_x000D_RBS 6000 FAMILY ACCEPTANCE TEST FORM 1 (163)

PT. XL AXIATA, Tbk


BTS ACCEPTANCE TEST DOCUMENT
( Turnkey Project - LTE )

VENDOR/CONTRACTOR :
PROJECT NAME :
NBWO/EWO NUMBER :
SITE NAME :
SITE NUMBER :
SITE COORDINATE : E/W
S/N
DATE OF ACCEPTANCE :
ACCEPTANCE STATUS :
PASS, NO PENDING ITEMS
PASS WITH PENDING ITEMS
REJECTED BY CUSTOMER

ACCEPTANCE BY :
VENDOR
Person Name & Signature ,Date

PT. HUAWEI SERVICE


1. FOC Engineer Name & Signature, Date

2. FOP Engineer Name & Signature, Date

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved: EID/OJI/CE Yulpien Teng


_x000D_Rev: B
Date: 2015-06-26
_x000D_RBS 6000 FAMILY ACCEPTANCE TEST FORM 2 (163)
3. FOC Supervisor Name & Signature, Date

This document and all material contained herein is protected by copyright, trade marks and other rights which are owned and/or controlled by
Ericsson Indonesia and/or its affiliates or by other parties that have licensed their material to PT Ericsson I

Copyright 2015 PT Ericsson Indonesia

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved: EID/OJI/CE Yulpien Teng


_x000D_Rev: B
Date: 2015-06-26
_x000D_RBS 6000 FAMILY ACCEPTANCE TEST FORM 3 (163)

OCUMENT
LTE )

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved: EID/OJI/CE Yulpien Teng


_x000D_Rev: B
Date: 2015-06-26
_x000D_RBS 6000 FAMILY ACCEPTANCE TEST FORM 4 (163)

s which are owned and/or controlled by PT


nI

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved: EID/OJI/CE Yulpien Teng


_x000D_Rev: B
Date: 2015-06-26
ACCEPTANCE TEST FORM
RADIO BASE STATION - LTE

Site Name :
Site Number :
Site Address :

I Radio Base Station Data


RBS Type : c RBS 6102/6102V2 c RBS 6201/6201V2
: c RBS 6301 c RBS 6601
: c RBS Single RAN 6102/6201/
RBS S/N :
No. Of Cabinet :
IP OAM :
Band : c 900 c 1800
LTE Configuration : c Stand Lone c Mixed Mode
RU Type :

Items
II Radio Base Station Check List
II.1 Grounding
Earth grounding system installed according to SID (connect to Grounding Bar)
II.1.1

II.1.2 RBS earth washer in place & tightened


II.1.3 Earth ground cable lugs & C-clamp correcty crimped
Earthing cable size is 35 mm2 (minimum)
II.1.4
RBS 6201 & 6601 default is 25 mm
II.1.5 Cable insulation undamaged
II.2 Cable Ladder & Cables (for Indoor RBS only)
Cable ladder installed according to SID, aligned,leveled at the correct height & properly assemble
II.2.1

II.2.2 Cable ladder properly earthed


II.2.3 Cables are properly installed or dressed on cable ladder
II.2.4 Power & signal cables are bundled separately
II.2.5 Cables secured with tie wraps
II.2.6 Cabling is undamaged
II.2.7 Cables are protected from hazardous conditions (sharp edges, heat or pinching)
II.2.8 Excess cable has been cut off and properly dressed
II.2.9 Cables are free of stress & strain
II.2.10 All cables that are not connected have ends taped
II.3 Cabinet
II.3.1 Cabinet installed according to SID
II.3.2 Cabinet is clean & undamaged
II.3.3 Cabinet is properly aligned
II.3.4 Cabinet fastened to base frame & locking bolts tightened
II.3.5 Equipment units & boards installed properly & in correct position according to SID
II.3.6 All fans are working properly
II.3.7 Equipment labeled as required according to SID
II.3.8 Protective covers, dust caps & terminations plugs are installed on unused ports
II.3.9 Air filter in place & clean
II.4 DUS or DUL (LTE Only)
Installing a GPS cable has been installed between DU (Mixed Mode configuration)
II.4.1

Installation of data cables from DU to RUS has been installed (Mixed Mode
II.4.2
configuration)
II.4.3 DU bracket adapter is installed correctly (If there are additional DU)
II.5 Labels
II.5.1 All labels are correctly attached
II.5.2 All labels are easy to read (not blocked)
II.5.3 No labels are peel, tear off at the major parts
II.6 Cleaness and Tidiness
II.6.1 No trash or garbage left after acceptance process
II.7 Safety
II.7.1 No hazardous voltage is exposed for the personal
There is no possibility of a short circuit of the installation related to Power . All power connections
II.7.2
neatly closed .

II.8 TRANSPORT CONFIGURATION (LTE)


Items
II.8.1 IP Configuration, IpInterface=2
II.8.1.1 IP Access Host Et (S1) , ipAddress =
II.8.1.2 GpsSyncRef=1
II.8.1.3 IP Sync Ref 1 , ipAddress =
II.8.1.4 IP Sync Ref 2 , ipAddress =
II.8.1.5 IP Sync Ref 3 , ipAddress =
II.8.1.6 IP Sync Ref 4 , ipAddress =
II.8.1.7 IP Sync Ref 5 , ipAddress =
II.8.1.8 IP Sync Ref 6 , ipAddress =
II.8.1.9 IP Sync Ref 7 , ipAddress =
II.8.1.10 IP Sync Ref 8 , ipAddress =
II.8.1.11 VLAN ID S1 , Vid =
II.8.1.12 S1 defaultRouter0, ipAddress =
II.8.1.13 IP Configuration, IpInterface=1
II.8.1.14 IpOam=1,Ip=1,IpHostLink=1, ipAddress =
II.8.1.15 VLAN ID OAM , Vid =
II.8.1.16 OAM defaultRouter0, ipAddress =
II.8.1.17 TermPoint To Mme
II.8.1.18 ipAddress1 =
II.8.1.19 ipAddress2 =
II.8.1.20 mme Names =
II.8.1.21 NTP Server
II.8.1.22 ntpServerAddressPrimary , ipAddress =
II.8.1.23 ntpServerAddressSecondary, ipAddress =
II.8.1.24 ntpServerAddressThird, ipAddress =

II.8.2 Electrical Transmission & Alarm Cables


II.8.2.1 Electrical transmission cables connected according to SID
II.8.2.2 Electrical transmission cables labeled in both ends

II.8.3 Outdoor Remote Radio Unit (for RBS 6301 & 6601 )
II.8.3.1 Units installed according to SID
II.8.3.2 Units are clean & undamaged
II.8.3.3 Units are properly aligned
II.8.3.4 Equipment labeled as required according to SID
II.8.3.5 Protective covers & dust caps are installed on unused ports

II.9 RADIO NETWORK TEST (LTE)


Items
II.9.1 Cell Status
II.9.1.1 EUtranCellFDD=
II.9.1.2 EUtranCellFDD=
II.9.1.3 EUtranCellFDD=
II.9.1.4 EUtranCellFDD=
II.9.1.5 EUtranCellFDD=
II.9.1.6 EUtranCellFDD=
II.9.1.7 EUtranCellFDD=
II.9.1.8 EUtranCellFDD=
II.9.1.9 EUtranCellFDD=
II.9.1.10 EUtranCellFDD=
II.9.1.11 EUtranCellFDD=
II.9.1.12 EUtranCellFDD=
II.9.1.13 Configuration
II.9.1.14 Startable CV
II.9.1.15 CV on RollbackList 1
II.9.1.16 SW Level
II.9.1.17 RBS Restart

II.10 INTEGRATION TEST (LTE)


Items
II.10.1 CS Fall Back
II.10.1.1 Sector 1
II.10.1.2 Sector 2
II.10.1.3 Sector 3
II.10.1.4 Sector 4
II.10.1.5 Sector 5
II.10.1.6 Sector 6
II.10.1.7 Sector 7
II.10.1.8 Sector 8
II.10.1.9 Sector 9
II.10.1.10 Sector 10
II.10.1.11 Sector 11
II.10.1.12 Sector 12
II.10.2 Data
II.10.2.1 Sector 1
II.10.2.2 Sector 2
II.10.2.3 Sector 3
II.10.2.4 Sector 4
II.10.2.5 Sector 5
II.10.2.6 Sector 6
II.10.2.7 Sector 7
II.10.2.8 Sector 8
II.10.2.9 Sector 9
II.10.2.10 Sector 10
II.10.2.11 Sector 11
II.10.2.12 Sector 12
II.10.3 SMS
II.10.3.1 Sector 1
II.10.3.2 Sector 2
II.10.3.3 Sector 3
II.10.3.4 Sector 4
II.10.3.5 Sector 5
II.10.3.6 Sector 6
II.10.3.7 Sector 7
II.10.3.8 Sector 8
II.10.3.9 Sector 9
II.10.3.10 Sector 10
II.10.3.11 Sector 11
II.10.3.12 Sector 12

II.11 QOS Configuration


Parameter & Value
II.11.1 Ip=1 dscp
II.11.2 Sector IpAccessHostEt=1 ntp Dscp
II.11.3 ENodeBFunction=1 dscp Label
II.11.4 QciProfilePredefined=default dscp
II.11.5 QciProfilePredefined=qci1 dscp
II.11.6 QciProfilePredefined=qci2 dscp
II.11.7 QciProfilePredefined=qc3 dscp
II.11.8 QciProfilePredefined=qci4 dscp
II.11.9 QciProfilePredefined=qci5 dscp
II.11.10 QciProfilePredefined=qci6 dscp
II.11.11 QciProfilePredefined=qci7 dscp
II.11.12 QciProfilePredefined=qci8 dscp
II.11.13 QciProfilePredefined=qci9 dscp
**) fill in accordance ATND & TRM design

II.12 dscpToPbitMap
dscp Pbit OK N/A Remarks
II.12.1 0 c c
II.12.2 1 c c
II.12.3 2 c c
II.12.4 3 c c
II.12.5 4 c c
II.12.6 5 c c
II.12.7 6 c c
II.12.8 7 c c
II.12.9 8 c c
II.12.10 9 c c
II.12.11 10 c c
II.12.12 11 c c
II.12.13 12 c c
II.12.14 13 c c
II.12.15 14 c c
II.12.16 15 c c
II.12.17 16 c c
II.12.18 17 c c
II.12.19 18 c c
II.12.20 19 c c
II.12.21 20 c c
II.12.22 21 c c
II.12.23 22 c c
II.12.24 23 c c
II.12.25 24 c c
II.12.26 25 c c
II.12.27 26 c c
II.12.28 27 c c
II.12.29 28 c c
II.12.30 29 c c
II.12.31 30 c c
II.12.32 31 c c
II.12.33 32 c c
II.12.34 33 c c
II.12.35 34 c c
II.12.36 35 c c
III Fiber Optic Feeder Installation
Check Fiber optic feeder length and overall insertion loss compliance to design using OTDR. Creat
PDF certification report for handover pack and .SOR file for reference.

III.1
Check insertion loss and reflectance of each network component/event using OTDR. Create PDF
certification report for handover pack and .SOR file for reference.

III.2
Check all LC feeder connectors are clean and free from dust, moisture, contamination and scratch
and meet IEC-61300-3-35. Create consolidated certificate report of connector for handover pack.

III.3
Check BBU, RRU TX ports are clean and free from dust, moisture, contamination and scratches an
meet IEC-61300-3-35. Create consolidated certificate report of connector for handover pack.

III.4

IV Antenna System Checklist


Items
IV.1 Installation Check
IV.1.1 Antenna system installed according to SID
IV.1.2 Correct cable is connected to correct antenna
IV.1.3 No cables or connectors are damaged
IV.1.4 All feeder & jumper cables are properly labeled
All labels are easy to read (not blocked)
IV.1.5

IV.1.6 No labels are peel/tear off at major parts


IV.1.7 All feeders properly earthed
IV.1.8 Connectors are properly connected
IV.1.9 RBS jumper connectors tightened
IV.1.10 Minimum bending radius is fulfilled
IV.1.11 Indoor feeders & jumpers strapped every 60 cm on cable ladder
IV.1.12 Outdoor jumper strapped every 30 cm
IV.1.13 Outdoor antenna system connector properly sealed
IV.1.14 Drip loop applied on feeder at outer inlet
IV.1.15 Drip loop on RETU cable
IV.1.16 Antenna bolts & nuts are completely installed
IV.1.17 Optical Interface Link (OIL) cables properly connected, labeled and strapped (6301 & 6601 )
IV.1.18 OIL cable lead-in is sealed (6301 & 6601 )
IV.1.19 Drip loop applied on OIL at outer inlet (6301 & 6601 )
IV.1.20 OIL clamped (6301 & 6601 )
IV.1.21 TMA/ASC/RIU is properly installed & earthed
IV.1.22 RETU is properly installed & earthed

IV.2 Antenna Type


IV.2.1 Antenna sector 1
IV.2.2 Antenna sector 2
IV.2.3 Antenna sector 3

IV.3 Antenna Position & Height


IV.3.1 Antenna sector 1
IV.3.2 Antenna sector 2
IV.3.3 Antenna sector 3

IV.4 Antenna Direction


IV.4.1 Antenna sector 1 c
IV.4.2 Antenna sector 2 c
IV.4.3 Antenna sector 3 c

IV.5 Mechanical Tilt


IV.5.1 Antenna sector 1 c
IV.5.2 Antenna sector 2 c
IV.5.3 Antenna sector 3 c

IV.6 Electrical Tilt


IV.6.1 Antenna sector 1 c
IV.6.2 Antenna sector 2 c
IV.6.3 Antenna sector 3 c

V ME Power System
V.1 Rectifier Cabinet
V.1.1 RBS power cables routed properly
V.1.2 RBS power cables are labelled
V.1.3 RBS power cables terminated correctly
V.1.4 Breakers are properly labeled
V.1.5 Rectifier occupancy max 83% (N+1 module ) at peak including for charge battery
V.1.6 Breakers are properly connected according to XL specification
V.1.7 Cable distribution meet withh current carrying capacity and XL specification
V.1.8 End cable termination connected to MCB must use veruless*)
V.1.9 Jumpering MCB line (if any) must be connected properly refer to XL specification
V.1.10 Cooling sytem at peak level meet the BTUH calculation
V.1.11 ACPDB occupancy at peak (including charge battery) max 90%
V.1.12 Change Over Switch (COS) occupancy at peak (including charge battery) max 90%
V.1.13 PLN occupancy at peak (including charge battery) max 95%
V.1.14 Genset occupancy at peak (including charge battery) max 70% of its kVA
V.1.15 All rack equipment must be connected to respective grouding bar

V.2 Batteries
V.2.1 Batteries undamaged
V.2.2 Batteries installed & secured according properly
V.2.3 Protective covers correctly installed batteries pole
V.2.4 Temperatur sensor installed properly
V.2.5 Spacers pasted between batteries to ensure air flow
V.2.6 Battery back up test (1 hr test including LTE load),end volt not less than -48VDC
V.2.7 Battery installed must be same brand,type & capacity in one rectifier system

V.3 Incoming Voltage


V.3.1 Outdoor Cabinet
V.3.1.1 L1 (Between 180 - 250 VAC)
V.3.1.2 L2 (Between 180 - 250 VAC)
V.3.1.3 L3 (Between 180 - 250 VAC)

V.3.2 Indoor Cabinet


V.3.2.1 DC Voltage (Between -48 to -60 VDC)

VI Civil Works
VI.1 Outdoor Foundation
VI.1.1 Foundation is constructed as per The CME-ENG Drawing
VI.1.2 Inspection has been done to the concrete foundation and No Crack were found
VI.1.3 Concrete Grade K225
VI.1.4 Concrete Hammer Test Reports for 7 days are available and the test results are accepted

VI.2 RBS/RRU and Bracket Mounting Installation


VI.2.1 Antenna RBS/RRU position heigh : __ /____ mtr.
400mm Horizontal and Vertical Cable Tray and support are provided (complete fixed with Dynabol
VI.2.2 wall/floor)
VI.2.3 Antenna support is at 0' perpendicular from ground
VI.2.4 Antenna mounting position is correct. All bracket mounting, pole and accessories are completed
bolts & nuts are tightened as per the requirements

VI.3 Grounding Cable Condition


VI.3.1 Grounding cable connection is secure
VI.3.2 The bracket grounding cable holder has isolation
VI.3.3 The grounding cable doesn't contact with tower body
Connection between grounding all equipment in the tower (antenna RBS, Minilink, RRU) and the m
VI.3.4
grounding cable already installed
Connection between grounding all equipment in the tower (antenna RBS, Minilink, RRU) and the m
VI.3.4
grounding cable already installed
VI.3.5 Connection in the grounding bar is good with no corrosion
VI.3.6 Outdoor Cabin grounding should be connected to grounding perimeter
VI.3.7 Equipment Grounding Conductor, BC50 mm2
VI.3.8 Equipment Grounding Resistance <1 Ohm
a. Indoor (at grounding bar) = . Ohm , acceptable ?
b. Outdoor (at cable ladder) = .Ohm , acceptable ?
VI.3.9 Additional grounding bar must be provided (if existing grounding bar full/NA)

VII DOCUMENT COMPLETION


All Site Instructions have been closed and signed by related persons and the docs enclosed
VII.1
VII.2 Concrete Hammer Test acknowledge and approved by PT.HS
As Built Drawing is available and verified accordingly while acceptance process took place
VII.3
Photo documentation (RBS/RRU/Bracket position, Cable Tray, Outdoor Foundation & Cabin, ground
VII.4 connection)
VII.5 Concrete Hammer Test acknowledge and approved by PT.HS

VIII Pending Items


Please list down all the pending items and timeline to complete it

No. Items Completion Date

Additional Notes
Acceptance Process by:
Vendor:_____________________

____________________________
Name, date & signature
TEST FORM
TATION - LTE

Date of Acceptance:

c RBS 6101
c RBS 6

OK NOK N/A Remarks

Bar)
c c c

c c c
c c c

c c c

c c c

ght & properly assembled


c c c

c c c
c c c
c c c
c c c
c c c
ching) c c c
c c c
c c c
c c c

c c c
c c c
c c c
c c c
g to SID c c c
c c c
c c c
ports c c c
c c c

uration)
c c c

c c c

c c c

c c c
c c c
c c c

c c c

c c c
. All power connections
c c c

OK OK N/A Remarks

c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

c c c
c c c

c c c
c c c
c c c
c c c
c c c

OK OK N/A Remarks

c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

OK OK N/A Remarks

c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

OK OK N/A Remarks
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

dscp Pbit OK N/A Remarks


36 c c
37 c c
38 c c
39 c c
40 c c
41 c c
42 c c
43 c c
44 c c
45 c c
46 c c
47 c c
48 c c
49 c c
50 c c
51 c c
52 c c
53 c c
54 c c
55 c c
56 c c
57 c c
58 c c
59 c c
60 c c
61 c c
62 c c
63 c c
64 c c
65 c c
66 c c
67 c c
68 c c
69 c c
70 c c
71 c c
esign using OTDR. Create

c c c
ing OTDR. Create PDF

c c c
ntamination and scratches
ctor for handover pack.

c c c
nation and scratches and
for handover pack.

c c c

OK NOK N/A Remarks

c c c
c c c
c c c
c c c

c c c

c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
ed (6301 & 6601 ) c c c
c c c
c c c
c c c
c c c
c c c

c c c
c c c
c c c

c c c Height: m
c c c Height: m
c c c Height: m

c Value: c NBWO c Existing


c Value: c NBWO c Existing
c Value: c NBWO c Existing

Measured by Tilt Meter


c Value: c NBWO c Existing
c Value: c NBWO c Existing
c Value: c NBWO c Existing

NBWO Actual
c Value:
c Value:
c Value:

c c c
c c c
c c c
c c c
battery c c c
c c c
on c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c
c c c

c c c
c c c
c c c
c c c
c c c
48VDC c c c
em c c c

c c c
c c c
c c c

c c c

c c c
ound c c c
c c c
ts are accepted
c c c

c c c
plete fixed with Dynabolts to
c c c
c c c
essories are completed. All
c c c

c c c
c c c if any additional
c c c
Minilink, RRU) and the main
c c c
c c c
c c c
c c c
c c c
c c c
c c c
NA) c c c

he docs enclosed
c c c
c c c
ocess took place
c c c
ndation & Cabin, grounding
c c c
c c c

Completion Date Person In Charge Contact No.


Verified & Approved by:
Customer:____________________

____________________________
Name,Name, date & signature
LTE XL AXIATA RBS ATP FORM Rev B
Speed Test Repoert
LTE SITE ID : LTE SITE NAME :

Sector 1
Sector1 LTE (4G): Sector1 LTE (4G):
eNodeB ID and Cell ID at normal hour

Sector 2
Sector1 LTE (4G): Sector1 LTE (4G):
eNodeB ID and Cell ID at normal hour
Sector 3
Sector1 LTE (4G): Sector1 LTE (4G):

eNodeB ID and Cell ID at normal hour


Sector 4
Sector1 LTE (4G): Sector1 LTE (4G):

eNodeB ID and Cell ID at normal hour


Sector 5
Sector1 LTE (4G): Sector1 LTE (4G):

eNodeB ID and Cell ID at normal hour

NA NA

Sector 6
Sector1 LTE (4G): Sector1 LTE (4G):

eNodeB ID and Cell ID at normal hour

NA NA
ACCEPTANCE PROCESS BY : VERIFIED AND APPROVED BY PT. HUAWEI S
VENDOR Construction & Installation
(For ATP with contractor and handover to Field O

Name
Field Operation
Name

Name Date & Signatur


RBS ATP FORM Rev B
d Test Repoert
LTE SITE NAME :

Sector1 LTE (4G):


at busy hour

Sector1 LTE (4G):


at busy hour
Sector1 LTE (4G):

at busy hour
Sector1 LTE (4G):

at busy hour
Sector1 LTE (4G):

at busy hour

NA

Sector1 LTE (4G):

at busy hour

NA
APPROVED BY PT. HUAWEI SERVICES

tractor and handover to Field Operation)

Date & Signature


LTE XL AXIATA RBS ATP FORM Rev B
eNodeB Capture
LTE SITE ID : LTE SITE NAME :

Alarm & Site label

CABX
Inventori HW & License

Inventori HW & License


Inventori HW & License

Inventori HW & License


Inventori HW & License
Interface Status

Ip_Address_S1

Default_Gateway_S1
IpSyncRef Status

Test Connectivty S1 to IpSyncRef


Test Connectivty S1 to IpSyncRef

Test Connectivty S1 to Default_Gateway_S1


Test Connectivty S1 to Vlan_S1

MME Status
Test Connectivty S1 to MME

Ip_Address_OAM
Default_Gateway_OAM

Test Connectivty OAM to Default_Gateway_OAM & to V


NtpServer status & Test Connectivty OAM to NtpSe

EUtranCellId & Ue Status

Band, ENODEB_ID & TAC Status


Sector & CID Status

PCI, earfcnd & ChannelBandwidth


LTE Tech Configuration

2x2 MIMO = 2 TAntennas + 2 RxAntennas


1X2 SISO = 1 TxAntennas + 2 RxAntennas

QOS & dscpToPbitMap


QOS & dscpToPbitMap
QOS & dscpToPbitMap
CV & Update SW Level

ACCEPTANCE PROCESS BY : VERIFIED AND APPROVED BY PT. HUAWEI S


VENDOR Construction & Installation
(For ATP with contractor and handover to Field O

Name
Field Operation
Name

Name Date & Signatur


RBS ATP FORM Rev B
deB Capture
LTE SITE NAME :

m & Site label

CABX
ori HW & License

ri HW & License
ri HW & License
ri HW & License
rface Status

Address_S1

t_Gateway_S1
ncRef Status

tivty S1 to IpSyncRef
tivty S1 to IpSyncRef

S1 to Default_Gateway_S1
ctivty S1 to Vlan_S1

ME Status
ectivty S1 to MME

ddress_OAM
_Gateway_OAM

fault_Gateway_OAM & to Vlan_Oam


Connectivty OAM to NtpServer

ellId & Ue Status

DEB_ID & TAC Status


r & CID Status

& ChannelBandwidth
ch Configuration

dscpToPbitMap
dscpToPbitMap
dscpToPbitMap
pdate SW Level

APPROVED BY PT. HUAWEI SERVICES

tractor and handover to Field Operation)


Date & Signature
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 71 (163)

STANDARD PRACTICE FOR ACCEPTANCE PROCESS


OTDR / ATTENUATION MEASUREMENT
DOCUMENT NO. :

TESTING REPORT

SITE ID_NAME : MC2412608_CIRENDEUGUNUNG


NETWORK ELEMENT : 2G 3G LTE
MEASUREMENT METHOD : BEFORE INSTALLATION
CABLE ROUTE : DU_RRU DU_RRU_RRU
CABLE TYPE : 2F LC- LC SM
NUMBER OF FIBER :6
: S1=70.m, S2=70..m,
TOTAL CABLE LENGTH (M)
S3=70..m, S

OPTICAL ATTENUATION
FIBER#
LENGTH M TOT
FIBER# LABEL m db/km db/km
1 Sector 1 #TX 70 0.1 0.26
2 Sector 1 #RX 70 0.14 0.19
3 Sector 2 #TX 70 0.11 0.16
4 Sector 2 #RX 70 0.1 0.04
5 Sector 3 #TX 70 0.09 0.16
6 Sector 3 #RX 70 -0.008 0.04

**) Max ATTENUATION (dB/km) : 0.22 (1310nm)/0.36 (1550nm)


**) Max ATTENUATION (dB/m) : 0.00022 (1310nm)/0.00036 (1550nm)
**) Max TOT ATTENUATION (dB/km) : 0.40(1310nm) / 0.25(1550nm)
**) Max TOT ATTENUATION (dB/m) : 0.00040(1310nm) / 0.00025(1550nm)

sample Capture

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 72 (163)

Sector 1 TX
A. ALL EVENT RESULT CAPTURE

B. 2 POINT MARKERS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 73 (163)

Sector 1 RX
A. ALL EVENT RESULT CAPTURE

B. 2 POINT MARKERS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 74 (163)

Sector 2 TX
A. ALL EVENT RESULT CAPTURE

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 75 (163)

B. 2 POINT MARKERS LOSS MEASUREMENT

Sector 2 RX
A. ALL EVENT RESULT CAPTURE

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 76 (163)

B. 2 POINT MARKERS LOSS MEASUREMENT

Sector 3 TX
A. ALL EVENT RESULT CAPTURE

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 77 (163)

B. 2 POINT MARKERS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 78 (163)

Sector 3 RX
A. ALL EVENT RESULT CAPTURE

B. 2 POINT MARKERS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 79 (163)

FIBER SCOPE INSPECTION FOR OPTICAL CONNECTOR

SECTOR 1
A. CONN_TX_TO_DU

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 80 (163)
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 1
B. CONN_RX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 81 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 1
C. CONN_TX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 82 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 1
D. CONN_RX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 83 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 2
A. CONN_TX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 84 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 2
B. CONN_RX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 85 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 86 (163)

SECTOR 2
C. CONN_TX_TO_RRU

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 87 (163)

Result = Pass/Reject

SECTOR 2
D. CONN_RX_TO_RRU

Inspection Summary
Zone Diameter Defects

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 88 (163)
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 3
A. CONN_TX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 89 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 3
B. CONN_RX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 90 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 3
C. CONN_TX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 91 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

SECTOR 3
D. CONN_RX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 92 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

FIBER SCOPE INSPECTION for TX Bulk Head Only

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 93 (163)

SECTOR 1
A. Bulk Head_TX_DU

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject
** For RX port Bulk Head RX can not be measured because of its port just glass only

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 94 (163)

SECTOR 1
B. Bulk Head_TX_RRU

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 95 (163)
** For RX port Bulk Head RX can not be measured because of its port just glass only

SECTOR 2
A. Bulk Head_TX_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 96 (163)
Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject
** For RX port Bulk Head RX can not be measured because of its port just glass only

SECTOR 2
B. Bulk Head_TX_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 97 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject
** For RX port Bulk Head RX can not be measured because of its port just glass only

SECTOR 3
A. Bulk Head_TX_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 98 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject
** For RX port Bulk Head RX can not be measured because of its port just glass only

SECTOR 3
B. Bulk Head_TX_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 99 (163)

Inspection Summary
Zone Diameter Defects
Inner Outer Result Count
Zone_A 0 25 Pass 0
Zone_B 25 120 Pass 0
Zone_C 120 130 Pass 0
Zone_D 130 250 Pass 0

Result = Pass/Reject
** For RX port Bulk Head RX can not be measured because of its port just glass only

ADDITIONAL NOTES

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 100 (163)

ACCEPTANCE PROCESS BY : VERIFIED AND APPROVED BY PT. HUAWEI SER


VENDOR Construction & Installation
(For ATP with contractor and handover to Field Ope

Name
Field Operation
Name

Name

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 101 (163)

ICE FOR ACCEPTANCE PROCESS


NUATION MEASUREMENT
DOCUMENT NO. :

PT. XL AXIATA

NG

AFTER INSTALLATION
OPERATING WAVE LENGTH : 1310 nm 1550 nm
ATTENUATION (dB/km) : 0.22 (1310nm)/0.36 (1550nm)
TOT ATTENUATION (dB/km) : 0.40(1310nm) / 0.25(1550nm)

OTDR TYPE : VePAL FX300

FIBER SCOPE TYPE : DI-1000 (JO. VePAL FX300)

REMARKS

)/0.36 (1550nm)
nm)/0.00036 (1550nm)
0nm) / 0.25(1550nm)
310nm) / 0.00025(1550nm)

ure

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 102 (163)

ctor 1 TX
ULT CAPTURE

RS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 103 (163)

ctor 1 RX
ULT CAPTURE

RS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 104 (163)

ctor 2 TX
ULT CAPTURE

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 105 (163)

RS LOSS MEASUREMENT

ctor 2 RX
ULT CAPTURE

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 106 (163)

RS LOSS MEASUREMENT

ctor 3 TX
ULT CAPTURE

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 107 (163)

RS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 108 (163)

ctor 3 RX
ULT CAPTURE

RS LOSS MEASUREMENT

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 109 (163)

TICAL CONNECTOR

CTOR 1
NN_TX_TO_DU

Scratches
Result Count
Pass 0

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 110 (163)
Pass 0
Pass 0
Pass 0

CTOR 1
NN_RX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 111 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 1
TX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 112 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 1
RX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 113 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 2
NN_TX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 114 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 2
NN_RX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 115 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 116 (163)

CTOR 2
TX_TO_RRU

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 117 (163)

CTOR 2
RX_TO_RRU

Scratches

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 118 (163)
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 3
NN_TX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 119 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 3
NN_RX_TO_DU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 120 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 3
TX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 121 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

CTOR 3
RX_TO_RRU

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 122 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

Bulk Head Only

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 123 (163)

CTOR 1

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

e of its port just glass only

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 124 (163)

CTOR 1
k Head_TX_RRU

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 125 (163)
e of its port just glass only

CTOR 2

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 126 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

e of its port just glass only

CTOR 2

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 127 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

e of its port just glass only

CTOR 3

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 128 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

e of its port just glass only

CTOR 3

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 129 (163)

Scratches
Result Count
Pass 0
Pass 0
Pass 0
Pass 0

e of its port just glass only

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
RBS 6000 FAMILY ACCEPTANCE TEST FORM_x000D_ 130 (163)

RIFIED AND APPROVED BY PT. HUAWEI SERVICES


struction & Installation
ATP with contractor and handover to Field Operation)

d Operation

Date & Signature

Prepared: EID/OJI/CCA Tatang Sukaman_x000D_Approved:


Date: 2015-02-02 EID/OJI/CE [M. Raymil _x000D_Rev:
Mirza] G
Sheet: Optical Measurement
u t h
s e p
P l e a O Q
B Sp
ec h
i al T
at er
M
e re
uht
s e p t
l e a Q i f i c a
P O
B Spe c
ec h
i al T
t er
e
t i o n
i f i c a
c
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008
SITE
RADIO BASE STA

SITE DATA
SITE ID :
SITE NAME :
PO NUMBER :
AREA :
PROJECT ITEMS :

I RBS System

BTS Open & Close View

Jumper Feeder Near BTS sector 1

PT EXCELCOMINDO PRATAMA - Proprietary 137 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Rectifier

Power BTS on Rectifier

PT EXCELCOMINDO PRATAMA - Proprietary 138 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Grounding BTS

II Antenna System

Mechanical Tilting Sector 1

Tilt Meter Value : ......... Mounting Tilt Value : .........

Mechanical Tilting Sector 2

PT EXCELCOMINDO PRATAMA - Proprietary 139 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Tilt Meter Value : ......... Mounting Tilt Value : .........

Mechanical Tilting Sector 3

Tilt Meter Value : ......... Mounting Tilt Value : .........

Antenna Heigh

PT EXCELCOMINDO PRATAMA - Proprietary 140 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Height : ......... m

PT EXCELCOMINDO PRATAMA - Proprietary 141 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Azimuth & Panoramic sector 2

Azimuth Value : .........

Grounding Kit Feeder

View Routing Feeder Cable to BTS

PT EXCELCOMINDO PRATAMA - Proprietary 142 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Jumper Feeder to Antenna Sector 1

Jumper Feeder to Antenna Sector 3

PT EXCELCOMINDO PRATAMA - Proprietary 143 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

View Site

View Building / Access

ACCEPTANCE PROCESS BY :
VENDOR : ________________

PT EXCELCOMINDO PRATAMA - Proprietary 144 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008
NAME & DATE
NOTES: - For ATP between Contractor and CNI, both parts shall sign the forms

- For HANDOVER between CNI and FOP, both parts shall sign the forms

- For ATP between VENDOR and FOPs, both parts shall sign the forms

PT EXCELCOMINDO PRATAMA - Proprietary 145 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008
SITE DOCUMENTATIONS
RADIO BASE STATION & ANTENNA SYSTEMS

ose View Module RBS 2G/3G

BTS sector 1 Jumper Feeder Near BTS sector 2

PT EXCELCOMINDO PRATAMA - Proprietary 146 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

r Jumper Feeder Near BTS sector 3

Rectifier DDF/IP Transmission

PT EXCELCOMINDO PRATAMA - Proprietary 147 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

BTS

g Sector 1 Electrical Tilting Sector 1

ting Tilt Value : ......... Electrical Tilt Value : .........

g Sector 2 Electrical Tilting Sector 2

PT EXCELCOMINDO PRATAMA - Proprietary 148 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

ting Tilt Value : ......... Electrical Tilt Value : .........

g Sector 3 Electrical Tilting Sector 3

ting Tilt Value : ......... Electrical Tilt Value : .........

eigh Azimuth & Panoramic sector 1

PT EXCELCOMINDO PRATAMA - Proprietary 149 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Azimuth Value : .........

PT EXCELCOMINDO PRATAMA - Proprietary 150 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

mic sector 2 Azimuth & Panoramic sector 3

Azimuth Value : .........

Feeder View Routing Feeder Cable on Horisont

r Cable to BTS View Label Feeder

PT EXCELCOMINDO PRATAMA - Proprietary 151 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

tenna Sector 1 Jumper Feeder to Antenna Sector

tenna Sector 3 Grounding Busbar Tower

PT EXCELCOMINDO PRATAMA - Proprietary 152 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

e View Tower

/ Access

VERIFIED AND APPROVED BY PT. HS :


CONSTRUCTIONS&INSTALLATION(for ATP with contractor &

NAME:
FIELD OPERATIONS (for handover from CNI, ATP with vendor)

PT EXCELCOMINDO PRATAMA - Proprietary 153 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008
NAME:

PT EXCELCOMINDO PRATAMA - Proprietary 154 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008
ONS
ENNA SYSTEMS

Module RBS 2G/3G

Jumper Feeder Near BTS sector 2

PT EXCELCOMINDO PRATAMA - Proprietary 155 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Jumper Feeder Near BTS sector 3

DDF/IP Transmission

PT EXCELCOMINDO PRATAMA - Proprietary 156 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Electrical Tilting Sector 1

Electrical Tilt Value : .........

Electrical Tilting Sector 2

PT EXCELCOMINDO PRATAMA - Proprietary 157 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Electrical Tilt Value : .........

Electrical Tilting Sector 3

Electrical Tilt Value : .........

Azimuth & Panoramic sector 1

PT EXCELCOMINDO PRATAMA - Proprietary 158 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Azimuth Value : .........

PT EXCELCOMINDO PRATAMA - Proprietary 159 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Azimuth & Panoramic sector 3

Azimuth Value : .........

View Routing Feeder Cable on Horisontal Tray

View Label Feeder

PT EXCELCOMINDO PRATAMA - Proprietary 160 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

Jumper Feeder to Antenna Sector 2

Grounding Busbar Tower

PT EXCELCOMINDO PRATAMA - Proprietary 161 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008

View Tower

D AND APPROVED BY PT. HS :


TIONS&INSTALLATION(for ATP with contractor & handover to FOP)

signature
RATIONS (for handover from CNI, ATP with vendor)

PT EXCELCOMINDO PRATAMA - Proprietary 162 of 12


RBS ACCEPTANCE FORM
FRM/NFOP/100001
Issue 8.1
Effective Date 1 Jan 2008
signature

PT EXCELCOMINDO PRATAMA - Proprietary 163 of 12


RBS ACCEPTANCE FORM