Mano de Obra
470102 OPERARIO HH 3.00 12.0000 13.12 157.44
470103 OFICIAL HH 2.00 8.0000 11.70 93.60
470104 PEON HH 1.00 4.0000 10.58 42.32
293.36
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 2.0000 4.00 8.00
021015 PERNOS HEXAGONALES DE 3/4" X 6" INC.TUER UND 12.0000 1.50 18.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 1.2000 21.50 25.80
380000 HORMIGON M3 0.4800 40.00 19.20
430025 MADERA NACIONAL P/ENCOFRADO-CARP P2 80.0000 4.00 320.00
440322 TRIPLAY DE 4'x8'x 6 mm PLN 3.0000 55.00 165.00
540242 PINTURA ESMALTE SINTETICO GLN 1.0000 45.00 45.00
601.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 293.36 8.80
8.80
Mano de Obra
470101 CAPATAZ HH 0.10 0.0571 15.63 0.89
470102 OPERARIO HH 2.00 1.1429 13.12 14.99
470103 OFICIAL HH 1.00 0.5714 11.70 6.69
470104 PEON HH 2.00 1.1429 10.58 12.09
34.66
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.3500 4.00 1.40
430103 MADERA TORNILLO P2 4.5000 4.00 18.00
440322 TRIPLAY DE 4'x8'x 6 mm PLN 0.5500 55.00 30.25
560106 CALAMINA PZA 0.6600 27.00 17.82
67.47
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 34.66 1.04
1.04
Mano de Obra
470102 OPERARIO HH 1.00 0.0160 13.12 0.21
470104 PEON HH 0.50 0.0080 10.58 0.08
0.29
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0400 4.00 0.16
309903 ESTERA UND 0.3330 22.00 7.33
430103 MADERA TORNILLO P2 2.0000 4.00 8.00
15.49
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.29 0.01
0.01
Mano de Obra
470110 GUARDIAN HH 1.00 8.0000 3.00 24.00
24.00
Materiales
300110 ENERGIA ELECTRICA GLB 1.0000 30.00 30.00
30.00
Pgina : 1 de 25
Empresa no registrada
Mano de Obra
470032 TOPOGRAFO HH 1.00 0.0267 13.12 0.35
470101 CAPATAZ HH 0.10 0.0027 15.63 0.04
470103 OFICIAL HH 1.00 0.0267 11.70 0.31
470104 PEON HH 2.00 0.0533 10.58 0.56
1.26
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0400 4.00 0.16
300106 ESTACA DE MADERA P2 0.0100 3.33 0.03
390148 YESO DE 28 KG BOL 0.0050 25.00 0.13
540242 PINTURA ESMALTE SINTETICO GLN 0.0020 45.00 0.09
0.41
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 1.26 0.04
491901 TEODOLITO HM 1.00 0.0267 8.74 0.23
498802 NIVEL TOPOGRAFICO HM 1.00 0.0267 5.61 0.15
0.42
Mano de Obra
470101 CAPATAZ HH 0.10 0.0114 15.63 0.18
470104 PEON HH 1.00 0.1143 10.58 1.21
1.39
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 1.39 0.07
0.07
Mano de Obra
470101 CAPATAZ HH 0.10 0.0640 15.63 1.00
470104 PEON HH 1.00 0.6400 10.58 6.77
7.77
Equipo
370101 HERRAMIENTAS MANUALES %MO 10.0000 7.77 0.78
0.78
Mano de Obra
470101 CAPATAZ HH 0.10 0.0107 15.63 0.17
470102 OPERARIO HH 1.00 0.1067 13.12 1.40
470104 PEON HH 0.50 0.0533 10.58 0.56
2.13
Equipo
240188 MARTILLO NEUMATICO 24 KG C/CINCEL -ACCS HH 1.00 0.1067 10.00 1.07
370101 HERRAMIENTAS MANUALES %MO 5.0000 2.13 0.11
490193 COMPRESORA NEUMATICA 335-375 PCM, 93 HP HM 1.00 0.1067 85.00 9.07
10.25
Mano de Obra
470104 PEON HH 2.00 3.2000 10.58 33.86
33.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 33.86 1.69
1.69
Pgina : 2 de 25
Empresa no registrada
Mano de Obra
470104 PEON HH 2.00 1.6000 10.58 16.93
16.93
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 16.93 0.85
0.85
Partida 03.01.00 EXCAVACION PARA ZAPATAS DE 1.40 MT A 1.70 MT DE PROFUNDIDAD TERRENO DURO
Rendimiento 1.250 M3/DIA Costo unitario directo por : M3 80.04
Cdigo Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
470101 CAPATAZ HH 0.10 0.6400 15.63 10.00
470104 PEON HH 1.00 6.4000 10.58 67.71
77.71
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 77.71 2.33
2.33
Mano de Obra
470101 CAPATAZ HH 0.10 0.6400 15.63 10.00
470104 PEON HH 1.00 6.4000 10.58 67.71
77.71
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 77.71 2.33
2.33
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470104 PEON HH 1.00 1.0000 10.58 10.58
12.14
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 12.14 0.36
0.36
Mano de Obra
470101 CAPATAZ HH 0.10 0.0200 15.63 0.31
470104 PEON HH 5.00 1.0000 10.58 10.58
10.89
Equipo
480185 CAMION VOLQUETE DE 10 M3 HM 1.00 0.2000 67.23 13.45
13.45
Mano de Obra
470101 CAPATAZ HH 0.10 0.0080 15.63 0.13
470102 OPERARIO HH 1.00 0.0800 13.12 1.05
470104 PEON HH 4.00 0.3200 10.58 3.39
4.57
Materiales
431652 REGLA DE MADERA P2 0.0300 4.88 0.15
0.15
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 4.57 0.14
490192 COMPACTADOR VIBRA. TIPO PLANCHA DE 4 HP HM 0.50 0.0400 12.00 0.48
0.62
Pgina : 3 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0667 15.63 1.04
470104 PEON HH 1.00 0.6667 10.58 7.05
8.09
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 8.09 0.24
0.24
Mano de Obra
470101 CAPATAZ HH 0.10 0.0320 15.63 0.50
470102 OPERARIO HH 1.00 0.3200 13.12 4.20
470104 PEON HH 1.00 0.3200 10.58 3.39
8.09
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 8.09 0.40
0.40
Mano de Obra
470101 CAPATAZ HH 0.10 0.0044 15.63 0.07
470102 OPERARIO HH 1.00 0.0444 13.12 0.58
470103 OFICIAL HH 1.00 0.0444 11.70 0.52
470104 PEON HH 8.00 0.3556 10.58 3.76
4.93
Materiales
050100 AFIRMADO M3 0.2438 40.00 9.75
9.75
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 4.93 0.15
490192 COMPACTADOR VIBRA. TIPO PLANCHA DE 4 HP HM 1.00 0.0444 12.00 0.53
0.68
Mano de Obra
470101 CAPATAZ HH 0.10 0.0320 15.63 0.50
470102 OPERARIO HH 1.00 0.3200 13.12 4.20
470103 OFICIAL HH 2.00 0.6400 11.70 7.49
470104 PEON HH 8.00 2.5600 10.58 27.08
39.27
Materiales
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 2.9000 21.50 62.35
380000 HORMIGON M3 1.2500 40.00 50.00
390500 AGUA M3 0.1470 5.00 0.74
113.09
Equipo
370101 HERRAMIENTAS MANUALES %MO 1.0000 39.27 0.39
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.3200 15.00 4.80
5.19
Mano de Obra
470101 CAPATAZ HH 0.20 0.0640 15.63 1.00
470102 OPERARIO HH 2.00 0.6400 13.12 8.40
470103 OFICIAL HH 2.00 0.6400 11.70 7.49
470104 PEON HH 10.00 3.2000 10.58 33.86
50.75
Materiales
050009 PIEDRA GRANDE DE 8" M3 0.5040 43.00 21.67
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 3.0000 21.50 64.50
380000 HORMIGON M3 0.8300 40.00 33.20
390500 AGUA M3 0.1050 5.00 0.53
Pgina : 4 de 25
Empresa no registrada
119.90
Equipo
370101 HERRAMIENTAS MANUALES %MO 1.0000 50.75 0.51
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.3200 15.00 4.80
5.31
Mano de Obra
470101 CAPATAZ HH 0.10 0.0667 15.63 1.04
470102 OPERARIO HH 2.00 1.3333 13.12 17.49
470103 OFICIAL HH 1.00 0.6667 11.70 7.80
470104 PEON HH 8.00 5.3333 10.58 56.43
82.76
Materiales
050134 PIEDRA MEDIANA DE 4" M3 0.2500 40.00 10.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 4.2500 21.50 91.38
380000 HORMIGON M3 0.8500 40.00 34.00
390500 AGUA M3 0.1740 5.00 0.87
136.25
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 82.76 4.14
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.6667 15.00 10.00
14.14
Mano de Obra
470101 CAPATAZ HH 0.10 0.0552 15.63 0.86
470102 OPERARIO HH 1.00 0.5517 13.12 7.24
470103 OFICIAL HH 1.00 0.5517 11.70 6.45
14.55
Materiales
020008 ALAMBRE NEGRO RECOCIDO # 8 KG 0.2600 4.00 1.04
020105 CLAVOS PARA MADERA C/C 3" KG 0.1000 4.00 0.40
430103 MADERA TORNILLO P2 3.3500 4.00 13.40
14.84
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 14.55 0.44
0.44
Mano de Obra
470101 CAPATAZ HH 0.20 0.0800 15.63 1.25
470102 OPERARIO HH 2.00 0.8000 13.12 10.50
470103 OFICIAL HH 1.00 0.4000 11.70 4.68
470104 PEON HH 8.00 3.2000 10.58 33.86
50.29
Materiales
050003 PIEDRA CHANCADA DE 1/2" M3 0.7500 67.00 50.25
050104 ARENA GRUESA M3 0.5000 40.00 20.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 9.7400 21.50 209.41
390500 AGUA M3 0.1840 5.00 0.92
280.58
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 50.29 1.51
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.4000 15.00 6.00
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 1.00 0.4000 7.00 2.80
10.31
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0500 3.45 3.62
Pgina : 5 de 25
Empresa no registrada
3.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
489602 CIZALLA HM 1.00 0.0320 6.00 0.19
0.22
Mano de Obra
470101 CAPATAZ HH 0.10 0.0444 15.63 0.69
470102 OPERARIO HH 2.00 0.8889 13.12 11.66
470103 OFICIAL HH 2.00 0.8889 11.70 10.40
470104 PEON HH 10.00 4.4444 10.58 47.02
69.77
Materiales
050003 PIEDRA CHANCADA DE 1/2" M3 0.7500 67.00 50.25
050104 ARENA GRUESA M3 0.5500 40.00 22.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 9.7400 21.50 209.41
390500 AGUA M3 0.1840 5.00 0.92
282.58
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 69.77 2.09
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.4444 15.00 6.67
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 1.00 0.4444 7.00 3.11
11.87
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 1.00 0.4000 13.12 5.25
470103 OFICIAL HH 1.00 0.4000 11.70 4.68
10.56
Materiales
020008 ALAMBRE NEGRO RECOCIDO # 8 KG 0.3000 4.00 1.20
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.4700 4.00 1.88
430103 MADERA TORNILLO P2 4.2400 4.00 16.96
20.04
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 10.56 0.53
0.53
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0500 3.45 3.62
3.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
489602 CIZALLA HM 1.00 0.0320 6.00 0.19
0.22
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 2.00 0.8000 13.12 10.50
470103 OFICIAL HH 2.00 0.8000 11.70 9.36
470104 PEON HH 10.00 4.0000 10.58 42.32
62.81
Materiales
050003 PIEDRA CHANCADA DE 1/2" M3 0.7500 67.00 50.25
050104 ARENA GRUESA M3 0.5500 40.00 22.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 9.7400 21.50 209.41
390500 AGUA M3 0.1840 5.00 0.92
Pgina : 6 de 25
Empresa no registrada
282.58
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 62.81 1.88
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 0.50 0.2000 15.00 3.00
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 0.50 0.2000 7.00 1.40
491824 WINCHE DE DOS BALDES (350KG)M.E. 3.6HP HM 0.50 0.2000 14.20 2.84
9.12
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 1.00 0.4000 13.12 5.25
470103 OFICIAL HH 1.00 0.4000 11.70 4.68
10.56
Materiales
020008 ALAMBRE NEGRO RECOCIDO # 8 KG 0.2600 4.00 1.04
020105 CLAVOS PARA MADERA C/C 3" KG 0.4500 4.00 1.80
430103 MADERA TORNILLO P2 5.1500 4.00 20.60
23.44
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 10.56 0.53
0.53
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0500 3.45 3.62
3.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
489602 CIZALLA HM 1.00 0.0320 6.00 0.19
0.22
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 3.00 1.2000 13.12 15.74
470103 OFICIAL HH 2.00 0.8000 11.70 9.36
470104 PEON HH 10.00 4.0000 10.58 42.32
68.05
Materiales
050003 PIEDRA CHANCADA DE 1/2" M3 0.7500 67.00 50.25
050104 ARENA GRUESA M3 0.5500 40.00 22.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 9.7400 21.50 209.41
390500 AGUA M3 0.1840 5.00 0.92
282.58
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 68.05 2.04
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 0.50 0.2000 15.00 3.00
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 0.50 0.2000 7.00 1.40
491824 WINCHE DE DOS BALDES (350KG)M.E. 3.6HP HM 0.50 0.2000 14.20 2.84
9.28
Mano de Obra
470101 CAPATAZ HH 0.10 0.0444 15.63 0.69
470102 OPERARIO HH 1.00 0.4444 13.12 5.83
470103 OFICIAL HH 1.00 0.4444 11.70 5.20
11.72
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.1100 4.00 0.44
430103 MADERA TORNILLO P2 5.1500 4.00 20.60
Pgina : 7 de 25
Empresa no registrada
21.04
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 11.72 0.35
0.35
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0500 3.45 3.62
3.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
489602 CIZALLA HM 1.00 0.0320 6.00 0.19
0.22
Mano de Obra
470101 CAPATAZ HH 0.10 0.0004 15.63 0.01
470102 OPERARIO HH 1.00 0.0040 13.12 0.05
470104 PEON HH 10.00 0.0400 10.58 0.42
0.48
Materiales
170104 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. UND 1.0500 1.82 1.91
1.91
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.48 0.01
0.01
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 3.00 1.2000 13.12 15.74
470103 OFICIAL HH 2.00 0.8000 11.70 9.36
470104 PEON HH 10.00 4.0000 10.58 42.32
68.05
Materiales
050003 PIEDRA CHANCADA DE 1/2" M3 0.7500 67.00 50.25
050104 ARENA GRUESA M3 0.5500 40.00 22.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 9.7400 21.50 209.41
390500 AGUA M3 0.1840 5.00 0.92
282.58
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 68.05 2.04
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 0.50 0.2000 15.00 3.00
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 0.50 0.2000 7.00 1.40
491824 WINCHE DE DOS BALDES (350KG)M.E. 3.6HP HM 0.50 0.2000 14.20 2.84
9.28
Mano de Obra
470101 CAPATAZ HH 0.10 0.0444 15.63 0.69
470102 OPERARIO HH 1.00 0.4444 13.12 5.83
470103 OFICIAL HH 1.00 0.4444 11.70 5.20
11.72
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.1100 4.00 0.44
430103 MADERA TORNILLO P2 5.1500 4.00 20.60
21.04
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 11.72 0.35
0.35
Pgina : 8 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0500 3.45 3.62
3.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
489602 CIZALLA HM 1.00 0.0320 6.00 0.19
0.22
Mano de Obra
470101 CAPATAZ HH 1.00 0.3200 15.63 5.00
470102 OPERARIO HH 2.00 0.6400 13.12 8.40
470103 OFICIAL HH 2.00 0.6400 11.70 7.49
470104 PEON HH 8.00 2.5600 10.58 27.08
47.97
Materiales
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 5.0000 21.50 107.50
380000 HORMIGON M3 1.1300 40.00 45.20
390500 AGUA M3 0.1700 5.00 0.85
153.55
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 47.97 1.44
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.3200 15.00 4.80
6.24
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0500 3.45 3.62
3.86
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
489602 CIZALLA HM 1.00 0.0320 6.00 0.19
0.22
Mano de Obra
470101 CAPATAZ HH 0.10 0.0800 15.63 1.25
470102 OPERARIO HH 1.00 0.8000 13.12 10.50
470104 PEON HH 0.50 0.4000 10.58 4.23
15.98
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.0280 4.00 0.11
050104 ARENA GRUESA M3 0.0300 40.00 1.20
170450 LADRILLO K.K. UND 36.0000 0.75 27.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.3000 21.50 6.45
390500 AGUA M3 0.0200 5.00 0.10
430103 MADERA TORNILLO P2 0.4000 4.00 1.60
36.46
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 15.98 0.80
0.80
Pgina : 9 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470102 OPERARIO HH 1.00 1.0000 13.12 13.12
470104 PEON HH 0.75 0.7500 10.58 7.94
22.62
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.0200 4.00 0.08
050104 ARENA GRUESA M3 0.0700 40.00 2.80
170450 LADRILLO K.K. UND 64.0000 0.75 48.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.4500 21.50 9.68
390500 AGUA M3 0.0140 5.00 0.07
430103 MADERA TORNILLO P2 0.1000 4.00 0.40
61.03
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 22.62 0.68
0.68
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470102 OPERARIO HH 1.00 1.0000 13.12 13.12
470104 PEON HH 0.70 0.7000 10.58 7.41
22.09
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.0200 4.00 0.08
050104 ARENA GRUESA M3 0.0150 40.00 0.60
170450 LADRILLO K.K. UND 28.0000 0.75 21.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1300 21.50 2.80
390500 AGUA M3 0.0040 5.00 0.02
430103 MADERA TORNILLO P2 0.5800 4.00 2.32
26.82
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 22.09 0.66
0.66
Mano de Obra
470101 CAPATAZ HH 0.10 0.0032 15.63 0.05
470102 OPERARIO HH 1.00 0.0320 13.12 0.42
470103 OFICIAL HH 1.00 0.0320 11.70 0.37
0.84
Materiales
020007 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0600 4.00 0.24
029702 ACERO DE REFUERZO FY=4200 GRADO 60 KG 1.0700 3.45 3.69
3.93
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 0.84 0.03
0.03
Mano de Obra
470101 CAPATAZ HH 0.10 0.0533 15.63 0.83
470102 OPERARIO HH 1.00 0.5333 13.12 7.00
470104 PEON HH 0.75 0.4000 10.58 4.23
12.06
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.0220 4.00 0.09
040000 ARENA FINA M3 0.0160 48.00 0.77
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1170 21.50 2.52
390500 AGUA M3 0.0040 5.00 0.02
430103 MADERA TORNILLO P2 0.5800 4.00 2.32
431652 REGLA DE MADERA P2 0.0250 4.88 0.12
5.84
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 12.06 0.36
0.36
Pgina : 10 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0533 15.63 0.83
470102 OPERARIO HH 1.00 0.5333 13.12 7.00
470104 PEON HH 0.50 0.2667 10.58 2.82
10.65
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0220 4.00 0.09
040000 ARENA FINA M3 0.0160 48.00 0.77
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1500 21.50 3.23
390500 AGUA M3 0.0043 5.00 0.02
430103 MADERA TORNILLO P2 0.2000 4.00 0.80
431652 REGLA DE MADERA P2 0.0500 4.88 0.24
5.15
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 10.65 0.32
0.32
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470102 OPERARIO HH 1.00 1.0000 13.12 13.12
470104 PEON HH 0.40 0.4000 10.58 4.23
18.91
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.0300 4.00 0.12
040000 ARENA FINA M3 0.0170 48.00 0.82
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1170 21.50 2.52
390500 AGUA M3 0.0040 5.00 0.02
430103 MADERA TORNILLO P2 0.5800 4.00 2.32
431652 REGLA DE MADERA P2 0.0388 4.88 0.19
5.99
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 18.91 0.57
0.57
Mano de Obra
470101 CAPATAZ HH 0.10 0.1231 15.63 1.92
470102 OPERARIO HH 1.00 1.2308 13.12 16.15
470104 PEON HH 0.40 0.4923 10.58 5.21
23.28
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0220 4.00 0.09
040000 ARENA FINA M3 0.0200 48.00 0.96
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1500 21.50 3.23
390500 AGUA M3 0.0044 5.00 0.02
430103 MADERA TORNILLO P2 2.0000 4.00 8.00
431652 REGLA DE MADERA P2 0.0388 4.88 0.19
12.49
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 23.28 0.70
0.70
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 1.00 0.4000 13.12 5.25
470104 PEON HH 0.30 0.1200 10.58 1.27
7.15
Materiales
040000 ARENA FINA M3 0.0020 48.00 0.10
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.0358 21.50 0.77
430103 MADERA TORNILLO P2 0.1270 4.00 0.51
431652 REGLA DE MADERA P2 0.0500 4.88 0.24
1.62
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 7.15 0.21
0.21
Pgina : 11 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0400 15.63 0.63
470102 OPERARIO HH 1.00 0.4000 13.12 5.25
470104 PEON HH 0.33 0.1320 10.58 1.40
7.28
Materiales
040000 ARENA FINA M3 0.0040 48.00 0.19
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.0240 21.50 0.52
390500 AGUA M3 0.0010 5.00 0.01
0.72
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 7.28 0.22
0.22
Mano de Obra
470101 CAPATAZ HH 0.10 0.0571 15.63 0.89
470102 OPERARIO HH 1.00 0.5714 13.12 7.50
470104 PEON HH 0.50 0.2857 10.58 3.02
11.41
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0100 4.00 0.04
040000 ARENA FINA M3 0.0180 48.00 0.86
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1600 21.50 3.44
390500 AGUA M3 0.0040 5.00 0.02
430103 MADERA TORNILLO P2 2.1600 4.00 8.64
13.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 11.41 0.34
0.34
Partida 09.01.00 PINTURA LATEX EN MURO INTERIOR Y EXTERIOR C/LATEX VINILICO (VINILATEX O
SIMI) 2 MANOS
Rendimiento 40.000 M2/DIA Costo unitario directo por : M2 7.72
Cdigo Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
470101 CAPATAZ HH 0.10 0.0200 15.63 0.31
470102 OPERARIO HH 1.00 0.2000 13.12 2.62
470104 PEON HH 1.00 0.2000 10.58 2.12
5.05
Materiales
309919 LIJA UND 0.1000 1.50 0.15
540115 IMPRIMANTE GLN 0.0500 15.00 0.75
540300 PINTURA LATEX GLN 0.0400 38.00 1.52
2.42
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 5.05 0.25
0.25
Mano de Obra
470101 CAPATAZ HH 0.10 0.0229 15.63 0.36
470102 OPERARIO HH 1.00 0.2286 13.12 3.00
470104 PEON HH 1.00 0.2286 10.58 2.42
5.78
Materiales
309919 LIJA UND 0.1000 1.50 0.15
540115 IMPRIMANTE GLN 0.0500 15.00 0.75
540300 PINTURA LATEX GLN 0.0400 38.00 1.52
2.42
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 5.78 0.29
0.29
Pgina : 12 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0250 15.63 0.39
470102 OPERARIO HH 1.00 0.2500 13.12 3.28
470104 PEON HH 1.00 0.2500 10.58 2.65
6.32
Materiales
309919 LIJA UND 0.2000 1.50 0.30
540115 IMPRIMANTE GLN 0.0330 15.00 0.50
540300 PINTURA LATEX GLN 0.0440 38.00 1.67
2.47
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 6.32 0.32
0.32
Mano de Obra
470101 CAPATAZ HH 0.10 0.0267 15.63 0.42
470102 OPERARIO HH 1.00 0.2667 13.12 3.50
470104 PEON HH 0.50 0.1333 10.58 1.41
5.33
Materiales
309919 LIJA UND 0.2000 1.50 0.30
540242 PINTURA ESMALTE SINTETICO GLN 0.0319 45.00 1.44
540600 PINTURA ANTICORROSIVA GLN 0.0500 55.00 2.75
4.49
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 5.33 0.27
0.27
Mano de Obra
470101 CAPATAZ HH 0.10 0.0267 15.63 0.42
470102 OPERARIO HH 1.00 0.2667 13.12 3.50
470104 PEON HH 0.50 0.1333 10.58 1.41
5.33
Materiales
309919 LIJA UND 0.2000 1.50 0.30
540154 BARNIZ SELLADOR PARA MADERA GLN 0.0770 25.00 1.93
540155 AGUARRAS GLN 0.0046 14.00 0.06
540800 BARNIZ MARINO GLN 0.0500 45.00 2.25
4.54
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 5.33 0.16
0.16
Mano de Obra
470101 CAPATAZ HH 0.10 0.0178 15.63 0.28
470102 OPERARIO HH 1.00 0.1778 13.12 2.33
470104 PEON HH 0.50 0.0889 10.58 0.94
3.55
Materiales
540242 PINTURA ESMALTE SINTETICO GLN 0.0120 45.00 0.54
0.54
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 3.55 0.18
0.18
Pgina : 13 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 1.00 0.0800 15.63 1.25
470102 OPERARIO HH 2.00 0.1600 13.12 2.10
470103 OFICIAL HH 2.00 0.1600 11.70 1.87
470104 PEON HH 6.00 0.4800 10.58 5.08
10.30
Materiales
050134 PIEDRA MEDIANA DE 4" M3 0.1000 40.00 4.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.4410 21.50 9.48
380000 HORMIGON M3 0.1250 40.00 5.00
390500 AGUA M3 0.0156 5.00 0.08
18.56
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 10.30 0.31
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 0.25 0.0200 15.00 0.30
0.61
Mano de Obra
470101 CAPATAZ HH 0.10 0.0889 15.63 1.39
470102 OPERARIO HH 1.00 0.8889 13.12 11.66
470104 PEON HH 0.50 0.4444 10.58 4.70
17.75
Materiales
240189 LOSETA CERAMICA 40X40 CM ANTIDESLIZANTE DE ALTO TRANSITO. M2 1.0500 26.00 27.30
300111 PEGAMENTO PARA CERAMICO KG 6.0000 2.00 12.00
300112 FRAGUA KG 0.1950 7.00 1.37
300113 WAIPE KG 0.5000 1.50 0.75
390500 AGUA M3 0.0060 5.00 0.03
430246 REGLA METALICA DE 1"X2"X6M UND 0.1000 20.00 2.00
720121 CRUCETA DE 3MM BOL 0.0250 10.20 0.26
43.71
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 17.75 0.53
0.53
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470102 OPERARIO HH 1.00 1.0000 13.12 13.12
470104 PEON HH 0.50 0.5000 10.58 5.29
19.97
Materiales
240186 LOSETA CERAMICA 20X20 CM. M2 1.0500 25.00 26.25
300111 PEGAMENTO PARA CERAMICO KG 6.5000 2.00 13.00
300112 FRAGUA KG 0.1950 7.00 1.37
300113 WAIPE KG 1.0000 1.50 1.50
390500 AGUA M3 0.0060 5.00 0.03
430246 REGLA METALICA DE 1"X2"X6M UND 0.1000 20.00 2.00
720121 CRUCETA DE 3MM BOL 0.0250 10.20 0.26
44.41
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 19.97 0.60
0.60
Mano de Obra
470101 CAPATAZ HH 0.70 0.0560 15.63 0.88
470102 OPERARIO HH 6.00 0.4800 13.12 6.30
470103 OFICIAL HH 1.00 0.0800 11.70 0.94
470104 PEON HH 9.00 0.7200 10.58 7.62
15.74
Materiales
020105 CLAVOS PARA MADERA C/C 3" KG 0.0600 4.00 0.24
040000 ARENA FINA M3 0.0140 48.00 0.67
050004 PIEDRA CHANCADA DE 3/4" M3 0.0570 67.00 3.82
050104 ARENA GRUESA M3 0.0460 40.00 1.84
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.8680 21.50 18.66
Pgina : 14 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0267 15.63 0.42
470102 OPERARIO HH 1.00 0.2667 13.12 3.50
470104 PEON HH 1.00 0.2667 10.58 2.82
6.74
Materiales
050011 PIEDRA MEDIANA DE 6" M3 0.1300 43.00 5.59
5.59
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 6.74 0.20
0.20
Mano de Obra
470101 CAPATAZ HH 0.30 0.0240 15.63 0.38
470102 OPERARIO HH 3.00 0.2400 13.12 3.15
470103 OFICIAL HH 1.00 0.0800 11.70 0.94
470104 PEON HH 6.00 0.4800 10.58 5.08
9.55
Materiales
040000 ARENA FINA M3 0.0070 48.00 0.34
050004 PIEDRA CHANCADA DE 3/4" M3 0.0300 67.00 2.01
050104 ARENA GRUESA M3 0.0300 40.00 1.20
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.5000 21.50 10.75
390500 AGUA M3 0.0105 5.00 0.05
14.35
Equipo
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.0800 15.00 1.20
1.20
Mano de Obra
470101 CAPATAZ HH 0.10 0.0444 15.63 0.69
470102 OPERARIO HH 1.00 0.4444 13.12 5.83
470103 OFICIAL HH 0.50 0.2222 11.70 2.60
470104 PEON HH 0.50 0.2222 10.58 2.35
11.47
Materiales
040000 ARENA FINA M3 0.0051 48.00 0.24
050003 PIEDRA CHANCADA DE 1/2" M3 0.1139 67.00 7.63
050104 ARENA GRUESA M3 0.0575 40.00 2.30
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.9600 21.50 20.64
390500 AGUA M3 0.0237 5.00 0.12
430103 MADERA TORNILLO P2 0.0075 4.00 0.03
30.96
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 11.47 0.57
480111 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.00 0.4444 15.00 6.67
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 1.00 0.4444 7.00 3.11
10.35
Mano de Obra
470102 OPERARIO HH 1.00 0.5000 13.12 6.56
470103 OFICIAL HH 1.00 0.5000 11.70 5.85
470104 PEON HH 1.00 0.5000 10.58 5.29
17.70
Materiales
020008 ALAMBRE NEGRO RECOCIDO # 8 KG 0.2000 4.00 0.80
Pgina : 15 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0080 15.63 0.13
470102 OPERARIO HH 1.00 0.0800 13.12 1.05
1.18
Materiales
040000 ARENA FINA M3 0.0100 48.00 0.48
040112 ASFALTO RC -250 GLN 0.3500 6.50 2.28
2.76
Equipo
370101 HERRAMIENTAS MANUALES %MO 5.0000 1.18 0.06
0.06
Materiales
790007 VIDRIO TRANSPARENTE INCOLORO CRUDO MEDIODOBLE P2 1.0500 7.00 7.35
7.35
Mano de Obra
470101 CAPATAZ HH 0.10 0.4000 15.63 6.25
470102 OPERARIO HH 1.50 6.0000 13.12 78.72
470104 PEON HH 1.00 4.0000 10.58 42.32
127.29
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0500 4.00 0.20
309919 LIJA UND 0.5000 1.50 0.75
430199 MADERA CEDRO P2 28.5700 8.00 228.56
540156 COLA SINTETICA GLN 0.0500 15.50 0.78
230.29
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 127.29 3.82
3.82
Mano de Obra
470101 CAPATAZ HH 0.10 0.2500 15.63 3.91
470102 OPERARIO HH 1.00 2.5000 13.12 32.80
470104 PEON HH 0.50 1.2500 10.58 13.23
49.94
Materiales
020102 CLAVOS PARA MADERA C/C 2 1/2" KG 0.0300 4.00 0.12
020161 FIERRO LISO DE 1/2" M 2.7000 4.00 10.80
309919 LIJA UND 0.5600 1.50 0.84
430199 MADERA CEDRO P2 16.4500 8.00 131.60
540156 COLA SINTETICA GLN 0.0500 15.50 0.78
144.14
Equipo
370101 HERRAMIENTAS MANUALES %MO 20.0000 49.94 9.99
9.99
Pgina : 16 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.2000 15.63 3.13
470102 OPERARIO HH 1.00 2.0000 13.12 26.24
29.37
Materiales
260192 CERRADURA EXTERIOR DE TRES GOLPES (TIPO PARCHE) UND 1.0000 95.50 95.50
95.50
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 29.37 0.88
0.88
Mano de Obra
470101 CAPATAZ HH 0.10 0.1600 15.63 2.50
470102 OPERARIO HH 1.00 1.6000 13.12 20.99
23.49
Materiales
260756 CERRADURA P/INTERIOR DE UN GOLPE UND 1.0000 45.00 45.00
45.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 23.49 0.70
0.70
Mano de Obra
470101 CAPATAZ HH 0.10 0.0667 15.63 1.04
470102 OPERARIO HH 1.00 0.6667 13.12 8.75
9.79
Materiales
260193 BISAGRA CAPUCHINA ALUMINIZADA DE 4" UND 1.0000 6.00 6.00
6.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 9.79 0.29
0.29
Mano de Obra
470101 CAPATAZ HH 0.10 0.0667 15.63 1.04
470102 OPERARIO HH 1.00 0.6667 13.12 8.75
9.79
Materiales
260194 BISAGRA CAPUCHINA ALUMINIZADA DE 2 1/2" UND 1.0000 4.76 4.76
4.76
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 9.79 0.29
0.29
Mano de Obra
470102 OPERARIO HH 1.00 0.1455 13.12 1.91
1.91
Materiales
430244 MANIJA DE BRONCE DE4" PZA 1.0000 11.90 11.90
11.90
Pgina : 17 de 25
Empresa no registrada
Mano de Obra
470102 OPERARIO HH 1.00 0.1600 13.12 2.10
2.10
Materiales
260195 CERROJO DE 2" PARA PUERTAS UND 1.0000 6.00 6.00
6.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 1.0000 2.10 0.02
0.02
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470102 OPERARIO HH 1.00 1.0000 13.12 13.12
470104 PEON HH 0.50 0.5000 10.58 5.29
19.97
Materiales
040000 ARENA FINA M3 0.0210 48.00 1.01
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.1870 21.50 4.02
240330 MAYOLICA BLANCA 1ra 20cm x 20cm M2 1.0500 23.00 24.15
301516 PORCELANA KG 0.1950 3.50 0.68
390500 AGUA M3 0.0040 5.00 0.02
431652 REGLA DE MADERA P2 0.0580 4.88 0.28
720121 CRUCETA DE 3MM BOL 0.0250 10.20 0.26
30.42
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 19.97 0.60
0.60
Mano de Obra
470101 CAPATAZ HH 0.10 0.0133 15.63 0.21
470103 OFICIAL HH 2.00 0.2667 11.70 3.12
470104 PEON HH 2.00 0.2667 10.58 2.82
6.15
Materiales
040000 ARENA FINA M3 0.0310 48.00 1.49
170406 LADRILLO PASTELERO 24X 24X3 CM UND 25.0000 0.90 22.50
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.3000 21.50 6.45
390500 AGUA M3 0.0010 5.00 0.01
30.45
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 6.15 0.18
0.18
Materiales
020164 PIZARRA ACRILICA DE 2.50X1.20 UND 1.0000 200.00 200.00
200.00
Partida 16.01.00 SALIDA DE TECHO C/CABLE AWG TW 2.5MM(14)+D PVC SEL 19MM(3/4)
Rendimiento 6.000 PTO/DIA Costo unitario directo por : PTO 48.60
Cdigo Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
470101 CAPATAZ HH 0.10 0.1333 15.63 2.08
470102 OPERARIO HH 1.00 1.3333 13.12 17.49
470104 PEON HH 0.50 0.6667 10.58 7.05
26.62
Materiales
070100 CABLE TW # 14 AWG 2.5 MM2 M 8.1500 1.00 8.15
120154 INTERRUP.DE BAKELITA X 1 SWITCH UND 1.0000 6.72 6.72
120904 CAJA RECTANG GALV 4"X2 1/8" UND 0.5000 1.00 0.50
120949 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 1.0000 1.00 1.00
720901 CURVA PESADO PVC SAP P/INST. ELECT. 3/4" UND 1.0000 0.34 0.34
Pgina : 18 de 25
Empresa no registrada
721101 CONEXION A CAJA PVC SAP INST ELECT 3/4" UND 2.0000 1.50 3.00
740102 TUBO PVC SAP (LUZ) (E/C) 3/4" X 3 M. PZA 2.0000 1.00 2.00
21.71
Equipo
370101 HERRAMIENTAS MANUALES %MO 1.0000 26.62 0.27
0.27
Mano de Obra
470101 CAPATAZ HH 0.10 0.1000 15.63 1.56
470102 OPERARIO HH 1.00 1.0000 13.12 13.12
470104 PEON HH 0.50 0.5000 10.58 5.29
19.97
Materiales
120156 FLUORES. CIRCULAR DE 32 W C/ACCESORIOS UND 1.0000 20.00 20.00
20.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 2.0000 19.97 0.40
0.40
Mano de Obra
470101 CAPATAZ HH 0.10 0.1600 15.63 2.50
470102 OPERARIO HH 1.00 1.6000 13.12 20.99
470104 PEON HH 0.75 1.2000 10.58 12.70
36.19
Materiales
070136 CABLE TW # 12 AWG 4.0 MM2 M 9.0000 1.50 13.50
120157 TOMACORRIENTE BAKELITA SIMPLE UND 1.0000 10.00 10.00
120904 CAJA RECTANG GALV 4"X2 1/8" UND 1.0000 1.00 1.00
290401 CINTA AISLANTE RLL 0.1000 1.00 0.10
740102 TUBO PVC SAP (LUZ) (E/C) 3/4" X 3 M. PZA 1.5000 1.00 1.50
740302 UNION SIMPLE PRESION PVC SAP (LUZ) 3/4" PZA 1.0000 0.20 0.20
740402 CONEXION A CAJA PVC SAP 3/4" PZA 2.0000 1.50 3.00
29.30
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 36.19 1.09
1.09
Mano de Obra
470101 CAPATAZ HH 0.10 0.0500 15.63 0.78
470102 OPERARIO HH 1.00 0.5000 13.12 6.56
470104 PEON HH 0.50 0.2500 10.58 2.65
9.99
Materiales
120224 INTERRUPTOR TERMOMAGNETICO DE 2x15Ax240V UND 1.0000 49.80 49.80
49.80
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 9.99 0.30
0.30
Mano de Obra
470101 CAPATAZ HH 0.10 0.0500 15.63 0.78
470102 OPERARIO HH 1.00 0.5000 13.12 6.56
470104 PEON HH 0.50 0.2500 10.58 2.65
9.99
Materiales
120225 INTERRUPTOR TERMOMAGNETICO DE 2x20Ax240V UND 1.0000 55.00 55.00
55.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 9.99 0.30
0.30
Pgina : 19 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0500 15.63 0.78
470102 OPERARIO HH 1.00 0.5000 13.12 6.56
470104 PEON HH 0.50 0.2500 10.58 2.65
9.99
Materiales
120158 INTERRUPTOR DIFERENCIAL DE 2X25A UND 1.0000 50.00 50.00
50.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 9.99 0.30
0.30
Mano de Obra
470101 CAPATAZ HH 0.10 0.0267 15.63 0.42
470102 OPERARIO HH 1.00 0.2667 13.12 3.50
470104 PEON HH 1.00 0.2667 10.58 2.82
6.74
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0010 30.00 0.03
740102 TUBO PVC SAP (LUZ) (E/C) 3/4" X 3 M. PZA 0.3500 1.00 0.35
740202 CURVA PVC SAP LUZ 3/4" PZA 0.1087 0.30 0.03
740302 UNION SIMPLE PRESION PVC SAP (LUZ) 3/4" PZA 0.3333 0.20 0.07
0.48
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 6.74 0.20
0.20
Mano de Obra
470101 CAPATAZ HH 0.10 0.4000 15.63 6.25
470102 OPERARIO HH 1.00 4.0000 13.12 52.48
470104 PEON HH 0.50 2.0000 10.58 21.16
79.89
Materiales
120155 TABLERO ACRILICO DE 4 POLOS PZA 1.0000 100.00 100.00
100.00
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 79.89 2.40
2.40
Mano de Obra
470101 CAPATAZ HH 0.20 4.0000 15.63 62.52
470102 OPERARIO HH 1.00 20.0000 13.12 262.40
470104 PEON HH 2.00 40.0000 10.58 423.20
748.12
Materiales
040103 TIERRA DE CHACRA O VEGETAL M3 1.4000 22.00 30.80
040113 THOR GEL (DOSIS QUIMICA) BOLSA DE 10 KG EST 1.0000 80.00 80.00
050004 PIEDRA CHANCADA DE 3/4" M3 0.0600 67.00 4.02
050104 ARENA GRUESA M3 0.0300 40.00 1.20
065092 CONECTORES DE COBRE PZA 2.0000 5.00 10.00
070135 CABLE DE COBRE DESNUDO 6 AWG M 12.0000 4.25 51.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.5000 21.50 10.75
301000 VARILLA DE COBRE DE 1/2" x 2.40m UND 1.0000 175.00 175.00
652403 MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" UND 1.0000 12.61 12.61
720811 TUB. PVC SAP P/INST. ELECT. DE 1" M 5.0000 2.75 13.75
720902 CURVA PESADO PVC SAP P/INST. ELECT. 1" UND 1.0000 1.43 1.43
390.56
Equipo
370101 HERRAMIENTAS MANUALES %MO 2.0000 748.12 14.96
14.96
Pgina : 20 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.2286 15.63 3.57
470102 OPERARIO HH 1.00 2.2857 13.12 29.99
470104 PEON HH 1.00 2.2857 10.58 24.18
57.74
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0500 30.00 1.50
721311 TUB. PVC SAL P/DESAGUE DE 4" M 1.5000 5.00 7.50
721629 RAMAL TEE DOBLE C/REDUC PVC SAL 4" A 2" UND 1.0000 4.50 4.50
725404 CODOS PVC SAL 90 X 4" PZA 1.0000 7.00 7.00
20.50
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 57.74 1.73
1.73
Mano de Obra
470101 CAPATAZ HH 0.10 0.2286 15.63 3.57
470102 OPERARIO HH 1.00 2.2857 13.12 29.99
470104 PEON HH 1.00 2.2857 10.58 24.18
57.74
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0500 30.00 1.50
721309 TUB. PVC SAL P/DESAGUE DE 2" M 1.5000 2.00 3.00
721401 CODO DE 90 PVC SAL DE 2" UND 2.0000 2.50 5.00
721601 RAMAL TEE SIMPLE PVC SAL DE 2" UND 2.4350 3.00 7.31
16.81
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 57.74 1.73
1.73
Mano de Obra
470101 CAPATAZ HH 0.10 0.2000 15.63 3.13
470102 OPERARIO HH 1.00 2.0000 13.12 26.24
470104 PEON HH 1.00 2.0000 10.58 21.16
50.53
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0100 30.00 0.30
721309 TUB. PVC SAL P/DESAGUE DE 2" M 2.5000 2.00 5.00
721401 CODO DE 90 PVC SAL DE 2" UND 1.0000 2.50 2.50
7.80
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 50.53 1.52
1.52
Mano de Obra
470101 CAPATAZ HH 0.10 0.2667 15.63 4.17
470102 OPERARIO HH 1.00 2.6667 13.12 34.99
470104 PEON HH 1.00 2.6667 10.58 28.21
67.37
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0100 30.00 0.30
721309 TUB. PVC SAL P/DESAGUE DE 2" M 6.0000 2.00 12.00
721401 CODO DE 90 PVC SAL DE 2" UND 1.0000 2.50 2.50
14.80
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 67.37 2.02
2.02
Pgina : 21 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.4000 15.63 6.25
470102 OPERARIO HH 1.00 4.0000 13.12 52.48
470104 PEON HH 0.75 3.0000 10.58 31.74
90.47
Materiales
040000 ARENA FINA M3 0.0300 48.00 1.44
170450 LADRILLO K.K. UND 84.0000 0.75 63.00
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 1.5000 21.50 32.25
380000 HORMIGON M3 0.0100 40.00 0.40
390500 AGUA M3 0.0100 5.00 0.05
500612 TAPA C/MARCO FF DE DESAGUE 10" X 20" PZA 1.0000 30.00 30.00
127.14
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 90.47 2.71
2.71
Mano de Obra
470101 CAPATAZ HH 0.10 0.0200 15.63 0.31
470102 OPERARIO HH 0.80 0.1600 13.12 2.10
470104 PEON HH 4.00 0.8000 10.58 8.46
10.87
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0050 30.00 0.15
720120 TUB. PVC SAL P/DESAGUE DE 6" M 1.0500 7.15 7.51
7.66
Mano de Obra
470101 CAPATAZ HH 0.10 0.0200 15.63 0.31
470102 OPERARIO HH 0.80 0.1600 13.12 2.10
470104 PEON HH 4.00 0.8000 10.58 8.46
10.87
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0050 30.00 0.15
721311 TUB. PVC SAL P/DESAGUE DE 4" M 1.0300 5.00 5.15
5.30
Mano de Obra
470102 OPERARIO HH 0.80 0.2667 13.12 3.50
470104 PEON HH 1.60 0.5333 10.58 5.64
9.14
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0040 30.00 0.12
721309 TUB. PVC SAL P/DESAGUE DE 2" M 1.0300 2.00 2.06
2.18
Equipo
370101 HERRAMIENTAS MANUALES %MO 1.0000 9.14 0.09
0.09
Mano de Obra
470101 CAPATAZ HH 0.10 0.2000 15.63 3.13
470102 OPERARIO HH 1.00 2.0000 13.12 26.24
470104 PEON HH 0.50 1.0000 10.58 10.58
39.95
Materiales
101522 REGISTRO DE BRONCE DE 4" UND 1.0000 9.00 9.00
721703 TEE SANITARIA SIMPLE PVC SAL DE 4" UND 1.0000 4.50 4.50
725404 CODOS PVC SAL 90 X 4" PZA 1.0000 7.00 7.00
Pgina : 22 de 25
Empresa no registrada
20.50
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 39.95 1.20
1.20
Mano de Obra
470101 CAPATAZ HH 0.10 0.2000 15.63 3.13
470102 OPERARIO HH 1.00 2.0000 13.12 26.24
470104 PEON HH 0.50 1.0000 10.58 10.58
39.95
Materiales
101559 SUMIDERO CROMADO DE 2" UND 1.0000 3.50 3.50
721309 TUB. PVC SAL P/DESAGUE DE 2" M 1.0000 2.00 2.00
721401 CODO DE 90 PVC SAL DE 2" UND 1.0000 2.50 2.50
721629 RAMAL TEE DOBLE C/REDUC PVC SAL 4" A 2" UND 1.0000 4.50 4.50
12.50
Mano de Obra
470101 CAPATAZ HH 0.10 0.0320 15.63 0.50
470102 OPERARIO HH 1.00 0.3200 13.12 4.20
470103 OFICIAL HH 1.00 0.3200 11.70 3.74
8.44
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0030 30.00 0.09
732301 SOMBRERO DE VENTILACION PVC SAL 2" PZA 1.0500 12.00 12.60
12.69
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 8.44 0.25
0.25
Mano de Obra
470104 PEON HH 1.00 1.5385 10.58 16.28
16.28
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 16.28 0.49
0.49
Mano de Obra
470102 OPERARIO HH 1.00 1.2121 13.12 15.90
470104 PEON HH 1.00 1.2121 10.58 12.82
28.72
Materiales
050104 ARENA GRUESA M3 0.0720 40.00 2.88
390500 AGUA M3 0.0270 5.00 0.14
3.02
Equipo
370101 HERRAMIENTAS MANUALES %MO 2.0000 28.72 0.57
490192 COMPACTADOR VIBRA. TIPO PLANCHA DE 4 HP HM 0.03 0.0364 12.00 0.44
1.01
Materiales
100169 INODORO TQUE. BAJO PARA NIOS UND 1.0000 160.00 160.00
160.00
Pgina : 23 de 25
Empresa no registrada
Materiales
100170 LAVATORIO 23"X17" P/GRIF.4" BLANCO PARA NIOS UND 1.0000 178.00 178.00
178.00
Materiales
100211 INODORO TQUE. BAJO NORMAL BLANCO C/A. UND 1.0000 160.00 160.00
160.00
Materiales
100490 LAVATORIO 23"X17" 1 GRIF 4" COLOR C/A UND 1.0000 178.00 178.00
178.00
Mano de Obra
470101 CAPATAZ HH 0.10 0.2000 15.63 3.13
470102 OPERARIO HH 1.00 2.0000 13.12 26.24
470103 OFICIAL HH 1.00 2.0000 11.70 23.40
470104 PEON HH 0.50 1.0000 10.58 10.58
63.35
Mano de Obra
470101 CAPATAZ HH 0.10 0.2667 15.63 4.17
470102 OPERARIO HH 1.00 2.6667 13.12 34.99
470104 PEON HH 0.50 1.3333 10.58 14.11
53.27
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0075 30.00 0.23
720030 TUB. PVC SAP PRESION C-10 C/R. 3/4" x 5m UND 0.2500 13.00 3.25
720081 TUB. PVC SAP PRESION P/AGUA C-10 R. 1/2" M 2.1700 3.50 7.60
720600 CODO DE 90C/R PVC SAP P/AGUA DE 1/2" UND 3.5000 1.19 4.17
720601 CODO DE 90C/R PVC SAP P/AGUA DE 3/4" UND 3.4600 1.55 5.36
20.61
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 53.27 1.60
1.60
Mano de Obra
470101 CAPATAZ HH 0.19 0.0608 15.63 0.95
470102 OPERARIO HH 1.00 0.3200 13.12 4.20
470104 PEON HH 1.00 0.3200 10.58 3.39
8.54
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0075 30.00 0.23
720081 TUB. PVC SAP PRESION P/AGUA C-10 R. 1/2" M 1.0300 3.50 3.61
720700 TEE PVC SAP DE 1/2" C/R PARA AGUA UND 1.0100 1.80 1.82
5.66
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 8.54 0.26
0.26
Pgina : 24 de 25
Empresa no registrada
Mano de Obra
470101 CAPATAZ HH 0.10 0.0320 15.63 0.50
470102 OPERARIO HH 1.00 0.3200 13.12 4.20
470104 PEON HH 1.00 0.3200 10.58 3.39
8.09
Materiales
304635 PEGAMENTO PARA PVC 1/4 GLN UND 0.0075 30.00 0.23
720030 TUB. PVC SAP PRESION C-10 C/R. 3/4" x 5m UND 1.0500 13.00 13.65
720701 TEE PVC SAP 3/4" C/R P/AGUA UND 1.0100 2.60 2.63
16.51
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 8.09 0.24
0.24
Mano de Obra
470101 CAPATAZ HH 0.10 0.1333 15.63 2.08
470102 OPERARIO HH 1.00 1.3333 13.12 17.49
470103 OFICIAL HH 1.00 1.3333 11.70 15.60
35.17
Materiales
304832 CINTA TEFLON PZA 0.1000 1.00 0.10
650512 UNION UNIVERSAL DE Fo. GALV. DE 3/4" UND 2.0000 1.50 3.00
651385 NIPLE DE Fo Go DE 3/4" x 1 1/2" UND 2.0000 1.80 3.60
770003 VALVULA COMPUERTA DE BRONCE DE 3/4" UND 1.0000 15.00 15.00
21.70
Equipo
370101 HERRAMIENTAS MANUALES %MO 3.0000 35.17 1.06
1.06
Pgina : 25 de 25