ARJUN SKYLIFE
Manpower Report_March_2017
Sr. No Date Carpenter Fitter Labour Total
1 3/1/2017 73 30 20 123
2 3/2/2017 65 30 20 115
3 3/3/2017 60 28 2 90
4 3/4/2017 47 28 20 95
5 3/5/2017 35 28 20 83
6 3/6/2017 58 40 20 118
7 3/7/2017 65 50 0 115
8 3/8/2017 55 30 20 105
9 3/9/2017 65 50 20 135
10 3/10/2017 65 10 20 95
11 3/11/2017 20 10 0 30
12 3/12/2017 0 0 0 0
13 3/13/2017 0 0 0 0
14 3/14/2017 0 0 0 0
15 3/15/2017 39 12 0 51
16 3/16/2017 47 20 0 67
17 3/17/2017 0
18 3/18/2017 0
19 3/19/2017 0
20 3/20/2017 0
21 3/21/2017 0
22 3/22/2017 0
23 3/23/2017 0
24 3/24/2017 0
25 3/25/2017 0
26 3/26/2017 0
27 3/27/2017 0
28 3/28/2017 0
29 3/29/2017 0
30 3/30/2017 0
31 3/31/2017 0
ARJUN SKYLIFE
Quantity Report_March_2017
Sr. No Date Actual Qty
1 3/1/2017 0.00
2 3/2/2017 56.50
3 3/3/2017 0.00
4 3/4/2017 7.25
5 3/5/2017 85.75
6 3/6/2017 13.15
7 3/7/2017 0.00
8 3/8/2017 110.75
9 3/9/2017 0.00
10 3/10/2017 172.00
11 3/11/2017 0.00
12 3/12/2017 0.00
13 3/13/2017 0.00
14 3/14/2017 0.00
15 3/15/2017 0.00
16 3/16/2017 0.00
17 3/17/2017
18 3/18/2017
19 3/19/2017
20 3/20/2017
21 3/21/2017
22 3/22/2017
23 3/23/2017
24 3/24/2017
25 3/25/2017
26 3/26/2017
27 3/27/2017
28 3/28/2017
29 3/29/2017
30 3/30/2017
31 3/31/2017
445.40
CONCRETE CONSUMPTION
3160
ARJUN SKYLIFE
ARJUN Group , SAHAJANAND Group
Ravidhya Developers
Concrete
1
Total Qty.
Material Consumption
1 0 Bag 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 47
2 Fitter nos 20
3 Labour nos 0
Total Qty 67
Quantity
Executed
0.00
Date : 16.03.17
Actual Qty.(
Wastage (CMT)
CMT )
0.00
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag M40 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 39
2 Fitter nos 12
3 Labour nos 0
Total Qty 51
Quantity
Executed
0.00
Date : 15.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag M40 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 0
2 Fitter nos 0
3 Labour nos 0
Total Qty 0
Quantity
Executed
0.00
Date : 14.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag M40 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 0
2 Fitter nos 0
3 Labour nos 0
Total Qty 0
Quantity
Executed
0.00
Date : 13.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag M40 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 0
2 Fitter nos 0
3 Labour nos 0
Total Qty 0
Quantity
Executed
0.00
Date : 12.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag M40 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 20
2 Fitter nos 10
3 Labour nos 0
Total Qty 30
Quantity
Executed
0.00
Date : 11.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1 C Block Basement Slab Cum M30 1
2
3
2
1
1
1
2
2
1
1
2
2
1
1
1
2
1
2
1
1
1
1
1
1
1
Horizontal Beam 3
2
1
1
1
Vertical Beam 6
1
9
4
Staircase 1
8
3
4
2
2
1
Total Qty.
Material Consumption
1 C Block Basement Slab Bag M30 1200
2 Slurry Bag 6
Total Bags 1206
Manpower Report
1 Carpenter nos 65
2 Fitter nos 10
3 Labour nos 20
Total Qty 95
Quantity
Executed
173.12
Date : 10.03.17
Actual Qty.(
Wastage (CMT)
CMT )
172.00
172.00
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag 0
2 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 65
2 Fitter nos 50
3 Labour nos 20
Total Qty 135
Quantity
Executed
0.00
Date : 09.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1 B Block 4th Fl. (Flat 402&403) Cum M30
Horizontal Beam
Vertical Beam
Chajja
Total Qty.
Material Consumption
1 B Block 4th Fl. (Flat 402&403) Bag M30
2 C Block Staircase Bag M30
3 Slurry Bag
Total Bags
Manpower Report
1 Carpenter nos
2 Fitter nos
3 Labour nos
Total Qty
Quantity
Nos
Executed
Column/Beam No. L B H
2 S1 6.19 10.42 0.225
2 S2 6.927 12.554 0.225
2 S4 1.845 1.934 0.125
2 S3 4.17 5.282 0.2
2 14.32 0.2 0.65
2 7.19 0.2 0.65
1 7.272 0.2 0.65
3 25.71 0.2 0.65
2 3.784 0.6 0.125
2 2.84 0.6 0.125
2 3.479 0.6 0.125
2 1.352 0.6 0.125
1 4.068 0.6 0.125
2 3.754 0.6 0.125
2 2.23 0.6 0.125
2 1.115 0.3 0.125
1 0.867 0.305 0.125
5 Steps 2.01 0.305 0.16
1 Flight 3.444 2.01 0.2
4 0.8 0.8 0.72
2 1.79 0.2 0.72
2 1.05 0.2 0.93
2 2.1 0.2 0.72
1 1.85 0.2 0.72
4 0.55 0.2 0.72
1 Flight 5.551 2.01 0.2
1 Steps 2.01 0.305 0.16
1 Mid Landing 4.17 1.81 0.125
2 MB 4.17 0.3 0.6
728
43
8
779
55
30
20
105
Date : 08.03.17
Actual Qty.
Wastage (CMT)
( CMT )
Total Qty.
29.02
39.13
0.89
8.81
3.72
1.87
0.95
10.03
0.57
0.43
0.52
0.20
0.31
0.56
0.33
0.09
0.03
0.49
1.38
1.84
0.52
0.39
0.60
0.27
0.32 104.50
2.23
0.10
0.94
1.50 6.25
108.05 110.75
Remark
Concrete
1
Total Qty.
Material Consumption
1 0 Bag M40 0
3 Slurry Bag 0
Total Bags 0
Manpower Report
1 Carpenter nos 65
2 Fitter nos 50
3 Labour nos 0
Total Qty 115
Quantity
Executed
0.00
Date : 07.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
0.00
Remark
Concrete
1 B Block Col. (4th 5th Fl.) Cum M40 7
3
1
Total Qty.
Material Consumption
1 B Block Col. (4th 5th Fl.) Bag M40 56
2 Cop Col. (Gf. To 1st Fl.) Bag M40 18
3 Cop Col. (Gf. To 1st Fl.) Bag M30 24
4 Slurry Bag 10
Total Bags 108
Manpower Report
1 Carpenter nos 58
2 Fitter nos 40
3 Labour nos 20
Total Qty 118
Quantity
Executed
12.47
Date : 06.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
7.25
2.40
3.50
13.15
Remark
Concrete
1 A Block 5th Fl. (Flat 502&503)
Slab Cum M30 2
2
2
2
2
2
2
1
Vertical Beam Cum M30 8
3
1
Horizontal Beam Cum M30 6
2
1
4
1
1
Chajja Cum M30 1
1
1
1
2
2
1
2
1
1
2
1
2
1
Staircase Cum M30 1
5
Total Qty.
Material Consumption
1 A Block 5th Fl. (Flat 502&503) Bag M30 547
2 A Block Col. (5th to 6th Col.) Bag M40 56
3 Slurry Bag 4
Total Bags 607
Manpower Report
1 Carpenter nos 35
2 Fitter nos 28
3 Labour nos 20
Total Qty 83
Quantity
Executed
84.41
Date : 05.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
78.50
7.25
85.75
Remark
Concrete
1 A Block Col. (5th to 6th Fl.) Cum M40 6
2
1
Total Qty.
Material Consumption
1 A Block Col. (5th to 6th Fl.) Bag M40 29
2 B Block Col. (4th to 5th Fl.) Bag M40 27
3 Slurry Bag 6
Total Bags 62
Manpower Report
1 Carpenter nos 47
2 Fitter nos 28
3 Labour nos 20
Total Qty 95
Quantity
Executed
7.35
Date : 04.03.17
Actual
Qty.
Wastage (CMT)
( CMT
)
3.75
3.50
7.25
Remark
Concrete
1
Total Qty.
Material Consumption
1 Bag
2 Slurry Bag
Total Bags 0
Manpower Report
1 Carpenter nos 60
2 Fitter nos 28
3 Labour nos 2
Total Qty 90
Quantity
Executed
Column/Beam No. L B H Total Qty.
0.00
Date : 03.03.17
Actual Qty.(
Wastage (CMT)
CMT )
Remark
Total Qty.
Material Consumption
1 Podium Slab Front of A Block Bag M30 394
2 Slurry Bag 4
Total Bags 398
Manpower Report
1 Carpenter nos 65
2 Fitter nos 30
3 Labour nos 20
Total Qty 115
Quantity
Executed
Column/Beam No. L B H Total Qty.
S1 3.6 1.229 0.15 0.66
S3 5.914 1.229 0.175 1.27
S3 3.6 1.914 0.175 2.41
S3 5.914 1.914 0.175 3.96
S1 3.6 1.585 0.15 0.86
S3 5.914 1.585 0.175 1.64
S1 3.6 1.884 0.15 2.03
S1 5.914 1.884 0.15 3.34
S1 3.6 1.59 0.15 0.86
S1 5.914 1.59 0.15 1.41
S1 3.6 1.585 0.15 1.71
S1 5.914 1.585 0.15 2.81
B5-B9,B5-B22 11.313 0.3 0.45 6.11
B10,B22 5.914 0.3 0.45 4.79
B5,B23 3.6 0.3 0.45 2.92
18.168 0.6 0.45 19.62
56.41
Date : 02.03.17
Actual Qty.(
Wastage (CMT)
CMT )
56.50
56.50
Remark
Concrete Quantity In Cum
Plant Concrete = 56.5 Cum + 1 Slurry
ARJUN SKYLIFE
ARJUN Group , SAHAJANAND Group
Ravidhya Developers
Sr.No. Description Unit Grade Nos
Concrete
1
Total Qty.
Material Consumption
1 Bag M40
2 Slurry Bag
Total Bags 0
Manpower Report
1 Carpenter nos 73
2 Fitter nos 30
3 Labour nos 20
Total Qty 123
Quantity
Executed
Column/Beam No. L B H Total Qty.
0.00
Date : 01.03.17
Actual Qty.(
Wastage (CMT)
CMT )
Remark
Concrete Quantity In Cum
Plant Concrete = Cum + Slurry