Documente Academic
Documente Profesional
Documente Cultură
Figure 2. Arc flash simulation for a typical MV switchgear Figure 3. Incident Energy curves for typical LV MCC and Switchgear
table categories against those obtained by Time Current Characteristic curves bolted fault current and corresponding
the IEEE 1584-2002 method. Please note (TCCs) of the protective device expected arcing time combination that yields 25
that this table is not comprehensive and to clear the arc fault. Variations in the cal/cm2 (onset of hazard/risk Category 4
only illustrates a brief summary of a few short circuit current levels and clearing level). An overcurrent relay curve is
of the comparisons made for tasks at dif- times may result in higher arc flash ener- shown below the incident energy curves.
ferent voltage levels. gies. Figure 3 depicts a quick method to The bolted fault current is shown
The Hazard/Risk Categories obtained check if a combination of bolted fault below as an arrow. As long as the fault
using Table 130.7(C)(9)(a) may be less current and arcing time yield incident current and the TCC curve are below the
conservative for tasks expected to be energy levels below the PPE rating. incident energy curve, then the incident
within Hazard/Risk Category 3 and 4 Purple and green curves in the TCC energy should be less than the allowable
levels. It may be possible to use the view of Figure 3 represent an incident limit. A set of curves of this type can be
table for tasks involving Hazard/risk energy level of 25 cal/cm2 for 600V developed for each of the types of equip-
Categories 0, 1 and 2, as long as the class MCCs and switchgear. The curves ment listed in Table 130.7(C)(9)(a).
available bolted short-circuit current were generated using typical working
and arcing time are within the limits distances of 24 and 18 inches. To yield Conclusion
specified in the table footnotes. more conservative results, make sure Although its still necessary to con-
The comparisons presented in Table 2 the example assumes the systems are tinue the use of NFPA 70E tables under
demonstrate why performing a thor- ungrounded. some circumstances, care must be taken
ough arc flash hazard analysis instead of The curves show the relationship to ensure it is only applied under the con-
solely relying on Table 130.7(C)(9)(a) is between bolted fault current and fault ditions and limitations stated in the table
recommended. clearing time. If the bolted fault current footnotes. Careful consideration must be
increases, the required clearing time given to the effect of variables not listed
Checking TCC Curves should be less to ensure it doesnt in the table(s), such as working distances
Regardless of the expected task Haz- exceed the incident energy level. and equipment configuration (grounding
ard/Risk Category level, you should According to Figure 3, the right side and gaps between conductors).
always perform a thorough check of the end of the curves represents the maximum These parameter variations may cause
the incident energy exposure to be much
NFPA 70E IEEE 1584
2002
Max Ibf
at Fault
Fault
Clearing
larger than the level suggested by the
Table
Task
Equipment
Type
Voltage
Level
130.7(C)(9)(a)
Calculated
Hazard /
Location
(kA)
Time
(sec)
table. Thats why the best approach for
Hazard/Risk
Category
Risk
Category
determining the arc rating of PPE is by
Removal of bolted covers (to expose
Panelboard < 240 1 0 25 0.03
having a detailed engineering-based arc
bare energized parts)
Work on energized parts, including Panelboard
flash hazard analysis study completed.
voltage testing > 240 2 0 &1 25 0.03
Switchboard
insertion or removal of individual
starter buckets from MCC MCC < 600 3 3, 4, & >4 65 0.330
Albert Marroquin is a senior electrical
inserting or removal (racking) of CB
from cubicles, doors open2
Switchgear < 600 3 3, 4, & >4 65 1.000 engineer and testing manager for Opera-
inserting or removal (racking) of CB Switchgear > 1000 4 3, 4, & >4 25 1.05 tion Technology, Inc., developer of ETAP
from cubicles, doors open1
Arc Flash analysis software. For more
Note: The IEEE 1584 2002 results were obtained using only typical gaps and working distances for the type of
equipment being modeled. The maximum bolted fault current and clearing times are taken from notes 1, 2, 3, 4 & 5. information, visit etap.com.
Note 1: 36 inch working distance. Note 2: 24 inch working distance
Table 2. Summary of comparisons made between Table 130.7(C)(9)(a) and IEEE 1584 results
Circle 89 on Reader Service Card