1.
(a) Define a non-renewable energy source.
A non-renewable resource (also known as a finite resource) is a resource that does not renew itself at a
sufficient rate for sustainable economic extraction in meaningful human timeframes. Example: Fossil fuels
(Coal, Petroleum, and Natural-Gas), and certain aquifers.
Several other factors need to be taken into account for sitting, like restrictions on the use of rooftop solar
panels. Barriers can also consist of regulatory gaps - the absence of standards needed to support grid
interconnection. Moreover, other factors in the form of sitting-related incentives or benefits that are
available only or predominantly for non-renewable generation. For example, the availability of statutory
benefits for utility-scale projects may operate in the inverse as a measurable barrier to smaller non-utility
projects relative to their larger counterparts. Similarly, other laws outlining the cost recovery for sitting and
related pre-construction costs for nuclear power plants, irrespective of whether the facility is in fact built,
provide a significant incentive to build nuclear power plants. Without the same provision for large-scale
renewable projects, it may function as an inverse regulatory barrier relative to non-renewable facilities.
http://www.ozassignmenthelp.com.au/
ECE464 Power Electronics Assignment Solution
Some exemplary details of the renewable energy systems deploying power electronic systems are as
follows:
Wind Power
o Synchronous Generator with rectifier and inverter for grid interconnects
o Induction Generator with AC-DC convertor for frequency and power control
Solar Power
o Solar Cells to convert sunlight into electrical energy based on solar photovoltaic
principles
o First Stage AC-DC Converter for circuit power conditioning
2. Sizing of PV Modules
Assuming Panel-generation factor of 3, the total Watt-peak rating of the PV Module required = 1157.89/3
= 385.97 W
Therefore, No. of PV Panels required = 385.97/60 = 6.43 or 7 (approximately)
Result of the calculation is the minimum number of PV panels. If more PV modules are installed, the
system will perform better and battery life will be improved. If fewer PV modules are used, the system
may not work at all during cloudy periods and battery life will be shortened.
3. Inverter sizing
The input rating of the inverter should never be lower than the total watt of appliances. The inverter must
have the same nominal voltage as your battery. The inverter size should be 25-30% bigger than total load
in Watts.
Therefore, Inverter Size = 1430 W
http://www.ozassignmenthelp.com.au/
ECE464 Power Electronics Assignment Solution
4. Battery Sizing
Total Load = 1100 W
Nominal Battery Voltage = 70 V (average)
Therefore Battery Ampere Rating = 1100/70 = 15.71 Amp
The Solar Charge Controller can be similarly designed if the ratings are specified.
Get more information Electronic Assignment Help
5. Sketch a simple grid-connected photovoltaic system and describe
how the main components function.
The grid-connected photovoltaic power systems feed excess power to the grid, which in this case acts as
a battery for the system. This feedback is done through a meter to monitor the amount of power
transferred based on the concept of Net-metering. Moreover, the photovoltaic wattage may be less than
average consumption and require the consumer to purchase a lesser amount of grid energy. On the other
hand, if the photovoltaic wattage substantially exceeds the average consumption, the excess energy
produced by the panels can yield revenue by selling it to the grid. Therefore, the consumer only needs to
pay the cost of electricity consumed less the value of electricity generated.
6. What are the characteristics of a good wind power site and why are
they important?
The main characteristics for sitting wind turbines and assessing the feasibility of a proposed wind power
site include the following:
http://www.ozassignmenthelp.com.au/
ECE464 Power Electronics Assignment Solution
A wind turbine site is built on relatively small area on the ground that is expected to receive continuous
vibrations due to rotating blades. Therefore, the dynamic properties of the ground at construction site can
be especially pertinent from geotechnical engineering perspectives. The seismic survey is a thorough and
appropriate approach for site characterization than conventional drilling because it does not need the
bulky, heavy equipment that drilling does, the convenient accessibility to the site is another advantage.
Overall cost is also usually some fraction of the drilling cost.
Height Considerations
Height is related to the full extent of turbines (comprising tower, nacelle and maximum blade length in an
upright position) and involves the actual height and the perceived height relative to topography. Different
possibilities are acceptable, depending on context:
Site details:
Site Name: PQR Region (Total Area of a1b2c3 Sq. Miles)
Location: ABC Town, XYZ City
Capacity: 100 kWp
Latitude: nnnnnnN
Longitude: eeeeeeE
Elevation: hhhh ft.
http://www.ozassignmenthelp.com.au/
ECE464 Power Electronics Assignment Solution
Scope of work:
Technical Specifications:
Each of the 100 kWp Power Plant suitable to operate the above mentioned loads should have the
following sub-systems: