MEETING ATTENDEES
S.No Name Organization/ Designation Mail Address
1 Zuhair Minez ACTCO / Project Manager zuhairqahwaji@gmail.com
2 Saqib Adnan ACTCO / Sr.MEP Engineer s.adnan@actco.ae
3 Ahmad Ghazi ACTCO / Electrical Engineer ahmad.190770@yahoo.ae
4 Aswin Madhu Susnomics/ Green Building Engineer aswin@susnomics.com
MEETING KEY NOTES
S.No. Documents Required Notes for Action ACTCO Reply
Proof (Photograph and attendance sheets) of Training to M/s. Actco are requested to provide the same, since the
1 staff on Waste Management, IAQ during construction, Construction activities are by M/s. ACTCO under the Please find in Section-1
Sustainability tool box talk supervision of M/s. Al- Gurg
External lighting simulation (as per external lighting ACTCO to provide the exterior lighting simulation report
8 layout) report as per EHS requirements (1 lux at site meeting the EHS requirements for both, i.e. lux at site Please find in Section-6
boundary & 0.1 lux at 15ft away from the boundary) boundary & lux at 15 ft. away from the boundary.
ACTCO to provide the Handover certificate & training Partially attached. Please find in
9 Handover certificate
records on Tenant handover. Section-7
Photographs confirming the onsite location of Handover
Al-Gurg to provide the photographs where all the
10 & building maintenance documents such as O&M Al-Gurg
Handover documents will be located in the project
Manuals, As built drawings, building log book,etc.,
Proof of payment of In-House Certification Fees Al-Gurg to share the EHS In-house certification payment
11 Al-Gurg
(Certification fee receipt) receipt
All the documents (Actco scope) requested above are agreed to be shared by M/s. Actco on or before 24th April 2017