Documents Required for Responding To EHS BCC Comments / EHS In-house Certification

Project : Jebel Ali Recreation Club


Consultant : Al- Gurg Consultant
Contractor : Actco General Contracting
Date : 19 April 2017

MEETING ATTENDEES
S.No Name Organization/ Designation Mail Address
1 Zuhair Minez ACTCO / Project Manager zuhairqahwaji@gmail.com
2 Saqib Adnan ACTCO / Sr.MEP Engineer s.adnan@actco.ae
3 Ahmad Ghazi ACTCO / Electrical Engineer ahmad.190770@yahoo.ae
4 Aswin Madhu Susnomics/ Green Building Engineer aswin@susnomics.com
MEETING KEY NOTES
S.No. Documents Required Notes for Action ACTCO Reply
Proof (Photograph and attendance sheets) of Training to M/s. Actco are requested to provide the same, since the
1 staff on Waste Management, IAQ during construction, Construction activities are by M/s. ACTCO under the Please find in Section-1
Sustainability tool box talk supervision of M/s. Al- Gurg

HVAC (FAHU , AHU/FCU/ Chiller, Outdoor Units, chilled


water pumps)
Lighting (lux reports for internal & external lighting) ,
Associated controls (motion sensor, timer, daylight It is noted that only the office areas are under the scope of
sensor, thermostat, Outdoor Air flow monitor, Fresh air M/s. ACTCO for Air conditioning & Fresh air.
So kindly request to share the Commissioning & test
panel, etc.)
2 reports of A/c units, FAHU units, lighting systems, Please find in Section-2
Provide the below documents for all the above associated controls which are under the ACTCO scope.
mentioned systems: Also share the O&M manuals and datasheets for all civil &
a. Installation checklist MEP items.
b. Prefunctional checklist
c. Functional checklist
d. Commissioning report

ACTCO to provide the snag list on all the systems


3 Snag List & Closeout report (MEP only) installation & commissioning, after completing the Phase 2 After Phase-2 completion
(or) after all the work under ACTCO scope are completed.
S.No. Documents Required Notes for Action ACTCO Reply
ACTCO to provide the handover certificate & documents
which were handed over to the Client for Phase 1 of the
Proof of training of operating personnel and building
4 project. N/A
occupants ACTCO to provide the GB training records on Tenant/ FM
team. (Attendance sheet)

Actco to share the O&M manuals and datasheets for the


A/c units, lighting fixtures (internal & external) , motion
5 O&M Manual Please find in Section-3
sensor, timer, energy meter, irrigation systems, sanitary
fixtures, fire suppression systems.
Please provide the As built drawings for Civil & MEP in
6 As built drawings (HVAC, Civil, Electrical & Plumbing) Please find in Section-4
AutoCAD

Please provide the Asbuilt SLD highlighting the Energy


Meter locations in AutoCAD.
As built Single Line Drawing (SLD) of energy meters with
7 As discussed add an energy meter in the HVAC i.e. to Please find in Section-5
Meter schedule measure all the A/c load which are under Client scope.
Also provide the meter schedule separately in excel sheet.

External lighting simulation (as per external lighting ACTCO to provide the exterior lighting simulation report
8 layout) report as per EHS requirements (1 lux at site meeting the EHS requirements for both, i.e. lux at site Please find in Section-6
boundary & 0.1 lux at 15ft away from the boundary) boundary & lux at 15 ft. away from the boundary.
ACTCO to provide the Handover certificate & training Partially attached. Please find in
9 Handover certificate
records on Tenant handover. Section-7
Photographs confirming the onsite location of Handover
Al-Gurg to provide the photographs where all the
10 & building maintenance documents such as O&M Al-Gurg
Handover documents will be located in the project
Manuals, As built drawings, building log book,etc.,
Proof of payment of In-House Certification Fees Al-Gurg to share the EHS In-house certification payment
11 Al-Gurg
(Certification fee receipt) receipt

AlGurg to co-ordinate with M/s. Nakheel to share the


12 Confirmation of Appointment of Recycling Waste Hauler information on the Recycling waste hauler to be proposed Al-Gurg
for the project.

Photograph/Extracts of the Building log book (Energy


Actco to prepare the building log book to track the
metering & Water metering , recycling waste quantity
13 Common area HVAC/ Lighting load energy consumption Al-Gurg
diversion) that will be followed onsite & the details of based on the meter schedule.
the F&M designated staff in-charge
S.No. Documents Required Notes for Action ACTCO Reply

Photographs for the following:


o Car Pooling
o Landscape
o Roof with SRI material
o Light fixtures (Internal & External)
o Sanitary fixtures (Faucets & Water Closets, shower
heads)
o Irrigation system
o Energy Meters (separate meters for lighting & HVAC) Photographs under the scope of Actco such as Landscape,
roof, sanitary fixtures, lighting fixtures are received.
o Water Meters
14 Pending from Actco are Car Pooling, Bicycle parking, No Please find Section-8
o Recycle Bins (At Floor levels & Centralised bins) smoking signages, recycle bins (5 bins to be provided i.e.
o No Smoking signages Paper, plastic, Glass, Metal & cardboard)
o FAHU with Air flow monitor
o Floor mat (At the main entrances of the building 3m
length)
o Motion sensor (lighting controls)
o CO2 Sensors (Applicable only for densely occupied
spaces)
o Bicycle Parking, if applicable
o Shower & changing rooms, if applicable

All the documents (Actco scope) requested above are agreed to be shared by M/s. Actco on or before 24th April 2017