( in P'000 )
9. BUDGET BY LOCATION
Total ( P )
Location Original Revised 2013 2014 2015 2016 2017 Bal.
Region I to n CAR 50,000.00 50,000.00
Province I to n Abra
District I to n Abra - DEO
Municipality I to n Langiden
TOTAL 50,000.00 50,000.00
MURIEL DIVINA GRACIA B. VALERA EDWIN T. BRINGAS NERIO P. PLURAD LORETO B. DACOROON
Administrative Assisstant III Chief, Maintenance Section Accountant III Assistant District Engineer
(Caretaker)
SPHALT OVERLAY)
RB Form No.
Project Details:
Requirements:
o Letter of Request
o Program of Work and Detailed Estimates with Unit Price Analysis,
o Plans (Vicinity Map, Straight Line Diagram indicating road condition and surface type with station limits supported by lates
ROCOND, Cross Sections
o Size 5R colored pictures of defects (if any) with inset road name, station limits and date. Submit at least ten(10) pictures,
o Certification of No Obstruction (if applicable)
o Bar Chart showing implementation schedule
o Canvass of materials that is not included in the CMPD
I hereby certify thet the above mentioned request pertains to a priority project of the District/Regional Office and it will not duplicate an
other request for the same road section and scope of work from another funding source. I further certify that the information contain he
is true and correct.
LORETO B. DACOROON
Assistant District Engineer
Caretaker Endorsed By:
2nd floor Ave Maria Bldg., 1517 Quezon Avenue cor, Examiner St. Quezon City, Manila
Tel No. (02) 376-6269; Fax (02) 376-9028
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Abra District Engineering Office
Bangued, Abra
PROGRAM OF WORK
EQUIPMENT
ITEM DESCRIPTION OF WORKS TO BE DONE %
DESCRIPTION REQUIRED
Total 100.00%
Total : P 49,499,574.17
BREAKDOWN OF EXPENDITURES
1. Labor 242,567.46 A. Total Direct Cost 39,302,311.87
2. Materials 37,348,430.80 B. OCM and Profit 7,840,156.42
3. Rental of Equipment 1,711,313.61 C. Value Added Tax 2,357,105.88
4. (OCM, Profit) 7,840,156.42 D. EAO, 1.0% 500,000.00
5. Value Added Tax (VAT) 2,357,105.88 E. Construction Contigency 425.83
6. Eng'g & Administrative Overhead (EAO), 1.0% 500,000.00 F. RROW Acquisition
7. Construction Contigency 425.83 G. Total Estimated Cost 50,000,000.00
8. RROW Acquisition
9. Total Estimated Cost 50,000,000.00
SUMMARY OF QUANTITIES
ITEM NO. UNIT QUANTITY UNIT COST
B.5 Project Billboards each 2.00 P 4,996.00
B.7 Occupational Safety & Health Program month 1.33 P 23,231.00
B.9 Mobilization/Demobilization l.s. 1.00 P 85,730.40
302 (2) Emulsified Asphalt sq.m. 47,190.21 P 45.53
310(1)c Bituminous Concrete Surface Wearing Course, Hot-Laid sq.m. 47,190.21 P 963.24
612(1) Reflectorized Thermoplastic Pavement Markings White sq.m. 1,934.03 P 896.00
612(2) Reflectorized Thermoplastic Pavement Markings Yellow sq.m. 36.00 P 1,000.00
#REF!
#REF!
#REF!
qty. of PSH
#REF!
MARK-UP VAT COST/ITEM DC
P 704.90 P 475.81 P 9,991.99
P 2,179.69 P 1,471.29 P 30,897.14 23,230.93 5 27,246.16
P - P 4,082.40 P 85,730.40 85,730.40 6 81,648.00
P 341,057.40 P 102,317.22 P 2,148,661.66 45.53 6 1,705,287.04
P 7,215,178.84 P 2,164,553.65 P 45,455,626.69 963.24 6 36,075,894.20
P 274,968.80 P 82,490.64 P 1,732,303.47 895.69 7 1,374,844.03
P 5,716.23 P 1,714.87 P 36,012.25 6 28,581.15
P - 7 -
P -
P -
P -
P -
P -
P 7,839,805.86 P 2,357,105.88 P 49,499,223.61 -
P (350.56) P 49,499,223.61
7,840,156.42 49,499,574.17
(350.56)
ADJ.COST/ITEM % DURATION
P 9,992.00
P 30,897.23
P 85,730.40
P 2,148,570.26
P 45,455,497.88
P 1,732,886.40
P 36,000.00
P -
P - 0.00 0
P -
P -
19 0.00
P 49,499,574.17 0 0.00 #REF! #REF!
0
0 #REF!
0 0
14,176,563.78 0 34
252 0 63.000
(35,323,010.39) 49,499,223.61 8.4 64 0
124
8.4
say 8 months
63
188
DC
27,246.16
81,648.00
1,705,287.04
36,075,894.20
1,374,844.03
28,581.15
-
-
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Days Daily Rate Amount
Person
1. Labor :
Construction Foreman 1 1 575.60 575.60
Skilled Laborers 1 1 416.48 416.48
Laborers 1 1 321.20 321.20
No. of
Designation No. of Days Daily Rate Amount
Person
1. Labor :
Part time Practitioner 1 10 465.44 4,654.40
First Aider 1 40 404.80 16,192.00
No. of
Designation No. of Hours Hourly Rate Amount
Person
A. Labor :
man-days = 58.000
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor :
Construction Foreman 1 275.00 71.95 19,786.25
Skilled Laborer 4 275.00 52.06 57,266.00
Laborer 8 275.00 40.15 88,330.00
man-days = 446.875
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor :
Construction Foreman 1 77.00 71.95 5,540.15
Skilled Laborer 2 77.00 52.06 8,017.24
Laborer 6 77.00 40.15 18,549.30
man-days = 86.625
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor :
Construction Foreman 1 1.44 71.95 103.61
Skilled Laborer 2 1.44 52.06 149.93
Laborer 6 1.44 40.15 346.90
man-days = 1.620
Volume = 5,804.40 MT
5,804.40 MT
Utilizing 6 Dumptruck
= 6.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 6.00 DT x 24.60 MT/DT = 147.60 MT
5,804.40
No of Days Required = = 66.38 days
147.60 x 0.59
Equipment Cost
Dumptrucks = 6.00 DT 10,816.00 /day x 66.38 days = P 4,307,796.48
P 4,307,796.48
ITEM 612
TABULATION AND COMPUTATION OF QUANTITIES FOR ITEM 612
LENGTH Edge line White Center line White Center line Yellow
STATION TO STATION DESCRIPTION Length x .10m x(Length/9x3)
(m) 2 x .15m (Length x .15m
(sq.m) (sq.m) (sq.m)
K0 ### + 000 - K0 410 + 000 1000.0 200.00 50.00
K0 ### + 000 - K0 411 + 000 1000.0 200.00 50.00 13.5
K0 ### + 000 - K0 412 + 000 1000.0 200.00 50.00 22.5
K0 ### + 000 - K0 413 + 000 1000.0 200.00 50.00
K0 ### + 000 - K0 414 + 000 1000.0 200.00 50.00
K0 ### + 000 - K0 415 + 000 1000.0 200.00 50.00
K0 ### + 000 - K0 416 + 000 1000.0 200.00 50.00
K0 ### + 000 - K0 416 + 740 740.0 147.22 36.81
-
TOTAL 1,547.22 386.81 36.00
ITEM 612(2a) = ### Sq.m.
ITEM 612(2b) = 36.00 Sq.m.
Standard Form Number: SF-INFR-01
Revised on: July 28, 2004
APPROVED BUDGET FOR THE CONTRACT
REPAIR/REHABILITATION/IMPROVEMENT OF ABRA-ILOCOS NORTE ROAD(ASPHALT OVERLAY)
0
#REF!
K0390+169-K0390+662; K0392+053.40-K0393+000; K0408+114-K0408+190 (ABRA ILOCOS SUR ROAD)
Project Name and Location
Stations:
Length: 1,818 METERS Contract Duration :
MARK-UPS
TOTAL MARK-UP TOTAL
ESTIMATED IN PERCENT
DESCRIPTION QUANTITY UNIT INDIRECT
ITEM DIRECT COST VAT[3] COST
NO. OCM[1] PROFIT MOB.\ DEMOB.[2] % VALUE
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
K0409+000- K0416+740
B.7 Occupational Safety & Health Program 1.33 month 27,246.16 8.00% 8.00% #REF! #REF! #REF!
302 (2) Emulsified Asphalt 47190.21 sq.m. 1,705,287.04 9.00% 8.00% 17.00% #REF! #REF! #REF!
310(1)c Bituminous Concrete Surface Wearing Course, Hot-Laid 47190.21 sq.m. 36,075,894.20 9.00% 8.00% 17.00% #REF! #REF! #REF!
612(1) Reflectorized Thermoplastic Pavement Markings White 1934.03 sq.m. 1,374,844.03 9.00% 8.00% 17.00% #REF! #REF! #REF!
B.5 Project Billboards 2.00 each 8,811.28 8.00% 8.00% #REF! #REF! #REF!
SUB TOTAL 1=
K0392+053.4-K0393+000
A-1 PROVISION FOR SAFETY AND HEALTH 1.00 lot 10,512.84 8.00% 8.00% P 841.03 P 567.69 P 1,408.72
302 BITUMINOUS TACK COAT (Emulsified Asphalt) 7.00 m.tons 359,705.62 9.00% 8.00% 17.00% P 61,149.96 P 21,042.78 P 82,192.74
310 BITUMINOUS CONCRETE SURFACE COURSE 10483.20 sq.m. 7,899,980.56 9.00% 8.00% 17.00% P 1,342,996.70 P 462,148.86 P 1,805,145.56
603(3)a METAL GUARDRAILS(Metal Beam)including concrete post) 92.00 l.m. 271,948.22 9.00% 8.00% 17.00% P 46,231.20 P 15,908.97 P 62,140.17
603(3)b METAL BEAM END PIECE 2.00 ea. 3,138.84 9.00% 8.00% 17.00% P 533.60 P 183.62 P 717.22
612(1) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (White) 288.00 sq.m. 189,428.17 9.00% 8.00% 17.00% P 32,202.79 P 11,081.55 P 43,284.34
612(2) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (Yellow) 153.00 sq.m. 111,963.67 9.00% 8.00% 17.00% P 19,033.82 P 6,549.87 P 25,583.69
SPL. 1 PROJECT BILLBOARDS 2.00 each 8,811.28 8.00% 8.00% P 704.90 P 475.81 P 1,180.71
SUB TOTAL 2=
K0408+114-K0408+190
A-1 PROVISION FOR SAFETY AND HEALTH 1.00 lot 646.59 8.00% 8.00% P 51.73 P 34.92 P 86.65
302 BITUMINOUS TACK COAT (Emulsified Asphalt) 0.54 m.tons 28,032.88 9.00% 8.00% 17.00% P 4,765.59 P 1,639.92 P 6,405.51
310 BITUMINOUS CONCRETE SURFACE COURSE 759.45 sq.m. 577,553.83 9.00% 8.00% 17.00% P 98,184.15 P 33,786.90 P 131,971.05
612(1) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (White) 31.13 sq.m. 20,022.46 9.00% 8.00% 17.00% P 3,403.82 P 1,171.31 P 4,575.13
SPL. 1 PROJECT BILLBOARDS 1.00 each 4,405.64 8.00% 8.00% P 352.45 P 237.90 P 590.35
SUB TOTAL 3=
GRAND TOTAL=
SIXTEEN MILLION SIX HUNDRED EIGHTY EIGHT THOUSAND NINE HUNDRED SIX PESOS & 13 CENTS
PREPARED/SUBMITTED BY: APPROVED:
58 #REF!
(13) (14)
P 30,897.23 P 23,231.00
P 2,148,570.26 P 45.53
P 45,455,497.88 P 963.24
P 1,732,886.40 P 896.00 #REF! #REF!
P 9,992.00 P 4,996.00
P 49,377,843.77
#DIV/0! -
P 11,922.00 P 11,922.00 #REF!
P 441,896.00 P 63,128.00
P 9,705,136.90 P 925.78
P 334,088.80 P 3,631.40
P 3,856.06 P 1,928.03
P 232,704.00 P 808.00
P 137,547.00 P 899.00
P 9,992.04 P 4,996.02
P 10,877,142.80
P 733.00 P 733.00
P 34,438.50 P 63,775.00
P 709,523.76 P 934.26
P 24,588.75 P 790.00
P 4,996.03 P 4,996.03
P 774,280.04
P61,029,266.60
HUNDRED SIX PESOS & 13 CENTS
LORETO B. DACOROON
CARETAKER
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Cordillera Administrative Region
Office of the District Engineer
Bangued, Abra
SUMMARY
PROGRAM OF WORK
DIRECT COST
1. Labor P 71,900.61
2. Equipment P 69,669.23
3. Materials P 925,244.01
4. Project Supervision
Total Direct Cost P 1,066,813.85
INDIRECT COST
1. Mark-up(OCM, Profit) P 112,791.69
2. VAT P 69,930.85
3. Quality Control
4. Eng'g & Administrative Overhead #VALUE!
5. Construction Contigency P 12,073.30
6. Central Office Retention
7. Road Right-of-Way
8. Soil Exploration
9. Survey and Plan Preparation
10. Aggregate Tax P 4,240.31
11. Publication Fee
339.23
UNIT COST DERIVATION OF BITUMINOUS CONCRETE SURFACE COURSE
Fine Aggregates
Volume = 5,804.40 cu.m.
5,804.40 cu.m.
Utilizing 6 Dumptruck
= 6.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 6.00 DT x 10.00 cu.m./DT = 60.00 cu.m.
5,804.40
No of Days Required = = 226.82 days
60.00 x 0.43
Equipment Cost
Payloader = 1.00 13,864.00 /day x 226.82 days = P 3,144,700.49
Dumptrucks = 6.00 DT 10,816.00 /day x 226.82 days = P 14,720,029.09
P 17,864,729.58
A. GRAVEL
Unit Cost of Hauling = 3,078.00 /cu.m.
Cost at Source = 400.00 /cu.m.
Unit Cost of Coarse Aggregates = 3,478.00 /cu.m.
SAY = 3,478.00 /cu.m.
B. SAND
Unit Cost of Hauling = 3,078.00 /cu.m.
Cost at Source = 350.00 /cu.m.
Unit Cost of Coarse Aggregates = 3,428.00 /cu.m.
SAY = 3,428.00 /cu.m.
Fine Aggregates
Volume = #REF! cu.m.
Considering 15% Swell Factor, Total Vol. Req'd.= #REF! cu.m.
Utilizing 6 Dumptruck
= 6.00 DT
= 6.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 6.00 DT x 10.00 cu.m./DT = 60.00 cu.m.
#REF!
No of Days Required = = #REF! days
60.00 x 5.95
Equipment Cost
Payloader = 1.00 13,864.00 /day x #REF! days = #REF!
Dumptrucks = 6.00 DT 10,816.00 /day x #REF! days = #REF!
#REF!
Boulders
Volume = #REF! cu.m.
Considering 5% Swell Factor, Total Vol. Req'd.= #REF! cu.m.
Mountainous Paved :
12.50 kms. x 60 min./hr.
Loaded Trip = = 37.50 mins.
20 kms./hr.
12.50 kms. x 60 min./hr.
Unloaded Trip = = 25.00 mins.
30 kms./hr.
80.70 mins.
mins.
Total Cycle Time
8 hrs. x 60 min./hr.
No. of Trip per Day = = 5.95 trip
80.70 mins.
Utilizing 6 Dumptruck
= 6.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 6.00 DT x 10.00 cu.m./DT = 60.00 cu.m.
#REF!
No of Days Required = = #REF! days
60.00 x 5.95
#REF! days
Equipment Cost
Payloader = 1.00 13,864.00 /day x #REF! days = #REF!
Dumptrucks = 6.00 DT 10,816.00 /day x #REF! days = #REF!
#REF!
A. BOULDERS
Unit Cost of Hauling = #REF! /cu.m.
Cost at Site = 500.00 /cu.m.
Unit Cost of Boulders (Class A) = #REF! /cu.m.
SAY = #REF! /cu.m.
Cement
Quantity Required = #VALUE! bags
#VALUE! bags
No of Days Required = =
480.00 mins./day CT x 225.00 #VALUE! days
x 1
186.00 mins./trip trip
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,512.00 /day x #VALUE! days = #VALUE!
Labor Cost
6 Laborers = 6.00 x 312.24 /day x #VALUE! days = #VALUE!
#VALUE!
A. CEMENT
Cost/bag at Source 230.00 /bag
#VALUE!
Unit Cost of Hauling = #VALUE! /bag
#VALUE!
Total Cost of Cement = #VALUE! /bag
SAY = #VALUE! /bag
UNIT COST DERIVATION OF REINFORCING STEEL BAR
#REF! kgs.
No of Days Required = = #REF! days
0.39 trip x 6,000.00 kgs.
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,512.00 /day x #REF! days = #REF!
Labor Cost
6 Laborers = 6.00 x 312.24 /day x #REF! days = #REF!
#REF!
Cycle Time
SOURCE : Bangued, Abra
Average Hauling Distance = 21 kms.
Loading Time = 15 min.
Unloading Time = 15 min.
Slack Time = 6 min.
Paved :
11.37 kms. x 60 min./hr.
Loaded Trip = = 34.11 mins.
20 kms./hr.
11.37 kms. x 60 min./hr.
Unloaded Trip = = 22.74 mins.
30 kms./hr.
Mountainous Unpaved :
kms. x 60 min./hr.
Loaded Trip = = 0.00 mins.
15 kms./hr.
- kms. x 60 min./hr.
Unloaded Trip = = 0.00 mins.
25 kms./hr.
92.85 mins.
Total Cycle Time
8 hrs. x 60 min./hr.
No. of Trip per Day = = 5.17 trip
92.85 mins.
40.00 ln.m.
No of Days Required = = 0.77 days
5.17 trip x 10.00 pcs.
say 0.77 days
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,512.00 /day x 0.77 days = P 7,324.24
1 Chain Block = 1.00 CB 500.00 /day x 0.77 days = P 385.00
Labor Cost
6 Laborers = 6.00 x 312.24 /day x 0.77 days = P 1,442.55
P 9,151.79
Fine Aggregates
Volume = #VALUE! cu.m.
Considering 15% Swell Factor, Total Vol. Req'd.= #VALUE! cu.m.
Utilizing 6 Dumptruck
= 7.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 7.00 DT x 10.00 cu.m./DT = 70.00 cu.m.
#VALUE!
No of Days Required = = #VALUE! days
70.00 x 10.50
Equipment Cost
Payloader = 1.00 13,864.00 /day x #VALUE! days = #VALUE!
Dumptrucks = 7.00 DT 10,816.00 /day x #VALUE! days = #VALUE!
#VALUE!
A. GRAVEL
Unit Cost of Hauling = #VALUE! /cu.m.
Cost at Source = 400.00 /cu.m.
Unit Cost of Coarse Aggregates = #VALUE! /cu.m.
SAY = #VALUE! /cu.m.
B. SAND
Unit Cost of Hauling = #VALUE! /cu.m.
Cost at Source = 350.00 /cu.m.
Unit Cost of Coarse Aggregates = #VALUE! /cu.m.
SAY = #VALUE! /cu.m.
Fine Aggregates
Volume = #REF! cu.m.
Considering 15% Swell Factor, Total Vol. Req'd.= #REF! cu.m.
Utilizing 6 Dumptruck
= 6.00 DT
= 6.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 6.00 DT x 10.00 cu.m./DT = 60.00 cu.m.
#REF!
No of Days Required = = #REF! days
60.00 x 10.50
Equipment Cost
Payloader = 1.00 13,864.00 /day x #REF! days = #REF!
Dumptrucks = 6.00 DT 10,816.00 /day x #REF! days = #REF!
#REF!
Boulders
Volume = #REF! cu.m.
Considering 5% Swell Factor, Total Vol. Req'd.= #REF! cu.m.
Mountainous Paved :
5.50 kms. x 60 min./hr.
Loaded Trip = = 16.50 mins.
20 kms./hr.
5.50 kms. x 60 min./hr.
Unloaded Trip = = 11.00 mins.
30 kms./hr.
45.70 mins.
mins.
Total Cycle Time
8 hrs. x 60 min./hr.
No. of Trip per Day = = 10.50 trip
45.70 mins.
Utilizing 6 Dumptruck
= 6.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 6.00 DT x 10.00 cu.m./DT = 60.00 cu.m.
#REF!
No of Days Required = = #REF! days
60.00 x 10.50
#REF! days
Equipment Cost
Payloader = 1.00 13,864.00 /day x #REF! days = #REF!
Dumptrucks = 6.00 DT 10,816.00 /day x #REF! days = #REF!
#REF!
A. BOULDERS
Unit Cost of Hauling = #REF! /cu.m.
Cost at Site = 500.00 /cu.m.
Unit Cost of Boulders (Class A) = #REF! /cu.m.
SAY = #REF! /cu.m.
Cement
Quantity Required = #VALUE! bags
#VALUE! bags
No of Days Required = =
480.00 mins./day CT x 225.00 #VALUE! days
x 1
166.00 mins./trip trip
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,512.00 /day x #VALUE! days = #VALUE!
Labor Cost
6 Laborers = 6.00 x 312.24 /day x #VALUE! days = #VALUE!
#VALUE!
A. CEMENT
Cost/bag at Source 230.00 /bag
#VALUE!
Unit Cost of Hauling = #VALUE! /bag
#VALUE!
Total Cost of Cement = #VALUE! /bag
SAY = #VALUE! /bag
UNIT COST DERIVATION OF REINFORCING STEEL BAR
#REF! kgs.
No of Days Required = = #REF! days
0.39 trip x 6,000.00 kgs.
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,512.00 /day x #REF! days = #REF!
Labor Cost
6 Laborers = 6.00 x 312.24 /day x #REF! days = #REF!
#REF!
Cycle Time
SOURCE : Bangued, Abra
Average Hauling Distance = 17 kms.
Loading Time = 15 min.
Unloading Time = 15 min.
Slack Time = 6 min.
Paved :
11.37 kms. x 60 min./hr.
Loaded Trip = = 34.11 mins.
20 kms./hr.
11.37 kms. x 60 min./hr.
Unloaded Trip = = 22.74 mins.
30 kms./hr.
Mountainous Unpaved :
kms. x 60 min./hr.
Loaded Trip = = 0.00 mins.
15 kms./hr.
- kms. x 60 min./hr.
Unloaded Trip = = 0.00 mins.
25 kms./hr.
92.85 mins.
Total Cycle Time
8 hrs. x 60 min./hr.
No. of Trip per Day = = 5.17 trip
92.85 mins.
40.00 ln.m.
No of Days Required = = 0.77 days
5.17 trip x 10.00 pcs.
say 0.77 days
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,512.00 /day x 0.77 days = P 7,324.24
1 Chain Block = 1.00 CB 500.00 /day x 0.77 days = P 385.00
Labor Cost
6 Laborers = 6.00 x 312.24 /day x 0.77 days = P 1,442.55
P 9,151.79