1. UNITS OF MEASUREMENTS

UNIT UNIT
SL.N ITEMS FOR FOR COMPLETED
O LABOU ITEM
R (MATERIAL+LABOU
WORK R)
01 Excavation cum / cft cum / cft
02 Back filling / soling cum / cft cum / cft
03 Footing No. cum / cft
(Concreting)
04 P.C.C sqm / sft cum / cft
05 Column / Beam / rm / rft cum / cft
Lintel Concreting
06 Slab concreting sqm / sft cum / cft
07 Pardi / Chajja / Loft sqm / sft cum / cft
Concreting
08 Staircase No. (per cum / cft
Concreting step)
09 Brick masonry sqm / sft sqm / sft
10cm to 15cm thick
10 Brick masonry sqm / sft cum / cft
23cm thick
11 Brick masonry cum / cft cum / cft
35cm thick
12 U.C.R. masonry cum / cft cum / cft
13 Plastering / sqm / sft sqm / sft
Pointing
14 Flooring / Tiling sqm / sft sqm / sft
15 Skirting / Steps rm / rft rm / rft
16 Sill Patti rm / rft rm / rft
17 Kitchen otta No. or rm / rm / rft
rft
18 Painting sqm / sft sqm / sft
19 Doors / Windows No. or sqm / sqm / sft
sft
20 Plumbing pipes rm / rft rm / rft
21 Plumbing fitting / No. No.
sanitary ware
22 Water tanks ltr. ltr.
23 Septic tanks ltr. No. of users

1
ENGINEERING INTEGRATED TRAINING INSTITUTE- NELLORE

24 Road work sqm / sft sqm / sft


(asphalting)
25 Electrical cabling / rm / rft rm / rft
Wiring
26 Electrical points No. No.
27 Water-proofing to sqm / sft sqm / sft
terrace
28 Water-proofing of No. sqm / sft
W.C
29 Gardening (lawn) sqm / sft sqm / sft
30 Gardening (trees / No. No.
bushes)

2. CONVERSION TABLE

SR.NO UNIT EQUIVALENT UNITS


01 1 meter 100 centimeter

02 1 meter 3.28 feet


04 1 centimeter 0.393 inch
05 1 foot 0.305 meter
07 1 inch 2.54 centimeter/ 25.4 mm
08 1 tone 1000 kg
09 1 kg 1000 grams
10 1 kg 0.001 tone
11 1 gram 0.001 kg
13 1 sq meter 10.76 sq feet
14 1 brass 100 sq feet
15 1 brass 9.29 sq meter
16 1 cu meter 35.28 cu feet
17 1 cu meter 1000 liters

18 1 cu feet 28.315 liters


19 1 brass 100 cu feet
20 1 cu feet 0.0283 cu meter
21 1 liter 0.001 cu meter
22 1 liter 0.0353 cu feet
23 1 cu feet 0.01 brass
24 1 cu meter 0.35 brass

3. WEIGHTS OF BUILDING MATERIAL

SR.NO MATERIAL THEORETICAL WEIGHT IN

2
ENGINEERING INTEGRATED TRAINING INSTITUTE- NELLORE

Kg/cum
01 Cement 1440
02 Steel 7850
03 Dry sand 1600
04 River sand 1840
05 Stone 2850 to 2960
06 Water 1000
07 P.C.C 2240
08 R.C.C. (2% steel) 2420
09 Bricks 1600 to 1920
10 Brick masonry 1920
11 Soil 1760
12 Cement concrete block (solid) 1800
13 Cement mortar 2080
14 Lime mortar 1760
15 Lime 640
16 Glass 2530
17 Teak wood 670 to 830
18 Sal wood 990
19 Marble stone 2620
20 Granite stone 2460 to2800
21 Cuddappa 2720
22 Bitumen 1040

2. BRICK WORK
Considering 1:4 ratios for cement mortar in 150mm thick brickwork.

Calculation of quantity for 5 cu.m volume in brickwork as follows:

Size of brick = 19 cm x9 cm x9 cm.

Vol. of brick = (0.19 x 0.09 x 0.09) cu.m

= 0.00154cu.m.

Vol. of brick with cement mortar

= (0.2 x 0.1 x 0.1) cu.m

= 0.002 cu.m.

No. of bricks in 5 cu.m

= 5 (vol. of one brick with mortar).

3
ENGINEERING INTEGRATED TRAINING INSTITUTE- NELLORE

= 5 0.002

= 2500

Vol. of 2500 bricks = 2500 x vol. of one brick without mortar.

=2500 x 0.00154

= 3.85cu.m.

Vol. of mortar = 5 3.85 = 1.15 cu.m.

Add 15% (Bulkage + wastage)

Vol. of wet mortar = 1.15 + {1.15 x (15 100)}

= 1.323cu.m

Vol. of dry mortar = 1.323 + 33% in wet mortars for interlocking =1.759cu.m

Vol. of cement = 1.759 (1+4) =0.352cu.m

No. of cement bags = 0.352 0.035

=10.057bags.

10.00bags

Vol. of sand = 0.352 x 4


= 1.408cu.m.

3. INTERNAL PLASTER

12mm thick internal plaster

Considering 100sqm area

Proportion of C:M = 1:4

Summation of proportion =5

Quantity of one cement bag = 0.035cum

Quantity of wet mortar = 0.012 x 100 = 1.2cum

4
ENGINEERING INTEGRATED TRAINING INSTITUTE- NELLORE

Adding 15% wastage = 1.2 + (1.2 x 0.15) =1.38cum

Volume of dry mix = 1.38 + (1.38 x 1/3) =1.84cum

Volume of cement = (dry volume / 5) x 1

= (1.84 /5) x 1

= 0.368cum

= 0.368 / 0.035

=10.5 bags

Volume of sand = (dry volume / 5) x 4

= (1.84 /5) x 4

= 1.472 cum

MATERIALS QUANTITY RATE (RS) AMOUNT (RS)

Sand 1.472cum 1300 /cum 1913


Cement 10.5bags 250 / bag 2625
Scaffolding L.S 550 550
LABOURS QUANTITY RATE (RS) AMOUNT (RS)

Mason 8nos 200 1600


Helper 12nos 90 1080
Total 7768

Tools & Plants 1% 0f total 77.68

Total 7845.68

Water charges 2% Of total 156.91

Total 8002.59

Supervisor, Overhead & 25% Of the total 2000.65


Profit

5
ENGINEERING INTEGRATED TRAINING INSTITUTE- NELLORE

Total 10003.23

RATE FOR 100m = 10003.23Rs.


RATE FOR 1m = 100.03Rs.

4. EXTERNAL PLASTER
20mm thick external plaster

Considering 100sqm area.


Proportion for mix C:M = 1:4.
Summation of proportion = 5.
Quantity of one cement bag = 0.035cum.
Quantity of wet mortar = 0.02 x 100 = 2cum.
Adding 20% wastage = 2 +( 2 x 0.2 ) = 2.4cum.
Volume of dry mix = 2.4 + (2.4 x 1/3) = 3.2cum.
Volume of cement = (dry volume / 5) x 1
= (3.2 /5) x 1
= 0.64cum
= 0.64 / 0.035
= 18.3 bags
= 19 bags
Volume of sand = (dry mix / 5) x 4
= (3.2 /5) x 4
= 2.56cum.