SPEC. NO.

COASTAL GUJARAT POWER LIMITED SECTION: C15


TCE. 5146A -H -510-02 TITLE 4000 MW UMPP AT MUNDRA
SHEET 1 OF 6
STEAM GENERATOR AND AUXILIARIES CONTRACT
DOCUMENT

DATA/DRAWINGS TO BE FURNISHED BY VENDOR AFTER THE


AWARD OF CONTRACT

The CONTRACTOR will submit the following key drawings/data having


engineering information as a minimum to the ENGINEER according to the
schedule which will be mutually agreed. Certified drawings will be delivered
by the CONTRACTOR not later than three (3) weeks after the approved
drawing are returned to him.

1. General arrangement of steam generator showing floor plans, purpose


of floors, sectional plans, cross sections, rear, front and side
elevations (Details such as staircases, landings, ladders, access
walkways, galleries, ducting etc., should be covered)

2. Boilers safety valve data (No off, size, capacities, set pressures,
over pressures, blow downs, reaction forces, self weights, locations,
drawings, etc.)

3. General arrangement of steam generator auxiliaries indicating location


of all fans, air preheaters, steam generator water circulation pump (if
provided), air and flue gas ducts, etc. and with equipment to comply
with requirement of item 1.02 of Section C1 (coal feeders, coal mills,
reject disposal system etc.)

4. a) Steam generator foundation drawing indicating layout of


columns, column and base plate sizes, location and magnitude
of loads, required for foundation design.

b) Steam generator auxiliary equipment viz. fans etc., outline


drawing with setting dimensions and foundation design.

5. General arrangement as in 1.01 and 1.02 above showing VENDORS


all terminal connections with coordinates and forces and moments at
those points

6. Boiler foundation plan


Boiler auxiliaries Foundation plan

7. Boiler structural steel drawings:

a) Column drawings

b) Horizontal and vertical bracings

c) Roof supporting structure, staircases, landings, walkways, floor


framing plans, interconnecting platforms between steam
generator, elevator and station building, weather cladding
details

8. Boiler piping terminal points schedule (as per TCE format)


ISSUE
R1
SPEC. NO. COASTAL GUJARAT POWER LIMITED SECTION: C15
TCE. 5146A -H -510-02 TITLE 4000 MW UMPP AT MUNDRA
SHEET 2 OF 6
STEAM GENERATOR AND AUXILIARIES CONTRACT
DOCUMENT

9. General arrangement of air and flue gas duct and breaching with load.

10. Recommended routing of critical piping in boiler area and


recommended location of safety valves, main steam stop valve,
desuperheater.

11. Boiler cold and hot startup curves.

12. Writeup on chemical cleaning and steam-blow out

13. Pressure parts drawing and details pressure part calculations required
for approval of the local steam generator inspector with materials used
and temperatures which the elements are designed to withstand.

14. Speed/torque curves for fans with dampers/blades closed and wide
open.

15. General arrangement of fuel oil pumps and heaters, outline and
foundation drawings.

16. Damper schedule indicating torque requirement make, type, angle of


travel, number of motor drives, quantity and scope

17. Desuperheater location and details (dimensions, self weight,


drawings)

18. Desuperheater piping layout with elevations in plan and section with
steam temperature control station

19. Soot blower layout location showing movement of and terminal sizes
including hanger and support details.

20. Water volumes of pressure parts and water volume of reheater

21. General arrangement drawing of fuel oil/gas and ignition oil/gas


burning system with piping, ducting, valves etc. around burners with
details of burners.

22. General arrangement drawing of coal burning system with piping


ducting, valves etc. around burners with details of burners to comply
with the requirement .

23. Fuel oil flow, pressure and compressed air requirement around burner

24. Auxiliary steam requirements

25. Performance curves of fans and pumps

26. Outline showing location of all thermocouples for steam drum and
SH/RH/Economiser tube and header thermocouple and terminal
junction boxes.
ISSUE
R1
SPEC. NO. COASTAL GUJARAT POWER LIMITED SECTION: C15
TCE. 5146A -H -510-02 TITLE 4000 MW UMPP AT MUNDRA
SHEET 3 OF 6
STEAM GENERATOR AND AUXILIARIES CONTRACT
DOCUMENT

27. a) Outline locating the PURCHASERS electrical connections,


junction boxes and terminal blocks

b) Detail electrical connection diagram showing location, size and


marking-up of all the PURCHASERS connections

28. Final list of motors including voltage, phase, kilowatt, service and
location etc. as per the ENGINEERS format

29. Schedule of valves and fittings on all systems including requirement of


boil-out, acid cleaning and steam blow-out; details drawing of motor
operated valves and safety valves.

30. Allowable forces and moments and initial movement data for critical
piping.

31. Final list of auxiliary cooling water and compressed air requirements

32. Details of specification of insulating materials, procedure for applying


insulation, reinforcement, cladding sheet finishing method, curing and
setting.

33. Calculation for thermal insulation thickness and thickness envisaged


for various parts of steam generator and piping

34. Cross section drawing of steam generator showing the gas velocities
in meters/second for each tube bank, duct and breaching and gas
temperature entering various key locations at 100% steam generator
MCR

35. Details of isolation dampers wherever applicable

36. Detailed writeup on boil-out, acid cleaning and steam blowout


procedures

37. Information on operating procedures essential to engineer Data


Acquisition System

38. Erection Instruction Manual

39. Drawings of equipment to be supplied by CONTRACTOR for


mounting on PURCHASERS pipe lines

40. Basic scope drawing for power and signal cables, air supply piping
and pneumatic tubine

41. Flow scheme drawings indicating recommended measurement and


control for SG Systems and auxiliaries clearly indicating scope of
supply.
ISSUE
R1
SPEC. NO. COASTAL GUJARAT POWER LIMITED SECTION: C15
TCE. 5146A -H -510-02 TITLE 4000 MW UMPP AT MUNDRA
SHEET 4 OF 6
STEAM GENERATOR AND AUXILIARIES CONTRACT
DOCUMENT

42. Schedule of measurements complete with scope of supply, operating


parameters, make, model, range, line/duct sizes, connection details,
types of thermocouples/RTD, and signalling contact requirements

43. a) Write-up, recommended schemes for the automatic controls to


be provided by PURCHASER for SG Systems and auxiliaries

b) SG dynamics, model tests data and any data required by I & C


Vendor for all SG controls provided by PURCHASER

44. Write up and recommended logic schemes for interlock, protection


and sequential controls to be provided by PURCHASER for SG
Systems and auxiliaries.

45. Performance measurement scheme complete with measurement


points and type of connection, etc.

46. Schedule of alarm and trip functions complete with initiating device
details indicating the scope.

47. List of analogue input signals for Data Acquisition system (DAS)
indicating the scope

48. List of contact (Digital) input signals for DAS indicating the scope

49. List of inputs (analogue/contact) required from PURCHASERS


systems to SG systems and auxiliaries

50. List of outputs (analogue/contacts) provided in SG and auxiliary


systems to PURCHASERS systems

51. Schemes and writeup for the automatic controls and interlock
protection, and sequential controls supplied by CONTRACTOR for SG
System and auxiliaries

52. Instrument air requirement indicating pressure and quantity of flow for
intermittent and continuous services and power supply requirement for
panels/cubicles/cabinets/ console insert/instruments under
CONTRACTOR scope

53. SG drum instrument tapping point details

54. Characteristics of primary flow elements included under


CONTRACTOR scope and flow, inlet pressure and pressure drop
conditions at various loads for control valves (by OTHERS) coming in
CONTRACTORs piping scope.

55. Characteristics of temperature elements included under


CONTRACTORs scope

ISSUE
R1
SPEC. NO. COASTAL GUJARAT POWER LIMITED SECTION: C15
TCE. 5146A -H -510-02 TITLE 4000 MW UMPP AT MUNDRA
SHEET 5 OF 6
STEAM GENERATOR AND AUXILIARIES CONTRACT
DOCUMENT

56. Electrical ratings of contact inputs from PURCHASERS systems to


CONTRACTORs system

57. Electrical ratings of contact outputs from CONTRACTORs system to


PURCHASERS systems

58. Signal range, input impendence of analogue inputs from


PURCHASERS system to CONTRACTORs system.

59. Signal range, output impedence and signal verses parameter


characteristics for the analogue outputs from CONTRACTORs
systems to PURCHASERS systems

60. Electrical data such as voltage, ratings, in rush and hold on current for
solenoid valves included their scope.

61. Bill of Material and drawings indicating cutout and overall dimensional
details of console inserts / instruments / hardware supplied by SG
CONTRACTOR for mounting on PURCHASERS panel/desks.

62. List and general arrangement of panels, cubicles, cabinets under SG


CONTRACTORs scope, complete with dimensional details, floor
cutout requirement, mounting details, weight with equipment mounted,
maximum door swing, etc

63. Heat release rate for panels, cabinets, cubicles, etc. under
CONTRACTORs scope.

64. List of alarm and trip setting

65. List of settings for the various timer used in the interlock, protection
and sequential control systems for SG auxiliary systems provided by
PURCHASER

66. Wiring diagrams for console inserts/ instruments / hardware supplied


by CONTRACTOR and are mounted on PURCHASERS Panel/Desk

67. Wiring diagram for panels/cubicles/cabinets under SG VENDORS


scope

68. List and General Arrangement drawing of field mounted junction


boxes/ enclosures/transmitter racks/local Panels including external
wiring diagram and terminal details under CONTRACTORs

69. Physical location of instrument tappings, control vavles, dampers on


piping/ducting/equipments under CONTRACTORs scope clearly
indicating the accessibility plateforms

70. Certified data sheets dimensional drawings for field mounted


instruments and panels under CONTRACTORs scope indicating the
connection details and maintenance space requirements.
ISSUE
R1
SPEC. NO. COASTAL GUJARAT POWER LIMITED SECTION: C15
TCE. 5146A -H -510-02 TITLE 4000 MW UMPP AT MUNDRA
SHEET 6 OF 6
STEAM GENERATOR AND AUXILIARIES CONTRACT
DOCUMENT

71. Installation drawing and Bill of Material for the instruments covered in
CONTRACTORs scope

Note: CONTRACTOR will provide all necessary drawings and


documents required for interface engineering with Turbine, BOP DCS
and HP bypass valve VENDORs.

ISSUE
R1