Sunteți pe pagina 1din 9

Steel Bridge

N AT I O N A L S T E E L B R I D G E A L L I A N C E

REPLACEMENT
NEWS DECEMBER 2006

New Bridge Slated for Columbus


To pave the way for a new downtown The project team is led by DLZ Ohio, the construction engineer. S.N. Pollalis of
landmark, demolition began the week Inc., with HNTB Corporation as the lead the Harvard University Graduate School
of September 25 on the 68-year-old structural design rm. The prime contrac- of Design developed the initial design
Main Street Bridge in Columbus, Ohio. tor is Kokosing, and Jansen & Spaans is concept.
The new span will link parkway develop-
ments on both sides of the Scioto River,
contributing to the revitalization of the
Columbus Civic Center. Total cost of the
project is projected to be $44.1 million,
with completion in 2009.
The new bridge will feature an inno-
vative single-rib tied arch with a 400-ft
span that will carry separate vehicle and
pedestrian lanes. The arch will be inclined
at a 10 angle from vertical, adding to the
uniqueness of this signature structure. A
pedestrian deck will sweep horizontally
and vertically away from the roadway to
provide an unobstructed view of the citys
downtown.

A MESSAGE FROM THE


Executive Director
As 2006 comes to a sign, fabrication and erection and include decision-makers in using steel components.
close, the steel bridge several design examples. The completed Many state and local authorities are choos-
industry continues its Steel Bridge Design Handbook will provide the ing to look offshore, avoiding the Buy
efforts to increase mar- steel bridge community with a valuable tool America Provision. Not only are these chal-
ket share, advance tech- for answering many of their technical and lenges presenting themselves on our coasts,
nology in bridge design design questions. but they have also migrated to several inland
and construction, and Our increased trade and public awareness states. NSBA is dedicated to preserving the
promote improvements efforts have continued to provide informa- Buy American Provision and will continue
for accelerated steel tion on several signature bridges as well as to represent member mills and fabricators
bridge deployment. We also continue to everyday steel bridges. Included in this effort in their effort to keep our domestic steel
make excellent strides in providing protec- are interesting articles and information to bridge industry strong. The midterm elec-
tion and inuence on the Buy American educate and inuence the decision maker in tions should provide interesting times. Our
Provision for our industry. making the right choice in steel design and efforts will evolve and we will continue nur-
Phase I of the Steel Bridge Design Hand- construction. A new web site (www.steel- turing existing relationships and making
book has been completed, and the chapters bridges.org) was developed, compiling in- new friends where ofces change.
are available as PDF downloads from our formation about NSBA as well as steel bridge On behalf of the entire staff of the Na-
new web site. Phase II is scheduled for a information from all sectors of the industry. tional Steel Bridge Alliance, I would like to
completion date of mid-2007 and the third The web site can be viewed for all updated take this opportunity to wish you and your
and nal phase will begin later this year. The news, AASHTO documents, opinion state- family a wonderful and happy holiday sea-
chapters are based on the AASHTO LRFD ments, and meeting dates for the industry. son and a prosperous new year.
Bridge Design Specications, Third Edition, The political scene remains active. Priva-
and will be upgraded online for each new tization of roads and bridges is receiving Best regards,
specication edition. The chapters cover a more and more consideration, and our in- Conn Abnee
wide range of topics about steel bridge de- uence will be directed to assist these new NSBA Executive Director

DECEMBER 2006 MODERN STEEL CONSTRUCTION


EVENTS
Steel Bridge Symposium
The 2007 World Steel Bridge Sympo-
sium will take place December 47,
2007 at the Sheraton New Orleans Ho-
tel, New Orleans, La. For exhibit and spon-
sorship information, contact Jody Lovsness
at 402.758.9099 or lovsness@nsbaweb.org.
For general information, contact Elizabeth
Purdy at 312.670.5421 or purdy@aisc.org.
Visit www.steelbridges.org for the latest
information.

National Steel Bridge Alliance


One East Wacker Drive, Suite 700
Chicago, IL 60601-1802
www.nsbaweb.org
www.steelbridges.org

Conn Abnee
Executive Director
Phone: 606.724.2347
Cell: 312.804.1524
abnee@nsbaweb.org

Mike Moftt
Director of Engineering Services
1228 S. 4th Street
St. Charles, IL 60174-4019
Phone: 630.443.8090
moftt@nsbaweb.org

Jody Lovsness
Marketing and Membership
Coordinator
11708 Jackson Road
Omaha, NE 68154
Phone: 402.758.9099
Fax: 402.778.9499
lovsness@nsbaweb.org

Calvin R. Schrage
Regional Director (west)
5620 Harding Drive
Lincoln, NE 68521
Phone: 402.466.1007
Fax: 402.466.1027
schrage@nsbaweb.org

William F. McEleney
Regional Director (east)
45 Pasture View Lane
Cranston, RI 02921-2732
Phone: 401.943.5660
Fax: same as phone
mceleney@nsbaweb.org

Regional Directors Territories

MODERN STEEL CONSTRUCTION DECEMBER 2006


NATIONAL STEEL BRI D G E A L L I A N C E STEEL BRIDGE NEWS
MATERIALS

Prefabricating Standard Orthotropic Steel Decks


BY ROMAN WOLCHUK

The American steel industry must offer


new and better products to more ef-
fectively compete in the bridge market.
Wider use of cost-effective orthotropic steel
decks provides one possible way to increase
the role of structural steel for bridges. Cur-
rently, bridge engineers tend to consider
these decks expensive and useful only for
large bridges. They also associate them with
complex design and analysis.
Specications permitting the use of
standardized orthotropic decks not re-
quiring elaborate analytical investigations
would encourage their increased use. The
Eurocode provisions for orthotropic decks,
for example, expressly exempt some com-
mon bridge types from numerical fatigue
investigations, provided that the decks sat- Figure 1. Proposed prefabricated orthotropic deck panels.
isfy certain geometric requirements and
fabrication rules. The Japanese bridge code
contains similar provisions.
The 1994 edition of the AASHTO
LRFD specications for orthotropic decks
also dispenses with numerical investiga-
tions of fatigue strength of certain details
not easily amenable to analytical treatment.
The junctions of the ribs with the deck
plate can be considered to have adequate
fatigue resistance if the stipulated require-
ments for geometric proportions and weld-
ing details are satised.
It should be noted that provisions permit-
ting the use of certain standard pre-tested
bridge components, such as steel gratings,
precast concrete deck panels or T-beams,
without numerical strength and fatigue anal-
ysis by the designer have been already includ-
ed in the earlier AASHTO specications.
Figure 2. Applications to new bridges.
Designing the Standard Panel
Figure 1 shows a proposed design for a
standard orthotropic steel deck panel. It is pressed ribs would have to be used because wearing surface.
suggested that hot-rolled ribs replace the the steel mills could produce hot-rolled pro- Substantially longer rib spans of 9.8 m
conventional cold-pressed ribs. Cold press- les only if assured of sufcient tonnage. (32 ft) have already been used on one of our
ing of ribs in the fabricators shop is an ex- The cost of fabrication and erection of projects. They perform well under heavy
pensive process, requiring specialized heavy orthotropic decks depends primarily on trafc. To further reduce the labor cost, the
equipment. Generally, the length handled specialized labor, not the cost of the steel detail at the rib intersections with the cross
by fabrication presses cannot exceed about plate. The rib intersections with the cross beams may be simplied by omitting the free
12 m (40 ft). Other disadvantages of cold beams are labor-intensive. Proposed deck cut-outs at the rib bottoms, which require
pressing are the high residual stresses and panel design minimizes the number of such laborious wrapping around of the welds
strain hardening at the corners of the ribs, intersections by spacing the cross beams at and costly grinding smooth the weld ends
reducing their fatigue resistance. Cold 8 m (26 ft) and spreading the ribs farther and around the cut-out. Instead, the ribs with
pressing also increases the difculty of at- apart. This modication requires a thicker rounded bottoms are tted tightly in the web
taining the prescribed straightness toleranc- (18 mm) deck plate, which is also desirable cut-outs and welded continuously all around
es, essential for correct welding of the ribs for reducing local deck exibility. A stiffer the rib periphery. This alternative is possible
to the deck plate. Initially, however, the cold- deck plate improves the performance of the where the depth of the cross beam is at least

DECEMBER 2006 MODERN STEEL CONSTRUCTION


Figure 3. Re-decking of short-span stringer bridges.

twice the rib depth. the resulting strains may be safely withstood
For good fatigue resistance, fabrica- by the thin surfacing of our choice. But much
tors must strictly adhere to required tight larger strains and stresses will develop in a
dimensional tolerances. They should also thick bituminous pavement at low tempera-
choose welding methods and sequences to tures, possibly causing its failure.
minimize residual stresses. The size of the
proposed prefabricated panels is governed Applying the Prefabricated Panels
by their ability to be transported to the proj- Figure 2 shows that prefabricated panels
ect site by truck. of this type could be used for all kinds of
The panels will act as top anges of lon- steel bridges with two or more rolled-beam
gitudinal girders, as shown in Figure 2. Erec- stringers or plate girders. The needed road-
tors will weld the edges of the panels to the way width can be obtained by longitudinally
tops of the girders in the eld. These welds splicing the deck plates of two or more pan-
will resist the interaction shears between the els. For skewed bridges the end panels may
steel roadway deck and the girder. be cut at any angle. In the end bays the rib
spans should not exceed 6 m (20 ft). In truss
Wearing Surfaces bridges the panels will function as partici-
Weve proposed a thin (12-mm or -in.) pating components of the truss chords and
epoxy-polymer surfacing of the type proven as the lateral bracing.
on such projects as the Poplar Street Bridge Figure 3 shows possible application of
in St. Louis and the Macdonald Bridge in prefabricated panels to re-decking of short
Halifax, Nova Scotia, Canada. This material span stringer bridges. Overpass structures
has relatively low susceptibility to tempera- over the interstate highways built in the
ture effects. Bituminous surfacings exhibit 1950s to 1980s typically consist of four
undesirable stiffening at low temperatures simple spans, as shown in Section 44.
that may result in pavement embrittlement Rolled-beam stringers are generally spaced
and cracking. at about 2.1 m (7 ft) with composite or non-
Note the critical location on the deck in composite concrete decks that have open
the vicinity of the rigid main girders where joints at the piers and the abutments. On
the deck plate is subject to sharp local curva- most of these structures the concrete decks
ture, causing maximum tensile strain in the are deteriorated. The use of prefabricated
surfacing, as shown in Figure 4. To minimize orthotropic panels would offer the follow-
this effect the distance c between the web ing advantages:
of the rib and the deck plate support at the elimination of the open deck joints at the
girder (see Sect. 11, Figure 1) must be suf- piers by using a continuous deck plate be-
ciently large. Our investigation indicates that, tween the end abutments.
with distance c within the indicated limits, conversion of simple span stringers to con-

MODERN STEEL CONSTRUCTION DECEMBER 2006


Figure 4. Proposed testing of panel prototypes.

tinuity, considerably decreasing the posi- experienced in full-scale testing of large or-
tive moments due to live loads. thotropic deck prototypes. This work could
the possibility of eliminating two out of possibly be shared with laboratories in Eu-
the existing ve stringers, as shown in the rope or in Japan where the steel industry and
cross section. transportation authorities may be interested
Installation of the new deck can be done in prefabrication of standard decks.
expeditiously, one lane at a time, minimizing The testing program will also include
trafc restrictions. Eliminating two string- testing of wearing surfacing for fatigue re-
ers provides the further advantage of reduc- sistance in exural tension. Such tests are
ing future painting and maintenance cost. made on small specimens of the deck plate
with applied surfacing as shown schemati-
Testing Prefabricated Panels cally in Section 77 of Figure 4. Practical
The use of prefabricated panels with- methods for such testing at various tem-
out detailed numerical investigation by the peratures have been worked out by the
designer will require certication of their University of Missouri, where tests of this
strength and fatigue resistance by test- kind were successfully carried out for the
ing of prototypes. Such certied standard Poplar Street Bridge and other projects.
prefabricated panels could then be con- Manufacturers of the thin surfacing pro-
dently specied by engineers and owners posed for the panels may be willing to co-
without the need for analytical drudgery sponsor such testing.
and uncertainty. We expect that such pre-fabricated stan-
Figure 4 shows the proposed testing dard panels, produced in large quantities by
panel. Its framing plan will make it possible to industrial methods, will be substantially less
study the structural behavior of the 8-m (26-ft) costly than the decks designed and fabri-
interior spans and the 6-m (20-ft) spans of the cated for a specic project. Current practice
ribs at the ends of a bridge. The tests should requires:
subject the panels to live loads representing considerable engineering design effort
current AASHTO specications and possible excessive time needed for preparation, re-
future European heavy truck loading. view and approval of the shop drawings
Several panels must be fabricated to engineering inspection.
complete the loading test series and to com- Avoiding these time-consuming proce-
pare the effects of various fabrication factors, dures will not only reduce the cost, but will
tolerances, welding procedures and panel also considerably shorten the construction
treatment methods. This will be a large and period.
costly testing program. We are fortunate
to have in the U.S. the excellent Lehigh Roman Wolchuk is a principal with Roman Wol-
University/ATLLS testing facilities, well chuk consulting Engineers, Jersey City, N.J.

DECEMBER 2006 MODERN STEEL CONSTRUCTION


National Steel Bridge Alliance
A Division of American Institute of Steel Construction, Inc.

2007 PRIZE BRIDGE Competition

Deadline for entries: June 15, 2007


For more information or an online Entry Form, visit www.steelbridges.org
NATIONAL STEEL BRI D G E A L L I A N C E STEEL BRIDGE NEWS

Simple-Made-Continuous Bridge
Cuts Costs
Cost-effective detailing was only one of the advantages of a simple-made-
continuous weathering steel girder bridge in New Mexico.

T
BY TED L. BARBER, P.E.

THE NEW MEXICO DOT HAS GREAT- stressed concrete required ve girder lines, tion. The steel girders, all grade 50W, have
LY IMPROVED MULTI-SPAN, PLATE- but steel plate girders required only four a total depth of 54 in. The web is 0.472 in.,
GIRDER STEEL BRIDGES DESIGNED girder lines. and the cross sections of the top and bot-
AS SIMPLE-SPAN FOR DEAD LOADS A shallower depth decreased the earth- tom anges are 0.866 in. by 13.78 in. and
AND CONTINUOUS FOR LIVE LOADS. work required to build the bridge ap- 0.866 in. by 17.32 in., respectively.
These designs ease fabrication and erection, proaches, as well as the amount of right-
helping to keep steel bridges competitive of-way needed for a new parallel offset Superstructure Detailing
with concrete. The simple-made-continu- alignment. It also improved the bridge aes- New detailing ensured that the top plate
ous concept cuts costs through repetitive thetics in the river area. Other bridges built connecting in-line girders at the piers would
fabrication, full-length girder erections, along the same river have vertical curves slip properly under DC1 construction load-
simplied connections, and exible deck- that seem somewhat out of place for this ings, allowing beam-end rotation. By con-
pour sequencing. river valley. trast, on the US 70 project the contractor
The economical steel bridge design placed the deck and pier diaphragm in one
Bridge Overview incorporated an easily fabricated and con- continuous pour. Construction workers had
The bridge discussed here crosses structible bridge superstructure with no to tighten all top continuity plate connec-
the Rio Grande River on NM 187, near traditional bolted splices between piers. tion bolts before slab pour because of their
Array. This two-lane, four-girder struc- Eliminating these bolted splices avoided the location inside the concrete pier diaphragm.
ture, designed by the NMDOT, has ve shoring towers required for erection. The This induced some level of stress through-
105-ft spans and a width of 34.5 ft. The design implemented constant plate thick- out the beam. The shear resistance of neo-
substructure consists of driven, lled, steel nesses and dimensions with no ange tran- prene bearing devices induced these forces,
pipe piles. Concrete curtain walls surround sitions. One-piece diaphragms, positioned which are caused by beam-end rotation un-
the piles to ve feet below grade. The con- on wide spacing, also facilitated easy erec- der deck pour loadings.
struction phase started in the fall of 2004,
completing in the summer of 2005.
On an earlier project, the simple-made-
continuous concept served in a dual-design
analysis (steel vs. pre-stressed concrete
bridges) for a bridge on US 70 in southern
New Mexico. Design consultant for the US
70 bridge alternates was Parsons Brincker-
hoff, Inc. Bids by construction contractors
for these bridge alternates differed by only
0.2 percent out of a total project construc-
tion cost of $21 million. This small dif-
ferential cost tipped the decision to look
at applying the simple-made-continuous
concept to steel bridges located in similar
geographies.
The NM 187 steel bridge project in-
corporated further improvements in de-
sign and construction details. Selection of
the superstructure type depended heavily
on economic analyses of various congu-
rations of steel girders and pre-stressed
concrete beams, while limiting the depth
of the new superstructure. The prelimi- Figure 1. Dual-design analysis indicated that steel required only four girders, while concrete
nary design scenarios determined that pre- pre-stressed beams required five (for the same depth).

DECEMBER 2006 MODERN STEEL CONSTRUCTION


Figure 2. Connection plate bolts outside the pier permit tightening after
the deck pour, minimizing induced stresses.

NMDOT improved the girder connec- the connection continuity plates to con- stage transformed joints at piers to mo-
tion for the NM 187 bridge design by plac- form to beam dead-load camber at each ment connections for girder-line analysis.
ing the bolts outside the poured concrete beam end. This allowed the connection STAAD Pro also allowed factoring of loads
diaphragm at the piers (Figure 2). Bolts plate to t up with loose bolting during and graphical presentation of the location
placed heads-up and nuts-exposed-down dead-load application. The top-plate slip- of axle loads and their position at maxima.
permitted tightening of the connection page also avoided unintended shear de- Many of todays software programs seem to
after pouring of the deck and pier dia- ections in the steel-reinforced neoprene lack presentation of positions for the load-
phragms. After deck pours, the bolt heads bearing pads during the slab pour, as well ing on the structure. Mathcad performed
were locked into the concrete deck. Work- as any induced moment in the girders. the calculations for the steel design using
ers tightened bolts by turning nuts with Additionally, the reviewers requested a the LRFD code.
direct tension indicators from below. Final small increase in the length of the slotted
tightening came after all concrete had been hole in the continuity plates to aid erec- Fabrication and Erection
poured for the deck and pier and abutment tion tolerances. As a result, the contractor Global steel market conditions delayed
diaphragms, prior to opening for trafc. was able to erect beams and lift continuity the start of fabrication of the girders for
The design required adding reinforcing plates (with bolts) into place without any the project. The nationwide supply of steel
bars to normal deck reinforcement patterns alignment problem. Bridge erection was decreased between the time of bidding and
longitudinally over the piers. The addi- simple and straightforward. notice to proceed. The contractor asked
tional reinforcement achieved the required The design intentionally centers the for suspension of work on the contract for
negative moment capacity for the bridges bridges vertical alignment at the crest of a three months over the winter to allow for
continuous live-load function. Under live vertical curve, allowing for the uniformity delivery of the raw plate to the fabricator.
loads the continuity connection plate will of all girders and greatly simplifying the NMDOT planned this bridge for con-
be lightly stressed. The continuity plate bridge in design and detailing for construc- struction during the low-ow stage of the
connection also added redundancy in the tion. Steel girders for this bridge were de- river. It was essential to complete spans 4
event that future deck deterioration reduc- tailed for the same exact length, plate thick- and 5, the two spans over the river, before
es the effectiveness of the deck reinforce- ness, dimensioning, and camber, facilitated the water reached spring irrigation levels.
ment for negative moment capacity. by a slight adjustment to the length of end In spite of the three-month suspension of
The bearing stiffener plate on each spans. Simple horizontal steel channel dia- work, fabricated steel delivery and erec-
beam end at the piers served to develop phragms added to the bottom ange in the tion took place to complete the two river
compression for this moment connection. negative moment region over the piers spans on time. The exibility of the simple-
A simple plate perpendicular to the web provide additional buckling resistance. made-continuous girder system permitted
and bearing stiffener braced the bearing the contractor to pour spans 4 and 5 while
plate in the compression zone. Design Firsts beams had not yet been erected on spans 1,
This type of connection also gave more The bridge represents the rst in-house 2, and 3. Thus, the contractor was able to
exibility to the bridge contractor on pour design of a steel bridge with this detail- fulll this contact requirement.
sequences. Contractors in the state want ing and the rst project to implement Economical and fast fabrication resulted
to pour entire bridges in one day. The AASHTO LRFD Bridge Design Specica- primarily from the repetition of girder de-
500+ cubic-yard volume of concrete on tions. No commercial software packages are sign throughout the structure. Repetition
this bridge deck prevented a one-day pour. available for the simple-made-continuous in shop fabrication increased productivity
But with this design, contractors can pour steel design concept. Instead, STAAD Pro by at least 25 percent. Like-size anges,
across spans, pier concrete diaphragms, and structural analysis software and Mathcad webs, and girder lengths provided the most
bulkhead 6.5 ft from a pier cap. performed a two-stage analysis and design advantageous price and delivery of steel
Reviewers of shop drawings made a calculation for the beam lines. For the rst plate from the mill. Additional advantages
change requesting that the fabricator bend stage, all spans were simple. The second included:

54 MODERN STEEL CONSTRUCTION DECEMBER 2006


Figure 3. A connection plate bolts the top
flanges of the two girders that meet at a pier,
making the girders continuous for live loads.

Detailers could develop shop drawings for Two relatively small cranes, readily showed that steel bridges can compete
one girder; all others were nearly alike. available in the state, easily erected the steel with pre-stressed concrete in a predomi-
The fabricator cut anges and webs using beams. Prestressed concrete beam bridges nantly concrete bridge state. This concept
only one drawing. often require much larger cranes and large will work well in other similar river and dry
Shop fabrication necessitated only one jig mobilization costs, difcult lift congura- stream-bed crossings of signicant length
for tacking and welding. tions, and more erection time. The State and requiring at least two spans. This type
The continuity plates that spliced the of New Mexico is in the middle of a $1.5 of design is limited to maximum girder
girders together at the piers were all iden- billion road and bridge improvement bond lengths that can be hauled to the bridge
tical and could be processed full-size us- program over six years. One of the goals is location; otherwise, expensive traditional
ing CNC equipment. to facilitate smaller bonding requirements eld splices are necessary.
The girders did not require full layout so that more construction rms are able to
and assembly in runs. bid projects. Using resources within the Ted Barber is a bridge design unit supervisor
Assembly drilling, required for conven- state are essential for this program. with the New Mexico Department of Trans-
tional bolted girder splices, was unneces- The design phase of this project started portation (NMDOT) in the Bridge Design
sary. before steel price levels increased over the Section.
With all parts alike, erection efforts in past few years. Despite these increases, cost
the eld were much more efcient as well. per square foot for this bridge came in lower Owner and Designer
Big savings resulted from: than some other concrete bridges recently New Mexico Department of
Eliminating bolted eld splices between bid in the state. With a total deck area of Transportation
piers. 18,170 sq. ft, the cost of this bridge as re- Contractor
Eliminating sandblasting of girders (the ported to the Federal Highway Administra- Reiman Corp., Cheyenne, Wyoming
bridge is not in an area exposed to view). tion was $75 per sq. ft. Prestressed concrete
Fabricator
Specifying weathering steel, which will girder bridges of comparable square footage
Roscoe Steel & Culvert Co., Billings,
develop a rich color and form a protec- were $68 and $88 per sq. ft. each.
Montana (AISC member)
tive patina in time. This simple-made-continuous project

DECEMBER 2006 MODERN STEEL CONSTRUCTION

S-ar putea să vă placă și