Documente Academic
Documente Profesional
Documente Cultură
Thecriticalpathmethod(CPM)
Thecriticalpathmethod(CPM)isaplanningandcontroltechniquethatprovides
anaccurate,timely,andeasilyunderstoodpictureoftheproject.
Itpurposeistoallocateresourcesovertimeinanoptimalmannerandinaway
thatallowseffectivereallocationandschedulecontrol,aftertheprojectstarts.
ThemostimportantfeaturesoftheCPMisthelogicdiagramwhichgraphically
portraystherelationshipsbetweenprojectactivities.
SYW
Planning
Thegoalofplanningistominimizeresourceexpenditureswhilesatisfactorily
completingagiventask.
Planningcreatesanorderlysequenceofevents,definestheprinciplestobe
followedincarryingforththeplan,anddescribestheultimatedispositionofthe
results.
SYW
PlanningProcess
AssumptionBasedonFacts
WhenPlanningconstructionoperations,themanagermustcarefullyassessallfactorsthatimpactthe
work.
AlternativeCoursesofAction
Variouscoursesofactionarecomparedintermsofpersonnel,material,equipment,andtime.
(Thisisoftendifficultbecausetypicallyplanningconsidersmultiplesourcesofuncertainties)
SelecttheCourseofAction
Derivativeplansmustbedevelopedtosupportthebasicplan.
Importantprojectaspectsthatshouldbeaddressedare
Availabilityoflabor,equipment,andmaterials
Movingontothejobsite
Bringinginsuppliesandequipment
Obtainingandusingnaturalresources
Planningforinclementweather
Providingforadequateconstructionsitedrainage
SYW
ACTIVITIES
EXAMPLESOFACTIVITIESNAME(ToBuildtheBridge)
Pilecap
Drivepiles Installdecking
Constructabutment
Placecap
Placestringers
Placestringers
Installdecking
Construct
abutment
Drivepiles
Anactivityisatimeconsuming,definabletask
SYW
NetworkDiagrams
1. ActivityonNode (AON)
2. ActivityonArrow(AOA)
SYW
ActivityonNode(AON)
ActivityID
Early Early
Start Finish
Duration
Late Late
Start Resources Finish
Exampleofactivitynodeinformation,thespecificarrangement
willdependontheschedulingsoftwareused
SYW
FinishtoStart
Place Strip
Cure7 Shoring
concrete1
days 2days
day
AONnetworkfinishtostart relationshipwithoutlag
Place Strip
concrete1 Shoring
day FS=7 2days
AONnetworkfinishtostart relationshipwithlag
SYW
StarttoStart
Excavate Excavate
footings16 footings712
1day 1day
AONnetworkfinishtostart
relationshipwithoutlag
Form&place
concrete
footings16
2days
Excavate
footings
2 days
AONnetworkstarttostart
SS=1 Form&place relationshipwithlag
concrete
2days
SYW
FinishtoFinish
Form
Formfootings footings
1924 1224
3days FF=2
Placeconcrete 6days
footings1924
2days Place
Place concrete
concrete footings1224
footings1218 4days
2days
AONnetworkfinishtostart AONnetworkfinishtofinish
relationshipwithoutlag relationshipwithlag
SYW
StarttoFinish
Mostschedulingsoftwaredoesnotsupportuseofthe
starttofinishrelationship.
SYW
CRITICALPATH
3 L 4
4 1 5
0 I 3 3 K 5 5 O 8 8 P 9 10 R 12
0 3 3 3 2 5 5 3 8 9 1 10 10 2 12
3 J 4 5 M 3 8 Q 10
5 1 6 6 2 8 8 2 10
Schedulingnetworkactivities
SYW
Workdays
Activity
1 2 3 4 5 6 7 8 9 10 11 12
I(J,K,L) 2 2 2
J(M) 1
K(O) 3 3
L(O) 2
Barchartforscheduling
M(Q) 1 1
networkactivities
O(P,Q) 4 4 4
P(R) 2
Q(R) 3 3
R 2 2
Sum 2 2 2 6 6 5 4 4 5 3 2 2
3 L 4
4 1 5
0 I 3 3 K 5 5 O 8 8 P 9 10 R 12
0 3 3 3 2 5 5 3 8 9 1 10 10 2 12
3
5
J
1
4
6
5
6
M
2
3
8
8
8
Q
2
10
10 SYW
FLOAT
Thetimeflexibilityofactivityperformancethatstatesthemaximum
allowablefornotdelayingafollowingactivityortheproject.
FLOAT=LS ES=LF EF
SYW
Resources
Ifcarpentercrewsareidentifiedasacontrollingresource,thenumberswithin
theactivitydataboxeswouldindicatehowmanycarpentercrewsare
requiredforeachoftheactivities.
Itisnecessarytoconsideronlymajorcontrollingresourceswhendeveloping
theschedule.
Eachprojecthasitsowncontrollingresourcesdependingonthenatureofthe
work.
Thenumberofavailableresourcesisoftenlessthantheneededresourcesfor
agivenday,andactivitiesmustbedelayed(intofloatwheneverpossible)to
spreadresourceuseacrossthetimeframeoftheproject.
SYW
Resources
Option1
Workdays
Activity
1 2 3 4 5 6 7 8 9 10 11 12
I(J,K,L) 2 2 2
J(M) 1
K(O) 3 3
L(O) 2
M(Q) 1 1
O(P,Q) 4 4 4
P(R) 2
Q(R) 3 3
R 2 2
Sum 2 2 2 3 5 5 5 5 5 3 2 2
Asmoothresourceconstrainedschedule,maximumfivecrews.
SYW
Resources
Option2
Workdays
Activity
1 2 3 4 5 6 7 8 9 10 11 12
I(J,K,L) 2 2 2
J(M) 1
K(O) 3 3
L(O) 2
M(Q) 1 1
O(P,Q) 4 4 4
P(R) 2
Q(R) 3 3
R 2 2
Sum 2 2 2 4 5 5 5 4 5 3 2 2
Asmoothresourceconstrainedschedule,maximumfivecrews.
SYW
Comparison of Option1 & Option2
Option1 Option2
That schedule results in a uniform increase in With this schedule some float has been
the number of the required crews, a level retained for activities J, M and P. The problem,
requirement for five crews from day 5 through however, is that on day 8 it is necessary to lay
day 9, then a uniform decrease of crew off one crew and then on day 9 you need one
requirements at the end of the project. This is more crew for only 1 day. If the resource was a
a good situation because it is difficult to crane instead of a carpenter crew there would
manage the work when the required number be the added consideration of the cost to
of resources is constantly changing. The mobilize and demobilize the machine. In that
problem with this schedule is that, with only case, the manager may decide to pay the extra
the exception of activity P, we have now made day of machine rent and retain schedule
every activity critical. If anything should delay flexibility. Leveling of crew resources is always
a critical activity, the project will also be a challenge when trying to keep productive
delayed. crews together.
SYW
Crashing
If the CPM indicates that the projects duration exceeds the desired
completion date, the manager should examine the logic diagrams
critical path to find activity durations which may be shortened. This is
known as expediting, compressing, or crashing the project.
SYW
Activity A B C D E F G H S J K T M
Precede None None A A B B B C D,E F H H,S,J J
Duration
2 3 3 2 4 3 9 3 4 2 1 6 1
Days
3 C 6 6 H 9 9 K 10
5 3 8 8 3 11 16 1 17
0 A 2 3 D 5
3 2 5 5 2 7 7 S 11 11 T 17
7 4 11 11 6 17
3 E 7
0 B 3 3 4 7
0 3 3 3 F 6 6 J 8 8 M 9
6 3 9 9 2 11 16 1 17
3 G 12
8 9 17 SYW