Daily Report

www.GQIS.co.uk

Project: HPC-HINKLEY POINT C-


AGGREGATE JETTY-
Customer: Egden Murray PRELIMINARY STEEL
PILE PROJECT
Sub-Vendor: ZHEJIANG CHANKONG
Vendor: ESC GROUP
STEEL PIPE CO.,LTD
PUTUO,SHANG HAI, Sub-Vendor Address: TIANNING,JIASHAN,ZHE
Vendor Address:
CHINA JIANG

Vendor Reference: Sub-Vendor Reference:

Purchase Order No: 3568 Customer Reference:

GQIS Assignment No: Report No: GQIS--010

8 am, 2nd Sept. -- 8 pm, Next Visit Date:


Date of Visit:
2nd Sept.,2016
MATERIAL INSPECTED THIS VISIT
Item No. Quantit Description Tag No., Batch No., Serial
No., Cast, Heat No.
y

3568-C04-065 1 914x25x20.233M SSAW


3568-C04-066 1 914x25x20.233M SSAW
3568-C05-067 1 914x25x20.715M SSAW
3568-C05-068 1 914x25x20.715M SSAW
3568-C06-057 1 1778x(25x2.7M+30x5.7M+25x9.689M)
SSAW+LSAW+SSAW

SUMMARY / AREAS OF CONCERN

GUI-036-00 (Revision 0) Flash Report Dated: 22nd March 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

1.0 SUMMARY / AREAS OF CONCERN

1. Patrol inspection for material cutting of main lift padeye, there is no material identification on the padeye,
already inform the manufacturer and they promised to improve it.

Reference: Inspection Test Plan


No.11 Material Identification-material traceability (Marking of material identify, and recording
of heat number for each components)
No.13 Raw material preparation-visual and dimensional inspection

GUI-035-00 (Revision 0) Inspection Report Dated: 22nd March 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

1.2 Witness UT inspection at site, one area has problem and was marked, will be repaired by welding.Pi;e
No.:3568-C06-057.

Reference: Inspection Test Plan


No.22 Welding inspection-UT inspection, 100% of butt weld(spiral weld, longitudinal weld,
CIRC weld)

GUI-035-00 (Revision 0) Inspection Report Dated: 22nd March 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

1.3 Witness MT inspection for ancillaries at site, no findings and the result is accepted.

Reference: Inspection Test Plan


No.23 Welding inspection-Magnetic Particle Inspection, 10% for fillet weld of ancillaries, 100%
for welds mark with W.

GUI-035-00 (Revision 0) Inspection Report Dated: 22nd March 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

1.4 Conduct in-process inspection for production and installation of ancillaries, one findings is that the position of
opening on the pile is too close to the butt welds, this is not a reasonable practice, already instructed the worker at
site and they promised to improve it in the future and take this into consideration. Pile No.: 3568-C04-065, 3568-
C04-066, 3568-C05-067, 3568-C05-068.

Reference: Inspection Test Plan


No.15 Production and installation of ancillary

GUI-035-00 (Revision 0) Inspection Report Dated: 22nd March 2016


Daily Report
www.GQIS.com
Customer: Egden Murray Purchase Order 3568
No.:

Summary: The comments that I proposed are typical, and applicable to all of our products, but not just limited to
the products that I conduct actual inspection.

Accepted Yes Non-Compliant No


Technical Specialist: Robin Gu Operations Coordinator:
Date:
Date: 8 am, 2nd Sept. -- 8 pm, 2nd Sept.,2016

GUI-035-00 (Revision 0) Inspection Report Dated: 22nd March 2016