Sunteți pe pagina 1din 2

SAUDI ARAMCO ID/PID - 18-May-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Communication System -Equipment Rack -Installation And


SAIC -T-5309 15-Dec-09 TELECOM-
Pre-Commissioning
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. Equipment Rack Installation

Verify and ensure the grounding for the installed AC outlets on the SAES-T-795,
A1
communications equipment rack is isolated from the equipment chassis. 4.4.2

Verify and ensure the minimum working clearance of 91 cm is provided


SAES-T-916,
A2 in front of the equipment and sufficient access space is provided in the
4.3.5
rear of the equipment rack to allow access for maintenance purposes.

Verify and ensure that the communication bonding conductor used for SAES-T-916,
A3 bonding & grounding the equipment racks is an insulated (green) no. 6 Illustration III,
AWG. pg.94

Verify and ensure that the equipment racks are self supporting, channel
A4 type, having standard 1-3/4"(4.45 cm) multiple vertical Pre-threaded EIA-310-D
mounting holes on front and rear prior the start of installation.

Verify and ensure that the panel horizontal mounting center is either 19" IFC drawings &
A5
or 23" and the racks height is as shown on the IFC drawings. Specification

Verify that the number of equipment racks installed is in accordance with IFC drawings &
A6
the Floor Diagram drawings. Specification

REMARKS:

REFERENCE DOCUMENTS:
1. EIA-310-D Standard
2. SAES-T-795, Communication Facility Grounding System dated 27 February, 2007
3. SAES-T-916, Telecommunications Building Cable Systems dated 7 February, 2007

NOTES:

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

Page 1 of 2
Quality Record Approved:
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED