Sunteți pe pagina 1din 1

S.No.

Item Description Unit of Labour(on the basis Quantity


Qty of 8 hours working (Nos.)
per day)
1 Cement concrete in 10 m3 Head mason 1/4
foundation Mason 2
Mazdoors 20
2 R.C.C. (1:2:4) 10 m3 Head Mason(Mate) 1/2
Mason 3
Mazdoor(ins. 23
Bhisti)
3 Supplying, fitting, 7 m2 Carpenter 1
fixing and removing Mazdoor 2
shuttering and staging
4 Reinforcement for 100 kg Bar binder 1
R.C.C. work including Mazdoor 1
cutting, bending and
placing in position
5 Damp proof course 100 m2 Head Mason 1/2
Mason 5
Mazdoor 6
3
6 First class brickwork in 10 m Head Mason 1/2
1: 6 in superstructure Mason 9
Mazdoor (2 nos as
Bhisti) 20
2
7 Brick on edge flooring 100 m Head Mason 1/2
with cement mortar 1:3 Mason 10
Mazdoor (1 no as
Bhisti) 15
2
8 Ironite flooring (40mm 100 m Head Mason 1
thick) Mason 24
Mazdoor 27
Mazdoor for 3
rubbing
2
9 C.G.I. sheet on roof 10 m Carpenter 1
Fitter (Blacksmith) 1/2
Mazdoor 2
10 H.C.I. rain water pipe 9 m (1.8m Mason 1/2
fixing length 5no Mazdoor 21/2

11 12mm thk. cement 100 m2 Head Mason 1


plaster on brickwork in Mason 10
1:6 or any proportion Mazdoor (incl. 1 no.
Bhisti) 15
2
12 Ruled Pointing (1:3) 100 m Head Mason 1/2
Mason 10
Mazdoor (incl. 1 no.
Bhisti) 10
2
13 White washing primer 100 m Painter 1/2

S-ar putea să vă placă și