Sunteți pe pagina 1din 10

CONTROLLING CHEMISTRY DURING

STARTUP AND COMMISSIONING


OF ONCE-THROUGH
SUPERCRITICAL BOILERS
Originally Issued: October 2007
Updated: December 2008

AbstractAs new power plants commit to once-through supercritical boilers and rush to come on line,
engineering, procurement, and construction (EPC) turnkey contractors face both a short-term and long-term
chemistry dilemma related to oxygenated treatment (OT) during normal long-term operation. Since most
industry experience is based on converting existing once-through boilers from all volatile treatment (AVT) OT,
relatively little information exists on newer boilers operating on OT. Electric Power Research Institute (EPRI)
all volatile treatment oxidizing (AVT[O]) and all volatile treatment reducing (AVT[R]) startup guidelines
facilitating conversion to OT are sound but untested on new boilers and do not address considerations like
cycles without deaerators, which must be treated on a case-by-case basis. The startup and commissioning cycle,
including startup on AVT and quick conversion to OT, is the EPC turnkey contractors responsibility. To
ensure efficient startup and commissioning of once-through supercritical boilers, the EPC turnkey contractor
must address these chemistry issues and develop a practical approach to achieving steam purity and specified
feedwater chemistry requirements.
Keywordsaction level, all volatile treatment (AT); all volatile treatment (oxidizing) (AVT[O]); all volatile
treatment (reducing) (AVT[R]); American Society of Mechanical Engineers (ASME); coal-fired power plants;
chemistry guidelines; commercial operation; condensate polishers; Electric Power Research Institute (EPRI);
engineering, procurement, and construction (EPC) contractor; lump-sum, turnkey (LSTK); once-through
boilers; oxygenated treatment (OT); risk assessment, startup; steam and cycle chemistry; steam purity;
supercritical

INTRODUCTION practice for cycle chemistry control. Within

T he engineering, procurement, and the past 15 years, supplier and industry group
construction (EPC) contractor may ensure chemistry limits have been re-evaluated and
efficient once-through supercritical boiler startup revised for once-through supercritical boilers.
and commissioning by developing practical Revisions include operating under various
Kathi Kirschenheiter steam purity chemistry limits and a timely, control modes, such as oxygenated treatment
workable approach to meeting these limits. (OT) and all volatile treatment (AVT). Operators,
kakirsch@bechtel.com
Once-through supercritical boiler chemistry is engineers, and turnkey contractors have also
uncontrollable by boiler blowdown; therefore, reviewed chemistry limit guidelines. Further
Michael Chuk constant, stringent chemistry control is required. examination of revised chemistry guidelines
Significant operation outside boiler and turbine show that specified chemistry constraints can be
mjchuk@bechtel.com achieved during operation using full-flow, online
manufacturer chemistry limits may void the
warranty, leaving the owner/EPC contractor condensate polishers with timely regenerations.
solely responsible for all costs associated with However, during commissioning, it is difficult
Colleen Layman
repairs required within the warranty period. to ensure that these stringent limits are met
cmlayman@bechtel.com without allowing for an uncharacteristically long
In addition to boiler and turbine supplier
startup time.
warranty-related water quality and steam purity
Kumar Sinha limits, various industry groups (e.g., American Most chemistry control guidelines developed
ksinha@bechtel.com Society of Mechanical Engineers [ASME], by industry groups address plant operation
VGB PowerTech, and Electric Power Research after commissioning and initial startup. These
Institute [EPRI]) have developed standards that guidelines include action levels outlining
represent industry consensus on good, prudent acceptable chemistry deviations based on hours of

2008 Bechtel Corporation. All rights reserved. 1


ABBREVIATIONS, ACRONYMS, AND TERMS
ACC air-cooled condensers EPRI Electric Power Research Institute
ASME American Society of Mechanical LSTK lump-sum, turnkey
Engineers
ORP oxidation-reduction potential
AVT all volatile treatment
OT oxygenated treatment
AVT(O) all volatile treatment (oxidizing)
VPCI vapor phase corrosion inhibitor
AVT(R) all volatile treatment (reducing)
EPC engineering, procurement, and
construction
The sooner
full-load
turbine roll operation outside recommended chemistry limits, steam chemistry. Although increasing blowdown
is reached, and are valuable tools for operators. Action levels and makeup demineralized water to the cycle is
and allowable hours of chemistry excursion are effective for cleaning drum boilers, these simple
the sooner
implemented to protect power plant components cleaning methods are not practical for once-
target feedwater from corrosion; however, controlling chemistry through supercritical boilers. As demonstrated
chemistry and during startup and commissioning of once- in numerous startups, full-load turbine roll will
steam purity through supercritical boilers and steam-related dilute concentrated pockets of impurities in
systems is a completely different scenario. the feedwater system and uniformly mix
may be achieved.
feedwater with condensate. Therefore, the sooner
full-load turbine roll is reached, the sooner
CHEMISTRY CONTROL PHILOSOPHY FOR target feedwater chemistry and steam purity
ACHIEVING STEAM PURITY may be achieved.

T he EPC contractor may ensure that


chemistry limits are met during and after
once-through supercritical boilers commissioning
Before awarding a contract (boiler or turbine),
the EPC contractor should negotiate startup and
commissioning feedwater quality and steam
by implementing the following steps: purity guidelines with the boiler and turbine
Control system component cleanliness suppliers to ensure that long-term warranties are
during shop fabrication not voided during startup and commissioning
Control system component cleanliness activities. In addition, industry standard steam
during construction purity guidelines for operation should be relaxed
to the most practical limits feasible during
Flush system components prior to startup
commissioning, while considering the owners
Implement stringent water quality long-term warranty interests.
requirements for hydrotesting
Perform boiler and feedwater system
chemical cleaning EPC CONTRACTORS CHEMISTRY CONTROL
Flush system components thoroughly PROGRAM
following chemical cleaning
Perform steamblows to obtain steam cycle T he EPC contractors chemistry control program
must start at the equipment manufacturers
fabricating facilities where cleanliness methods
cleanliness
for boiler tubes and other system components
Implement time-based, progressively
are initiated. To ensure that system components
improving feedwater and steam chemistry
have been kept clean during fabrication,
targets
contract-negotiated cleaning and inspection
Boiler and feedwater system startup cleaning procedures should be implemented. Hydrotesting
issues depend on boiler type, heat exchanger components in the shop using pH-adjusted
equipment type and metallurgy, and success demineralized water to maintain component
of pre-commissioning cleanliness measures. cleanliness followed by a final rinse with a
Without industry standard guidelines for power silica-free, vapor phase corrosion inhibitor
plant component cleaning methods, the EPC (VPCI) to reduce corrosion from residual
contractor must implement its own methods to moisture after shop cleaning or hydrotesting
quickly achieve and control boiler feedwater and is recommended.

2 Bechtel Technology Journal


Next, the EPC contractor must implement ONCE-THROUGH BOILER STARTUP CHEMISTRY
cleanliness methods during field fabrication to TRENDS

M
ensure that all construction debris is removed ost once-through supercritical boilers in the
from the system upon completion, and US have been converted from previously
cleanliness is maintained during component predominant AVT to OT, with new facilities almost
installation by capping pipe ends and cleaning exclusively using OT. This chemistry change
weld areas. pH-adjusted demineralized water requires all-ferrous metallurgy in the feedwater
is recommended during boiler, condensate, train, and precludes copper or copper-based alloy
and feedwater system components and piping feedwater heat exchangers in system design and
flushing and hydrotesting to eliminate potential bronze impellers in condensate pumps and valve
scaling and deposits. Potable quality water is trims in the condensate system. The benefits from
acceptable for flushing and hydrotesting if a operating a once-through supercritical boiler on
thorough chemical cleaning of components OT include: Most
follows flushing and hydrotesting, and if a once-through
Lowering overall corrosion rates by forming
pH-adjusting chemical or silica-free VPCI is
a protective, double-oxide layer with a supercritical boilers
added to flush or hydrotest water.
controlled amount of oxygen present in the in the US
Following flushing and hydrotesting, boiler, condensate (This protective layer is considered
have been
condensate and feedwater systems should be to be more stable than the oxide layer formed
chemically cleaned using demineralized water using AVT.) converted from
as the chemical dilution medium. After cleaning, Decreasing boiler chemical cleaning frequency previously
boiler and feedwater systems should be flushed due to reduced amounts of iron transport and predominant
with pH-adjusted demineralized water treated deposition AVT to OT.
with a suitable, silica-free VPCI. Chemical
Allowing quicker, cleaner startups and
cleaning is essential to the chemistry control
reduced corrosion product transport rates
program as it improves boiler chemistry
during cold and hot startups
stability by safely removing all deposits from
inside boiler tubes (including organics from Allowing boiler operation at lower pH with
manufacturing; rust, mill scale, and welding slag overall objective of minimizing chemical
from construction; and residual contaminants costs
from hydrotesting). Eliminating feeding, handling, and storage of
oxygen scavenger products
Finally, the EPC contractor must meet agreed-
upon chemistry limits in a timely fashion and To achieve these overall short- and long-term
complete system steamblows. Steamblows, which objectives, chemistry controls must be tightened
clear final debris and surface scale from the during startup and commissioning. However,
steam side of the system through thermal tighter chemistry controls add extra time to
cycling and physical force of steam through the the already tight startup schedule, and longer
components, are the final step in ensuring steam startup time equates to lost revenue.
chemistry meets required limits. Steamblows
Some once-through supercritical boiler
should be conducted using pH-adjusted
manufacturers have instituted penalties against
demineralized water.
the allowable pressure drop during initial boiler
Bechtel contends that startup chemistry guidelines performance testing, an additional complication
should primarily focus on main steam chemistry that may impact startup and commissioning
targets, including cation conductivity, silica, activities. These penalties are based on extended
and sodium, as they are easily and reliably operation on all volatile treatment reducing
measured using relatively inexpensive online (AVT[R]) during startup and commissioning.
instrumentation. Targets for chlorides, sulfates, The reducing environment (negative oxidation-
and organic compounds should be deferred until reduction potential [ORP]) present when operating
the end of the commissioning cycle. Degassed on AVT(R) may contribute to increased iron
cation conductivity is the preferred conductivity to transport, subsequently increasing the pressure
be measured during commissioning since system drop through the boiler. These pressure drop
air leaks are still being discovered and sealed correction penalties will be fervently debated by
during the startup and commissioning phase. The the EPC contractor during commissioning and
measurement of degassed cation conductivity challenged by both owners and plant operators.
will aid in differentiating between air leaks and
other contamination sources.

December 2008 Volume 1, Number 1 3


EPRI OT CHEMISTRY GUIDELINES Table 2. EPRI Feedwater Chemistry Control Guidelines for
Once-Through Boilers on OT [1]

D uring steam-side startup and commissioning,


the EPC contractor is mostly interested in
main and reheat steam chemistry. Table 1 lists
Parameter
Cation Conductivity, S/cm
Normal Limit
0.15
EPRI recommendations for once-through boilers pH, STU 8.0 to 8.5
operating under OT, including normal target Dissolved Oxygen at Economizer Inlet, ppb 30 to 150
value and action levels 1, 2, and 3. Iron, ppb 2
Ammonia, ppm 0.02 to 0.07
Table 1. EPRI Recommendations for Main and Reheat
Steam Chemistry for Once-Through Boilers on OT [1]
The two most important parameters in
Target Table 2 are feedwater cation conductivity and pH.
Action Levels
Parameter Value
The Cation conductivity should be maintained below
pH/conductivity N 1 2 3 0.15 S/cm during operation on OT. Normal pH
Cation Conductivity, S/cm 0.15 0.3 0.6 >0.6 range for feedwater under OT is 8.0 to 8.5. The
relationship
Silica, ppb 10 20 40 >40 EPC contractor is challenged with controlling
is crucial for pH when feedwater cation conductivity
Sodium, ppb 2 4 8 >8
once-through Chloride, ppb 2 4 8 >8 increases to concentration levels listed in
cycles on OT. Sulfate, ppb 2 4 8 >8 Table 1, action levels 1, 2, and 3 (0.3 S/cm,
0.6 S/cm, >0.6 S/cm, respectively). [1]
TOC, ppb 100 >100
Controls for pH and cation conductivity are
discussed in boiler and steam turbine startup
Table 1 includes three parameters requiring documents; however, these chemistry control
special consideration during commissioning: guidelines are not always consistent. The
cation conductivity, silica, and sodium. pH/conductivity relationship is crucial for
Monitoring cation conductivity is essential since once-through cycles on OT; thus, the EPC
it warns of salts and acids that may cause turbine contractor implements the chemistry control at
corrosion. Controlling silica levels in the steam its own risk.
is important as silicate scaling may contribute to Important issues to be addressed when
turbine capacity and efficiency losses. Monitoring implementing OT include:
sodium is critical for avoiding corrosion because
uncontrolled sodium hydroxide concentrations At what point during the startup and
are known to cause corrosion damage failures in commissioning process should the
boiler tubes. [1] chemistry regime be switched from AVT to
OT to prevent frequent switching back and
Recommendations listed in Table 1 are based forth between a reducing and an oxidizing
on stringent steam quality and feedwater environment?
requirements for long-term corrosion control
What would be the detrimental effects of
and for reducing forced outages caused by water
going from an oxidizing atmosphere to a
quality. Most boiler and turbine manufacturers
reducing (or close to reducing) atmosphere,
have either agreed to the chemistry limits outlined
for temporary periods?
in Table 1 or have proposed similar limits. From
Bechtels perspective, these recommendations How can these detrimental effects be
are acceptable during operation. quantified and addressed during design and
equipment procurement?
Although recommendations listed in Table 1 are
acceptable for targeted chemistry limits during
operation, EPC contractors would like to see the ROLE OF CONDENSATE POLISHERS DURING
following two columns added to this table: COMMISSIONING

Allowable chemistry excursions during


hot startup
O nce-through supercritical boilers are
commonly installed with full-flow
condensate polishers to control corrosive
Allowable chemistry excursions during impurities concentration in condensate and
cold startup feedwater systems. The presence of impurities
Feedwater chemistry control is also essential for in feedwater will significantly affect feedwater
successful OT. Table 2 specifies EPRI feedwater chemistry, potentially exceeding boiler supplier
chemistry guidelines. feedwater limits and turbine supplier steam

4 Bechtel Technology Journal


purity specifications. Although chemistry control CASE HISTORIES
with full-flow condensate polishers makes startup
and commissioning activities progress smoothly, Case History 1: Once-Through Supercritical
a certain degree of boiler cleanliness must be Boiler Commissioning With ACC
achieved before placing condensate polishers in This case study discusses a power plant
operation. If condensate polishers are operated currently in full operation. It has a once-through
before a certain level of cleanliness is achieved, supercritical boiler, commissioned in early 2000,
there will be an increase in chemical regenerations and an air-cooled condenser (ACC). Startup
frequency (for deep-bed condensate polishers) followed a chemistry control program similar
or resin replacement (for precoat condensate to what is now classified as all volatile treatment
polishers), which will lead to an increase in oxidizing (AVT[O]).
operations and maintenance costs during
Feedwater chemistry and steam purity control
commissioning. Feedwater
is a challenge on ACC-equipped units. During
The EPC contractor should evaluate both precoat commissioning, the EPC contractor faced chemistry and
and deep-bed condensate polishers for use during numerous difficulties controlling oxygen, pH, steam purity control
commissioning and startup. Tight, perfectly and cation conductivity due to the ACCs large is a challenge
installed condenser tubes cant be confirmed condensing surface and frequent regenerations
during startup without extensive condenser on ACC-equipped
required by precoat condensate polishers at
tube testing and installation of an expensive ammonia break. In addition, turbine supplier units.
leak detection system. Therefore, the EPC silica requirements couldnt be relaxed because
contractor must use its own experience in this provision hadnt been negotiated with the
selecting one type of polisher over the other, turbine supplier before turbine contract award.
weighing the cost/benefit of each type of
polisher. Generally, when circulating water is The EPC contractor mitigated chemistry and
brackish or seawater, a deep-bed polisher is steam purity control issues using a membrane
required without exception. Bechtels design contactor to remove dissolved gasses, particularly
standard is to use deep-bed condensate dissolved oxygen, from the makeup water to
polishers on all cycles designed to operate the cycle. Membrane contactors containing
on OT. microporous hydrophobic membranes were
used to bring gas and liquids in direct contact
Impurities shaken loose during startup may cause without mixing. The contactors lowered gas
a chemistry hold, where plant load increases are pressure and created a driving force that removed
temporarily halted until these impurities are dissolved gasses from the water. Installed at
removed from the system. For a once-through the optimum location, membrane contactors are
supercritical boiler, impurities are removed highly efficient and compact. Using a membrane
exclusively by condensate polishers subsequent contactor allowed the EPC contractor to reduce
to chemical cleaning and boiler flush. Once makeup water impurities, resulting in improved
impurities are removed, the chemistry hold is feedwater quality control.
lifted and the plant is allowed to continue to
ramp up to full load without exceeding allowable Challenges of Commissioning a Once-Through
boiler or turbine chemistry limits. Operation at Supercritical Boiler with an ACC
low or reduced loads during startup is frequently Chemistry control during commissioning of a
insufficient to eliminate these chemistry holds. once-though supercritical boiler with an ACC
Installation of polishers allows the plant to is complicated by the ACCs large condensing
reach full power more quickly, resulting in surfaces, on which high-purity steam must
substantial cost savings and increasing revenue condense. To meet steam quality requirements,
production. The cost of condensate polisher these surfaces must be contaminant free.
regenerations should be accounted for in the However, ACCs cannot be chemically cleaned
overall commissioning costs. To minimize the or efficiently flushed with water; therefore,
number of condensate polisher regenerations, the EPC contractor must rely on cleanliness
polishers should be operated beyond ammonia controls implemented during shop fabrication
break, if feasible. However, presence of a full- and site installation. In addition, large surface
flow condensate polisher doesnt make the areas dramatically increase iron content in
unit immune to chemistry problems. A major condensate. Full-flow condensate polishers help
condenser leak during commissioning will still to remove iron; however, pressure drop through
lead to severe chemistry excursions, even with the polishers increases rapidly, compared to a
the aid of a condensate polisher. system operating with a traditional steam surface
condenser, and requires frequent regenerations

December 2008 Volume 1, Number 1 5


or polisher bed cleanings. Additional precoat If the chemistry limits in Table 4 are not met
filters or cartridge filters upstream of the main within the allotted 168 operating hours, the EPC
condensate polishers should be considered, at a contractor and turbine supplier shall mutually
minimum, for initial startup and commissioning agree to an approach for demonstrating balance-
to provide additional cleaning, to supplement of-commissioning-period chemistry limits while
online condensate polishers in crud removal, operating in the bypass mode.
and to speed up the plant startup process.
The negotiation of relaxed turbine steam purity
limits during startup confirms that an additional
Case History 2: Once-Through Supercritical allowance can be given to the EPC contractor for
Boiler Commissioning impurities that could impact startup and delay
This case history discusses a unit in the final the overall commissioning schedule.
stages of construction. The preliminary startup
The negotiation and commissioning chemistry control philosophy
Recommended Startup Feedwater Chemistry for
of relaxed turbine has been developed. The unit will start up on
Once-Through Boilers When Implementing OT
steam purity limits AVT(O) and will normally operate on OT.
AVT(O) and AVT(R) are the two best-known
during startup The EPC contractor and the boiler and turbine methods referenced by EPRI for startup
suppliers negotiated target chemistry guidelines of once-through boilers implementing OT
confirms that
to be used during plant commissioning. After during operation. Operational chemistry
an additional control guidelines for each of these methods
cleaning and flushing contaminants from
allowance condensate, feedwater, and boiler systems and are summarized in Table 5 and Table 6,
can be given completing steamblows, the EPC contractor will respectively.
to the EPC initiate startup in turbine bypass mode until
startup steam chemistry limits listed in Table 3 Table 5. AVT(R) Feedwater Chemistry Control Guidelines [1]
contractor.
are met. Parameter Normal Limit
Table 3. Startup Steam Chemistry Limits Cation Conductivity, S/cm 0.2
pH, STU 9.2 to 9.6
Parameter Limit
Dissolved Oxygen at Economizer Inlet, ppb <5
Degassed Cation Conductivity, S/cm <0.45
Iron, ppb <2
Sodium, ppb <12
Copper, ppb <2
Silica, ppb <40
ORP, mV 300 to 350
Chloride, ppb <12
TOC, ppb <100
Sulfate, ppb <12 Table 6. AVT(O) Feedwater Chemistry Control Guidelines [1]

Parameter Normal Limit


After demonstrating that startup steam Cation Conductivity, S/cm 0.2
chemistry limits have been met, turbine roll will pH, STU 9.2 to 9.6
be initiated and the turbine startup process will Dissolved Oxygen at Economizer Inlet, ppb <10
continue, including loading the turbine to full Iron, ppb <2
load. The steam chemistry will be monitored to
Copper, ppb <2
ensure that chemistry is continually improving
from the startup steam chemistry limits listed
in Table 3 to the balance-of-commissioning During commissioning, the EPC contractor must
period chemistry limits listed in Table 4. develop a chemistry implementation program
A negotiated period of 168 operating hours to meet guidelines specified in Table 5 and
will be allowed to achieve steam chemistry Table 6, respectively. For startup and
below the balance-of-commissioning-period commissioning of a once-through supercritical
chemistry limits. boiler with a deaerator, feedwater chemistry
control guidelines specified under AVT(O) and
Table 4. Balance-of-Commissioning-Period Chemistry Limits AVT(R) are readily achievable. However, for
Parameter Limit cycles without a deaerator, it is more difficult
Degassed Cation Conductivity, S/cm <0.30
to achieve AVT(O) and AVT(R) feedwater
chemistry guidelines (particularly dissolved
Sodium, ppb 3
oxygen and iron limits), even if oxygen is
Silica, ppb <20
removed from makeup water prior to intro-
Chloride, ppb 3
duction into the cycle through, for example,
TOC, ppb 100
membrane contactors. Elimination of
Sulfate, ppb 3 noncondensable gases from the system is

6 Bechtel Technology Journal


limited to the condenser air removal system available. Once cation conductivity has reached
efficiency and capacity when no deaerator is the required 0.15 S/cm level, the unit will be
included in the cycle design. switched from AVT to in accordance with the
EPRI guidelines. [1]
Suggested chemistry guidelines for cycles
without deaerators are listed in Table 7. These
proposed guidelines are based on Bechtels
startup experience, taking into account that EPC STARTUP CHALLENGES
oxygen removal to the low levels proposed
for AVT(R) and AVT(O) operation is an I n addition to stringent steam quality limits
implemented by steam turbine suppliers,
boiler manufacturers have tightened limits
important, but not crucial, requirement in the
absence of a deaerator. on feedwater chemistry. OT guidelines call
for consistent feedwater quality with cation
In addition to
Table 7. Suggested Startup Feedwater Chemistry conductivity 0.15 S/cm (see Table 2) before
and during OT chemistry program implemen- stringent steam
Guidelines for Once-Through Cycles Without Deaerators
tation. AVT guidelines call for similar chemistry quality limits
Parameter Limit
limits (<0.2 S/cm). Since meeting these implemented by
Cation Conductivity, S/cm <0.2 chemistry limits during startup and
pH, STU 9.2 to 9.6
steam turbine
commissioning is extremely difficult, the EPC
Dissolved Oxygen at Economizer Inlet, ppb <100 contractor requires standards to be relaxed during suppliers,
Iron, ppb <5 commissioning to permit timely unit startup. boiler manufacturers
Copper, ppb <2 have tightened
One of the EPC contractors biggest dilemmas
during commissioning is determining the limits on
appropriate time to switch from AVT to OT,
feedwater chemistry.
Case History 3: Once-Through Supercritical even when considering EPRI and boiler supplier
Boiler Commissioning Without Deaerator guidelines. Once cation conductivity levels are
This case history discusses a project development stable below 0.15 S/cm, EPRI recommends
phase, once-through supercritical unit without a operation on OT with oxygen injection in a pH
deaerator. However, a preliminary plant startup range of 8.0 to 8.5. EPRI guidelines also state that
and commissioning plan has been developed. oxygen injection into feedwater may continue
The unit will be operated on OT during normal with pH controlled between 9.2 and 9.6 and
operation. Because there is no deaerator, cation conductivity between 0.15 S/cm and
reaching EPRI-recommended cation conductivity, 0.3 S/cm. However, at cation conductivity
iron, and dissolved oxygen limits will be a levels greater than 0.3 S/cm, EPRI recommends
greater challenge. that oxygen injection be terminated and AVT
resumed. [1] Upsets in cation conductivity may
The commissioning and startup plan includes
lead to serious corrosion problems if oxygen
unit startup on AVT, as recommended by EPRI.
is continuously fed during upset conditions.
[1] However, to minimize high iron transport
Defining stable operation, given the many factors
and deposition, the plan calls for unit startup on
in play and pieces of equipment still being tested
AVT(O). Startup on AVT(O) will control pH by
during typical unit startup, is the true challenge to
adding ammonia, increase temperature to reduce
the EPC contractor. Preventing system chemistry
dissolved oxygen concentration through use of
switching back and forth between AVT and OT is
an auxiliary boiler and sparging in the hotwell,
extremely important. Detrimental effects caused
and reduce cation conductivity by treating
by system chemistry switching between AVT
water through full-flow condensate polishers.
and OT include increased iron transport through
Additional startup schedule time, compared to
dissolution of magnetite and protective hematite
time normally allotted for a unit with a deaerator,
(developed during OT operation) layers, boiler
has been included because reaching dissolved
deposits, and increased boiler pressure drop.
oxygen and cation conductivity limits is not
anticipated to be a quick and easy task. Additional
schedule time was also added for condenser and
WARRANTY IMPLICATIONS
feedwater sparging with steam from the auxiliary
boiler, helium sweep of condenser and vacuum
areas, and unit inspection for vacuum leaks. If it S team turbine suppliers are also setting
limits, in the equipment contract, on the
number of hours a turbine can be operated
is impossible to meet the dissolved oxygen and
cation conductivity limits within a reasonable with out-of-specification chemistry. These
timeframe, the option for startup on AVT(R) is limits are typically listed in an action-level

December 2008 Volume 1, Number 1 7


format where minor chemistry excursions Table 8. Steam Purity Limits During Startup
are allowable for predetermined time EPC Contractor Recommendation for Once-Through Boilers
periods without violating the equipment Parameter Frequency Limit
warranty. The more severe the chemistry Degassed Cation Continuous
<0.45
excursion, the shorter the allowable operating Conductivity, S/cm Sampling
time period the supplier will allow while Sodium, ppb Grab Daily <12
maintaining the equipment warranty. These Silica, ppb Grab Daily <40
action levels impose additional restraints on Chloride, ppb Grab Daily <12
steam turbine operation. The limit on number TOC, ppb Grab Weekly <200
of hours of operation in each action level is very
Sulfate, ppb Grab Daily <12
difficult to meet without adversely impacting the
equipment warranty should delays arise during
Stringent unit startup. During startup and commissioning, Using the practical chemistry limits provided
operational steam chemistry is expected to be degraded in Table 8, typical operation duration would
as compared to when the unit is in full-load, be about one week and would be outlined in
chemistry
steady-state operation because of numerous the equipment contracts. After this, the normal
guidelines cold and hot startups experienced in a short chemistry limits, as recommended by EPRI and
applied to timeframe. Therefore, during each startup, equipment manufacturers, would be met and
startup and the turbine will operate with degraded steam maintained. Time-based chemistry limits and
purity (within the specified action levels). From cumulative hours under action levels would be
commissioning
Bechtels perspective, hours of operation under started after commissioning.
activities each of the different action levels accumulated
For once-through supercritical boilers without
negatively impact during the commissioning and startup phase
deaerators, startup chemistry guidelines should
quick and should not count against allowable hours for
be developed allowing the EPC contractor
warranty purposes.
efficient startup. as much allowance on dissolved oxygen
as practical.

CONCLUSIONS Finally, it is important to develop a relationship


of trust among the EPC contractor, turbine and
T he EPC contractors ultimate goal is to perform
an efficient, once-through supercritical
boiler and turbine startup and commissioning.
boiler suppliers, and owners/operators. For it
is through trust that the combined chemistry
knowledge of these parties can be integrated
Stringent operational chemistry guidelines
to complement plant startup and bring the unit
applied to startup and commissioning activities
online more quickly, resulting in economic
negatively impact quick and efficient startup.
rewards for all.
To meet chemistry guidelines, rigorous cleaning
and inspection procedures must be adhered
to during all fabrication, construction, and
installation phases. The success of any cleaning REFERENCES
program is ultimately judged by the ease with [1] Cycle Chemistry Guidelines for Fossil Plants:
which acceptable feedwater and steam chemistry Oxygenated Treatment, Electric Power
Research Institute (EPRI) Technical Report
is achieved.
1004925, March 9, 2005 <http://my.epri.com/
Practical startup chemistry guidelines should portal/serverpt?space=CommunityPage&cached
be established by consensus among the turbine =true&parentname=ObjMgr&parentid=2&control
=SetCommunity&CommunityID=277&PageID
manufacturer, boiler manufacturer, and EPC =0&RaiseDocID=000000000001004925&RaiseDoc
contractor early on in project development Type=Abstract_id>.
and outlined in equipment contracts. These
startup guidelines should be based on
the EPC contractors startup experience,
the manufacturers desire to prevent
corrosion and deposition in equipment This paper was originally presented at the
components, and the EPC contractors and 68th Annual International Water Conference (IWC),
held October 2125, 2007, in Orlando, Florida.
owners desire for efficient and timely unit
startup. Table 8 provides practical chemistry
limits suitable for startup and commissioning
activities for once-through supercritical boilers.

8 Bechtel Technology Journal


BIOGRAPHIES and experience in the day-to-day operations of a
Kathi Kirschenheiter has power plant burning waste anthracite coal.
worked for Bechtel Power Currently, as manager of Bechtel Powers water
for more than 7 years. Her treatment group, she is responsible for the conceptual
experience has focused mainly design, process engineering, startup and operational
on engineering design of water support of the water/wastewater treatment systems,
and wastewater treatment and the steam/water chemistry issues for Bechtels
systems, including equipment power projects.
specification and procurement. Colleen is an active member of both the American
She has worked with several Society of Mechanical Engineers and the Society of
different Bechtel GBUs in Women Engineers. She currently serves as a
various locations, including Power in Alabama with member of ASME PTC 31 High-Purity Water
the Tennessee Valley Authoritys Browns Ferry Treatment Systems, as a member of the ASME
Nuclear Plant Unit 1 Restart, BNI in Washington Research and Technology Committee on Water
with the Hanford Waste Treatment Plant and Steam in Thermal Systems, and as President
Project, and OG&C in London with the Jamnagar of the Baltimore-Washington Section of the Society
Export Refinery Project. of Women Engineers.
Kathi holds a BS in Chemical Engineering from Colleen holds an MS in Water Resources and
Purdue University, West Lafayette, Indiana, and Environmental Engineering from Villanova
is currently pursuing an ME in Environmental University, Pennsylvania, and a BS in Mechanical
Engineering from the Johns Hopkins University, Engineering Technology from Thomas Edison
Baltimore, Maryland. She is a registered State College, Trenton, New Jersey. She is a
professional engineer in the state of Maryland in registered professional engineer in the state of Ohio.
Environmental Engineering and is currently
a Black Belt Candidate in Bechtel Powers Kumar Sinha, principal
Six Sigma program. engineer, water and waste-
water, on Bechtels mechanical
Michael Chuk has worked for engineering staff, has 40 years
Bechtels Power business for of experience (30 years of
more than 3 of his 4 years in which have been with
the industry. His experience Bechtel) dealing with water
includes the engineering, and wastewater for power
design, and procurement of plants, refineries, and
water and wastewater treat- other industries. He has
ment systems for power plant held increasingly responsible positions, including
projects. Michael is part of senior water treatment engineer, water treatment
the mechanical engineering supervisor, senior engineer and project engineer
group, and he has most recently been working with Bechtel Civil, supervisor and principal
on the Prairie State 1,600 MW supercritical coal- engineer with the Fossil Technology Group, and
fueled plant project. Mikes work has included principal engineer for the Mechanical Project
awarding water treatment packages and completing Acquisition Group. His experience includes project
system design and sizing calculations for all and process engineering, licensing, construction
of the projects water treatment equipment. support, startup, and hands-on operation of
Previously, he worked in Bechtel Powers water water and wastewater systems in the US and abroad.
treatment engineering group on several other Areas of expertise include boiler water and steam
fossil, nuclear, and integrated gasification chemistry, pretreatment and demineralization,
combined-cycle (IGCC) plant projects. His water desalination, treatment of cooling water, and
responsibilities included water balance calculations wastewater disposal, including water recycle and
and water characterization calculations, and early zero discharge.
procurement activities such as preparation of
material requisitions and specifications. Kumar has been an executive committee member of
the International Water Conference since 2004 and
Michael holds a BS in Chemical Engineering was general chair in 2007 and 2008, was a member
from Worcester Polytechnic Institute, Worcester, of the American Society of Mechanical Engineers
Massachusetts. He is an engineer-in-training in the Subcommittee on Water Technology and Chemistry,
state of Maryland. was a member and director of the Engineers
Colleen Layman, manager Society of Western Pennsylvania in 2007 and 2008,
of water treatment, has more and is a retired member of the American Institute
than 15 years of experience of Chemical Engineers.
in water and wastewater Kumar received an MS in Energy Engineering
treatment for power generating from the University of Illinois, Chicago Circle
facilities. Her wide variety of campus, and has completed various business
experience includes engineer- courses at Bechtel and Eastern Michigan University.
ing design, construction, and He holds a BS in Chemical Engineering from the
startup of power generating University of Ranchi, India, and is a registered
facilities; field service and professional engineer in the state of Illinois.
engineering of water and wastewater treatment
equipment and water quality control programs;

December 2008 Volume 1, Number 1 9


10 Bechtel Technology Journal

S-ar putea să vă placă și