SERIAL DESCRIPTION UNITS QTY RATE AMOUNT
NO
Earthworks
A. Grab and uproot vegetation, excavate
over the site to remove vegetative soils
up to a depth of not exceeding 200mm SM 30 400 12,000
B. Extra excavation on strip footing not
exceeding 1500mm. CM 40 400 16,000
C. Remove and cart away material
excavated from site to provide clear
working space. CM 30 400 12,000
D. Return, fill and ram selected excavated
soils around the foundations. CM 40 400 16,000
E. Base roller compacting ready to
receive hardcore. SM 30 200 6,000
F. Approved hardcore compacted into
layers of 150mm in small sizes. CM 10 1,500 15,000
G. 50mm stone/Quarry dust blinding. SM 30 300 9,000
H. Allow for approved Anti-termite
(Gladiator). SM 30 200 6,000
I. 100 gauge polythene sheet. SM 30 200 6,000

Concrete
A. 50 mm concrete blinding (1:4:8) SM 20 500 10,000
B. Vibrated concrete (1:2:4) on strip
footing and the ring beam. CM 5 12,500 62,500
C. 150mm thick concrete (1:2:4) for the
floor slab. CM 6 12,500 75,000

Formwork.
A. Sawn formwork to strip footing and
floor slab. SM 8 500 4,000
B. Sawn formwork for side of the beam. SM 12 500 6,000

Steelworks
A. BRC mesh A142 for the floor slab. SM 30 500 15,000
B. Steel bars Y12mm Diameter KG 105 160 16,800
Y10mm Diameter KG 65 160 10,400
Y 8 mm Diameter KG 52 160 8,320