00 30.45 30.00 SPT-20 30.00 60 88 12(Silt+Clay)

Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) 30.45m R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
B.D.L. = Below Detection Limit for soil samples SO 4 content is expressed as SO3.
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 3/7/2015 Level of Ground : 56.930 M Job No : 3363_09
Bore Hole No. : 5 Location : (L.C.No.48A/3T) Completion Date : 4/7/2015 Standing Water Level : 2.90 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)
56.930 54.030 150
0.00m
56.430 0.50 0.50 DS-01

55.930 1.00 1.00 DS-02

55.430 1.50 1.95 1.50 SPT-01 1.50 7

54.430 2.50 2.50 DS-03 Medium, brownish grey, Silty clay


/clayey silt. Observed kankars.
53.930 3.00 3.45 3.00 UDS-01 UU 18 77 5 1.58 0.00 0.609 19 31 21 0.60 0 7.50 0.0130 0.050

53.480 3.45 3.90 3.45 SPT-02 3.45 8

52.430 4.50 4.50 DS-04

51.930 5.00 5.45 5.00 SPT-03 5.00 17


5.00m
50.930 6.00 6.45 6.00 UDS-02 UU 8 81 11 1.57 2.72 27 39 16 0.81 0

50.480 6.45 6.90 6.45 SPT-04 6.45 18

49.430 7.50 7.50 DS-05

48.930 8.00 8.45 8.00 SPT-05 8.00 16

47.930 9.00 9.45 9.00 UDS-03 UU 7 73 20 1.62 2.71 0.600 24 39 17 0.87 0


Very stiff, yellowish grey, silty clay /
47.480 9.45 9.90 9.45 SPT-06 9.45 20 clayey silt. Observed kankars.

46.430 10.50 10.50 DS-06

45.930 11.00 11.45 11.00 SPT-07 11.00 25

44.930 12.00 12.45 12.00 UDS-04 UU 14 69 17 1.59 2.71 29 42 16 1.20 0

44.480 12.45 12.90 12.45 SPT-08 12.45 30

43.430 13.50 13.50 DS-07


14.50m
42.930 14.00 14.45 14.00 SPT-09 14.00 29

41.930 15.00 15.45 15.00 *UDS-05


Dense to very dense, yellowish brown,
41.330 15.60 16.05 15.60 SPT-10 15.60 39 89 11(Silt+Clay)
silty sand. Observed kankars.
40.430 16.50 16.50 DS-08

39.930 17.00 17.45 17.00 SPT-11 17.00 39


SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 3/7/2015 Level of Ground : 56.930 M Job No : 3363_09
Bore Hole No. : 5 Location : (L.C.No.48A/3T) Completion Date : 4/7/2015 Standing Water Level : 2.90 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)

38.930 18.00 18.45 18.00 *UDS-06

38.330 18.60 19.05 18.60 SPT-12 18.60 54 87 13(Silt+Clay)

37.430 19.50 19.50 DS-09

36.930 20.00 20.45 20.00 SPT-13 20.00 48

35.930 21.00 21.00 DS-10

35.430 21.50 21.95 21.50 SPT-14 21.50 55

34.430 22.50 22.50 DS-11

33.930 23.00 23.45 23.00 SPT-15 23.00 53 87 13(Silt+Clay)

32.930 24.00 24.00 DS-12 Dense to very dense, yellowish brown,


silty sand. Observed kankars.
32.430 24.50 24.95 24.50 SPT-16 24.50 54

31.430 25.50 25.50 DS-13

30.930 26.00 26.45 26.00 SPT-17 26.00 62 92 8(Silt+Clay)

29.930 27.00 27.00 DS-14

29.430 27.50 27.95 27.50 SPT-18 27.50 62

28.430 28.50 28.50 DS-15

27.930 29.00 29.45 29.00 SPT-19 29.00 54

27.130 29.80 29.80 DS-16


30.00 30.45 30.00 SPT-20 30.00 67 30.45m

Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
B.D.L. = Below Detection Limit for soil samples SO 4 content is expressed as SO3.
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 4/7/2015 Level of Ground : 54.180 M Job No : 3363_09
Bore Hole No. : 6 Location : (L.C.No.48A/3T) Completion Date : 6/7/2015 Standing Water Level : 1.90 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)
54.180 52.280 150
0.00m
53.680 0.50 0.50 DS-01

53.180 1.00 1.00 DS-02


Medium, brownish grey, clayey silt/silty
clay. Observed kankars.
52.680 1.50 1.95 1.50 SPT-01 1.50 5

51.680 2.50 2.50 DS-03


2.30m
51.180 3.00 3.45 3.00 UDS-01 UU 15 78 7 1.72 2.70 16 32 19 0.85 0

50.730 3.45 3.90 3.45 SPT-02 3.45 14


Stiff, yellowish grey, clayey silt.
Observed kankars.
49.680 4.50 4.50 DS-04

49.180 5.00 5.45 5.00 SPT-03 5.00 24


5.00m
48.180 6.00 6.45 6.00 UDS-02 UU 6 77 17 1.41 2.71 33 41 22 1.26 0

47.730 6.45 6.90 6.45 SPT-04 6.45 30

46.680 7.50 7.50 DS-05

46.180 8.00 8.45 8.00 SPT-05 8.00 34

45.180 9.00 9.45 9.00 UDS-03 UU 6 74 20 1.70 2.71 22 39 16 1.06 0


Very stiff, yellowish grey, clayey silt.
44.730 9.45 9.90 9.45 SPT-06 9.45 33
Observed kankars.
43.680 10.50 10.50 DS-06

43.180 11.00 11.45 11.00 SPT-07 11.00 36

42.180 12.00 12.45 12.00 UDS-04 UU 6 74 20 1.76 2.72 19 34 21 1.84 0

41.730 12.45 12.90 12.45 SPT-08 12.45 41

40.680 13.50 13.50 DS-07


14.00m
40.180 14.00 14.45 14.00 SPT-09 14.00 44 17 68 15 2.71

39.180 15.00 15.45 15.00 *UDS-05


Dense to very dense, yellowish grey,
38.580 15.60 16.05 15.60 SPT-10 15.60 43
silty sand. Observed kankars.
37.680 16.50 16.50 DS-08

37.180 17.00 17.45 17.00 SPT-11 17.00 50 86 14(Silt+Clay)


SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech Inv.work for proposed ROB replacing Level crossing,NH-28B Commencement Date : 4/7/2015 Level of Ground : 54.180 M Job No : 3363_09
Bore Hole No. : 6 Location : (L.C.No.48A/3T) Completion Date : 6/7/2015 Standing Water Level : 1.90 m. Sheet No :

Depth in Mete
S.P.T. blows Shearing Strength
below
per 30cm Characteristics
reference

Visual Description of Soil


pH
Cl (%)
SO4 (%)
Remarks

Void Ratio
Content (%)

at Laboratory

To
reference level
Percent RQD
Specific Gravity

Sample Ref. No.


%Gravel>72mm
Liquid Limit (%)

From
Natural Moisture
Plastic Limit (%)

Value
% Clay<0.002mm

Size of Hole (mm)

Elevation in Metre
Strength (kg/sqcm)

%Sand 2.0-0.06mm
Shrinkage Limit (%)

% Silt 0.06-0.002mm

Type of test conducted

Depth of Sample below


Dry Density in gms/cm3

Symbolic representation
Dry / Saturated Crushing

Percent Core Recovery

Depth in Metre

Level of Water table/L.W.L.


Angle of Shearing
Resistance in Deg.

Cohesion C (kg/cm2)

36.180 18.00 18.45 18.00 *UDS-06

35.580 18.60 19.05 18.60 SPT-12 18.60 52

34.680 19.50 19.50 DS-09

34.180 20.00 20.45 20.00 SPT-13 20.00 58

33.180 21.00 21.00 DS-10

32.680 21.50 21.95 21.50 SPT-14 21.50 54 91 9(Silt+Clay)

31.680 22.50 22.50 DS-11

31.180 23.00 23.45 23.00 SPT-15 23.00 62

30.180 24.00 24.00 DS-12 Dense to very dense, yellowish grey,


silty sand. Observed kankars.
29.680 24.50 24.95 24.50 SPT-16 24.50 60 89 11(Silt+Clay)

28.680 25.50 25.50 DS-13

28.180 26.00 26.45 26.00 SPT-17 26.00 60

27.180 27.00 27.00 DS-14

26.680 27.50 27.95 27.50 SPT-18 27.50 59 90 10(Silt+Clay) 2.68

25.680 28.50 28.50 DS-15

25.180 29.00 29.45 29.00 SPT-19 29.00 69

24.380 29.80 29.80 DS-16


24.180 30.00 30.45 30.00 SPT-20 30.00 65 30.45m 88 12(Silt+Clay)

Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
B.D.L. = Below Detection Limit for soil samples SO 4 content is expressed as SO3.
Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-01/UDS-01 Depth :1-1.45 meters


Description :Brownish grey clayey silt with traces of fine sand mixture.
Water content:Initial=22.7% Final =19.5% Initial Void Ratio =0.651

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 37 0.645 0.0371


0.10 - 0.25 91 0.630 0.0610 34.07 0.0402 293.0 2.788
0.25 - 0.50 104 0.613 0.0422 28.85 0.0300 277.4 2.830
0.50 - 1.00 140 0.589 0.0287 55.71 0.0127 247.3 3.015
1.00 - 2.00 165 0.562 0.0172 34.43 0.0113 175.4 3.977
2.00 - 4.00 202 0.529 0.0107 46.53 0.0057 240.0 2.677
4.00 - 8.00 274 0.483 0.0074 46.72 0.0039 173.4 3.311
8.00 - 0.25 191 0.515 0.0027

e-logp Curve

0.650
0.640
0.630
0.620
0.610
0.600
0.590
0.580
VOID RATIO

0.570
0.560
0.550
0.540
0.530
0.520
0.510
0.500
0.490
0.480
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-01/UDS-03 Depth :7-7.45 meters


Description :Reddish brown clayey silt.
Water content:Initial=23.3% Final =19.2% Initial Void Ratio =0.676

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 20 0.673 0.0200


0.10 - 0.25 58 0.663 0.0387 34.48 0.0253 1013.5 0.824
0.25 - 0.50 104 0.646 0.0418 27.88 0.0302 766.7 1.054
0.50 - 1.00 210 0.611 0.0427 32.86 0.0287 814.6 0.929
1.00 - 2.00 235 0.571 0.0244 12.18 0.0214 1922.1 0.357
2.00 - 4.00 285 0.524 0.0152 20.70 0.0120 821.4 0.743
4.00 - 8.00 309 0.472 0.0085 28.48 0.0061 2152.8 0.245
8.00 - 0.25 201 0.506 0.0029

e-logp Curve

0.680
0.670
0.660
0.650
0.640
0.630
0.620
0.610
0.600
VOID RATIO

0.590
0.580
0.570
0.560
0.550
0.540
0.530
0.520
0.510
0.500
0.490
0.480
0.470
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-02/UDS-01 Depth :3-3.45 meters


Description :Brownish grey clayey silt.
Water content:Initial=30.7% Final =26.5% Initial Void Ratio =0.849

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 37 0.842 0.0369


0.10 - 0.25 79 0.827 0.0527 21.52 0.0414 399.4 2.069
0.25 - 0.50 104 0.808 0.0420 26.92 0.0307 522.2 1.525
0.50 - 1.00 134 0.783 0.0273 20.90 0.0216 277.4 2.731
1.00 - 2.00 157 0.754 0.0162 36.31 0.0103 181.7 3.917
2.00 - 4.00 285 0.702 0.0150 31.58 0.0102 200.9 3.208
4.00 - 8.00 397 0.629 0.0108 35.77 0.0069 232.9 2.352
8.00 - 0.25 211 0.667 0.0031

e-logp Curve

0.850
0.840
0.830
0.820
0.810
0.800
0.790
0.780
0.770
0.760
VOID RATIO

0.750
0.740
0.730
0.720
0.710
0.700
0.690
0.680
0.670
0.660
0.650
0.640
0.630
0.620
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-03/UDS-01 Depth :3-3.45 meters


Description :Brownish grey clayey silt withn fine sand.
Water content:Initial=28% Final =25.5% Initial Void Ratio =0.769

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 18 0.766 0.0180


0.10 - 0.25 73 0.753 0.0486 56.16 0.0213 92.3 9.038
0.25 - 0.50 90 0.737 0.0362 73.13 0.0097 109.4 7.377
0.50 - 1.00 116 0.717 0.0236 59.48 0.0095 104.5 7.393
1.00 - 2.00 126 0.695 0.0130 61.90 0.0049 107.7 6.815
2.00 - 4.00 209 0.658 0.0109 64.11 0.0039 107.7 6.333
4.00 - 8.00 284 0.608 0.0076 76.41 0.0018 214.3 2.843
8.00 - 0.25 186 0.640 0.0026

e-logp Curve

0.770
0.760
0.750
0.740
0.730
0.720
0.710
0.700
VOID RATIO

0.690
0.680
0.670
0.660
0.650
0.640
0.630
0.620
0.610
0.600
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-03/UDS-03 Depth :9-9.45 meters


Description :Brownish grey clayey silt with traces of kankars.
Water content:Initial=18.4% Final =17% Initial Void Ratio =0.586

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 3 0.586 0.0030


0.10 - 0.25 32 0.581 0.0213 18.75 0.0173 60.0 14.125
0.25 - 0.50 45 0.574 0.0180 17.78 0.0148 60.0 13.908
0.50 - 1.00 97 0.558 0.0195 12.37 0.0171 192.2 4.217
1.00 - 2.00 132 0.538 0.0134 23.48 0.0102 1104.2 0.700
2.00 - 4.00 242 0.499 0.0124 -145.33 0.0305 80.7 8.842
4.00 - 8.00 364 0.442 0.0096 1.24 0.0095 60.0 10.378
8.00 - 0.25 164 0.468 0.0023

e-logp Curve

0.590

0.580

0.570

0.560

0.550

0.540

0.530
VOID RATIO

0.520

0.510

0.500

0.490

0.480

0.470

0.460

0.450

0.440
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-04/UDS-01 Depth :3-3.45 meters


Description :Brownish grey clayey silt.
Water content:Initial=21.7% Final =23.5% Initial Void Ratio =0.705

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 6 0.704 0.0060


0.10 - 0.25 32 0.699 0.0213 25.00 0.0160 87.8 9.607
0.25 - 0.50 63 0.688 0.0252 39.68 0.0152 747.7 1.107
0.50 - 1.00 129 0.666 0.0260 61.24 0.0101 192.2 4.141
1.00 - 2.00 170 0.637 0.0174 31.01 0.0120 138.6 5.394
2.00 - 4.00 250 0.594 0.0130 38.40 0.0080 121.0 5.640
4.00 - 8.00 349 0.535 0.0093 47.85 0.0049 532.8 1.115
8.00 - 0.25 272 0.581 0.0039

e-logp Curve

0.710
0.700
0.690
0.680
0.670
0.660
0.650
0.640
VOID RATIO

0.630
0.620
0.610
0.600
0.590
0.580
0.570
0.560
0.550
0.540
0.530
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-05/UDS-01 Depth :3-3.45 meters


Description :Brownish grey, clayey silt with traces of sand mixture.
Water content:Initial=18% Final =17% Initial Void Ratio =0.609

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 39 0.602 0.0389


0.10 - 0.25 61 0.593 0.0408 47.54 0.0214 297.4 2.781
0.25 - 0.50 98 0.577 0.0395 45.92 0.0214 194.4 4.119
0.50 - 1.00 109 0.559 0.0222 73.29 0.0059 173.8 4.413
1.00 - 2.00 146 0.536 0.0150 53.21 0.0070 167.3 4.341
2.00 - 4.00 170 0.509 0.0089 63.53 0.0032 381.0 1.778
4.00 - 8.00 219 0.473 0.0058 46.58 0.0031 95.3 6.508
8.00 - 0.25 217 0.508 0.0031

e-logp Curve

0.610

0.600

0.590

0.580

0.570

0.560
VOID RATIO

0.550

0.540

0.530

0.520

0.510

0.500

0.490

0.480

0.470
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Project : Geotech Inv. Work for C/O ROB in replacement of existing level crossings in Bihar.

Job No. 336309 Sheet No.

CONSOLIDATION TEST RESULTS

Sample Number:BH-05/UDS-03 Depth :9-9.45 meters


Description :Reddish brown clayey silt with traces of kankars.
Water content:Initial=22.1% Final =18.8% Initial Void Ratio =0.6

P1-P2 Dial Void Mv Comprn Mvc T90 1000.Cv


Kg/Sqcm Change Ratio Sqcm/kg % sqcm/kg Sec sqcm/sec

0.00 - 0.10 4 0.599 0.0040


0.10 - 0.25 23 0.595 0.0153 30.43 0.0107 1488.0 0.567
0.25 - 0.50 51 0.587 0.0204 12.90 0.0178 447.2 1.859
0.50 - 1.00 95 0.572 0.0191 14.74 0.0163 633.8 1.273
1.00 - 2.00 123 0.552 0.0125 18.70 0.0102 777.6 0.992
2.00 - 4.00 212 0.519 0.0109 21.98 0.0085 989.0 0.726
4.00 - 8.00 351 0.462 0.0092 27.35 0.0067 843.8 0.750
8.00 - 0.25 127 0.483 0.0018

e-logp Curve

0.600

0.590

0.580

0.570

0.560

0.550
VOID RATIO

0.540

0.530

0.520

0.510

0.500

0.490

0.480

0.470

0.460
0.10 1.00 10.00

PRESSURE RANGE KG / SQCM


Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-01,UDS-01, 1.00M
Grain size (mm) BH-01,UDS-02, 4.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-01,UDS-01, 1.00M 4.8 79.8 15.4 0.0 0.0 15.4 0.0
BH-01,UDS-02, 4.00M 5.6 88.8 5.6 0.0 0.0 5.6 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-01,UDS-03, 7.00M Grain Size(mm)


BH-01,UDS-04, 10.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-01,UDS-03, 7.00M 8.9 84.9 6.2 0.0 0.0 6.2 0.0
BH-01,UDS-04, 10.00M 14.8 70.6 14.6 0.0 0.0 14.6 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-01,SPT-09, 15.00M
Grain size (mm)BH-01,SPT-10, 16.60M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-01,SPT-09, 15.00M 0.0 91.1 4.6 3.2 1.1 8.9 0.0
BH-01,SPT-10, 16.60M 0.0 98.2 1.8 0.0 0.0 1.8 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-01,SPT-12, 19.50M Grain Size(mm)


BH-01,SPT-15, 24.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-01,SPT-12, 19.50M 0.0 73.4 11.7 12.5 2.4 26.6 0.0
BH-01,SPT-15, 24.00M 0.0 7.4 49.1 43.5 0.0 92.6 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-01,SPT-17, 27.00M
Grain size (mm)BH-01,SPT-19, 30.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-01,SPT-17, 27.00M 0.0 10.2 66.1 23.7 0.0 89.8 0.0
BH-01,SPT-19, 30.00M 0.0 7.4 53.3 39.3 0.0 92.6 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-02,SPT-08, 12.60M Grain Size(mm)


BH-02,UDS-01, 3.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-02,SPT-08, 12.60M 0.0 72.4 16.6 11.0 0.0 27.6 0.0
BH-02,UDS-01, 3.00M 7.2 84.4 8.4 0.0 0.0 8.4 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-02,UDS-02, 6.00M
Grain size (mm) BH-02,UDS-03, 9.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-02,UDS-02, 6.00M 16.6 73.2 10.2 0.0 0.0 10.2 0.0
BH-02,UDS-03, 9.00M 19.3 55.2 23.7 1.8 0.0 25.5 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-02,SPT-13, 20.00M Grain Size(mm)


BH-02,SPT-16, 24.50M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-02,SPT-13, 20.00M 0.0 8.6 42.2 49.2 0.0 91.4 0.0
BH-02,SPT-16, 24.50M 0.0 10.1 65.2 24.7 0.0 89.9 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-02,SPT-18, 27.50M
Grain size (mm)BH-02,SPT-20, 30.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-02,SPT-18, 27.50M 0.0 10.3 66.3 23.4 0.0 89.7 0.0
BH-02,SPT-20, 30.00M 0.0 9.1 27.5 55.5 7.9 90.9 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-03,UDS-01, 3.00M Grain Size(mm)


BH-03,UDS-02, 6.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-03,UDS-01, 3.00M 13.5 79.3 7.2 0.0 0.0 7.2 0.0
BH-03,UDS-02, 6.00M 8.7 82.7 8.6 0.0 0.0 8.6 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-03,UDS-03, 9.00M
Grain size (mm)BH-03,UDS-04, 12.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-03,UDS-03, 9.00M 19.9 72.1 8.0 0.0 0.0 8.0 0.0
BH-03,UDS-04, 12.00M 10.5 50.7 29.2 9.6 0.0 38.8 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-03,SPT-08, 12.45M Grain Size(mm)


BH-03,SPT-10, 15.60M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-03,SPT-08, 12.45M 0.0 77.0 11.3 7.7 4.0 23.0 0.0
BH-03,SPT-10, 15.60M 0.0 18.9 61.6 19.5 0.0 81.1 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-03,SPT-12, 18.60M
Grain size (mm)BH-03,SPT-15, 23.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-03,SPT-12, 18.60M 0.0 12.1 65.1 22.8 0.0 87.9 0.0
BH-03,SPT-15, 23.00M 0.0 8.9 78.3 12.8 0.0 91.1 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-03,SPT-17, 26.00M Grain Size(mm)


BH-03,SPT-19, 29.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-03,SPT-17, 26.00M 0.0 13.9 69.0 17.1 0.0 86.1 0.0
BH-03,SPT-19, 29.00M 0.0 6.7 19.5 59.7 5.7 84.9 8.4

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-04,UDS-01, 3.00M
Grain size (mm) BH-04,UDS-02, 6.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-04,UDS-01, 3.00M 9.8 79.0 11.2 0.0 0.0 11.2 0.0
BH-04,UDS-02, 6.00M 16.9 75.5 7.6 0.0 0.0 7.6 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-04,UDS-03, 9.00M Grain Size(mm)


BH-04,UDS-04, 12.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-04,UDS-03, 9.00M 18.3 76.1 5.6 0.0 0.0 5.6 0.0
BH-04,UDS-04, 12.00M 8.9 85.3 5.8 0.0 0.0 5.8 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-04,SPT-09, 14.00M
Grain size (mm)BH-04,SPT-11, 17.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-04,SPT-09, 14.00M 10.8 47.2 33.7 8.3 0.0 42.0 0.0
BH-04,SPT-11, 17.00M 0.0 13.0 54.9 32.1 0.0 87.0 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-04,SPT-13, 20.00M Grain Size(mm)


BH-04,SPT-15, 23.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-04,SPT-13, 20.00M 0.0 11.3 64.3 24.4 0.0 88.7 0.0
BH-04,SPT-15, 23.00M 0.0 4.0 18.9 54.6 19.4 92.9 3.1

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-04,SPT-18, 27.50M
Grain size (mm)BH-04,SPT-20, 30.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-04,SPT-18, 27.50M 0.0 13.1 62.6 24.3 0.0 86.9 0.0
BH-04,SPT-20, 30.00M 0.0 11.9 61.3 26.8 0.0 88.1 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-05,SPT-10, 15.60M Grain Size(mm)


BH-05,SPT-12, 18.60M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-05,SPT-10, 15.60M 0.0 11.1 63.4 25.5 0.0 88.9 0.0
BH-05,SPT-12, 18.60M 0.0 12.8 53.3 33.9 0.0 87.2 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-05,SPT-15, 23.00M
Grain size (mm)BH-05,SPT-17, 26.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-05,SPT-15, 23.00M 0.0 12.8 62.6 24.6 0.0 87.2 0.0
BH-05,SPT-17, 26.00M 0.0 8.5 51.8 39.7 0.0 91.5 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-05,SPT-19, 29.00M Grain Size(mm)


BH-05,UDS-01, 3.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-05,SPT-19, 29.00M 0.0 5.6 61.2 33.2 0.0 94.4 0.0
BH-05,UDS-01, 3.00M 4.8 77.6 17.6 0.0 0.0 17.6 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-05,UDS-02, 6.00M
Grain size (mm) BH-05,UDS-03, 9.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-05,UDS-02, 6.00M 10.6 81.2 8.2 0.0 0.0 8.2 0.0
BH-05,UDS-03, 9.00M 19.9 72.7 7.4 0.0 0.0 7.4 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-05,UDS-04, 12.00M Grain Size(mm)


BH-06,UDS-01, 3.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-05,UDS-04, 12.00M 16.8 68.6 14.6 0.0 0.0 14.6 0.0
BH-06,UDS-01, 3.00M 7.0 78.0 15.0 0.0 0.0 15.0 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-06,UDS-02, 6.00M
Grain size (mm) BH-06,UDS-03, 9.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-06,UDS-02, 6.00M 16.7 77.5 5.8 0.0 0.0 5.8 0.0
BH-06,UDS-03, 9.00M 19.9 73.7 6.4 0.0 0.0 6.4 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-06,UDS-04, 12.00M Grain Size(mm)


BH-06,SPT-09, 14.00M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-06,UDS-04, 12.00M 20.0 74.4 5.6 0.0 0.0 5.6 0.0
BH-06,SPT-09, 14.00M 15.5 67.5 17.0 0.0 0.0 17.0 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-06,SPT-11, 17.00M
Grain size (mm)BH-06,SPT-14, 21.50M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-06,SPT-11, 17.00M 0.0 14.1 54.8 31.1 0.0 85.9 0.0
BH-06,SPT-14, 21.50M 0.0 9.5 49.8 40.7 0.0 90.5 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

BH-06,SPT-16, 24.50M Grain Size(mm)


BH-06,SPT-18, 27.50M

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-06,SPT-16, 24.50M 0.0 11.2 50.9 37.9 0.0 88.8 0.0
BH-06,SPT-18, 27.50M 0.0 10.0 57.3 32.7 0.0 90.0 0.0

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75
0.001 0.01 0.1 1 10 100

BH-06,SPT-20, 30.00M #N/A


Grain size (mm)

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)
BH-06,SPT-20, 30.00M 0.0 12.1 42.2 45.7 0.0 87.9 0.0

100

80
Percentage finer

60

40

20

0
0.002

0.075

0.425

4.75

0.001 0.01 0.1 1 10 100

#N/A Grain Size(mm) #N/A

0.002- 0.075- 0.425-


Grain size (mm) <0.002 2.0-4.75 >4.75
0.075 0.425 2.00 Weighted
Total
Fine Coarse mean dia
Clay Silt Medium sand Gravel
Sample No. sand sand (mm)
(%) (%) sand (%) (%)
(%) (%)

Project:- Geotech Inv. Work for C/O ROB in replacement of existing level Job No.
crossings in Bihar. 3363-09

S-ar putea să vă placă și