Quote Ref.

: BHGQ/1/2010/117
Vessel Name : M/T "MARWAH-6" Date : 24th July, 2010
Item # Unit Qty. Rate Total
Description
US$ US$
01. Dry Docking and General Services
1.1 Preparation of special blocks arrangement LS 5,750.00
1.2 - Docking of the vessel /time 1 4,950.00 4,950.00
- Undocking of the vessel /time 1 4,950.00 4,950.00
(Including first and last day)
1.3 Subsequent lay days in dock (The above vessel will
stay alone in our floating dock # 1 as requssted by
owner's rep.) /day 15 4,360.00 65,400.00
1.4 - Mooring of Vessel /time 1 720.00 720.00
- Unmooring of vessel /time 1 720.00 720.00
1.5 Wharfage. /day 300.00
1.6 Pilotage
- From "A" anchorage to shipyard dock /time 1 1,290.00 1,290.00
- From shipyard to "A" anchorage /time 1 1,290.00 1,290.00
1.7 Tug boat assistance (Estimated) LS 7,700.00
02. Shore Power
a) - To provide electrical shore power connection
from ship yard source. AC 440V, 60Hz. (Assumed) /kwh 22,000 1.40 30,800.00
b) - Connection and disconnection of line. /line/time 1 220.00 220.00
03. Fire Line
3.1 - Fire line (Compulsory) /day 17 125.00 2,125.00
- Connection and disconnection of line. /line/time 2 200.00 400.00
3.2 Fire watchman (Compulsory)
(One man day shift and one man night shift) /day 17 440.00 7,480.00
3.3 Gas Free Inspection (from ship yard safety Officer)
a) - Initial Inspection LS 540.00
b) - Subsequent Inspection (Assumed) /time 16 210.00 3,360.00
04. Cooling water
a) - Provide cooling water for Air Conditioner /day 17 220.00 3,740.00
b) - Connection and disconnection of line. /line/time 1 200.00 200.00
05. Sewage line
- To provide sewage line including connection
and disconnection of line. /time 1 450.00 450.00
- Overboard pipe extension fit/remove /pc 100.00
- Keel block remove (if required) /block 220.00

Page 1 of 4
Quote Ref. : BHGQ/1/2010/117
Vessel Name : M/T "MARWAH-6" Date : 24th July, 2010
Item # Unit Qty. Rate Total
Description
US$ US$
06. Garbage Disposal
- Remove and dispose garbage (Assumed) /time 17 245.00 4,165.00
07. Gangway
- To provide one gangway to the vessel /time 2 290.00 580.00
08. Crane services
- To provide crane services in accordance with
instruction of owner's representative. (per one hour
or part there of) (Assumed) /time 8 210.00 1,680.00
09. Steel works
To renew following steel plates and internals using
yard supply materials. Provide ventilation, lighting, etc..
if required.
9.1 i) - To clean and gas free No.1 DOT (P) (28m3) and No.2
DOT (P) (16m3) for hot work. LS 2,860.00
ii) - To pump Out diesel oil using yard supply pump
and manpower and store in yard provided tank,
after completion of work Pump IN if required.
- Pump Out and Pump In Diesel Oil (Assumed) /ton 10 95.00 950.00
- Storage /ton/day 15 50.00 750.00
9.2 Bottom Plate
A-3 3250mm x 1500mm x 12mm (fr 19.5 - 25.5)
A-4 8600mm x 1500mm x 10mm (fr 25.5 - 39.5)
A-5 8850mm x 1500mm x 10mm (fr 39.5 - 54.5)
A-6 8600mm x 1500mm x 10mm (fr 54.5 - 68.5)
A-7 8950mm x 1500mm x 10mm (fr 68.5 - 83.5)
A-8 7200mm x 1500mm x 14mm (fr 83.5 - 95.5)
9.3 Bottom longitudinal
No.2 bottom long; 45,000 x 150/90 x T-10mm I.A (Fr 20-95)
No.3 bottom long; 45,000 x 150/90 x T-10mm I.A (Fr 20-95)
9.4 Transverse frame & BHD
- Frame: 1500mmx 200mm x T- 10mm - 26pcs
(Fr 21-27, 30, 32, 34, 36, 42, 46, 49, 52, 56, 60, 64, 67, 74,
78, 82, 85, 88, 92, 94).

Page 2 of 4
Quote Ref. : BHGQ/1/2010/117
Vessel Name : M/T "MARWAH-6" Date : 24th July, 2010
Item # Unit Qty. Rate Total
Description
US$ US$
BHD: 1500mm x 200mm x T -12mm -1pc (fr 28)
BHD: 1500mm x 200mm x T -10mm -2pcs (fr 38, 70)
- Price per KG renewal of straight material(Mild steel)
Wall thickness Location
Plates
- 12mm to 16mm (Estimated weight) /kg 8310 6.85 56,923.50
- 17mm and above /kg 5.80
Notes:
- Other structural steel works 12mm - 16mm 20% extra
- Other structural steel works 17 and above 18% extra
- Removal for access, staging, hot work, cleaning,
painting and testing not included.
- Renewal of stiffeners/longitudinal ONLY additional 20%
- Partial renewal of stiffeners/frames/longitudinal additional 15%
- Corrugated bulkhead additional 18% on straight BHD
- Single curvature additional 15% double curvature additional 25%
- Double bottom/cofferdams and confined spaces additional 20%
- Partial renewal of plates, less than 5 tons additional 10%
- Renewal of plates without renewing internals in way additional 15%
- High tensile steel material additional 10%
- Bulbous bow additional 100%
- Plates less than 1 ton and internals less than 100kgs, "case by case"
- Steel weights will be calculated on maximum dimensions
of piece using a specific weight of 8.
- Steel renewal price is subject to the cost of steel material
at the time of order confirmation.
- If Original steel material thickness is not available in the
yard, the yard reserves the right to use material with first
next available size subject to Class approval.
- Up normal areas will be calculated separately
- If steel material thickness is less than 12mm, following
percentage to be applied.
a) Up to 6mm +25%
b) Up to 7 to 11mm + 15%
10. HULL CLEANING & PAINTING
10.1 Flat bottom area (Assumed Repair area 70m2)
10.1.1 High pressure F.W jet wash /m 590 3.00 1,770.00
10.1.2 Full sand blasting to SA 2.5. /m 200 35.00 7,000.00

Page 3 of 4
Quote Ref. : BHGQ/1/2010/117
Vessel Name : M/T "MARWAH-6" Date : 24th July, 2010
Item # Unit Qty. Rate Total
Description
US$ US$
10.1.3 Apply 2 full coat of owner supply anti-corrosive paint /m/2coat 70 4.00 280.00
10.1.4 Apply 1 full coat of owner supply sealer paint /m/1coat 70 2.00 140.00
10.1.5 Apply 1 full coat of owner supply anti-fouling paint /m/1coat 70 2.00 140.00
10.1.6 Hose down with fresh water /m 70 1.50 105.00
Note:-
- The above mentioned areas are assumed
as mentioned in the scope of work will be
finalized upon completion of work.
- Minimum blasting area is 200 m per vessel.
Paint material to be supplied by owner
11. BOTTOM PLUG
Open up following bottom plugs and refit on
completion. Total 4nos.
NO.1 D.B BWT (P), No.2 D.B. BWT (P),
No1 FOT(P), No.2 FOT (P). /pc 4 100.00 400.00
12. MANHOLE COVER
Open and close manhole covers of No.1 D.B. BWT (P),
No.2 D.B. BWT (P), No.1 FOT (P) and No.2 FOT (P).
Total - 4nos /pc 4 120.00 480.00
13. PAINTING OF D.B.B TANKS
To paint on renew bottom plates and internal member of
No.1 & 2 D.B.BWT (P) using owner supply epoxy paint.
Bottom plate ; 52m2
Bottom long. and trans.frames : 43m2 LS 450.00
14. BALLAST WATER SUPPLY
To supply ballast water to following tanks for hydro
pressure test and undocking.
No.1 BWT (P) - 107m3
No.2 BWT (P) - 104m3 /m3 211 4.00 844.00

Estimated Amount in USD $221,602.50

(Except unit rates)


Note:
The above price is estimated and will be finalized
upon completion of work
** End of Page **