Analysis of factors influencing construction cost overruns in large construction projects of Tamilnadu
The purpose of this study is to critically review and To suggest some recommendations for the significant
identify the applicability of past studies on determining the factors to improve performance index of construction projects
factors causing cost overrun in current projects. This paper in Tamil Nadu.
attempts to identify the major factors of cost overrun in
construction practice of Tamil Nadu and can serve as the way III. DATA COLLECTION AND ANALYSIS
forward for future work in coping with these overruns.
Data collection was carried out by conducting a
II. RESEARCH METHODOLOGY questionnaire survey for identifying significant factors
affecting construction cost performance among contractors
The methodology of the study is as follows: and Engineers for accessing the significant factors of the
1. A thorough literature review was done and also the expert factors. A five point likert scale of 1-5 was adopted to assess
opinions from industry experts were taken, through which a the degree of agreement of each cause where 1 represents
number of cost overrun causes were identified in Tamil Nadu Strongly disagree, 2 - disagree, 3- moderately agree,
construction industry scenario. In total fifty four factors were 4-agree and 5-strongly agree. A total of 60 respondents
finalized to make part of the survey questionnaire. participated in the survey process. Statistical package for
2. A Questionnaire form which is consisting of two parts A social sciences was used to analyze the data. Data was
and B has been developed. In Part A personal Information of checked for reliability prior to ranking the factors. This
the respondents (for e.g. work experience, organization, four-point scale was converted to a Relative Importance Index
annual volume of construction work) was asked. Part B was (RII) for each individual factor,
aimed to obtain information about causes of cost overrun in Using the following formula, as adopted by
TamilNadu construction industry. It was asked to rate those Kumaraswany and Chan (1997, 1998), Assaf et al (1995) and
initially identified 54 factors according to their severity level Iyer and Jha (2005):
on the given scale, information regarding maximum, average Relative importance index
and minimum cost overrun ranges experienced over large (RII) = W (H x N) (1)
projects and average overruns over small projects were asked. Where W is the total weight given to each factor by the
3. Thirty (30) private Engineers and Thirty (30) Government respondents, which ranges from 1 to 5 and is calculated by an
Engineers have been approached for this study. addition of the various weightings given to a factor by the
4. Analysis has been carried out using SPSS (Statistical entire respondent, H is the highest ranking available (i.e. 5 in
package for social sciences) using the assessment of feedback this case) and N is the total number of respondents that have
from questionnaire survey. answered the question. Demographic characteristics of
5. Some mitigating measures have been developed for the respondents are District engineers and private contractors of
major influencing factors which can be used in assisting the Thiruvannamalai, Cuddalore, Chengalpattu and Chennai.
project managers to have a better control on their projects. From Table 1, the total years experience of the respondents is
The specific objectives include: 1350 with an average of 22.5.
To identify the variables influencing time and cost overruns
in construction projects and to evaluate their relative
importance. IV. QUESTIONNAIRE DEVELOPMENT
To examine the collective group perspectives (Government
Engineers and private Engineers ) points of view on the A comprehensive literature was conducted to identify the
relative significance of these factors. major factors affecting construction cost. Table 1 shows the
To evaluate the degree of agreement/disagreement in frequency of top twelve factors affecting construction cost.
ranking these factors.
Table. 1: Preliminary Ranking Factors affecting Construction Cost
43 www.erpublication.org
International Journal of Engineering and Technical Research (IJETR)
ISSN: 2321-0869, Volume-2, Issue-11, November 2014
44 www.erpublication.org
Analysis of factors influencing construction cost overruns in large construction projects of Tamilnadu
45 www.erpublication.org
International Journal of Engineering and Technical Research (IJETR)
ISSN: 2321-0869, Volume-2, Issue-11, November 2014
46 www.erpublication.org
Analysis of factors influencing construction cost overruns in large construction projects of Tamilnadu
and the design of the project in a good way to avoid delay in [17] Lee S., Thomas S., Tucker R., The relative impacts of selected
obtaining permits from municipality. Owners are also advised practices on project cost and schedule , Construction Management and
Economics, 23 (5), 2005, pp. 545-553.
not to pass always some change orders in the construction [18] Moura, H.P., J.C. Teixeira and B. Pires, Dealing With Cost and Time
activities and not to delay the payments for the work in the Portuguese Construction Industry, CIB World Building
concerned persons. Finally to carry out the cost planning Congress, 2007 ,pp. 1252-1265.
successfully during pre and post contract stages in all the [19] Memon, A.H., I.A. Rahman, M.R. Abdullah and A.A.A. Azis, Factors
construction activities from the start to finish in a better way, affecting construction cost in MARA large construction projects:
Perspective of project management consultants, Int. J. Sustainab.
soft wares like Primavera, MS project can be also used to
Construct. Eng. Technol., 1(2): 2010, pp 41-54.
schedule the various construction activities and thus to predict [20] Sambasivan M. and Soon Y., Causes and effects of delays in
and control the cost overruns in the construction projects. Malaysian construction industry, International Journal of Project
Management, Vol.25,No.5, 2007, pp. 517-526.
ACKNOWLEDGEMENT [21] Olawale, Y.A. and M. Sun,. , Cost and time control of construction
projects: Inhibiting factors and mitigating measures in practice,
Construct. Manag. Econ., 28(5): 2010, pp 509- 526
The authors are thankful to the District Engineers and
Private Engineers for providing their valuable suggestions Details of authors:
required to carry out this work.
First author:
REFERENCES
[1] Abdullah, M.R., A.A.A. Azis and I.A. Rahman, Causes of delay and its
effects in large MARA construction project, Int.
J. Integr. Eng., 1(1) 2009.
[2] Aftab Hameed Memon, Ismail Abdul Rahman, Mohd Razak Abdullah,
Shreenaath, AbrahamLincon, M.E.,construction engineering and
Ade Asmi Abdu Azis, Factors Affecting
management Annamalai University, TamilNadu,India.
Construction Cost in Mara Large Construction Project: Perspective of
Project Management Consultant, International
Journal of Sustainable Construction Engineering & Technology Vol 1, Second Author:
No 2, 2010, pp. 41-54.
[3] Al-Hammad, A, Factors affecting the relationship between contractors
and their sub-contractors in Saudi Arabia , Building Research and
Information, 21(5), 1993, pp.26973.
[4] Aibinu, A. and Jagboro, G, The effects of construction delays on project
delivery in nigerian construction industry,
International Journal of Project Management, 20(8), 2002, pp. 59399.
[5] Arditi, D., Akan, G., Gurdamar, S. , Cost overruns in public projects ,
Arunmozhi, Subramanian, B.E.,M.E.,
International Journal of Project Management 3
(4), pp.218-224. Assistant professor in civil and structural engineering department,
[6] Avots, I. (1983). Cost-Relevance Analysis for Overrun Control. Annamalai University,TamilNadu,India
International Journal of ProjectManagement, Vol.1
No.3, 1985 142-148. Third and Corresponding Author:
[7] Azhar N, Farooqui RU and Ahmed SM, Cost overrun factors in
construction industry in Pakistan, First international conference on
construction in developing countries ICCIDC-I, advancing and
integrating construction education, research and practice, 2008.
[8] Angelo, W. J., & Reina, P , Megaprojects Need More Study Up Front to
Avoid Cost Overruns, 2002
[9] Cooke, B. and Williams, P. Construction planning programming and
control. Blackwell publishing, 2004 Oxford. Sivagamasundari, Ranganathan.,B.E.,M.E.,Ph.D.,
[10] Elinwa, A.U. and S.A. Buba,. Construction cost factors in Nigeria. J. Assistant professor in civil and structural engineering department,
Construct. Eng.Manag., 119(4): 1993 698-713. Annamalai University,TamilNadu,India
[11] Enshassi, J. Al-Najjar, and M. Kumaraswamy, Delays and cost Mobile no: 9443992262
overruns in the construction projects in the Gaza Strip, Journal of Membership of Professional Bodies : 1. Life Member of Institution
Financial Management of Property and Construction, Vol. 14 No. 2, of Engineers (IEI)-M/128013/3
2009, pp. 126-151. 2. Life Member of Indian concrete Institute (ICI) LM 8436.
[12] Flyvbjerg, B., M.K.S. Holm and S.L. Buhl, How common and how
large are cost overruns in transport infrastructure projects?, Trans.
Rev., 23(1): 2003, pp.71-88.
[13] Frimpong, J. Oluwoye, L. Crawford, Causes of delay and cost
overruns in construction of groundwater projects in a developing
countries; Ghana as a case study, International Journal of project
management, 2003, pp.321-326.
[14] Hissani .A. Basioni, Cost overruns related to the design phases in the
Egyptian construction industry, Journal of Engineering Management
Research, Vol.1 No.5, 2013, pp 138-147.
[15] Kaming, P.F. , Olomolaiye, P.O. , Holt, G. D. , & Harris, F. C.,
Factors Influencing Construction Time and Cost Overruns on High-rise
Projects in Indonesia, Construction Management and Economics,
Vol.15, No.1, 1997, pp. 83-94.
[16] Koushki, P. A., Al-Rashid, K and Kartam, N, Delays and cost
increases in the construction of private residential projects in Kuwait,
Construction Management and Economics, 23, 2005, pp. 285-294.