Sunteți pe pagina 1din 7

LIST OF DOCUMENTS TO BE SUBMITTED

FOR COMPLETION INSPECTION


A. Holding BP:-

a. For obtaining Final / Partial BCC:

The following documents to be submitted in PDF through ePermit


site - eBCC module prior to inviting CED for final inspection to
obtain a BUILDING COMPLETION CERTIFICATE.

1. Consultant Covering Letter (see the attached standard


format-A1).
2. Clients Undertaking Letter (see the attached standard
format-A2).
3. EHS NOC Building Completion.
4. BU NOC for Business Units Projects.
[Business Units refers to DMCC, Nakheel, Limitless, Dubai
Water Fronts]

b. For obtaining NOC for DEWA Purpose:

The following documents to be submitted in PDF through ePermit


site - eBCC module prior to inviting CED for preliminary
inspection to obtain NOC for DEWA purpose:

1. Consultant Covering Letter (see the attached standard


format-A3).
2. EHS: NOC to Trakhees CED: DEWA POWER & WATER
SUPPLY.

B. Holding NOC:-

For obtaining Completion Certificate for Modifications / Fitout /


Renovation works / Racking System, the following documents to be
submitted in PDF through eMail: Ced.Bcc@Trakhees.ae prior to inviting
CED for inspection to obtain a COMPLETION CERTIFICATE.

1. Client Covering Letter (see the attached standard format-A4)


2. Contractor Covering Letter (see the attached standard format-A5)
3. EHS NOC Building Completion.
4. Application for the Completion Certificate (see the attached
standard format-A6).
N.B: The premises shall not be occupied for the purpose of conducting
business until the Completion Certificate is obtained. All the relevant
documents shall be produced on site at the time of inspection.
Standard Format-A1:
(Consultant Letter Head)

Ref:
Date:

Trakhees
Ports, Customs & Free Zone Corporation (PCFC)
Civil Engineering Department
P.O Box 17000
Jebel Ali

Attn: The Senior Manager Building Permit Section

Project : (List Project details as in Building Permit Description)

Location: Plot No. and Area:

Subject : Request for Building Completion Certificate

The above projects have been substantially completed as per the CED approved
drawings, Building Regulations & Design Guidelines and Building & General Civil
Work Construction Regulations . We assure you that all the required tests have been
done and found satisfactory.

We request CED to inspect the premises and issue Building Completion Certificate.

Thanking you

Yours faithfully

(Signature)

____________
(Designation)
Standard Format-A2:
(Letter Head)

Ref:
Date:

Trakhees
Ports, Customs & Free Zone Corporation (PCFC)
Civil Engineering Department
P.O Box 17000
Jebel Ali

Attn: The Senior Manager Building Permit Section

Project : (Mention the detail of project as in Building Permit Description)

Location: Plot No. and Area

Subject : Undertaking Letter to Process Building Completion Certificate

The above projects have been completed satisfactorily as per the contract terms,
conditions and project specification. We assure you that there are no outstanding issues
related to this project.

We request CED to inspect the premises and issue Building Completion Certificate.

Thanking you

Yours faithfully

(Signature)

____________
(Designation)
Standard Format-A3:
(Consultant Letter Head)

Ref:
Date:

Trakhees
Ports, Customs & Free Zone Corporation (PCFC)
Civil Engineering Department
P.O Box 17000
Jebel Ali

Attn: The Senior Manager Building Permit Section

Project : (List Project details as in Building Permit Description)

Location: Plot No. and Area:

Subject : Request for DEWA Purpose NOC

The above projects have been substantially completed as per the CED approved
drawings, Building Regulations & Design Guidelines and Building & General Civil
Work Construction Regulations . We assure you that DEWA power is required to carry
out the required tests to our satisfaction.

We request CED to inspect the premises and issue DEWA purpose NOC.

Thanking you

Yours faithfully

(Signature)

____________
(Designation)
Standard Format-A4:
(Letter Head)

Ref:
Date:

Trakhees
Ports, Customs & Free Zone Corporation (PCFC)
Civil Engineering Department
P.O Box 17000
Jebel Ali

Attn: The Senior Manager Building Permit Section

Project : (Mention the detail as in NOC Description)

Location: Plot No. / Area

Subject : Undertaking Letter to Process Completion Certificate

The above Modifications / Fitout / Renovation works / Racking Systems have been
completed satisfactorily as per the contract terms, conditions and specifications. We
assure you that there are no outstanding issues related to this work.

We request CED to inspect the premises and issue Completion Certificate.

Thanking you

Yours faithfully

(Signature)

____________
(Designation)
Standard Format-A5:
(Contractor Letter Head)

Ref:
Date:

Trakhees
Ports, Customs & Free Zone Corporation (PCFC)
Civil Engineering Department
P.O Box 17000
Jebel Ali

Attn: The Senior Manager Building Permit Section

Project : (Mention the detail as in NOC Description)

Location: Plot No. / Office Unit No. / Shop No.

Subject : Request for Completion Certificate

The above Modifications / Fitout / Renovation works / Racking Systems have been
substantially completed as per the CED approved drawings and Regulations. We assure
you that all the required tests have been done and found satisfactory.

We request CED to inspect the premises and issue Completion Certificate.

Thanking you

Yours faithfully

(Signature)

____________
(Designation)
Standard Format-A6:

APPLICATION FOR OBTAINING COMPLETION CERTIFICATE

NAME OF CONTRACTOR :______________________________________________

NAME OF CLIENT :______________________________________________

CED* NOC No. :______________________________________________

Description of Work :__________________________________________


(As in CED NOC Subject)
______________________________________________

Email-IDs:-

1. Consultant (if applicable) : ________________________________________

2. Client : ________________________________________

3. Contractor : ________________________________________

Site Engineer / Foreman / Representative :-

Name: ____________________________________________________________

Mob: ____________________________________________________________

Undertaking:
We certify that all the documents are submitted in compliance with List of Documents to
be submitted for completion inspection in pdf. And we confirm that the hard copy of CED
approved drawings, CED-NOC and EHS-NOCs are available at site for verification.

SIGNATURE & STAMP OF


CONSULTANT / CONTRACTOR

CED: Civil Engineering Department 15-Jan-2009

S-ar putea să vă placă și