Documente Academic
Documente Profesional
Documente Cultură
SPEC 00-C-02
CONCRETE WORKS
a) Class 15/20 ( / s)
Shall be used for all work not requiring special purpose concrete as
described in (a), (c) or (d).
d) Class 30/20 (s /)
The sub-classification ( /s) above indicates the option of using type "D"
cement instead of ordinary portland cement.
CONCRETE WORKS; INSTALLATION AND DESIGN SPECIFICATION NO. 00-C-02
REVISION B PAGE 3
AS1204 Grade 250, Fy = 250Mpa for standard embedded steel items shall be
the general standard.
2.7.1 Pedestals
The top of the pedestal shall be 200mm above the nominal floor level,
with all major pedestals in the one building being at the same reduced
level.
Where rock anchors have been used to resist uplift, the residual
ground pressure may be used to resist sliding. A safety factor of 1.5
CONCRETE WORKS; INSTALLATION AND DESIGN SPECIFICATION NO. 00-C-02
REVISION B PAGE 4
i.e., DL = 20 (Vertical)
WL = -30 (Vertical)
RA = 40 (Residual rock anchor force).
= u[ ( 20 + 40 ) - ( 1.5 x 30 ) ]
= u x 15
Where u is the co-efficient of friction between the rock and the footing
and shall be taken as 0.40.
The resulting shear resistance shall have a safety factor against the
actual calculated sliding force of 1.5.
The effect of the water table on the weight of the foundation shall be
considered when calculating the resisting moment.
Retaining walls shall have a minimum factor of safety against sliding of 1.5.
The eccentricity of the resulting force, measured from the centre line of the
base, should not exceed one sixth the width of base and the maximum
pressure should not exceed the allowable soil pressure. One or the other of
these two criteria commonly controls the width of the base.
When wind forces are resisted, then a 33% increase in the allowable soil
bearing pressure is allowed. The structure must be capable of resisting other
forces without the 33% increase in the allowable soil bearing pressure. No
increase in resistance to sliding is allowed due to the possibility of loss of
contact area between the base and soil.
All structures below or within maximum possible water table level shall be
designed with a minimum factor of safety of 1.25 against buoyancy.
2.10.1 Pedestals
At rest pressure
- Sand/Gravel 0.50
- Clay 0.80
Passive pressure
- Sand/Gravel 3.70
- Clay 1.00 (Kac = 2)
3.1 Records
The Contractor shall keep accurate and up to date records of concrete work,
as follows:
All works, stages of work, materials and processes, shall be made available
for, and be subject to, the inspection and approval of KCGM.
3.3.1 General
All excavations for foundations shall be true to line and level and shall
conform with the dimensions as shown on the drawings. All vertical
faces shall be barred down where necessary and the excavation shall
be cleared of all loose material and surface water immediately prior to
concrete placement.
The Contractor shall make available an adequate size labour force for
the operation in hand. During concreting, a competent steel fixer shall
be in attendance to adjust and correct the reinforcement if necessary.
Likewise a carpenter shall be present to ensure that formwork is
retained in place.
3.4.2 Pouring
3.5.1 Vibration
All structural concrete shall be compacted by vibration to a plan and in
a manner approved by KCGM.
3.6.1 General
3.7 Finishes
3.8 Concrete
3.8.3 The Contractor shall be responsible for the correct mix being delivered
to site, and placed in accordance with this specification.
3.8.4 If testing shows the concrete in place does not meet this specification,
the Contractor shall remove and replace the concrete not complying
with the specifications.
3.8.5 When ordering concrete, the Contractor shall specify to the supplier
the following:
- Characteristic Strength, F'c
- Water/Cement Ratio
- Minimum Cement Content
- Cement Type
- Slump
- Maximum Aggregate Size
3.8.6 Materials from local sources may be used if it can be shown that they
comply with the relevant code requirements.
3.8.8 The Contractor shall be responsible for taking samples of the concrete
and the testing of samples in accordance with AS1012, "Methods of
Testing Concrete" at the frequencies specified in the table below.
Each sample shall consist of three (3) test cylinders which shall be
tested by a laboratory registered with the "National Association of
Testing Authorities", as follows:
- one (1) at seven (7) days after the placing of the concrete;
- one (1) at twenty-eight (28) days after placing of the concrete;
- one (1) spare.
For each additional 50m3 of pour one (1) additional sample shall be
taken.
3.9 Reinforcement
3.9.1 Grades
Reinforcing bars shall be cut and bent in accordance with the bending
schedules. All cutting and bending of bars shall be in accordance with
AS3600.
3.9.4 Fixing
The ends of all binding wire shall be turned in to the concrete and on
no account shall they be left in contact with the shuttering.
Immediately prior to concrete placement, all loose rust, oil, paint, dried
mortar and other foreign substances affecting bond shall be cleared
off reinforcement.
3.10 Formwork
3.10.1 General
3.10.2 Stripping
Where not included in this table, the minimum stripping times shall be
as recommended in AS1509.
Notes:
1. Reference Standards: AS3600 SAA Concrete Code; AS1509 SAA Formwork Code; AS1082 Glossary of Formwork Terms; AS1510 Part
1 Control of Concrete Surfaces - Formwork.
This specification shall be read in conjunction with the above standards to determine full requirements for tolerances. In cases of
conflict this specification has precedence over the above standards.
CONCRETE WORKS; INSTALLATION AND DESIGN SPECIFICATION NO. 00-C-02
REVISION B PAGE 16
2. Tabulated tolerances apply both to tolerances on individual members and to accumulative tolerances.
3. "Measured Distance" is the distance over which the specified tolerance is measured and shall be the full length, width, depth or height
unless otherwise noted.
4. Variations in level for suspended floors shall be measured before the removal of supporting shores.
5. Tolerances for Class 5 Formwork shall also apply to concrete deposited in contact with ground, including floor slabs with membrane
underneath.
CONCRETE WORKS; INSTALLATION AND DESIGN SPECIFICATION NO. 00-C-02
REVISION B PAGE 17
All holes, grooves, chases and ribs shall be formed during the casting
operation, unless otherwise approved by KCGM.
3.12.2 Location
If the position of any of the above items is found to clash with major
reinforcement, and structural member of piece of plant, then KCGM
shall be consulted. KCGM will direct the Contractor regarding the
measures to be taken.
Where bolts are detailed on the drawings with base plate and sleeves,
full length sleeves of approved material shall be fitted centrally around
each holding down bolt and shall be kept in firm contact with the base
plate.
All control joints shall be in the positions and formed in accordance with the
typical details as shown on any drawings nominated by KCGM.
Recesses for control joints shall be accurately formed and filled with sealant
nominated on the drawings in strict accordance with the manufacturer's
recommendations. If curing compounds have been used on concrete any
compound film on concrete faces where a sealant bond is required shall be
CONCRETE WORKS; INSTALLATION AND DESIGN SPECIFICATION NO. 00-C-02
REVISION B PAGE 18
cleaned off and removed to the satisfaction of KCGM to provide clean fresh
concrete surfaces for contact with sealant compounds.
Prevailing Winds
Direction South to East
Basic Design Wind Velocity 37m/s (50 year return period)
Rainfall
General Rainfall Period Winter
Annual Mean (mm) 256
Max Monthly Mean (mm) 31 (June)
Avg Annual Thunderdays 20
CONCRETE WORKS; INSTALLATION AND DESIGN SPECIFICATION NO. 00-C-02
REVISION B PAGE 19
4.1 Vibration
4.2 Temperature
Allowances shall be made in the design of all equipment for the large
temperature range of the region and appropriate cooling facilities shall be
included in the design.
5.2 All works shall conform to the requirements of the current applicable
Australian Standards and relevant Statutory Authorities having jurisdiction in
Western Australia. Alternatively, where no Australian Standard exists, work
shall conform to the most current and applicable British Standard.