1- The forward pass review of the project management will indicate the following:

a- The earliest start of the task


b- The earliest finish of the task
c- Project Duration
d- Only A & B
e- All of the above

2- The back pass review of the project will indicate the following:
a- The latest start of the task.
b- The earliest finish of the task.
c- The critical path.
d- Only A & C
e- All of the above.

f- Forward pass is used by Early Start (ES) and Early Finish (EF)

g- Backward pass is used by Late start (ES) and Late finish (EF)

3- What is the last of estimation for project

a- Estimation
b- Assembly schedule

4- You are a bid manager. In one of the project bid date is already closed, but one
of the vendors did not submit their bid and they requested for extension. In
that case what will you do?
a) Wait for all the bids to proceed
b) Inform the others prices to the bidder to submit their bid.
c) Inform the bidder that date is already closed and not acceptable.
d) Give extension for bid submission

5- Which one is not significant role of Project manager


a) Technical support
b) Customer interaction
c) Vendor interaction
d) Project planning

6- DURING WHICH BELOW PROCESS , STATUS REPORTS,CHANGE


REQUESTS,CREATED

ANS-EXECUTION

7- THE ---- ACTIVITY IS IMPORTANT FOR COMPLETION OF PROJECT.

ANS- CRITICAL

8- In a construction firm the project manager has conducted the analysis for soil and has
designed the frame and structural which has the budget of $25000. However he was told
to bring down the budget to $20000. How can he manage it?
a. He will change the soil analysis report and framing to bring down the budget with
some effect on Specification
b. He will carry out the soil analysis again to bring some better figures
c. He will bring down the framing to an acceptable and within specification
d. He will do (b) & (c) both
9- Which shall be more sustainable for a the Project/Business
a. Economical
b. Environmental
c. Society
d. All the above

10- One of the following is not process of the project:


a. Concept
b. Initiating
c. Planning
d. Executing
e. Closing

11- Ultrasound test used to determine

a- Cracks
b- Position of cracks
c- Length of cracks
d- All of above

12- The heat loss inside a straight conductor is 60J upon applying current I for 5s.
if the resistance of the conductor is decease to half, and the same current is
applied for 5s, what will be the heat dissipation:
a 60J
b 30J
c 15J
d 120J

13- What is energy stored in the conductor when I current flows in a resistor R for
a period of time t.
a) I2Rt
b) IR2t
c) IRt2
d) None of the above

14- What do we call Synchronous motor working on a lead power factor at no


load
a. Synchronous condenser
b. Reluctance motor

15- Breaking for induction motor

Regeneration

Dynamic

Plugging
All above

16- Starting of induction motor using


a) Resistance
b) Capacitor
c) Reactance
d) Slip ring
17- Most economic method to start a single phase motor
a) Split Phase
b) Capacitance Type

18- In Power Station the efficiency of a turbine is 80% and generator is 90%,
What is the overall efficiency?
a) 80%
b) 90%
c) 70%
19- Synchronous motor is said to have over excited when the Power
factor is:
a) Normal
b) Leading
c) Lagging

20- Define Power Factor?


a) Sine of Voltage and Current
b) Cosine of Voltage and Current
c) Tan of Voltage and Current

21- Important Factor in Distributed System


a) Reliability
b) Efficiency

22- Power factor of over excited alternator


a) Unity
b) Lagging
c) Leading
d) Infinity

23- Power factor of over excited alternator


e) Unity
f) Lagging
g) Leading
h) Infinity

24- POWER FACTOR DEFINITION


ANS = VI COSphi

25- Generation of harmonics in power system is due to


a) Power electronic devices
b) Static components
c) Dynamic components
d) None of the above

26- What is the function of a circuit breaker?


Is an automatically operated electrical switch designed to protect an electrical circuit from
damage caused by overload or short circuit. Its basic function is to detect a fault condition
and interrupt current flow

27- WHAT IS THE MINIMUM WIRE GAUGE FOR EARTHING CABLE :


1) 20 AWG
2) 16 AWG
3) 8 AWG
4) 10 AWG

28- Minimum cross sectional area of earth continuity conductor in buildings used:
1. 20 AWG
2. 16 AWG = 1.5 mm2
3. 12 AWG
4. 10 AWGk

29- EARTHING ELECTRODE IS FILLED IN SAND :


1) LIME SAND + MIXTURE
2) SAW DUST + MIXTURE

30- WHEN TEMPERATURE INCREASE WHAT HAPPENS TO RESISTANCE.


1) INCREASE
2) DECREASE
31- 1200RPM, FREQUENCY 50HZ , CALCULATE NO OF POLES

ANS FORMULA- SPEED = 120 f/No of Poles

32- WHEN THE INSTRUMENT IS DRIFT WITH TIME, WHAT NEEDS TO BE DO.

1) CHANGE THE INSTRUMENT


2) CALIBRATE THE INSTRUMENT
3) MOVE THE POSITION IN HIGHER
33- Assembly language will be used for programming :

1) Microcontroller
2) FPGA
3) DSP
34- For the Smoke detector and door control system will have logic in
For the

1)DSP
2) Microcontroller
3) FPGA
4)ASCII

35- Programming used for smoke detector and control systems


a) DSP
b) Microcontroller
c) FGPA
d) ASCI

36- STRENGTH OF MATERIAL :


1. INTERNAL RESISTANCE TO THE APPLIED FORCE
2. STRAIN
3. STRESS
4. DEFORMATION

CB
37- If a fuse rating is 8Amps then it requires:
a) Minimum 8amps current to energize the fuse
b) More than 8 amps to energize the fuse.
c) It will melt if the current is more than 8amps.
38- Circuit Breaker commonly used in industrial application
a) SF6
b) Air Circuit

39- Uninterruptable Power Supply is used for :

a Connected in series for the critical load during normal operation


b Connected in parallel for the critical load during normal operation
c Connected in series for the critical load during voltage variation
d Connected in parallel for the critical load during voltage variation

40- If a wire is above the transformer, where it is connected?


a) Positive
b) Negative
c) Earth

41- If the Fire Panel is to be installed in the field, atmospheric pressure is 52C
and the electronics inside is allowed to produce only 45C what is the
appropriate method to install:
a) Panel shall be CE certified
b) Panel shall be Class-1 Certified
c) Panel shall be provided with some cooler or purge

42- Once the current draw from battery what happened to the capacity and why?
- Capacity gradually dissipated, relative to amp/hour utilization

43- Wind load law = K GI f, indicate what is K?


- wind directionality factor KD
- return period factor krW
- topographic factor Kzt
44- What do we mean by reproducibility of observation?
- is the ability of an entire experiment or study to be duplicated, either by the same
researcher or by someone else working independently. Reproducing an experiment is
called replicating it. Reproducibility is one of the main principles of the scientific method.

45- What is the 1st step to define a project?


- Step 1: Define the scope
- Brief but specific definition of result or mission
- Focuses on the project purpose throughout its life
- Agreement between costumer and project manager
- To plan and control performance.

46- What kind of motor used for crane?


- The crane motors are duty type rated for developing high starting torque
with low starting current. The motors are designed to withstand stresses
due to frequent starts/stops and reversals. Also, a rapid acceleration is
achieved by high pull out torque/rotor inertia ratio

47- What is the p.f?


-is defined as the ratio of the real power flowing to the load to the apparent power in the
circuit. A power factor of less than one means that the voltage and current waveforms are
not in phase, reducing the instantaneous product of the two waveforms (V x I).
48- What is the transistor?
- is a semiconductor device used to amplify or switch electronic signals and electrical
power. It is composed of semiconductor material with at least three terminals for
connection to an external circuit.

49- Flouriest light flickers when voltage is?


- It is caused when the voltage supplied to a light source changes or when
the power line voltage itself fluctuat

50- Rotor of Induction motor is rotating at synchronous speed, What is Torque?


a) High
b) Low
c) Zero
d) Infinity

51- Define Strength of Materials?


a) Strength of Internal resistance of the object applied with the external force
b) Absorbing the Strain

52- Define Power Factor?


a) Sine of Voltage and Current
b) Cosine of Voltage and Current
c) Tan of Voltage and Current

53- Harmonic Current in Power System:


a) Hystersis Loss
b) Eddy Current Loss

54- Weak Power System is due to:


a) Hi Short Circuit
b) Lo Short Circuit

55- Important Factor in Distributed System


a) Reliability
b) Efficiency

56- Transformer Amplifier used in CMRRS for:


a) Rejection of Noise
b) Amplifying
c) Differential Amplifier

57- Moving Cranes use what type of motor?


a) DC Shunt Motor
b) AC Motor
c) Compound DC Motor

58- A Household Ceiling Fan function with:


a) Start Capacitor Type
b) Permanent Capacitance Type

59- There is a contradiction in a Specification and a Drawing Note,


a) Details will be preceded by Notes
b) Details will be preceded by Drawing
c) Specification will be preceded by Drawing
d) Drawing will be preceded by Specification

60- The Manufacturing company gets material from 2 suppliers X & Y,


Task Task Nodes Duration
Procure material by X 2
Procure material by Y A 2
Delivery of Material from X B 7
Delivery of Material from Y B 11
Assembly and Completion C&D 2
If X delays the procurement of material by 2 days and company take 10 days to obtain the
material, what shall be the delay(days) for product completion

a. 0
b. 1
c. 2
d. 3

61- In a construction firm the project manager has conducted the analysis for soil and has
designed the frame and structural which has the budget of $25000. However he was told
to bring down the budget to $20000. How can he manage it?
e. He will change the soil analysis report and framing to bring down the budget with
some effect on Specification
f. He will carry out the soil analysis again to bring some better figures
g. He will bring down the framing to an acceptable and within specification
h. He will do (b) & (c) both

62- Advantages of Cascading the amplifiers


a. Input impedance
b. Output impedance
c. High Voltage gain

63- The system is maintained at 24V output voltage. The input source varies from 120V to
126V. while the output current varies from 0A to 5 A. What is the min power rating required
for the diode.

R Is
s

a. 80W
b. 150W
c. 300W
d. 600W

64- Harmonics are produced due to


a. Magnetic devices
b. Electronic Power devices

65- If the signal is doubled at the input of the transmitter what shall be the db ot the output
a. 0.5db
b. 2db
c. 3db
d. 4db

66- The undergroung cable is laid in a marine environment at system voltage,A. what shall be
the design of the cable insulation
a. (1/3) *A
b. 3 * A
c. 2 * A
d. 2 A

67- The series of cell combine to give output of 230V at no load. The rated output od 300V to
provide the power of 2 MW. If the cell are used in standard battery, what is the internal
resistenace of each battery.
a. 0.003
b. 0.05
c.

68- Which has the highest conductivity at room temperature


a. Aluminium
b. Copper
c. Gold
d. Silver

69- What is the top cable used for on the transmission lines
a. Ground
b. Phase
c. Neutral
d. Transmission

70- What are the HRC fuses


a. High Rupturing Capacity Fuse
b. ..
c. .

71- Permanent magnet has the relative permitivity ___________ than air
a. Higher
b. Lower
c. Same
d. ..
72- Breaking for induction motor
1. Regeneration
2. Dynamic
3. Plugging
4. All above
73- What is the top cable used for on the transmission lines
e. Ground
f. Phase
g. Neutral
h. Transmission

74- Humming happening in a Transformer due to

a) Due to the Vibration in brush


b) Due to magnetostriction in core laminations
c) Due to the Vibration in winding
d) None of the above
e) All of the above

75- Define Power Factor?


d) Sine of Voltage and Current
e) Cosine of Voltage and Current
f) Tan of Voltage and Current

76- Which of the following is unit of Conductance?


(a) Ohm
(b) Henry
(c) Mho
(d) Webers/metre