Documente Academic
Documente Profesional
Documente Cultură
AbstractAs new power plants commit to once-through supercritical boilers and rush to come on line,
engineering, procurement, and construction (EPC) turnkey contractors face both a short-term and long-term
chemistry dilemma related to oxygenated treatment (OT) during normal long-term operation. Since most
industry experience is based on converting existing once-through boilers from all volatile treatment (AVT) OT,
relatively little information exists on newer boilers operating on OT. Electric Power Research Institute (EPRI)
all volatile treatment oxidizing (AVT[O]) and all volatile treatment reducing (AVT[R]) startup guidelines
facilitating conversion to OT are sound but untested on new boilers and do not address considerations like
cycles without deaerators, which must be treated on a case-by-case basis. The startup and commissioning cycle,
including startup on AVT and quick conversion to OT, is the EPC turnkey contractors responsibility. To
ensure efficient startup and commissioning of once-through supercritical boilers, the EPC turnkey contractor
must address these chemistry issues and develop a practical approach to achieving steam purity and specified
feedwater chemistry requirements.
Keywordsaction level, all volatile treatment (AT); all volatile treatment (oxidizing) (AVT[O]); all volatile
treatment (reducing) (AVT[R]); American Society of Mechanical Engineers (ASME); coal-fired power plants;
chemistry guidelines; commercial operation; condensate polishers; Electric Power Research Institute (EPRI);
engineering, procurement, and construction (EPC) contractor; lump-sum, turnkey (LSTK); once-through
boilers; oxygenated treatment (OT); risk assessment, startup; steam and cycle chemistry; steam purity;
supercritical
T he engineering, procurement, and the past 15 years, supplier and industry group
construction (EPC) contractor may ensure chemistry limits have been re-evaluated and
efficient once-through supercritical boiler startup revised for once-through supercritical boilers.
and commissioning by developing practical Revisions include operating under various
Kathi Kirschenheiter steam purity chemistry limits and a timely, control modes, such as oxygenated treatment
workable approach to meeting these limits. (OT) and all volatile treatment (AVT). Operators,
kakirsch@bechtel.com
Once-through supercritical boiler chemistry is engineers, and turnkey contractors have also
uncontrollable by boiler blowdown; therefore, reviewed chemistry limit guidelines. Further
Michael Chuk constant, stringent chemistry control is required. examination of revised chemistry guidelines
Significant operation outside boiler and turbine show that specified chemistry constraints can be
mjchuk@bechtel.com achieved during operation using full-flow, online
manufacturer chemistry limits may void the
warranty, leaving the owner/EPC contractor condensate polishers with timely regenerations.
solely responsible for all costs associated with However, during commissioning, it is difficult
Colleen Layman
repairs required within the warranty period. to ensure that these stringent limits are met
cmlayman@bechtel.com without allowing for an uncharacteristically long
In addition to boiler and turbine supplier
startup time.
warranty-related water quality and steam purity
Kumar Sinha limits, various industry groups (e.g., American Most chemistry control guidelines developed
ksinha@bechtel.com Society of Mechanical Engineers [ASME], by industry groups address plant operation
VGB PowerTech, and Electric Power Research after commissioning and initial startup. These
Institute [EPRI]) have developed standards that guidelines include action levels outlining
represent industry consensus on good, prudent acceptable chemistry deviations based on hours of
M
ensure that all construction debris is removed ost once-through supercritical boilers in the
from the system upon completion, and US have been converted from previously
cleanliness is maintained during component predominant AVT to OT, with new facilities almost
installation by capping pipe ends and cleaning exclusively using OT. This chemistry change
weld areas. pH-adjusted demineralized water requires all-ferrous metallurgy in the feedwater
is recommended during boiler, condensate, train, and precludes copper or copper-based alloy
and feedwater system components and piping feedwater heat exchangers in system design and
flushing and hydrotesting to eliminate potential bronze impellers in condensate pumps and valve
scaling and deposits. Potable quality water is trims in the condensate system. The benefits from
acceptable for flushing and hydrotesting if a operating a once-through supercritical boiler on
thorough chemical cleaning of components OT include: Most
follows flushing and hydrotesting, and if a once-through
Lowering overall corrosion rates by forming
pH-adjusting chemical or silica-free VPCI is
a protective, double-oxide layer with a supercritical boilers
added to flush or hydrotest water.
controlled amount of oxygen present in the in the US
Following flushing and hydrotesting, boiler, condensate (This protective layer is considered
have been
condensate and feedwater systems should be to be more stable than the oxide layer formed
chemically cleaned using demineralized water using AVT.) converted from
as the chemical dilution medium. After cleaning, Decreasing boiler chemical cleaning frequency previously
boiler and feedwater systems should be flushed due to reduced amounts of iron transport and predominant
with pH-adjusted demineralized water treated deposition AVT to OT.
with a suitable, silica-free VPCI. Chemical
Allowing quicker, cleaner startups and
cleaning is essential to the chemistry control
reduced corrosion product transport rates
program as it improves boiler chemistry
during cold and hot startups
stability by safely removing all deposits from
inside boiler tubes (including organics from Allowing boiler operation at lower pH with
manufacturing; rust, mill scale, and welding slag overall objective of minimizing chemical
from construction; and residual contaminants costs
from hydrotesting). Eliminating feeding, handling, and storage of
oxygen scavenger products
Finally, the EPC contractor must meet agreed-
upon chemistry limits in a timely fashion and To achieve these overall short- and long-term
complete system steamblows. Steamblows, which objectives, chemistry controls must be tightened
clear final debris and surface scale from the during startup and commissioning. However,
steam side of the system through thermal tighter chemistry controls add extra time to
cycling and physical force of steam through the the already tight startup schedule, and longer
components, are the final step in ensuring steam startup time equates to lost revenue.
chemistry meets required limits. Steamblows
Some once-through supercritical boiler
should be conducted using pH-adjusted
manufacturers have instituted penalties against
demineralized water.
the allowable pressure drop during initial boiler
Bechtel contends that startup chemistry guidelines performance testing, an additional complication
should primarily focus on main steam chemistry that may impact startup and commissioning
targets, including cation conductivity, silica, activities. These penalties are based on extended
and sodium, as they are easily and reliably operation on all volatile treatment reducing
measured using relatively inexpensive online (AVT[R]) during startup and commissioning.
instrumentation. Targets for chlorides, sulfates, The reducing environment (negative oxidation-
and organic compounds should be deferred until reduction potential [ORP]) present when operating
the end of the commissioning cycle. Degassed on AVT(R) may contribute to increased iron
cation conductivity is the preferred conductivity to transport, subsequently increasing the pressure
be measured during commissioning since system drop through the boiler. These pressure drop
air leaks are still being discovered and sealed correction penalties will be fervently debated by
during the startup and commissioning phase. The the EPC contractor during commissioning and
measurement of degassed cation conductivity challenged by both owners and plant operators.
will aid in differentiating between air leaks and
other contamination sources.