Comparative for Approach Bridge at Bargadghat SPS - District A Zone 2

Allahabad Sewerage Network Project


L&T UPJN
S. No. Item Specifications Units Quantity
Rate Amount Rate Amount
Cement concrete 1:2:4 machine mixed with cement
content 325 kg/cum, but excluding the cost of steel
1 reinforcement centring and shuttering in foundation cum 50.25 8051.00 404562.75 7673.20 385578.30
and plinth including all aspects, as per the direction
of engineer incharge.
Reinforced cement concrete M-20 with cement
@450/kg per cum hand mixed but excluding steel
2 reinforcement centring and shuttering in foundation cum 305.66 9282.00 2837136.12 9177.60 2805225.22
and plinth, including all aspects, as per the
direction of engineer incharge.
Centering & shuttering for encasing of laid pipe in
3 proper shape & size as per the direction of engineer sqm 303.83 504.00 153130.32 494.00 150092.02
in charge.
Cement concrete 1:3:6 machine mixed with cement
content 225 kg/cum, in foundation and plinth
4 cum 5.29 7123.00 37680.67 6857.50 36276.18
including all aspects, as per the direction of
engineer incharge.
Providing & laying of good quality Earth free from
dewerage & other organic material including
5 cum 3457.70 521.00 1801461.70 503.65 1741470.61
compaction as per the direction of engineer
incharge.
Supply & fixing of Fe-500 TMT steel as per
drawing, including the cost of binding wite & other
6 MT 8.37 75630.00 633023.10 80000.00 669600.00
tools & tackels in all aspects as per the direction of
engineer in charge.
First class burnt Brick work laid in cement sand
7 mortar 1:4 in foundation and plinth including all Cum 28.21 6372.00 179754.12 6877.50 194014.28
aspects as per the direction of engineer in charge.

1
Supply & laying of 1400 mm dia R.C.C. NP-3
pipe, rubber rings jointing materials and specials
lowering the same in to the trenches up to depth as
specified below G.L. true to alignment and gradient
including barricading of site, refilling of trenches
8 meter 65.00 35550.00 2310750.00 35550.00 2310750.00
with proper compaction including disposal of
surplus earth. complete including supplyof all
material, labour, T&P etc. required for proper
completion of work as per direction of Engineer In
charge.
Supply & placing of Cement concrete 1:4:8 in
9 250mm thick layer to retain the embankment its sqm 300.42 1375.00 413077.50 1476.00 443419.92
original slope.
Total Amount 8770576.28 8736426.51