Documente Academic
Documente Profesional
Documente Cultură
Preamble: ................................................................................................................................................9
1. Brief Name and Start: .....................................................................................................................9
2. Definition ........................................................................................................................................ 9
a. Technical Assistance Team........................................................................................................9
b. Technical Inspection Team ........................................................................................................9
c. Technical Supervision Team......................................................................................................9
Government of Nepal National d. Third Party Monitoring Team ....................................................................................................9
Reconstruction Authority e. Grant Agreement........................................................................................................................ 9
f. Plinth Band ..............................................................................................................................10
Singhadurbar, Kathmandu
g. Roof Level ...............................................................................................................................10
h. Construction Completion ......................................................................................................... 10
Housing Reconstruction Programme i. Earthquake resilient structure ..................................................................................................10
3. Process of drawing approval and inspection of Houses under Housing reconstruction program .11
Section-1: Drawing Approval Process..............................................................................................11
Section-2: Inspection procedure up to plinth level. ..........................................................................12
Technical Inspection Guidelines Section-3: Inspection procedure above plinth level ..........................................................................14
5 6
Annex-10.1: Forms for first technical inspection and Certification of Category A and B Annex-15.2 (B): Form for inspection and Certification for category C building of Stone Masonry
buildings............................................................................................................................................42 with Cement Mortar..........................................................................................................................84
Annex-10.2: Forms for technical inspection and Certification of Category C buildings after the Annex-15.2 (C): Form for inspection and Certification for category C building of Brick Masonry
construction of the foundation (Technical Inspection-1) ..................................................................45 with Mud Mortar...............................................................................................................................86
Annex-10.2 (A): Form for inspection and Certification for category C buildings of Stone Annex-15.2 (D): Form for inspection and Certification for category C building of Brick Masonry
Masonry with Mud Mortar................................................................................................................45 with Cement Mortar..........................................................................................................................88
Annex-10.2 (B): Form for inspection and Certification for Category C building of Stone Masonry Annex-15.2 (E): Form for inspection and Certification for category C building of RCC Structure
with Cement Mortar..........................................................................................................................47 ..........................................................................................................................................................90
Annex-10.2 (C): Form for inspection and Certification for Category C building of Brick Masonry Annex- 16: Building Completion Certificate....................................................................................93
with Mud Mortar...............................................................................................................................49 Annex-17: Details of Construction completed Houses.....................................................................94
Annex-10.2 (D): Form for inspection and Certification for Category C building of Brick Masonry
with Cement Mortar..........................................................................................................................51
Annex-10.2 (E): Form for inspection and Certification for category C buildings of RCC Structure
..........................................................................................................................................................53
Annex-11: Correction/ Retrofitting Order and Inspection form .......................................................56
Annex 12: Inspection for under construction house .........................................................................58
Annex- 13: Forms for technical inspection and Certification of buildings after construction up to
roof level(Technical Inspection-2)....................................................................................................61
Annex- 13.1: Forms for technical inspection and Certification of category A and B buildings
(Technical Inspection-2) ...................................................................................................................61
Annex- 13.2: Forms for technical inspection and Certification of category C buildings after the
construction of the plinth (Technical Inspection-2) ..........................................................................65
Annex-13.2(A): Form for inspection and Certification for category C buildings of Stone Masonry
with Mud Mortar...............................................................................................................................65
Annex-13.2 (B): Form for inspection and Certification for category C building of Stone Masonry
with Cement Mortar..........................................................................................................................68
Annex-13.2 (C): Form for inspection and Certification for category C building of Brick Masonry
with Mud Mortar...............................................................................................................................70
Annex-13.2 (D): Form for inspection and Certification for category C building of Brick Masonry
with Cement Mortar..........................................................................................................................72
Annex-13.2 (E): Form for inspection and Certification for category C building of RCC Structure
..........................................................................................................................................................74
Annex-14: For grant disbursement of second/third tranche..............................................................77
Annex- 15: Forms for technical inspection and Certification of construction completed buildings
(Technical Inspection-3) ...................................................................................................................78
Annex- 15.1: Forms for technical inspection and Certification of category A and B buildings
(Technical Inspection-3) ...................................................................................................................78
Annex- 15.2: Forms for technical inspection and Certification of category C buildings after
completion of construction (Technical Inspection-3) .......................................................................82
Annex-15.2(A): Form for inspection and Certification for category C buildings of Stone Masonry
with Mud Mortar...............................................................................................................................82
7 8
Technical Inspection Guidelines for f. Plinth Band
The RCC, timber, Bamboo or other approved construction material band which is kept after the
Housing Reconstruction, 2073 completion of the foundation covering the complete part of the wall should be understood as plinth
band. Locally, it is also called DPC Band. In English it is called Plinth Band.
e. Grant Agreement
The agreement between beneficiary and VDC/Municipality to receive the grant support for housing
reconstruction based on grant distribution guidelines, 2072.
9 10
3. Process of drawing approval and inspection of Houses under 6. Certification of the design different than approved design model
11 12
provided in annex 11 and the house owner shall correct taking the help from the 2. The beneficiary house owner can withdraw the amount as per necessity of construction
technical assistance team. of the house
2. After completing the foundation and plinth level by adopting the corrective measures,
the beneficiaries should get the construction certified by the inspection team as
explained above.
12. Approval necessary for different design Section-3: Inspection procedure above plinth level
1. If the beneficiaries want to construct the building other than the building that they have
s during the period of enrollment camp, then they should give the application to the
VDC/municipality using the form provided in annex 7. Similarly the VDC/ 17. Based on certification construction above plinth level can be done
Municipality should also give the permission to construct the building by completing The beneficiaries can construct the houses under the provided certification based on annex
the procedure mentioned in point 4. 10. The further construction should not be carried out unless the beneficiaries get the
2. But if some beneficiaries has started the construction without giving application, then certification. But the beneficiaries can start the construction before achieving the second
he/she should follow the procedure mentioned in clause 9, 10 and 11 and get installment
certification by the inspection team
13. House owner must be clear about the construction above foundation 18. Technical assistance can be taken for construction above plinth level
1. After completing the construction up to plinth level by following the point mentioned 1. The beneficiaries can apply for the technical assistance for the further construction.
in clause 9, 10 and 11 the beneficiaries should be clear about the complete construction He/she should give the application form using the format provided in annex-5.
of the earthquake resistant building. Similarly, the respective VDC/municipality should also assign the technical Inspection
2. For this, the Technical Inspection Team should provide the knowledge of the Team for the guidance on the basis of priority.
earthquake resistant construction to the house owner. To construct the earthquake 2. For the construction of the house the beneficiaries should use the trained mason and
resistant building the beneficiaries can get the technical guidance by the technical carpenters.
assistance team. 19. Technical Inspection and certification after the construction of roof level of one story house
14. In case of technical problems advice can be taken from Inspection supervision team and and first floor of multistory house
Technical Standardization Committee 1. After completion of the roof band of one story and the first floor of the multistory
1. If the Technical Inspection Team cannot judge and certify the building for the during house, the beneficiaries should apply for the inspection of the house and third
inspection he/she should inform the Inspection Supervision team in DLPIU by filling installment using the form provided in annex 6
the form provided in annex 10 for necessary consultation. If the building needs to be 2. VDC/ Municipality shall inform the date of the prioritized visit of the Technical
corrected then the inspection supervision team should give the correction order by Inspection Team to the house owner for inspection and manage the inspection.
filling up the form provided in annex 11 , if the building can be certified then they 3. Technical Inspection Team should use the form in Annex-13 to certify the house if the
should fill up the form provided in annex 10. constructed house is according to earthquake resilient design and approved design
2. If the inspection supervision team of DLPIU cannot certify or recommend the 20. Correction order also can be given for the construction up to roof level of one story and first
correction then such type of buildings should be submitted to MOUD CLPIU and if floor of multistory house.
CLPIU cannot decide then it should be sent to Technical Standardization Committee 1. If correction has to be made, annex- 11 form is to be used by Technical Assistance
and should be decided Team informing about the things to be corrected.
15. The technical inspection form of foundation construction should be recommended by MOUD- 2. The concerned house owner beneficiary shall take a help from the technical assistance
DLPIU team and correct and apply to the VDC/ Municipality using the annex 6 form.
1. From the above mentioned points, using the form provided in annex 10 for the 3. The Technical Inspection Team shall inspect and certify the house using Annex-13 on
certification of the technical inspection, copy of one form should be provided to the the assigned date.
MOUD DLPIU for technical approval 4. If the DLPIU engineer cannot decide immediately and are confused in the decision then
2. MOUD DLPIU should check the details of documents of the annex 10 certification, the inspection should be done from the one step up Inspection Supervision team using
make a list of the beneficiaries using annex 14, send it to MOFALD-DLPIU (or DDC) the annex-13 form for certification and annex-11 form for correction and inform the
and recommend for the disbursement of second installment house owner.
3. MOUD-DLPIU should assign the Inspection Supervision team for the inspection of the 21. Certification, Recommendation and Disbursement of Third Tranche
quality of the construction and progress of the work upon necessity 1. After the process in point 19 and 20 the Technical Inspection Team should provide one
16. Disbursement of Second Tranche and Deposit in Bank Account copy of the certificate to the house owner and the other copy to VDC/ Municipality
1. The respective MOFALD-DLPIU will send the letter to the DTCO based on the 2. One copy of the Forms based on Annex 13 certified by Technical Inspection Team or
recommendation from MOUD-DLPIU and VDC/Municipality to disburse the second Inspection Supervision Team shall be sent from concerned VDC or Municipality office
installment amount to the beneficiaries account and the second installment amount will for technical approval to Ministry of Urban Development District Project
be deposited into bank account based on the recommendation from DTCO. Implementation Unit MoUD-DLPIU.
13 14
3. MOUD DLPIU should check the details of documents of the certification, make a list 1. According to above point no (24) inspection teams or inspection supervision team will
of the beneficiaries using annex 14, send it to DDC and recommend for the third observes the house but if the house is not reconstructed according to approved design,
installment Ministry of Urban Development, District Project Implementation Unit (MoUD-
4. MOFALD-DLPIU shall recommend and disburse the grant in the accounts of DLPIU) inspection teams, or Inspection Supervision team will fill the from in
beneficiaries through DTCO. accordance to Annex-11 and mention the things that needs to be improved and provide
22. Field Inspection during in roof level of one story and first floor level of multistory house to beneficiary house owner.
1. Ministry of Urban Development District Project Implementation Unit-MoUD-DLPIU 2. The respective beneficiary house owner can take the help of technical team and
can do field inspection if necessary by Technical supervision team on the basis of improve as suggested then again as mentioned above in Annex-14 form is filled and
description based on annex-14 forwarded form. submitted to the VDC or municipality office, while VDC or municipality will also
2. During the supervision by Inspection Supervision team if they find that the building is follow the same procedure immediately and inspect the house if the house is found to
not constructed on the basis of approved drawing and requirement then the team can be repaired as suggested then as mentioned in Annex-16 House reconstruction
cancel the certification and can stop the grant. completion certificate should be provided.
23. Construction above the roof level of single story and first floor level of multistory building 27. Apply for the inspection and certification of the multistory house after completing the roof of
can be continued ground floor and base of first floor
1. After receiving the certification letter in accordance with point no 21 by respective 1. The house owners who construct multiple story houses should construct the houses
beneficiary house owner can construct the roof of one story building or floor of multi- based on the approved design and apply to the VDC using the form in annex 6 to
story building as per approved design. In accordance with the certification letter request for certification and approval of construction above it. The VDC/ Municipality
construction of roof or construction of floor can be done before receiving the third shall prioritize and send the Technical Inspection Team for inspection
tranche. 2. If the construction is according to the approved design and safe the certification should
2. But According to point no 21 deployed supervision team of Ministry of Urban be provided using annex-14 and if it is to be corrected annex-11 form is used.
Development, District Project Implementation Unit (MoUD-DLPIU) or as specified in 28. Building completion certificate after the completion of multistory house construction
bottom Section-5 deployed third-party monitoring Authority will inspect the house, if 1. In case of multistory construction, the procedure on the point 24 needs to be followed
during the inspection or supervision any constructed house of beneficiary house owner and after all the construction is complete, the process on the clause 27 is followed and
is found to be unsafe or not as approved design then the tranche amount will be kept VDC/ Municipality can provide the construction completion certificate
pending and the respective beneficiary will have to correct as specified by that team. 2. During construction of upper story the house owner can take the technical assistance
applying to the VDC using the form in Annex- 5 and VDC/ Municipality shall send the
Technical Assistance team based on the priority on the assigned date.
3. Based on that completion certificate only, the concerned house owner can receive the
recommendation for support through different organizations.
Section-4: Process of Inspection of housing reconstruction completion 4. After issuance of the House reconstruction completion certificate, the
VDC/Municipality shall regularly prepare list using annex 17 and report it to
MOFALD and MOUD CLPIU.
24. Apply for getting the completion certificate after completing the roof of one story house
1. For construction of one story house respective house owner should constructed the roof
as mentioned in certification as Annex-13 by the Technical Inspection Team, after that
house owner should fill the application form as Annex-6 for construction completion Section-5: Inspection Process for Retrofitting/ Maintenance
certificate and submit to the respective VDC or municipality office
2. Respective VDC or municipality office should prioritize the application and manage 29. Application, inspection and completion certification related to retrofitting/maintenance
the time to inspect by the inspection team 1. The house owners who do the retrofitting/ maintenance should fill up the application
25. Certify the house after the completion of roof of one story house form attached in the annex 6 and apply to the VDC/ Municipality.
1. The Technical Inspection Team should inspect and fill the form as specified in Annex- 2. The concerned VDC/ Municipality shall manage the Technical Inspection Team in
15 and if the constructed house is found to be as approved design and earthquake priority on the assigned date
resilient then it is recommended for House reconstruction completion certificate 3. The Technical Inspection Team should visit the site and recommend for the
2. Based on the recommendation Inspection supervision team can supervise as needed and certification and based on that the technical supervision team shall visit the site and
provide House reconstruction completion certificate as annex-16. provide the certification.
3. After issuance of the House reconstruction completion certificate, the 30. Correction/retrofitting order can be given
VDC/Municipality shall regularly prepare list using annex 17 and report it to 1. If house is not repaired or retrofitted based on approved standards after inspection in
MOFALD and MOUD CLPIU. clause number 29, Technical Inspection Team of MOUD-DLPIU will give instructions
26. Correction order can be given if any correction has to be done in the completed hous by filling form of ANNEX-7
15 16
2. After improvement on previously done retrofit/repair as per instruction, concerned certified and based on the specified form the team must give direction to the house
house owner will get Certificate of completion retrofit/repair as according to clause 29. owner of respective beneficiary regarding the improvement of the house
3. Only after this certificate, concerned house owner will get the recommendation or 2. Also after the correction of the house by the respective beneficiary house owner, on the
facilities provided by VDC or Municipality or Concerned Government Agencies. basis of application given to VDC, a Technical Inspection Team and if required
inspection supervision team concluded that specified improvement have been done,
31. Technical assistance can be taken for retrofitting/maintenance then this team must certify the reconstruction up to the relevant level.
1. If any earthquake victim house owners give application to concerned VDC or 3. Based on Point no 34.1, arrangement will be made on prescribed grant only on the basis
Municipality after realizing the need of repair or retrofit, concerned VDC or of certification as given by the Technical Inspection Team or inspection supervision
Municipality should provide technical support and related advices by mobilizing team.
Technical Assistance Team 35. Grant will be provided based on the level of completion for houses already constructed before
2. If house owner give application according to annex-6 after doing retrofit/repair as per PA
advice of technical assistance team, retrofit/repair completion certificate should be 1. Based on Point no 34 arrangement will be made on prescribed grant only on the basis
provided after fulfilling procedure of clause 30. of certification as given by the Technical Inspection Team or inspection supervision
team.
32. Technical Monitoring through Third party for Reconstruction/ Retrofitting Section-8: Management and use of information system
1. For monitoring of reconstruct/retrofit or repair of private houses within specified time
after fulfilling above mentioned clauses, NRA will manage monitoring of at least 5%
of reconstruct/retrofit/repair required houses forming third party technical monitoring 36. Management and Development of Use of information system.
1. According to law mentioned above in various bullets to provide technical assistance in
team. In which one percentage of the house will be same from Foundation to
the rebuilding of private accommodation or technical inspection, supervision and
Completion and four percent house will done through random sampling.
2. The technical monitoring as mentioned in clause 32 (1) , team can monitor monitoring of financial assistance, if possible, available information technology to use,
reconstruction/Retrofitting or repair work anytime and concern house owner, VDC or and for this management information systems(MIS) shall be developed
2. According to the system the recommendations made by correspondence will also be
municipality, offices, and other related government agency, concerned person and other
recognized But in the case where there is no possibility to use information technology
organization should support the monitoring team.
and information management system, through paperwork process (hard copy) shall not
3. The formation process and monitoring procedure of the technical monitoring as
hinder the performance of its functions
mentioned in clause 32 (1) will be as per specified by NRA. The technical assistant
team, technical inspection team, Technical supervision team and other related agency
and person must make necessary improvement in private housing reconstruction work
as per the recommendation of above mentioned technical monitoring team.
4. Authority will manage a third party monitoring team in coordination with donor agency
or organizations who helped in private housing reconstruction and through them the
Section-9: The amendment in Guidelines
concern donor agency or organization can monitor to know the situation of their own
service operation 37. Guidelines can be amended
1. In the course of the implementation of this procedure, if any amendment is required,
Executive Committee of the Authority may amend.
Section-7: Process of inspecting the houses that are reconstructed before PA
17 18
Responsibility of Responsibilty of Responsibility Responsibility of
4. Annexes S.N
Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant
Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form
Annex 1: Procedure of Housing Reconstruction Program under the method of inspection and responsibility of related agencies. ahead for
Responsibility of Responsibilty of Responsibility Responsibility of construction
Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant
S.N 4.1 Technical Assistance Receive Provide Certificate Annex 9
Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form
team has been on a Inspection and
A To ensure the construction site in terms of geographical and geological safety and layout of foundation. construction site and certification
1 Before the construction Apply for Receive Annex 5 using the appropriate
of the foundation, to Inspection Application form for technical
inspect the construction inspection and to ensure
site from related that place is safety and
technical team to ensure appropriate in terms of
the Safety and geographical and
appropriate in terms of geological condition, and
geological and also carry out the
geophysical condition. In construction of
addition apply for foundation layout. After
supporting construction that also promote to
of foundation layout recommend additional
from technical team. construction.
4.2 Order to Correction Order to Annex 11
2 Mobilize Technical team Mobilize Management of Retrofitting or
for Inspection Technical team Technical Correction
Assistance team 4.3 Get detailed information Correct/ Retrofit
3 Technical Assistance at Provide the To ensure Annex 8 about the correction from
construction site for information to technical technical support team
Technical Inspection Technical inspection about and then after getting
Inspection about construction site directions household
the construction and further owner have to improve
site and recommend and layout and construction
foundation necessary site.
direction to move
19 20
Responsibility of Responsibilty of Responsibility Responsibility of Responsibility of Responsibilty of Responsibility Responsibility of
Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant
S.N S.N
Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form
4.4 After Correction re- To Apply To receive the Annex 5 house and provide them
apply for checking/ application certificate
examine. 8.2 Order retrofitting or Retrofitting or Support Annex 11
4.5 After getting re- Mobilize Correction Correction Technical
application mobilize Technical Inspection Team
technical assistance team Assistance Team on complex
4.6 Inspect the house After Provide the Technical Annex-9 technical subject
Correction information to inspection and 8.3 In case of which house Collects the detail To guide for to Provide more Annex-7
Technical certify are made in completely technical and improve the support MOUD-
Assistance different type or in send it MOUD- technical DLPIU
B House Construction work up to plinth level different techniques, DLPIU decisions
5 Apply for the technical Apply for Receive the Annex 6 Preparing the detail
inspection and pass after inspection application technical terms to guide
the completion of the for appropriate feedback
house up to plinth level send information to
do technical inspection-1 district, MOUD-DLPIU
6 Mobilize technical Mobilize Manage 8.4 Within 7 days after Order house To guide for Provide more Annex-11
Inspection Team for Inspection team Inspection team getting guidance from owner for improvement support MOUD-
inspection MOUD-DLPIU order correction and after technical DLPIU
7 Technical Inspection Provide Provide Appropriate household owner for retrofitting inspection
Team to be mobilized in information about certification and form of correction and
construction site using construction necessary Annex-10 retrofitting
appropriate form for technical direction after 8.5 After get detailed Construction
doing technical inspection team technical information and correction and
inspection-1 inspection instructions about retrofitting
8.1 The under construction Receive Technical Provide Appropriate correction from technical
house are according to Inspection Certification for form of team household owner
technical standard and if inspection Annex-10 should go ahead with
they can be pass, construction of his/her
immediately inspect the house.
21 22
Responsibility of Responsibilty of Responsibility Responsibility of Responsibility of Responsibilty of Responsibility Responsibility of
Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant
S.N S.N
Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form
9 After Correction re- To apply Receive the Annex 6 16 Inspection for under Mobilize technical
apply for inspection application construction house inspection team.
10 After getting re-applied Mobilize technical mobilize the technical
mobilize technical inspection team team in priority order
inspection team form.
11 Inspect the house after Provide Technical Appropriate 17 Technical inspection -2 Provide Technical To guide the Appropriate
correction information to Inspection form of for under construction information to inspection technical form of
technical Annex-10 house. Detailed technical inspection team Annex-13
inspection description of the inspection team
12 After certification from Provide the Order the To recommend Annex-14 technical checked was
technical inspection information about VDC/Municipalit the MOFALD- according to the
checked pass from that grant payment to y and MOUD- CLPIU about approved layout design
evidence to direct the MOUD-DLPIU CLPIU about grant payment. or minimum standard
second installment grant certify from whether or not. In that
payment. check pass and case follow point No. 8
grant aid. to 11 for necessary and
13 Second installment grant Take second appropriate procedures.
aid for VDC or installment grant
municipality to receive 18 Provide certification to Receive Provide Appropriate
money through a bank. house owner after certification certification form of
approve in terms of Annex-13
techniques of up to one
floor building or second
C Construction Works above the plinth band story floor level
completion
14 Do Construction Works
above the plinth band 19 After certification from Provide the Order the To recommend Annex-14
15 After the completion of To apply Receive the Annex-6 technical inspection information about VDC/Municipalit the MOFALD-
up to one floor building application checked pass from that grant payment to y and about CLPIU about
or second story floor evidence to direct the MOUD-DLPIU certification from third grant
level apply for technical third installment grant check pass and payment.
inspection-2 payment. grant aid.
23 24
Responsibility of Responsibilty of Responsibility Responsibility of Responsibility of Responsibilty of Responsibility Responsibility of
Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant
S.N S.N
Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form
20 Third installment grant Taken Third level of two story
aid for VDC or installment grant building
municipality to receive 26 Mobilize technical Mobilize Manage Technical
money through a bank. assistance Team to Technical Assistance
D Completion of construction one-floor building inspect the under Assistance Team mobilize team
21 To move ahead with Do construction construction house
construction works work 27 Technical inspection of Provide Do technical Appropriate
22 To apply for technical Apply Receive the Annex 6 construction house by information to inspection form of
inspection-3 of final application Technical assistance inspection Annex-13
certified of complete team. From 8.2 to 11 assistance team
construction work after points should be
complete construction incorporate the house
one-floor building that are not state as in
23 Mobilize technical Mobilize technical accordance of detail
Inspection Team for inspection team technical, map design
complete construction and minimum
work requirements.
24 Technical inspection-3 Provide the Do technical Do technical Annex 15 F Completion of two story building
of construction of the certification and inspection inspection 28 To apply for technical To apply Receive the Annex 6
house. From 8.2 to information about inspection after Application
11points should be complete completion of two story
applied the house that construction work building for final
are not state as in to technical certification.
accordance of detail inspection team 29 Mobilize Technical Mobilize technical
technical, map design Inspection Team for Inspection Team
and minimum standard. complete construction
E To move ahead two story building 30 Technical inspection-3 Provide Do Technical Mobilize Annex-16
25 To apply for technical To apply To receive the Annex 6 of constructed house. information to Inspection Technical
inspection after application From 9 to 14 points technical Inspection
completion of first floor should be applied the inspection team
house that are not state
25 26
Responsibility of Responsibilty of Responsibility Responsibility of Annex 2: Flow chart of Construction and Inspection Procedure
Works Related with Responsibility of VDC and Team of of MoUD- Technical Relevant
S.N House Owner VDC/Municipality Technical Inspection Team MOUD MOUD CLPIU and MOFALD DTCO Bank Technical
Technical Inspection Beneficiaries Municipality Inspection Team DLPIU Assistance Team Form DL-PIU Technical DL-PIU assistant team
(Inspection standardized (Partner
as in accordance of detail Participation agreement supervision Committee organization)
technical, map design Building permit (incase of municipality)
Selection of building typology team)
and minimum
requirements. Receipt of First
tranche through Bank
G Prepare report of Complete construction work of house
Application for
31 Submit overall summary Report Coordination for Annex 17 Inspection of Site and
foundation
5. Certification of
site and
of complete construction Preparation and report Assign the technical Foundation
Application for support team
work report of house to send to preparation and technical assistance
Inspection/re-inspection
Can be
NO
Can be decided NO decided
Process B
Correction/Retrofitting order (Incase of inspector
Fail
Pass
7. cant decide)
Correction/ Correction/Retrofitting
Certification Retrofitting order order (Incase of
inspector cant decide)
27 28
House Owner VDC/Municipality VDC/Municipality MOUD Technical MOFALD DTCO Bank Technical
(Inspector) DL-PIU standardized DL-PIU assistant team
(Inspection Committee (Partner
Receipt of Second supervision organization)
installment contd
team)
Application for
technical assistance
Assign the technical Technical support
Construction upto roof support team
band of single story
building and First floor
Annex-3: Type of house selected by beneficiary
of multistoried
building
Repeat A Payment of
Government of Nepal
third
Receipt of Third installment
installment
Ministry of Federal Affairs and Local Development
I agree to construct the house according to the building typology that has been provided by the NRA,
following the minimum requirement that has been selected above.
Beneficiaries/ representative:
Signature:..
Name:.
Address:.
30
Annex-4: Simplified process for Building Permit
Annex- 5: Application form for Technical Assistance
Steps Activities Responsibility and Timeline
Responsibility of House Timeline Responsibility of Timeline
Owner Municipality
First Apply with Drawing of the Submit the drawing and First Day Register the application First Day
house necessary documents
Second Publish Notice for check Publish notice with First day Prepare notice and First Day Government of Nepal
Officer provide it to House
owner/ Officer Ministry of Federal Affairs and Local Development
Third Check the drawing and consult Arrange the meeting of First day Finalise the technical Seventh Day ..VDC/Municipality Office
with the consultant for consultant with part / inform for
improvements Municipality correction to the
consultat
Application form for Technical Assistance
Fourth Check the site boundary and Layout to be done by Within Fifteenth Check the site Within Fifteenth Mr. President /Secretary of. VDC/Chief/executive officer of.
layout and orientation the consultant and day boundary along with day
regarding construction neighbours to be called the consensus of municipality. Under the housing reconstruction programme, I am writing this application to request you
for checking of neighbors and orient
boundary to check the below mentioned level and provide appropriate guidance. I have attached all the required
detail description along with this application letter.
Fifth Certification of drawing Contact Municipality With in seventeeth Provide certified Seventeenth day Site Selection and Layout
for approved drawing day drawing
Foundation
Above Plinth Level
31
Repair/Retrofit
32
Officer name (enrolled to register application): Annex- 6: Application form for Inspection and re-inspection
Post:..
Signature: Application
registration Date:..
Description of the technical mobile team enrolled for inspection: Government of Nepal
..VDC/Municipality Office
33 34
Signature:..Date:. Annex-8: If the construction of the building is different than that was agreed in
For Official use only: Application registered PA
No:
Officer name (enrolled to register application):
Post:..
Government of Nepal
Signature: Application
Ministry of Federal Affairs and Local Development
registration Date:..
..VDC/Municipality Office
Description of the technical mobile team enrolled for inspection: Application form if the building is different from that was agreed during PA
Application form to be filled for the Application form to be filled for the
supervision of under construction house. supervision of under construction house.
Selected Design number among the purposed Selected Design number among the purposed
design: design:
Or Or
The description of the building typology The description of the building typology
planned by the houseowner: planned by the houseowner:
1. Technique and construction 3. Technique and construction
materials. materials.
1.1 Stone masonry with mud mortar 1.1 Stone masonry with mud mortar
1.2 Stone masonry with cement mortar 1.2 Stone masonry with cement
1.3 Brick masonry with mud mortar mortar
1.4 Brick masonry with cement mortar 1.3 Brick masonry with mud mortar
1.5 Stone masonry with mud mortar 1.4 Brick masonry with cement
and wooden post and beam mortar
1.6 R.C.C framed structure 1.5 Stone masonry with mud mortar
1.7 House surrounded with wood or and wooden post and beam
CGI sheet in metal or wooden 1.6 R.C.C framed structure
frame 1.7 House surrounded with wood or
CGI sheet in metal or wooden
2. Construction of roof and materials. frame
2.1 CGI sheet over wooden beam,
rafter and purlin 4. Construction of roof and
2.2 Tile over wooden beam, rafter and materials.
purlin 2.1 CGI sheet over wooden beam,
2.3 CGI sheet over bamboo beam, rafter and purlin
rafter and purlin 2.2 Tile over wooden beam, rafter
2.4 Tile over bamboo beam, rafter and and purlin
purlin 2.3 CGI sheet over bamboo beam,
2.5 Tile over bamboo beam, rafter and rafter and purlin
purlin 2.4 Tile over bamboo beam, rafter
2.6 RCC slab and purlin
2.7 CGI sheet over metal beam, rafter 2.5 Tile over bamboo beam, rafter
and purlin and purlin
2.6 RCC slab
2.7 CGI sheet over metal beam, rafter
and purlin
35 36
I agree to build the type of the house selected based on the minimum requirements provided by Annex-8: Correction/ Retrofitting Order and Inspection form for site selection
National Reconstruction Authority and layout
Beneficiary or representative:
Signature:
Government of Nepal
Name:
Ministry of Federal Affairs and Local Development
Address:
..VDC/Municipality Office
The following points are found unsatisfactory, so it is recommended to follow below mentioned
correction order/ retrofitting order
37 38
Tentative Drawing after Retrofitting Annex 9: Form to be filled by the inspector for the certification of Site Selection
and layout for the construction of foundation.
Government of Nepal
Ministry of Urban Development
Central Level Project Implementation Unit
Form to be filled by the inspector for the certification of Site insurance and layout for the construction
of foundation.
Inspection sheet
Information of House Owner/Beneficiary Inspection date: Date - Month - Year
Name: Grant aggrement no:
a) After the detail description of the under constructed house, is it satisfactory to give permit for the Address: District VDC/Municipality ward tole Land plot No
further construction. SECTION-I: DESCRIPTION PROVIDED IN THE APPLICATION TO SURVEY THE HOUSE
Yes , No
If use fix design from design catalogue, Design No.
It is recommended to move ahead with the construction because it was found that the site selection Technique and Construction material
If free design by house owner Fill construction
and the layout is satisfactory typology from P.A form Construction of roof and materials
Technical Assistant Yes No Organization GON NGO/INGO
Correction/Retrofitting order is given because it was found to be corrected or retrofitted. SECTION- II: DETAILED TECHNICAL INSPECTION
Site condition during
MR
b) Acceptation of Description provided agreeing that the technical details during inspection is correct: Category Description inspection Remarks
Yes No
House owner/Beneficiaries or representative name:Signature:.. Geological fault or Ruptured Area
Steep Slope > 20
Relationship with house owner (In case of representative):..Date:... Landslide susceptible Area
1. Site River bank and Water logged Area
selection Rock-fall Area
c) Submit for Approval of the technical inspection:. Liquefaction susceptible Area
Filled Area
MOUD-DLPIU Supervisor: No. of bay
Area
Name Designation:. Shape of
2. Shape
House
Length
Signature. Date
Breadth
39 40
b. Tentative drawings of the site and purposed plan of building. Annex-10: Forms for technical inspection and Certification of buildings after
completion of foundation (Technical Inspection-1)
Government of Nepal
RCC (Category A and B)
Ministry of Urban Development
Central Level Project Implementation Unit First Inspection
c. After the detail description of the under constructed house, is it satisfactory to give
Inspection Sheet
permit for the further construction.
First Inspection of RCC (Category A and B) Buildings
Information of House Owner/Beneficiary Date of Inspection
Yes No Grant Agreement
Name No.
d. Acceptation of Description provided agreeing that the technical details during inspection is
Address District VDC/Municipality ward tole Land plot No
correct:
SECTION-I: DESCRIPTION PROVIDED IN THE APPLICATION TO SURVEY THE HOUSE
House owner/Beneficiaries or representative name:Signature:..
If use fix design from design catalogue, Design No.
Relationship with house owner (In case of representative):..Date:... If free design by house owner Technique and Construction
material
Fill construction typology from P.A form
Construction of roof and materials
41 42
Width Size
Tie Beam Rebar
6 Pillar
Height Ring
Size Connection
5 Plinth Beam
Rebar
Connection
Others:
c. After the detail description of the under constructed house, is it satisfactory to give permit
for the further construction.
Yes , No
it was passed through the inspection of the first inspection so the construction can move ahead
and VDC/ Municipality it is certified for necessary procedures of disbursement of second tranche.
d. Acceptation of Description provided agreeing that the technical details during inspection
is correct:
House owner/Beneficiaries or representative name:Signature:..
Designation:. Signature.
Date
f. Approved by:
Signature. Date
43 44
Annex-10.2: Forms for technical inspection and Certification of Category C Anchorage 60 times diameter of reinforcement -
Height from GL Not less than 300mm(1) from GL
buildings after the construction of the foundation (Technical Inspection-1)
Thickness 150mm(6)for medium and soft soil. 75mm(3) for hard soil
Width Not less than wall thickness/350mm
Annex-10.2 (A): Form for inspection and Certification for category C RC band Timber band
buildings of Stone Masonry with Mud Mortar 6 Plinth Main: 4-12dia for
150mm(6), 2-12dia for
Reinforcement 75mm(3) height Main member : 2-
45 46
Annex-10.2 (B): Form for inspection and Certification for Category C a. At least four number of photographs with their number
building of Stone Masonry with Cement Mortar b. Tentative drawings of building:
INSPECTION SHEET OF
STONE MASONRY WITH CEMENT MORTAR FOR FIRST INSPECTION
Information of House Owner/Beneficiary Date of Inspection D D - M M - Y Y Y Y
Name: Grant Agreement No.
Address:
District VDC/Municipality ward tole Land plot No
c. After the detail description of the under constructed house, is it satisfactory to give permit
SECTION-I: DESCRIPTION PROVIDED IN THE APPLICATION TO SURVEY THE HOUSE for the further construction.
If use fix design from design catalogue, Design No. SMC-1.1 Yes , No
If free design by house owner Technique and Construction material 1.1 it was passed through the inspection of the first inspection so the construction can move ahead
Fill construction typology from P.A form Construction of roof and materials 2.1
Technical Assistant YES, NO Organization GoN, NGO ( )
and VDC/ Municipality it is certified for necessary procedures of disbursement of second tranche.
Trained Masons used YES, NO Soil type Hard, Medium, Soft
SECTION- II: DETAILED TECHNICAL INSPECTION If was found to be corrected/retrofitted so correction order is given using Annex-6
MR Comply to MRs
Category Description Remarks
YES NO d. Acceptation of Description provided agreeing that the technical details during inspection
Geological fault or Ruptured Area is correct:
Steep Slope > 20
Landslide susceptible Area House owner/Beneficiaries or representative name:Signature:..
1 Site River bank and Water logged Area
selection Rock-fall Area Relationship with house owner (In case of representative):..Date:...
located
Liquefaction susceptible Area
away from
Filled Area
No. of storey Not more than two plus attic
Span of Wall Not more than 4.5m (149) e. Submit for Approval of the technical inspection:. MOUD-
Shape of
2 Size of room Not more than 13.5sq.m (1454sq.ft)
House DLPIU Supervisor: Name
Simple and regular shape as square and rectangular
Proportion
The length is not more than 3 times of its width
Avoid round, easily breakable soft stone
Designation:. Signature.
Stone Size: Thickness>50mm(2), length >150mm(6)
Mortar Strength is not less than 1 cement : 6 sand mixture Date
3 Materials Concrete M20grade (1cement: 1.5sand: 3aggregate)
Rebar fy = 415 Mpa /500 Mpa f. Approved by:
Timber Hard wood
MOUD DLPIU Supervision Engineer
Continuous strip footing
Depth below GL 800mm(28) for one storey, 900mm(3) for two storey Designation:.
4 Foundation 1 storey
Soft: >800mm(28), Medium: >600mm(2),
Base Hard: >600(2)mm
Signature. Date
Width 2 storey
Soft: Not recommended, Medium:>800mm(28),
Hard:>600mm(2)
Started right from the foundation
Vertical Placed at all corners, junctions of walls and openings
5
member Reinforcement 12mm for one storey, 16mm for two storey
Overlap 60 times diameter of reinforcement
Height from GL Not less than 300mm(1) from GL
150mm(6)for medium and soft soil. 75mm(3) for
Thickness hard soil
6 Plinth Width Not less than wall thickness/350mm(12)
Main: 4-12dia for 150mm(6), 2-12dia for 75mm(3)
Reinforcement height, Stirrups: 6mm dia. at 150mm(6)
Concrete cover of 25mm(1)
47 48
Main: 4-12dia for 150mm(6), 2- Main member : 2-
Annex-10.2 (C): Form for inspection and Certification for Category C 12dia for 75mm(3) height 75mmx38mm connected
building of Brick Masonry with Mud Mortar Stirrups: 6mm dia. at 150mm(6), with batten
Concrete cover of 25mm(1) 50mmX38mm@500c/c
49 50
Concrete cover of 25mm
Annex-10.2 (D): Form for inspection and Certification for Category C
Others:
building of Brick Masonry with Cement Mortar
a. At least four number of photographs with their number
First Inspection of BMC
Government of Nepal
Ministry of Urban Development b. Tentative drawings of building:
Central Level Project Implementation Unit
INSPECTION SHEET OF
BRICK MASONRY WITH CEMENT MORTAR FOR FIRST INSPECTION
Information of House Owner/Beneficiary Date of Inspection D D - M M - Y Y Y Y
Name: Grant Agreement No.
Address:
District VDC/Municipality ward tole Land plot No
51 52
Annex-10.2 (E): Form for inspection and Certification for category C Depth At least 5 ft
Loose soil >2.2 m
First Inspection of RCC
buildings of RCC Structure
Soft soil > 1.5 m
Government of Nepal Corner
Medium Soil > 1.25m
Buildings (Catetory-C)
Ministry of Urban Development
Hard Soil > 1.2m
Central Level Project Implementation Unit
Loose soil >2.4 m
Width of Soft soil > 1.65 m
Front
Inspection sheet Foundation Medium Soil > 1.4m
Hard Soil > 1.1m
4 Foundation
RCC Buildings FOR FIRST INSPECTION Loose soil >3 m
Information of House Owner/Beneficiary Date of Inspection Soft soil > 2.1 m
Mid
Name: Grant Agreement No. Medium Soil > 1.7 m
Address: Hard Soil > 1.5 m
District VDC/Municipality ward tole Land plot No Rebar
400 mm in middle and 300mm in
SECTION-I: DESCRIPTION PROVIDED IN THE APPLICATION TO SURVEY THE HOUSE Depth
other sides.
If use fix design from design catalogue, Design No. Beam Minimum 9X9 and 4-12 revars
If free design by house owner Technique and Construction Height At least 450 from GL
material
Size 9 X 9
Fill construction typology from P.A form Construction of roof and 5 Plinth beam
materials Rebar 4-12mm and 8 mm rods in 6 inches
Technical Assistant Organization Organization GoN, NGO ( Connection Not 50 % overlap
Trained Masons used YES, NO Soil type Hard, Medium, Soft The pillar should be aligned in one line
SECTION- II: DETAILED TECHNICAL INSPECTION Size 12 X 12
MR Comply to MRs Ground and first floor 4-16 + 4-12
Category Description Remarks Rebar
YES NO mm and third floor 8-12mm
Geological fault or Ruptured Area 6 Pillar Edge and joints 4 inch and 6 inch in
Ring
Steep Slope > 20 others , 8 mm
Landslide susceptible Area In the middle leaving 2 ft from edge
1 Site selection River bank and Water logged Area Joints and not more than 50 % and lap of
located
Rock-fall Area 60 X dia.
away from
Liquefaction susceptible Area
Filled Area Others:
Storey Limited up to 3 floor a. At least four number of photographs with their number
bay Two to six b. Tentative drawings of building:
Less than 1000 sq ft and area in between 4 pillars
Area
Shape of Height Less than 11m
2 13.5 sq m only
House Height of
Height of floor from 2.75m to 3.35m
floor
Shape Square or rectangular
Ratio Length less than 3 times the breadth
Mortar 1:6
3 Materials Concrete M 20 Grade (1:1.5:3)
Rebar fy = 415 Mpa /500 Mpa
c. After the detail description of the under constructed house, is it satisfactory to give permit
for the further construction.
Yes , No
it was passed through the inspection of the first inspection so the construction can move ahead
and VDC/ Municipality it is certified for necessary procedures of disbursement of second tranche.
53 54
d. Acceptation of Description provided agreeing that the technical details during inspection Annex-11: Correction/ Retrofitting Order and Inspection form
is correct:
55 56
g. Tentative drawings of building after correction
Government of Nepal
Ministry of Urban Development
Central Level Project Implementation Unit
h. After the detail description of the under constructed house, is it satisfactory to give permit for Houseowner / Beneficiaries name, surname: Grant agreement no
the further construction. :
Yes , No
it was passed through the inspection of the first inspection so the construction can move ahead Address: District:..
and VDC/ Municipality it is certified for necessary procedures of disbursement of second tranche. VDC/Municipality :.
Ward:. Tole:.. Land Plot
If was found to be corrected/retrofitted so correction order is given using Annex-6 no:..
i. Acceptation of Description provided agreeing that the technical details during inspection is
correct: a) Detail Technical description:
1. Number of storey:
House owner/Beneficiaries or representative name:Signature:..
2. Status of the construction:
Relationship with house owner (In case of representative):..Date:... Under construction
Construction completed
Roof Band in Ground Floor
Construction up to Roof Band
j. Submit for Approval of the technical inspection:. MOUD-
57 58
Detail 9. After the detail description of the under constructed house, is it satisfactory to give permit for
description: the further construction.
. Yes , No
it was passed through the inspection of the first inspection so the construction can move ahead
5. Description of roof in ground floor: and VDC/ Municipality it is certified for necessary procedures of disbursement of second tranche.
Materials:
. Construction
If was found to be corrected/retrofitted so correction order is given using Annex-6
technique:
..
Detail 10. Acceptation of Description provided agreeing that the technical details during inspection is
description: correct:
. House owner/Beneficiaries or representative name:Signature:..
6. Description of first floor: Relationship with house owner (In case of representative):..Date:...
Materials:
Construction
technique: 11. Submit for Approval of the technical inspection:. MOUD-
Detail
description: DLPIU Supervisor: Name
.
Designation:. Signature.
Date
8. Others:
g. At least four number of photographs with their number
h. Tentative drawings of building:
59 60
Annex- 13: Forms for technical inspection and Certification of buildings after Ring
construction up to roof level(Technical Inspection-2) Joints
Government of Nepal
RCC (Category A and B)
Ministry of Urban Development
Central Level Project Implementation Unit Second Inspection
Inspection Sheet
Second Inspection of RCC (Category A and B) Buildings
Information of House Owner/Beneficiary Date of Inspection
Name Grant Agreement No.
Address District VDC/Municipality ward tole Land plot No
Others:
a. At least four number of photographs with their number
b. Tentative drawings of building:
c. After the detail description of the under constructed house, is it satisfactory to give permit
for the further construction.
Yes , No
it was passed through the inspection so the construction can move ahead and VDC/ Municipality it
is certified for necessary procedures of disbursement of third tranche.
d. Acceptation of Description provided agreeing that the technical details during inspection
is correct:
House owner/Beneficiaries or representative name:Signature:..
MOUD-DLPIU Supervisor:
63 64
Annex- 13.2: Forms for technical inspection and Certification of category C Distance Not less than 600 mm (2).
Rc Timber
buildings after the construction of the plinth (Technical Inspection-2) Continuous band through all walls
Sill band Not less than 75mm (3) thick.
Annex-13.2(A): Form for inspection and Certification for category C buildings Not less than 75mm(3) thick,if
opening width<1.0m(33) and
of Stone Masonry with Mud Mortar masonry height above opening
Vertical Reinforcement
Placed at all corners,
junctions of walls and
75mm (3) x 100mm (4) for
corner.
d. Acceptation of Description provided agreeing that the technical details during inspection
5 is correct:
member openings Two member of 75mm(3) x
100mm(4) for openings
65 66
Signature. Date Annex-13.2 (B): Form for inspection and Certification for category C building
of Stone Masonry with Cement Mortar
f. Approved by:
Second Inspection of SMC
Government of Nepal
Ministry of Urban Development
MOUD DLPIU Supervision Engineer
Designation:.
Central Level Project Implementation Unit
Signature. Date INSPECTION SHEET OF
STONE MASONRY WITH CEMENT MORTAR FOR SECOND INSPECTION
Information of House Owner/Beneficiary Date of Inspection D D - M M - Y Y Y Y
Name: Grant Agreement No.
Address:
District VDC/Municipality ward tole Land plot No
67 68
Main: 4-12dia for 150mm(6), 2-12dia for 75mm(3)
Reinforcement height, Stirrups: 6mm dia. @ 150mm(6) c/c Annex-13.2 (C): Form for inspection and Certification for category C building
Concrete cover of 25mm(1) of Brick Masonry with Mud Mortar
Overlap
Second Inspection of BMM
60 times diameter of reinforcement Government of Nepal
Ministry of Urban Development
Central Level Project Implementation Unit
Others:
69 70
opening width<1.5m and masonry 50mmX38mm
height above opening 1.2m(4) @ 500c/c.
At corners and junctions,
stitch length>1.2m(4)
Not less than 75mm(3) thick
Continuous band through all walls. Not
Roof band less than 75mm(3) thick
Main: 4-12dia for 150mm (6), 2-12dia
for 75mm(3) height
reinforcement Stirrups: 6mm dia.@ 150mm (6)c/c,
Annex-13.2 (D): Form for inspection and Certification for category C building of
Concrete cover of 25mm (1) Brick Masonry with Cement Mortar
71 72
Not less than 150mm (6), if opening width>1.25m (
41) and masonry above opening upto 1.2m (4)
At corner and junction, not less than 75mm (3),
Stitch band
length<1.2m(4) Annex-13.2 (E): Form for inspection and Certification for category C building
Continuous bands through all walls,
Roof band Not less than 75mm (3)
of RCC Structure
Second Inspection of RCC
Main: 4-12mm dia for 150mm (6), 2-12mm dia for
Reinforcement 75mm (3), stirrups:6mm dia @150mm (6)c/c
Concrete cover of 25mm (1) Government of Nepal
Overlap 60 times diameter of reinforcement. Ministry of Urban Development
Others:
Central Level Project Implementation Unit
Buildings (Category-C)
Inspection sheet
a. At least four number of photographs with their number
b. Tentative drawings of building:
RCC Buildings FOR FIRST INSPECTION
Date of Inspection Date of Inspection
Grant Agreement
Name: No.
District VDC/Municipality ward tole Land plot No
Address:
73 74
9 X14 and less than size of If was found to be corrected/retrofitted so correction order is given using Annex-6
Size
pillar
Rebar d. Acceptation of Description provided agreeing that the technical details during inspection
Edge and joints 4 inch and 6 inch
Ring is correct:
in others , 8 mm
Upper rod to be connected in House owner/Beneficiaries or representative name:Signature:..
middle and lower rod after
Joints
leaving 2 feet from edge and lap Relationship with house owner (In case of representative):..Date:...
of 60 dia.
Size of beam should be less than pillar
Upper rod to be bent downwards and lower
Joint of beam e. Submit for Approval of the technical inspection:. MOUD-
5 rod to be bent upwards lapping 60 dia
and pillar
At least two rings in the joints
DLPIU Supervisor: Name
Should be constructed equally from two
sides Designation:. Signature.
Wall should be straight
Joints missed or not Date
Width 230 mm or 110 mm
f. Approved by:
Non Joints 10 mm to 20 mm
6 Minimum depth 75 mm and 2-
structural wall Sill MOUD DLPIU Supervision Engineer
8mm rebars should be connected
Band Designation:.
to pillar
Minimum depth 75 mm and 2- Signature. Date
Lintel
8mm rebars should be connected
Band
to pillar
Floor should not be in
Level
different levels
Openings Maximum 25 %
Size Minimum 125 mm
7 Floor Rebar Minimum 8 mm rod 6 inch cc
Cover Minimum 15mm
1 m maximum from center of
Overhang
pillar
Others:
a. At least four number of photographs with their number
b. Tentative drawings of building:
c. After the detail description of the under constructed house, is it satisfactory to give permit
for the further construction.
Yes , No
it was passed through the inspection so the construction can move ahead and VDC/ Municipality it
is certified for necessary procedures of disbursement of third tranche.
75 76
Annex-14: For grant disbursement of second/third tranche
Recommendation form to be filled by the VDC/ Municipality and MOUD-DLPIU
Government of Nepal Government of Nepal Annex- 15: Forms for technical inspection and Certification of construction
MOFALD MOUD
completed buildings (Technical Inspection-3)
VDC/Municipality DLPIU,
Annex- 15.1: Forms for technical inspection and Certification of category A
Recommendation form for grant disbursement of second/third tranche and B buildings (Technical Inspection-3)
Name of Bank: Branch Name: Date:
Name of
SN MIS_Batch PA_NO VDC/MUN Ward Citz_No Mobile A/C No Tranche Amount Remarks
Final Inspection
Central Level Project Implementation Unit
78
Rebar Size of beam should be less than pillar
Joint of beam
Ring 5 Joint
and pillar
Joints Ring
Position of wall
Wall straight or not
Joints missed or not
Non
6 Width
structural wall
Joints
Sill Band
Lintel Band
Level
Openings
Size
7 Floor
Rebar
Cover
Overhang
Others:
c) After the detail description of the under constructed house, is it satisfactory to give completion
certificate
Yes , No
It was passed through the inspection of the third inspection so the construction can be provided
building completion certificate from VDC/Municipality.
MOUD-DLPIU Supervisor:
Name Designation:.
79 80
Signature. Date Annex- 15.2: Forms for technical inspection and Certification of category C
buildings after completion of construction (Technical Inspection-3)
f) Approved by:
MOUD DLPIU Supervision Engineer Annex-15.2(A): Form for inspection and Certification for category C buildings
Designation:. of Stone Masonry with Mud Mortar
c) After the detail description of the under constructed house, is it satisfactory to give completion
certificate
Yes , No
It was passed through the inspection of the third inspection so the construction can be provided
building completion certificate from VDC/Municipality.
81 82
d) Acceptation of Description provided agreeing that the technical details during inspection is correct: Annex-15.2 (B): Form for inspection and Certification for category C building
of Stone Masonry with Cement Mortar
House owner/Beneficiaries or representative name:Signature:..
Government of Nepal
Relationship with house owner (In case of representative):..Date:... Ministry of Urban Development
Central Level Project Implementation Unit Final Inspection of SMC
INSPECTION SHEET OF
e) Submit for Approval of the technical inspection:. STONE MAONRY WITH CEMENT MORTAR FOR FINAL INSPECTION
MOUD-DLPIU Supervisor: Information of House Owner/Beneficiary Date of Inspection D D - M M - Y Y Y Y
Name: Grand Agreement No.
Name Designation:. Address:
District VDC/Municipality ward tole Land plot No
Signature. Date SECTION-I: DESCRIPTION PROVIDED IN THE APPLICATION TO SURVEY THE HOUSE
If use fix design from design catalogue, Design No. SMC-1.1
f) Approved by: 1.1
If free design by house owner Technique and Construction material
Fill construction typology from P.A form Construction of roof and materials 2.1
MOUD DLPIU Supervision Engineer
Technical Assistant YES, NO Organization GoN, NGO ( )
Designation:. Trained Masons used YES, NO Soil type Hard, Medium, Soft
SECTION- II: DETAILED TECHNICAL INSPECTION
Signature. Date
MR Comply to MRs
Category Description Remarks
YES NO
7 Walls Gable wall Lightweight materials
Material Use light roof
10 Roof Connection All member connected properly
For flexible diaphragm, Diagonal bracing shall be
Bracing considered.
Others:
c) After the detail description of the under constructed house, is it satisfactory to give completion
certificate
Yes , No
It was passed through the inspection of the third inspection so the construction can be provided
building completion certificate from VDC/Municipality.
83 84
d) Acceptation of Description provided agreeing that the technical details during inspection is correct: Annex-15.2 (C): Form for inspection and Certification for category C building
of Brick Masonry with Mud Mortar
House owner/Beneficiaries or representative name:Signature:..
Final Inspection of BMM
Government of Nepal
Ministry of Urban Development
Relationship with house owner (In case of representative):..Date:...
Central Level Project Implementation Unit
Others:
c) After the detail description of the under constructed house, is it satisfactory to give completion
certificate
Yes , No
It was passed through the inspection of the third inspection so the construction can be provided
building completion certificate from VDC/Municipality.
85 86
Relationship with house owner (In case of representative):..Date:... Annex-15.2 (D): Form for inspection and Certification for category C building
of Brick Masonry with Cement Mortar
MOUD-DLPIU Supervisor:
Ministry of Urban Development
Central Level Project Implementation Unit Final Inspection of BMC
Name Designation:. INSPECTION SHEET OF
BRICK MASONRY WITH CEMENT MORTAR FOR FINAL INSPECTION
Signature. Date Information of House Owner/Beneficiary Date of Inspection D D - M M - Y Y Y Y
f) Approved by: Name: Grand Agreement No.
Address:
MOUD DLPIU Supervision Engineer District VDC/Municipality ward tole Land plot No
Others:
c) After the detail description of the under constructed house, is it satisfactory to give completion
certificate
Yes , No
It was passed through the inspection of the third inspection so the construction can be provided
building completion certificate from VDC/Municipality.
87 88
House owner/Beneficiaries or representative name:Signature:..
MOUD-DLPIU Supervisor:
Name Designation:. Annex-15.2 (E): Form for inspection and Certification for category C building
of RCC Structure
f)
Signature. Date
89 90
Edge and joints 4 inch and 6 inch
Ring
in others , 8 mm c) After the detail description of the under constructed house, is it satisfactory to give completion
In the middle leaving 2 ft from certificate
Joints edge and not more than 50 %
and lap of 60 X dia.
Yes , No
The joints of the beam should be positioned It was passed through the inspection of the third inspection so the construction can be provided
in the beam building completion certificate from VDC/Municipality.
9 X14 and less than size of
Size
pillar If was found to be corrected/retrofitted so correction order is given using Annex-6
Rebar d) Acceptation of Description provided agreeing that the technical details during inspection is correct:
Edge and joints 4 inch and 6 inch
4 Beam Ring
in others , 8 mm House owner/Beneficiaries or representative name:Signature:..
Upper rod to be connected in
middle and lower rod after Relationship with house owner (In case of representative):..Date:...
Joints
leaving 2 feet from edge and lap
of 60 dia.
Size of beam should be less than pillar
e) Submit for Approval of the technical inspection:.
Upper rod to be bent downwards and lower
Joint of beam
5 rod to be bent upwards lapping 60 dia MOUD-DLPIU Supervisor:
and pillar
At least two rings in the joints
Should be constructed equally from two
Name Designation:.
sides
Wall should be straight Signature. Date
Joints missed or not
f) Approved by:
Width 230 mm or 110 mm
Non Joints 10 mm to 20 mm MOUD DLPIU Supervision Engineer
6 Minimum depth 75 mm and 2-
structural wall Sill Designation:.
8mm rebars should be connected
Band
to pillar Signature. Date
Minimum depth 75 mm and 2-
Lintel
8mm rebars should be connected
Band
to pillar
Floor should not be in
Level
different levels
Openings Maximum 25 %
Size Minimum 125 mm
7 Floor Rebar Minimum 8 mm rod 6 inch cc
Cover Minimum 15mm
1 m maximum from center of
Overhang
pillar
Others:
91 92
Annex-17: Details of Construction completed Houses
Ministry of Federal Affairs and Local Development Ministry of Federal Affairs and Local Development
Under Inspection SOP for reconstruction of houses, after the detail inspection of the building under District:
construction on .. (Date), it is certified that the building under construction was
VDC/ Municipaliy:
completed and technical inspection is also completed and this certificate is provided.
Ward no:
Name of house Owner/beneficiary..
Agreement Serial Number: . Inspection Certificate Serial Beneficiary Name Agreement Type of Date of completion
No: No: Serial No. House Certiciate
Survey Slip Number: ..
Citizenship Number: ...
93 94