Documente Academic
Documente Profesional
Documente Cultură
Malda Town
Under RE Kolkata
(From 23-01-2017 to 24-03-2017)
Pegging Plan
Following details are given in Pegging Plan:
Chainage
Location no.
Type of Mast
Span
Permanent Structure Details like level crossing, FOB, Culvert etc.
Pegging plan is useful in quantity estimation during tender.
LOP
Prepared and supplied by the OHE contractor.
Marking of Mast, Foundation Type on Rail.
Power line crossing
Conductor Details like length of contact and catenary wire.
Anchor Details
Insulator details, bracket details
Jumper details
Portal component details
All the details of pegging plan like Location no., Chainage, Span, Permanent
Structure Details etc. are also provided in LOP.
CSD
CSD is prepared for one km. on one sheet. In yard section CSD is prepared for each
location separately.
Following details are given in CSD:
Location No.
Chainage
Span
Implantation
Mast- Type, Length
Reverse Deflection (mm)
Soil- Type, Pressure (Kg/M2)
Foundation: Code, Type
Step Distance: Distance between top of foundation and rail level.
Mast embedded length: Distance between top of foundation and bottom of mast.
Cess level: Distance between ground level and rail level.
Extra depth/ super block
Radius of curvature
SED
Following details are provided in SED:
Location No.
Chainage
Span
Mast- Type, Length, length above rail level
Implantation
Catenary, contact wire height
Encumbrance
Stagger
A, B, C, D parameters
Regulating equipment: Type, Make/year
All other details of cantilever assembly
RDSO Drawing
Mast Employment Schedule
Volume Chart
Dropper Schedule
1st week
Asansol TSS
we have seen layout of substation, buried rail, substation equipment ,single feeder.
Actually there were two transformer one is standby and one is in service but due to
constraint the substation is served with one transformer.
Lightening arrester and its counter( how many time it has arrested lightening)
Noted the resistance of earth pit.
Sf6 gas circuit breaker(crompton greeves make)
Isolators
Breather (silica gel in orange colour)
Vacuum circuit breaker
Baffle wall
Dedicated oil spillage collection pit ( in which spillage oil is collected)
We have been to Material Store seen there contact wire bundles, catenary wire
bundles, caution board
2nd week
Visited to tildanga for foundation casting at locations 261/7 (BG-10) , 261/8 (BG-10).
Locations of mast are marked by sub contractor & respective implantation is given in
Line chart (mast implantation at this location was 3m).
Casting details are given in volume chart given by contractor. Excavation is dne by
hand.
Visited to kotalpakur to witness mast erection but since no mast erection was done
we have seen OHE inspection Car :
Step distance (distance between existing rail level to the top of foundation) shouldn't be
more than 50cm for regulated OHE and 40 cm for unregulated OHE.
Visit for Identification of feasible locations for insulated overlaps and switches(for
elementary sections) at following locations
New Farakka , Tildanga, Bonidanga, Jamirghata, Gour Malda, Khaltipur,
Chamagram.
4th Week
Conducted survey at Takia nala Bridge, Pagla Bridge and Farakka canal bridge for
mast erection feasibility.
Takia Nala
(33m length, height 6.1m) , location 270/0
250mm clearance for overbridge.
No mast requirement is there inside bridge.
Normal catenary height 7.20m
Maximum gradient allowed 3mm/m
Min. Encumbrance is 40cm, 25cm(in case of hard dropper) as in this case
6.10m(overbridge height)- 5.60(min. contact wire height)=50cm(which is sufficient
enough for encumbrance and clearance from bridge structure).
Pagla Bridge
(length 4*45.76m, height 6m), location 267/7 268/0.
pillar to pillar distance is 48.5m
Height up to angle is 4.6m
Height rail level to pillar is 1.65m
distance from rail level to pillar end is 5.10m
distance from rail level to bridge 2.82m
Cube testing: cube is replica of foundation material. Hydraulic pressure is used to test
the cube. As testing unit was out of order, separate third party test is done at civil
department of polytechnic college. One sample of size 50cucm (one set) for one
kilometer is the bench mark. 225kgf pressure for cube testing.
Pipes of different diameter are available there from which bracket arm, register arm,
steady arm are cut to size and are used in fabrication of cantilever assembly.
Droppers schedule varies with span and are placed separately as a set.
Different equipments available are drilling machine(for drilling of pipe), dropper ,runners,
fabrication machine, dark clamp, bonds , u bolt, droppers(5 mm diameter size),
anticreep, sectioners, bolts of different sizes, a,b,c,d clamps.
Catenary and contact wire bundles are provided by Railways and remaining all things
are procured by the contractor.
5th Week
6th Week
7th Week
At ROB we have seen clearances of catenary from bridge under structure, height of
contact wire with respect to rail level, height of catenary wire with respect to rail level,
metering of near by earth pits.
We have seen inspection of tower wagon shed, various stations in the inspection line.
At TSS Tapsi we have seen inspection of conditions of TSS and installation of various
equipments as per layout diagram, meggering of earth pits, caution boards.
8th Week
Retaining wall RCC Casting work control building base at SSP/GZM
9th Week