Supply & laying of 1400 mm dia R.C.C. NP-3
pipe, rubber rings jointing materials and specials
lowering the same in to the trenches up to depth as
specified below G.L. true to alignment and gradient
including barricading of site, refilling of trenches
8 meter 65.00 35550.00 2310750.00 35550.00 2310750.00
with proper compaction including disposal of
surplus earth. complete including supplyof all
material, labour, T&P etc. required for proper
completion of work as per direction of Engineer In
charge.
Supply & placing of Cement concrete 1:4:8 in
9 250mm thick layer to retain the embankment its sqm 300.42 1375.00 413077.50 1476.00 443419.92
original slope.
Total Amount 8770576.28 8736426.51