Sunteți pe pagina 1din 120

TJ_0513_OUTSIDE_FNT_COVER_PLUS_SPINE_001.

qxd:cover 22/4/13 20:22 Page 1

Tunnelling
www.tunnellingjournal.com April/May 2013

The international journal for the tunnelling industry


journal
SEE PAGE 18 SEE PAGE 34 SEE PAGE 40

SEGMENTAL PROJECT JUBILEE


INNOVATION POLITICS REPAIRS
TJ LOOKS AT NEW THE COMPLEX A FASCINATING
TECHNOLOGIES WORLD OF INSIGHT INTO
AVAILABLE TO THE PROJECT POLITICS AN INTRIGUING
SEGMENTAL LINING EXAMINED GROUTING
SECTOR PROBLEM
TUNNELLING JOURNAL APRIL/MAY 2013

SEGMENTAL
LININGS IN FOCUS
THE KORALMS SEGMENT
TRACKING SYSTEM
ROBBINS CONVEYORS SET THE PACE
High speed tunneling demands high speed muck removalwith maximum
capacity, minimal hands-on labor, and controlled operating costs.

Robbins builds the most efficient conveyor systems available today. 


Our continuously advancing conveyors simplify any sites logistics,
moving thousands of tons of muck per hour off the jobsite.
We keep you moving.
TJ_0513_CONTENTS_003.qxd:Feature 21/4/13 11:45 Page 3

contentS
5 Editors comment

6 Snapshots of
www.tunnellingjournal.com news

10 Koralm Tunnel segments


Strict quality control and tracking
requirements are being met with the SDS
computerised production control system for
the segments going into the new Koralm
tunnel in Austria

Above left and right: TBM


breakthroughs and contract 18 Pre-cast segments
Kristina Smith talks to CBE and
Herrenknecht Formwork Technology about
awards in the news (p6)
Left: Koralm segments (p10) recent developments for segmental linings
Below: ITA World Congress
preview (p28)
22 Developments in Joint Design for
SFRC Segmental Tunnel Linings
A new method is presented for limit state
design for steel fibre reinforced concrete
segmental linings

28 ITIG 2013 Subsurface Works Risk


Report
The International Tunnelling Insurers
Group (ITIG) presents a brief assessment
of the worlds current market conditions

31 World Tunnel Congress 2013


TJ previews the 39th General Assembly of
the International Tunnelling and
Underground Space Association to be held
in Geneva, Switzerland

34 Clearing the Hurdles


Desiree Willis of The Robbins Company
looks at the sometime complex political
backdrop that accompanies the
realization of many of todays large scale
tunnelling projects

40 The Jubilee Line Remediation


TJ reports on the emergency remedial
works needed to protect London
Undergrounds Jubilee Line and how it
spawned a new monitoring technique

49 The Future is Smart and Sustainable


Dr Benot Jones, Tunnelling and
Underground Space MSc Course
Manager at the University of Warwick,
UK, discusses sustainability

52 Customising Standards
Arnold Dix, Lawyer and Engineer gives
some guidance on regulatory
arrangements for subsurface tunnel risk
management from around the world
Above: The politics of
many a large scale
tunnelling project are
59 Successful tests in the Trnskog
Tunnel
SP Fire Technology reviews recent fire
becoming ever more tests carried out in the Trnskog road
complex (p34) tunnel in Stockholm
Left: SP Fire Technology
describe recent fire tests
carried out in the
61 A new system for water drainage
SP Fire Technology describe Rockdrain, a
new method and material used to control
Trnskog Tunnel in water leakage in a tunnel
Stockholm, Sweden

62 Contacts

TUNNELLING JOURNAL 3
Sika
Innovative
Solutions
The building owner expects timely completion of a project in high You have clear demands regarding economical rock support and
quality, also in consideration of local conditions. We provide you durable lining system, the concept of the waterproofing system
with system solutions that meet these demands and ensure you and of the sustainability of products and solutions used. Sika
competent service and punctual delivery of high quality products. provides quality products to meet your requirements, including
those for unforeseen circumstances.

Sika Services AG | CH-8048 Zurich | Switzerland


Phone: +41 58 436 40 40 | Fax: +41 58 436 41 50 Innovation & since
www.sika.com Consistency 1 9 1 0

new_advert_2011_Infrastructure.indd 1 11.04.2012 14:50:05


TJ_0513_005_COMMENT.qxd:Feature 22/4/13 20:13 Page 5

editorScomment
Priced out?
ITS INTERESTING TO READ the time, rather than US$350M once,
International Tunnelling Insurers then US$100M in claims, and
Group (ITIG) world market then another US$350M trying to
outlook report on p28 of this fix the damn thing.
issue of TJ. Although brief, it It seems totally incongruous to
certainly packs a punch and got me at the present time. I really
me thinking about where the believe the established industry
insurers see the strengths and is, within itself, trying everything
weaknesses of the industry. One possible to turn opinions around
area of particular concern is the and to push technology to a new
continued pressure from clients to level at an unprecedented scale.
push prices as low as possible, But it is sad to see that innovation
whilst showing an almost may well only be acceptable to
immovable reluctance to clients in terms of how much it
implement, or even try out any can cut cost, not in terms of
form of innovation in both design enhancing quality and
and construction methodology. revolutionizing civil engineering.
Reading between the lines, and The real problem is in our
adding a few of my own, makes modern world everything comes
for a worrying picture where down to hard money, and its very
spend thrift clients are awarding difficult to argue against a lower
contracts to alarmingly low bids bidder unless the client really
tendered by the new wave of understands where the lowest bid
worryingly inexperienced may take him!
contractors entering the market But lets not get too down; Ive
naively believing it to be both only focused on one negative
easy and lucrative. Cut to the aspect just to flag it up. There is
chase, and these in-experienced
contractors are exactly NOT the
type of companies you would
plenty to be positive about, and it
looks like tunnelling is still on the
up and the future looks very
The real problem
is in our modern
world everything
want to try innovation with, and bright indeed, despite our
in some case you wouldnt even dreadful few years at the mercy comes down to hard
want to try standard tunnelling of dodgy bank practices. And, as
practices with. There simply isnt for our in-experienced low
money, and its very
the in-house experience there to bidders, it really wouldnt surprise difficult to argue
allow it and consequently little me if many of them exit as fast as against a lower
new gets tried out and the same they arrived once they really
mistakes are repeated over and understand the risk and returns bidder unless the
over. Criminally, the established involved in underground client really
contractors with a wealth of construction. Having your fingers
experience in the locker room are burnt once in the tunnelling understands where
essentially being priced out of arena can spell the end for many the lowest bid may
new work by these crazy low a would be contractor! And if
bids. What a false economy on a
grand scale, indeed the
expression, buy cheap, buy
some are still here in ten years,
they will absolutely deserve to be
and good luck to them. After all,
take him!

twice instantly springs to mind. everybody has to start
Its not rocket science better to somewhere!
spend US$500M once on a
project that stands the test of Tris Thomas

TUNNELLING JOURNAL 5
NEWS FROM THE WEB

forces to foster further expertise on


Royal HaskoningDHV scoops sustainable sprayed concrete. This
Brazils first immersed tunnel cooperation follows Atlas Copcos
April 18, 2013 acquisition of the MEYCO Equipment
Royal HaskoningDHV has won a 5 million sprayed concrete manufacturer in
euro contract to lead the design process for Winterthur, Switzerland, from BASF. The
an immersed tube tunnel at Brazils largest acquisition was finalized yesterday with the
seaport, Santos. The 500m long tunnel will closing regular process.
directly link the cities of Santos and Guaruj The companies hope the joint research
located on either side of the fairway leading and development from Atlas Copco and
to Brazils most important port. BASF will enforce MEYCOs leading position
Advice provided by the firm was in the development of sprayed concrete
instrumental in the decision by authorities in technologies and applications for a global
So Paulo to opt for an immersed tunnel. A customer base in underground mining and
bridge was ruled out due to cost and tunnelling.
adverse impacts on the port. The tunnel will BASFs expert knowledge in chemical
relieve the burden on the existing passenger solutions for sprayed concrete together with
ferry services and significantly reduce Atlas Copcos global expertise in
driving time for freight vehicles, which must underground tunnelling and mining
currently make a detour of 50km when equipment will drive the optimization of
travelling to and from the port. sprayed concrete application, said Daniel
The Brazilian authorities (via the Ruckstuhl, Vice President and head of
government agency DERSA) selected the BASFs Global Underground Construction
experienced Dutch engineers as this is the business. The cooperation between the
first immersed tube tunnel to be built in two market leaders creates a globally
Brazil. Royal HaskoningDHV will lead the unmatched partnership to further develop
design process and oversee its content. sprayed concrete chemistry and equipment
Royal HaskoningDHV and Witteveen+Bos technology. This joint effort is formed to
have collaborated on major tunnel projects year old town on Taihu Lake are expected to enable high performance solutions
for 25 years in a partnership called Tunnel commence operation in 2014. Five metro supporting safety and cost and time
Engineering Consultants (TEC). Current lines are planned in total. efficiency in tunnelling and mining projects .
immersed tunnel projects include the The EPB Shields (which range in diameter We are pleased to announce this
Fehmarnbelt between Denmark and from 6.37m to 6.39m) have been tunnelling cooperation and look forward to working
Germany (19km tunnel), the Busan-Geoje since July 2011 to construct the first two of together, he added.
Link in South Korea (3.4km), the Hong five planned metro lines in the 4-million The cooperation will focus on the
Kong-Zhuhai-Macau Link in China (6km) strong metropolis of Wuxi. They completed development of innovative concrete
and the Coatzacoalcos tunnel in Mexico their mission with the final breakthrough of spraying solutions with high product
(1.5km). the S-730 TBM, which achieved top performance and availability, to satisfy our
performances of more than 33m (108ft) a customer needs, said Bob Fassl, President
TTC new appointment day and 164m (538ft) a week boring Atlas Copco Mining and Rock Excavation
2,508m (8228ft) of tunnel for the metro line Business Area. We are very pleased to be
April 5, 2013 2 in just 10 months. able to announce this most exciting
TTC are pleased to announce the Before this, machines mastered challenging cooperation with a most well- reputed
appointment of new international sales conditions on metro line 1. The S-663, a company, BASF.
manager, Graham Langshaw. Graham joins compact EPB Shield with a diameter of MEYCO Equipment invented the first
the company with a wealth of experience in 6.37m, completed portions of tunnel just a (gunite) machine operating according to the
the supply of connection and embedded few meters beneath residential and rotor principle the MEYCO GM and later
items to the segmentally lined tunnel commercial buildings. As the machine the MEYCO Piccola. Through MEYCO,
market. The appointment shows TTCs launched, on May 24, 2012, just 7m of Atlas Copcos Underground Rock Excavation
commitment to the supply chain and to overburden was above the machine, and the division will look to provide a unique
enhancing its global presence. All at TTC distance to the foundation pillars of the package of technology, equipment and
have worked with Graham before so his building above were only 3.7m. Therefore, in application expertise to the market.
seamless transition into the company order to facilitate the launch in ground
strengthens the team in their quest for consisting of waterlogged clay, a MTR awards SCL 1107
increased international success. groundfreeze operation was undertaken. to Seli/Chun Wo
Following a smooth start, the machine April 2, 2013
Final breakthrough for HK quickly passed beneath the building. On Hong Kongs MTR Corporation has awarded
in Wuxi December 7, 2012, the machine achieved the US$128M, SCL 1107 contract for the
March 20, 2012 final breakthrough. Diamond Hill to Kai Tak Tunnels on the
Eight Herrenknecht TBMs have excavated Shatin to Central Line to a 50% Seli
almost 16km (10-miles) of tunnel, in just 20 BASF and Atlas Copco to Spa/50% Chun Wo Joint Venture. SELI will
months, beneath the emerging metropolis of jointly assist sprayed concrete provide the TBM, and perform excavation as
Wuxi, near Shanghai, in the east of China. developments part of the JV.
On March 3, the Earth Pressure Balance April 3, 2013 The 17km long, almost entirely
Shields completed their mission with the final Atlas Copco Underground Rock Excavation underground Shatin to Central Link is a
breakthrough of the S-730 TBM for metro Division and BASF Construction Chemicals territory-wide strategic railway project with
line 2. These first two metro lines in the 3000 Europe Ltd. have signed an agreement to join 10 stations, amongst which Diamond Hill is

6 TUNNELLING JOURNAL
NEWS FROM THE WEB

one of the six interchange stations. The LU put out Northern


project is expected to be completed in two Correction Line extension pre-tender
phases, with the section between Tai Wai notice
During the production of Tunnelling
and Hung Hom finished in 2018 and the March 14, 2012
Journals February/March edition, a technical
Hung Hom to Admiralty section in 2020. London Underground (LU) has issued an
error led to an unapproved version of the
The order in Hong Kong adds to SELIs OJEU pre-tendering procurement notice
Sprayed Concrete Developments article
already impressive list of metro line projects. for the delivery of the 400M 600M
(p10) being published. Although copy
Others include Copenhagen, Milan, Northern Line Extension to Battersea
amendments had been provided by those
Thessaloniki, Turin, Rome and Vancouver. Power Station, which includes the
interviewed, not all of these were
SELI is also currently being considered for a construction of 3.3km of twin-bore 5.2m
incorporated in the version that went to
contract in Brazil by Odebrecht for a new i.d. running tunnels and two new stations,
print. TJ apologises unreservedly for the
section of the Sao Paolo metro. one at Battersea and the other at Nine
error and any embarrassment caused to
Elms.
Crossrail Tunnel fit-out award those who feel they were misrepresented, in
Companies have until 15 April to
particular to BASF and the Dr. Sauer Group
April 2, 2013 complete the pre-qualification process
Crossrail has announced that it intends to with contract signing slated for the 6th
award the contract to undertake the major
fit-out of the new rail tunnels to a joint
venture comprising Costain Ltd, TSO and
Alstom Transport. The award of the tunnel
fit-out contract is the last major
construction contract to be awarded by
Crossrail.
Andrew Wolstenholme, Crossrail Chief
Executive said: Construction of the new
rail tunnels under London continues to
advance. As tunnelling concludes work will
get underway to turn the tunnels into an
operational railway with new track installed
as well as power, drainage and ventilation
systems. Tunnel fit-out is one of the largest
contracts to be let by Crossrail and will
create hundreds of new job opportunities as
well as providing a welcome boost to
regionally-based manufacturers and
suppliers.
The contract also includes commitments
to provide apprenticeships and job
opportunities for Londoners. The contractor
will be required to create around 50 new

apprenticeships and new job start roles for


individuals who are long-term unemployed
or out of education or training for six
months or more during the life of their
contract. It is a requirement that all of the
new job starts be taken up by individuals
living within Greater London or within one
mile of the Crossrail route.

TUNNELLING JOURNAL 7
NEWS FROM THE WEB

connecting Central to the corridor at North


Point via Wan Chai and Causeway Bay.
Construction works for the project started
in 2009 and will be completed in 2017

Rail staff prevent tunnel


disaster
March 8, 2013
Prompt action by a train driver averted a
major Tube disaster in London, UK (Friday,
March 08) when two piling drills breached
the tunnel lining of the Moorgate to
Finsbury Park Northern City line.
The incident happened after the driver of
the 10.02am First Capital Connect (FCC)
train from Moorgate, in London, to
Welwyn Garden City, in Hertfordshire, saw
muddy water pouring on to the roof of his
train just north of Old Street station.
He reported the incident and all rail
services were stopped.
At 11.05am a Network Rail operations
manager joined another driver on board an
January 2014. A project completion date Hong Kongs Central-Wan empty train from Moorgate to investigate
has been set for the end of 2019. Chai Bypass tunnel awarded the problem.
March 20, 2013 As the train approached the area at low
Hong Kong SCL win for Hong Kongs Highways Department has speed, two large piling drills burst through
Leighton signed a $622m contract with China State the lining of the tunnel, dropping
March 20, 2013 Construction Engineering for the Central- brickwork into the tracks. The train stopped
Leighton Contractors (Asia) Limited, a part Wan Chai Bypass. in time but the driver was shaken by the
of the Leighton Asia, India and Offshore The contract involves the construction of incident.
Group, has secured an US$680M contract a 300m-long section of twin-box tunnel The rail route, used by two million City
from the MTR Corporation to construct a under the seabed of Causeway Bay workers every year, will remain closed while
critical component of its 17km long, Typhoon Shelter and a 150m-long slip-road the incident is investigated and repairs are
predominantly underground Shatin to tunnel beneath the existing Victoria Park carried out.
Central Link (SCL) development in Hong Road and the northern part of Victoria British Transport Police have visited an
Kong the Hung Hom Station and Stabling Park. office construction site above the line and
Sidings Contract 1112. Director of highways Lau Ka-keung said the Rail Accident Investigation Branch has
The scope of work includes significant this was the final contract for tunnel been notified.
modification works to an existing MTR construction under the project. FCC managing director Neal Lawson
station, platforms, tunnel box and With the commissioning of the project, said: This was a serious incident that could
approach tunnels. Construction works are the travelling time between Central and the have ended very differently had it not been
scheduled to begin immediately, with an Island Eastern Corridor at North Point via for the vigilance and prompt reporting and
expected completion date in 2018. the bypass will take only five minutes, said actions of our drivers. Whoever is
Managing Director of Leighton Asia, Lau. It will relieve the traffic congestion responsible must be held to account.
India and Offshore, Ian Edwards, said: We along Connaught Road Central, Harcourt Network Rail route managing director
are delighted to win yet another landmark Road and Gloucester Road. Phil Verster said: Our engineers are on site
project with a client with whom we share a The overall project is a 4.5km dual three- assessing the damage and we will restore
long and successful relationship. Leighton lane carriageway with a 3.7km tunnel the railway as soon as possible.
Asia, India and Offshore has a solid track
record in rail infrastructure in Hong Kong
over some three decades with a number of
significant projects, including the terminus Breakthroughs on Milans Line 5
of Guangzhou-Shenzhen- Hong Kong March 20, 2013
Express Rail Link and South Island Line Both EPBMs boring the Milan Metro Line 5 twin-tube tunnels have successfully
(East). Our significant rail and tunnelling broken through at Cenisio station and are now progressing well along the
experience makes us well suited to rest of the drives, SELI has announced. TBM S-388 broke through at Cenisio
successfully deliver the major infrastructure station on 22/01/2013 followed by TBM S-238 on 16/02/2013. TBM S-388 is
projects in the region and we are pleased currently at 1,118.04m (of 2,193.09 or 51% of tunnel) whilst TBM S-238 is
to be able to work with MTR again. currently at 756.38ms (of 2,198.9 or 34% of tunnel). The Client, Astaldi Spa is
The SCL development is a major excavating the tunnels using two EPBMS, one 6.79m diameter and the other
transport initiative in Hong Kong that will 6.76m. The lining of the tunnel comprises 300mm thick, 1400mm long precast
connect several existing railway lines to reinforced segments. Each ring has an outer diameter of 6.4m and an i.d. of
form two strategic railway corridors. It will 5.8m made up of 6 segments and a key.
be built in two sections, Tai Wai to Hung Excavation began in August 2012 and is scheduled for completion in May
Hom Section at 11km, and Hung Hom to 2014.
Admiralty Section at 6km.

8 TUNNELLING JOURNAL
Safety aspects are one of those high
priorities in equipment selection choice at
our company.When we looked at the types
of machines that could not only support our
project but also handle all the conditions
and the huge size of the tunnel we were
going to undertake, the Sandvik range
offered exactly what we needed.

Kim Bailey
Plant Manager
Leighton Contractors (Asia) Ltd.
Hong Kong

Invincible speed and accuracy

Expertise in crushing

Understanding
underground
For decades, Sandvik has worked with various tunneling methods at customer sites Meet us at
around the world, creating expertise that results in intelligent cutting-edge technology.
As the only manufacturer with its own underground R&D center at the factory, Sandvik
continues to be the clear forerunner in the tunneling equipment industry. Always striving
to serve you with the best possible solution for your application at hand.

Learn more at www.understandingunderground.sandvik.com

www.construction.sandvik.com

SANDVIK_UU_Leighton_210x297_ad_4-2013.indd 1 18.4.2013 10.19


TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:33 Page 10

SEGMENTAL LINING

The Koralm Project at a glance


Austria's new Koralm tunnel is one of the the west and the harder gneiss of the
largest infrastructure projects in Europe outside mountains. Strabag did that work in 2005-07,
of the three great Alpine pass crossings at making a small 45m2 cross-section bore.
Brenner, the Swiss Gotthard and France's Frjus. It was thought this might be a difficult area
At just under 33km long and with a maximum but in the end it was more straightforward than
cover of nearly 1200m it is at least approaching thought, says Lehner.
the same kind of scale. The interface fixes two different types of
The twin bores for high-speed rail trains will tunnelling for the project which uses
form a critical link through Klagenfort in conventional excavation in hard clays to the
southern Austria and on to the north east via west and switches to TBM for the longer hard
Graz and Vienna. Another major tunnel, the rock. This is mainly gneiss, a layered form first,
Semmering is also required and is currently with split planes - it is used locally for making
under tender by the Austrian Federal Railways, roof tiles and then solid older rock.
which is also the client for the Koralm. The main contract, for some 600M, was
The Austrian route section in turn is part of a begun in January 2011 with formation of two
key trans-European route, the Axis 23 Adriatic-B deep access shafts and the conventional drives
Baltic corridor which will eventually connect heading in both directions. They also saw the
Gdansk on the Polish north coast with Venice in creation of two large parallel caverns for the
north-east Italy. assembly of the TBMs.
The Koralm tunnel has been split into three The Aker Wirth machines, each with a double
main sections. A small southern contract has head, arrived on site late last year and the first
already formed the portal and an initial began driving in February with the second
conventionally excavated 2km of tunnel. It starting work just before Easter. They have an
starts near the little town of Deutschlandsberg outside diameter of 9.93m. Swiss firm Rowa
sited in the vine and farmland valley supplies the follow on back up train and
countryside before the Koralm mountain range. segment delivery equipment.
It is almost complete. They erect a six segment ring as they go, five
Second and largest of the contracts, pieces plus a full size key element; inner
underway since late 2011 is for the central diameter of the rings is 8.8m and the ring
portion, with around 2km of conventionally segment thickness is 350mm leaving an annulus
excavated tunnel required for each bore and of 200mm which is filled with pea gravel.
then long TBM drives through the hard rock of Details of the tunnelling will be explored in a
the Koralm mountains. These are slightly follow on article.
different lengths, 17.1km on the north side and
15.7km on the south. Both machines have just
begun work. Czech Republic

The drive length difference is due to previous


exploratory works on the third section and
Germany
logistical issues which alter the breakthrough Vienna
Slovakia

point on the southern bore, explains Wolfgang


Lehner. He is project director for the joint
IA

venture carrying out the work, formed from an


80% majority of contractor Strabag with R
Austrian tunnel specialist Jgerbau. T
S
There was a shaft and fairly long exploratory A U Graz
Hungary
tunnel of around 10km done for the Lot three,
he says. The third contract, to be let shortly, is Klagenfurt
for 12.8km of twin tunnel, most to be done by
Italy
TBM. Slovenia Croatia
An exploratory tunnel was also done for the
longest central section, to pin down the geology Above: plan map of the Koralm Tunnel
as much as possible and particularly to find the location. Below: section showing the
interface point between soft glacial ground in construction lots of the tunnel

Main construction sections Koralm tunnel


Percentage of the e
gen
overall excavation Neo
tyria .1km
sections: S M4 East portal
NAT
KAT I: 8%
KAT II: 57% thia t alline
Carin Crys km
KAT III: 35% 15.7
TBM
km
Fault 5.1
nttal NAT
M
ava m
e /L 12.1k TI
en TBM KA
go

km
17.1
Ne
km

TBM II
KAT
0.7

6km
l 10.
TM

unne
or y t
NA

rat
xplo
TM/e
NA Shaft: 60m
West portal III
KAT NATM: 4.4km
TBM: 32.8km

10 TUNNELLING JOURNAL
TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:33 Page 11

SEGMENTAL LINING

KORALM TUNNEL
SEGMENTS -
complex monitoring
and management
Strict quality control and tracking requirements
are being met with the SDS computerised
production control system for the segments going
into the new Koralm tunnel in Austria. Adrian
Greeman visited the site and files this report
DRIVES FOR THE MAIN sections of the segments have been set by the client BB-
Koralm high speed railway tunnel project Infrastruktur, the capital works division of
began work at the beginning of this year, two Austrian state railways. As well as tight quality
9.9m diameter TBM hard rock bores of 15.7km assurances it wants full traceability of the
and 17.1km length respectively form the lines components in the segments to allow for
on the north and south sides of the alignment. easier trouble-shooting and investigation in the
They will take around three years to complete event of damage or failure within the tunnels.
their eastwards progress, meeting eventually The requirements arise particularly from
with 12km and 10km drives coming the other caution about potential difficulties in the rock
way by another contractor. and particularly in the first seven or so
The Strabag-Jgerbau joint venture kilometres of the drives through striated gneiss
contractor for the central and largest section of with significant slip surfaces in the rock. For this
the project, Lot 2, is pleased with the start it section there is also a very unusual requirement
has made on the TBM sections. The first for an in situ lining.
machine began in February on the southern The TBM will install a basic segmental lining
bore and the second machine starting work and then we will follow on with a waterproof
earlier than expected, just before Easter. drainage membrane and in situ inner shell cast
Meanwhile in its first two years, the using a travelling formwork as you would in a
contractor has already made some 4.4km of conventional tunnel, says Strabag project
tunnel by conventional methods in soft ground director for the joint venture Wolfgang Lehner.
near the western end. But the hard rock drives In the later harder gneiss section the tunnel
are the key part of its 600M contract. will use simply the plain segmental lining.
A key element of its work in the initial period All these segments must be produced on
of the contract has been setting up and site. The client ruled out segment production
preparing for the segment production and elsewhere and delivery to site because of the
delivery to the machines which will consume potential disruption it would cause. The area is
eventually some 103,500 segments for the a pleasant rolling landscape of farmland,
rings and another 17,250 larger invert vineyards and small townships.
segments. These 13.4t pieces are for a flat floor The delivery of so many segments by trucks
which is installed immediately behind the over a three year period would have been
machine and to which are bolted twin railway impossible, says Andreas Lange, segment
tracks for personnel carriers, logistics and production manager. He says that it would also
machine supply of segments and grout. have been difficult to bring them in by rail,
Strict requirements for quality of the because although there is a line to the site,

TUNNELLING JOURNAL 11
ENVIRONMENTAL
MONITORING
AND MACHINE
CONTROL: FROM
BREAKING GROUND
TO BREAKING
THROUGH.
SEE THE LIGHT

Trolex is with you from project inception through the lifetime of


the tunnel, providing Environmental and Machine Monitoring and
Control. With a direct line to project engineers, rapid-response on-site
support and a full commissioning and maintenance service, youll find
working with us to be an enlightening experience.

See the light at www.trolex.com


or call +44 (0) 161 483 1435

TUNNELING JOURNAL AD A4 DPS.indd 1 22/03/2013 14:18


ENVIRONMENTAL
MONITORING
AND MACHINE
CONTROL: FROM
BREAKING GROUND
TO BREAKING
THROUGH.
SEE THE LIGHT

Trolex is with you from project inception through the lifetime of


the tunnel, providing Environmental and Machine Monitoring and
Control. With a direct line to project engineers, rapid-response on-site
support and a full commissioning and maintenance service, youll find
working with us to be an enlightening experience.

See the light at www.trolex.com


or call +44 (0) 161 483 1435

TUNNELING JOURNAL AD A4 DPS.indd 1 22/03/2013 14:18


TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:35 Page 14

SEGMENTAL LINING

installed as part of the mobilisation, it does not tolerances, says Nod Clarke-Hackston,
have sufficient capacity. It is needed for international sales manager for VMT, and
supplies like the pea gravel, grout and so forth even a fraction of a millimetre can set it out.
and for removal of spoil, he say. The system uses input from modern laser
But producing so many segments on site has scanners, two of which in fixed positions can
its own difficulties, most of all the space. be used either to scan the interior of a steel
Within a tightly constrained area the contractor form or the final segments once removed. The
must have not only its tunnel access and spoil factories at Koralm have a measuring space
disposal handling but also two segment fitted with Faro scanners.
factories and a storage area. That is very These can work in minutes compared to
small, says Lange. For his purposes, he has a painstaking day long checking with total
yard stretching approximately 150m in each stations required in the past. A 3-d best-fit
direction from the central tunnel access shafts, volume model is produced. VMT has specific
and just 50m wide. Within this enough software, TubGeo for this purpose.
segments must be stored to allow for 28 days Scans are carried out on a regular basis to
of hardening and supply to the machines. A check the forms and also on the output of
supplementary area is available to the back of segments with a specified procedure to check
the site but it is not much. the first ten from each model, then to sample
one-in ten and dropping to one in 500 if no
Different rings deviations are being picked up.
Complicating the picture is the need to The SDS also comes with a tagging and
produce various types of ring segment. There is recording system using bar codes in this case,
a basic ring, and then a high strength ring with though RFID mini-chips can also be embedded
more reinforcement and a stronger mix design for automated work. The various inputs into a
for the concrete. A third type of specially segment are all tagged with their own
reinforced ring is needed for the points in the Above: the invert. Top left: segments individual identifiers barcodes.
tunnel where the tunnel lining will be broken delivered to the base of the shaft. Top At Koralm there are two factories for
through to form cross passages, every 500m. right: segment installation at the TBM segments each using Herrenknecht made
These have more steel still and heavy 100mm forms, moving around a production carousel
diameter dowel bars at three points to connect with a seven-hour heat curing oven. There is a
to the next ring, to give the lining stability once of its first full outings at Koralm. separate batching plant for each factory fitted
some segments are broken out. It works with two main elements, firstly a with Liebherr pan mixers. An upper floor is
The big 4m long invert sections also have to labelling and tagging system to trap and then used to assemble the steel segment
be made and stored. They use a different enter information and then a relational reinforcement cages.
concrete mix still. database taking advantage of the ways that Deliveries of cement, additives and in some
The invert sections mean you need extra data can be added together, cross referenced cases, aggregate, are by rail, says engineer
space for those to have their own areas even if and queried to bring up all the pertinent Robert Goliasch, on a line we built for the
sometimes it is left empty, says Lange. information about any particular item. project from the main line.
The solution to these problems, both Management audits, reports, and other The various component streams into a
tracking and checking elements and then information can be drawn out in myriad forms. segment each have a bar code, including the
storing and locating them has been a relatively VMT has also developed software within the concrete batch, the steel form itself, and the
complex database and tagging system system for highly accurate measurement and reinforcement cage. Tags are heavy duty
developed by TBM guidance system maker virtual 3-d modelling of segments and the weatherproof plastic stuck on the outside or in
VMT. Called rather prosaically the Segment mould they are produced in. the case of the reinforcement cages, are like
Documentation System it has been given one Modern segments are made to exacting airline baggage tags around one of the bars,

14 TUNNELLING JOURNAL
TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:36 Page 15

SEGMENTAL LINING

Above left: a partial Koralm Tunnel ring. Above right: barcoding of each individual segment modern Smartphones, with touch screens to
call up the appropriate menu, explains Lange.
The final segment gets a new barcode as it
also in heavy plastic. Each barcode number scanners to record the particular barcodes as leaves the mould, made up of the form code,
references data on the particular elements such they go through the process and enter further the reinforcement and the concrete, and this
as details of time and date of mixing, water details. Mould preparation, moulding, then allows its progress to be traced.
content, cement content and aggregate for the concreting, de-moulding, initial indoor curing That code is used to follow the segment
concrete, the rebar design for the cages or the storage for 24hours, and outside storage all through to the machine. The segment erection
particular mould and its laser scan details. see data entry. procedure at the machine also uses barcode
The workers in the factory have hand held The scanners are quite easy to use, like readers so that the exact segment installed in

Reliable Ground Control Solutions

DSI has the


most extensive
product range
available on
the market.

Self-Drilling
lf D illi System
S t S
Solutions
l ti
AT Pipe
Pipe U
Umbrella
m b r ella S
Support
u p por t S
System
ys te m Quick - Safe - Reliable
Thee fastest
fastest and
and most most accurate
accurate c cased
ase d
drilling
ing system
system
Advanced
vanced drilling
d r illi n g u
unit
nit ffor
or a allll g
ground
round cconditions:
onditions:
from
m clay
clay to
to g
granite
ranite
Various
ious innovative
innovative p pipe
ip e c connections
onnections ffor or a
allll ffields
ields ofof application
ap
Unique
que AAutomation
utomation Un U
Unit it ffor
or u underground
nderground d drilling
rilling rrigs
igs

Local Presence - Global Competence


North America, USA South America, Chile EMEA, Austria APAC (ASEAN), Australia
www.dsiunderground.com www.dsi-chile.com www.dywidag-systems.at www.dsiminingproducts.com/au

www.dsi-tunneling.com

TUNNELLING JOURNAL 15
TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:37 Page 16

tracking systems in the container ports, which


the company primarily supplies and are able
easily to work here with the positional
information in the database.
VMT offers an optional interface between
the database and the crane navigation displays
in the cab and automation is also possible.
In consequence virtually no space is left free
in the yard. To further save space the yard has
adopted a double-stacked formation, with the
six elements of one ring stacked on six more
below. That is the reason we chose a full size
keystone design for the segment ring,
explains Stephan Frdl, a design engineer for
the segments at Zblins design unit, now part
of Strabag. A half unit would have prevented
stacking above it. Similar considerations made
the use of a universal ring the obvious choice,
since a left-right ring system would have
needed greater space.
The tracking system also helps limit the
number of high strength rings needed at any
one time. The exact requirement for the
stronger segments is not known until the TBMs
reach a patch of bad rock along the bore. Rings
are then needed immediately which means a
reserve of stronger rings has to be kept and
found on demand. There is a small surplus
needed all the time, says Lange. If there is still
a surplus by the end of the drive he says they
will simply replace basic rings for the last small
section of the tunnel to use them up.
The database can also store visual images,
which is particularly useful if there are cracks or
faults in any segments, so that images of the
problem can be attached to the other data all
the way back through production and delivery.
All this will more and more come into play
now as the two TBMs get into their stride on
the tunnels and the consumption of segments
reaches full use. Just how that works goes is
another story - to be told in the next issue.

the exact position in the tunnel is detailed. Preparation and arranging of the cages and the Herrenknecht Formwork segment factory
It means that very precise information is
available on every ring of the tunnel lining if
any issues develop, says Lehner. That allows
for a high level of fault diagnosis. Was there a
problem with the temperature, the concrete
mix, the rebar etc?
The individual segment tracking system has
another function too, in storage of the
segments. Because of the tight limits on space
Lange wants to avoid leaving empty voids in
the storage racks. But usually, to know where
segments are, and equally to access them
quickly, requires ordering then by type and age.
But the database can track very precisely
where a segment has been stored within the
yard, says Lange. That means the segments
can be piled up close and then to find any
particular type of segment and especially to
locate segments sufficiently aged for concrete
strength, the database is queried.
The 60t capacity Knz portal cranes used in
the yard work with such database storage

16 TUNNELLING JOURNAL
Seli_Pub_tj_II.qxp:Layout 1 19/03/13 11:48 Page 1
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 18

SEGMENTAL LINING

Pre-cast segments
The segments must achieve a minimum
strength of 15MPa before they are demoulded
and handled.
To ensure the segments wont be
damaged, the first thing is to have the correct
curing of the concrete, says Praut. If you
want to control and to set the same standard
for every single segment, you must have a
repetitive environment in terms of temperature
and humidity. You cannot do that with static
moulds.
Minimum strength assured, the next step is
to arrange every stage of the handling process
so that damage to the segments is avoided.
On New Zealands Waterview project, where
the segments weigh in at 10.6 tonnes, Wilson
Tunnelling has invested in all the latest
The Alaskan Way Ring handling and storage equipment in order to
assembled in all its glory achieve maximum efficiency, says Praut.
Handling and the logistics inside the
precast yard is a key issue, he says. You can
MOULD MANUFACTURER CBE GROUP can a narrower tolerance with a bigger surface. waste a lot of time by handling, moving and
now boast a hat-trick of mega-tunnels. Its The challenge is amplified, says Praut. turning these big segments. Wilson wanted to
latest contract in this family is the Bosphorous Imagine having the same tolerance over a have the most productive equipment for these
Strait Road Crossing in Istanbul, requiring rings 4m length as over a 2m length: its a very big big segments.
with an outer diameter of 13.2m. difference. They wanted to set a high standard for
The Istanbul project joins the Alaskan Way in Achieving those tighter tolerances requires producing segments in New Zealand. And
Seattle, with its 17m outer diameter rings and three things, says Praut: more man hours, the they may perhaps re-use the equipment for a
the Waterview project in New Zealand (see right equipment and a strict checking regime project following on from Waterview.
photo caption) which has a 14m outer using laser scanners. The equipment was manufactured by CBE
diameter. Though Alaskan Way is the big The extra time spent in making these Group company Acimex, which in February
brother of the trio, all these projects require moulds for mega-tunnels comes from the relocated from Paris to St Avertin next door to
the same, particular approach to mould iterative adjustments which have to be made its parent. Acimex supplied Waterview with
manufacture, casting and installation. to get the mould within those tight tolerances. equipment including a demoulding vacuum
The issue is precision, every step of the way, Laser scanning, which CBE has been using for lifter, a hydraulic turning device which restrains
says CBEs sales director Alain Praut: the last seven years, is a key tool in checking the segment on every access whilst rotating it
Because all of these tunnels are in seismic this. through 180 degrees and hydraulic trolleys
areas, the precision of the segments is a main Machinery is important too, says Praut. For deliver the segments automatically from inside
concern. example, the CNC machines which are used to the factory to the external storage yard.
In areas of seismic activity, the contact face machine the end faces of the moulds, which Due to the size of the segments, the
between segments is very significant. That will create the contact faces of the segments, equipment is pretty big, requiring a lot of
means any wrong positioning of the ring, must be big enough. design and a lot of complex systems such as
which can come when the TBM places the We have the capacity internally to machine the PLC and hydraulic controls, says Praut.
segments or due to the ring geometry, can the 8m-long sides in a single pass because we
break the segment, creating weakness or have the correct equipment to do it, says And so to site
failure in the ring. Praut. It means that we can guarantee the The theme of precision must continue once
This is something of which the tunnels geometry of that face and increase the the segments are on site, being placed behind
owners are very aware, says Praut. The accuracy. the TBM. During the boring process when
clients specifications are much more precise Once the moulds have been honed to the cylinders are pushing on the segments, the
than, say, for a 6m-diameter subway tunnel, perfection and delivered to the precast force required for these big TBMs is very
he says. On these projects control is very segment casting company, the next challenges high, says Praut. This means the position of
strict, very rigid. are how to produce accurate, identical the segments in relation to the previous rings
Insurance premiums on tunnels in this type segments and how to avoid damage during must be perfect. Otherwise the force from the
of geology are high, says Praut. The insurance demoulding, moving and storing. The only cylinders which are supplying the torque to the
companies demand more controls to reduce approach here, says Praut, is to create a cutting head can destroy the segment which
the premiums. manufacturing facility more akin to a car has just been installed.
production line. Human input is very limited A saving grace is that the advancement of
Precision, precision to avoid introducing stresses and to reduce the such large diameter machines will be slower
Avoiding the situation of an imperfect ring all change of mishaps, he says. than for a standard diameter TBM. The
starts with the manufacture of the moulds. For segments of this size, the only option is boring wont be very fast, so they will have
The challenge in making the moulds is having the controlled environment of the carousel. time to adjust the segments, says Praut.

18 TUNNELLING JOURNAL
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 19

SEGMENTAL LINING

a glimpse There are other reasons why accuracy of


ring build is important for these three large
diameter tunnels. First because other concrete
structures will be assembled in the tunnels
afterwards; these are double-deck tunnels.

into the future


Second, all the tunnels run beneath water
bodies, which means that getting the sealing
right between segments is crucial. The gasket
position on these segments is important for
avoiding leakage in the tunnel, says Praut.
From utility tunnels to mega-tunnels, precast Conventional gaskets, rather than cast-in,
will be used for all these three projects,
concrete segment technology continues to although Praut believes it is only a matter of
evolve. Below, Kristina Smith talks to the CBE time before this technology will be used on
large diameter tunnels such as these. We
Group about the challenges of manufacturing talked about it with the client on the
Bosphorous Strait, but at the moment the
and installing large-diameter rings and gasket suppliers do not have reference projects
which prove they can meet these
Herrenknecht Formwork Technology, who specifications.
reveals a new integrated liner it hopes will These huge tunnels are carrying human
beings, not waste water or utilities, so we do
revolutionise the wastewater sector. not want to take one single risk with them.

LANDMARK PROJECT FOR NEW ZEALAND


The Waterview Connection in Auckland, New Zealand, includes the countrys largest
tunnelling project for decades: two 2.5km tunnels requiring precast segments for
rings with an outer diameter of 14m. CBE Group has supplied four sets of segment
moulds, a carrousel and handling equipment (pictured) to precast manufacturer Wil-
son Tunnelling which is a sub alliance partner to the consortium delivering the job,
Well-Connected Alliance (Obayashi Corporation, Fletcher Construction, McConnell
Dowell Constructors, PB New Zealand, Beca Infrastructure and Tonkin & Taylor).
A Herrenknecht EPBM machine will create the tunnels, boring through the
areas volcanic geology. Due to start later this year, the tunnelling should be
complete by 2017.
The $1.4bn contract to build 5km of new motorway connecting highways to
the North and South of Auckland, will be New Zealands biggest ever transport
project ever. And the consortiums contract includes 10 years of maintenance
after the motorway has opened which means that build quality and accuracy
are high on the agenda.

TUNNELLING JOURNAL 19
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 20

SEGMENTAL LINING

Herrenknechts new inliner


system can cut build time in half
Herrenknecht Formwork Technology has recently been HERRENKNECHT FORMWORK TECHNOL-
working on furthering the usability of its Combisegments OGY has developed the next generation of
its Combisegments precast concrete lining
precast concrete lining segments. Instead of GRP, a new segments, using a new material for the cast-
material, pDCPD - Polydicyclopentadienefor, has been used in plastic liner. The manufacturer has
as the cast-in plastic liner. The manufacturer promises the swapped GRP for pDCPD - Polydicyclopenta-
replacement polymer provides not only improved strength diene a polymer with much improved im-
but also higher resistance to chemicals. pact resistance and better chemical
resistance.
Using pDCPD brings several benefits, not
least the fact that the EPDM gasket is
integrated into the plastic liner during the
first step of the two-stage manufacturing
process.
One of the main advantages is that the
gasket is 100% overmoulded and therefore
mechanically connected into the liner, says
Herrenknecht Formwork product manager
Jrg Riechers. After drilling the tunnel and
installation of the rings, its finished and
ready for operation. Thats truly a one-step
lining.
And because you are removing the need
to glue the lining onto the surface, this also
means we can raise the safety level during
ring installation in the tunnel.
Unlike other versions of precast segments
with cast-in liners, the joints need no second
operation to seal them. The EPDM gaskets,
pushed together and compressed, form a
totally watertight seal, containing the tun-
nels contents and protecting the concrete in
the segments from corrosion.
This means that not only the main inter-
nal surface of the segments is lined, but the
edges and seam area as well, says Riechers.
We believe this will lead to better durability
of the tunnel.
Contractors
will save time, Figure 1 Diagram
and therefore showing
money, says functionality of the
Riechers. First, EPDM gaskets
less excavation
will be required
as the Combiseg-
ments wall thick-
ness is thinner
compared to that 25

of a typical multi-
33
layer system. And
second, the inte-
grated gasket
means build time
is speeded up
Herrenknecht
says by up to
50%. 8
20
Designed for

20 TUNNELLING JOURNAL
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 21

SEGMENTAL LINING

sewage, stormwater and sea water tunnels, whereas with pDCPD it isnt likely to. that you will wait for the panels.
Herrenknecht started to show this version of There are two main steps in the manufac- Producing them on site will bring big ben-
Combisegments to its customers around six ture of Combisegments using pDCPD. The efits of time and cost. If you want to use a
months ago. Although the target diameter is first is to create the pDCPD liner using simple PE pipe for lining the concrete seg-
the typical utility tunnel diameter of 2m to Reaction Injection Moulding (RIM). ments in a second step, you have to ship it all
5m, there is no limit as to what size could be The EDPM gasket, handling sockets and over the world. That means a lot of transport
the system for anchoring time and costs.
the liner into the concrete - With pDCPD, the raw materials are shipped
a polypropylene honey- to site, taking up far less space. The polymer
comb structure - are placed is created by mixing two liquid resin compo-
into the mould. Once the nents, supplied by Telene, which combine in a
mould is closed, the injec- chemical reaction.
tion process takes a maxi- Though pDCPD will be new to most tun-
mum of 20 seconds. nelling markets, it has been used in sewage
The second step sees the and water tunnels in Japan on 12 projects
resin liner simply laid in the since 1995. There, the process is different,
bottom of the concrete with sheets of pDCPD laid into the moulds,
mould. Reinforcement can which means that the joints must be sealed
be added as required, and after the segments have been installed.
the concrete cast in the Japans experience has provided useful for
usual way. Herrenknecht which has visited projects
In February 2013, where pDCPD have been used earlier this
Herrenknecht Formwork year. We were impressed by the quality of
built the first ever structure the tunnels, says Riechers. Test data from
using the second-genera- the Japanese Institute of Wastewater Engi-
tion Combisegments: a neering Technology has also served to corrob-
vertical test section at its orate Herrenknechts findings.
factory in Schwanau, In Germany, tests by the German Institute
Germany. Five rings and of Underground Infrastructures (IKT) are also
4m high with an internal underway, with the manufacture aiming to
diameter of 2m, the manu- have national approval by the end of this
facturer is inviting potential year. The segments are being put through
customers to come and their paces, with properties from water tight-
inspect it. ness to pull-out strength of the anchoring
system being tested.
Sights on site This is a big development for us, says
Herrenknecht Formworks Riechers. People have heard of Combiseg-
Above: The Combisegments test ring in goal is that the segments ments but they havent heard about this new
the Herrenknecht factory in Schwanau be made on site. We are planning right now version with this new material. I think it could
to be able to produce Combisegments on make a big difference in the market.
site, says Riechers. When you produce pan-
produced, says Riechers. Already, els in Europe and ship them to the Middle
Herrenknecht is in discussion about East, there will probably be increased costs Below: Tests being carried out by the
Combisegments use on a number of projects due to shipment and there is always a risk German Infrastructure Institute
around the world.

Roots in Russia
Herrenknecht launched its first GRP version of
Combisegments in 2007, with the first and
only - use on the Yuzhny Sewage Pipeline in
Tzariayno, Moscow in 2009. Although this
project was counted as a success, GRP offers
challenges during both the manufacture and
installation phases, so Herrenknecht began to
research alternative materials around three
years ago.
GRP is very rigid, says Riechers. It takes
a lot of effort to put it into moulds and to fix
the gasket.
pDCPD, on the other hand, is not rigid. It
has good impact resistance; some of its com-
mon uses are for bumpers on trucks or fend-
ers on agricultural and construction plant.
This property brings benefits during
construction too. If someone drops a hammer
onto the GRP lining it is likely to break,

TUNNELLING JOURNAL 21
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:38 Page 22

SEGMENTAL LINING

Developments drawn between the concentrated compressive


forces applied to the segment joints and the
concentrated compressive force exerted by a
stiff centrally located bearing-type anchorage
in the case of a post-tensioned concrete

in Joint Design for beam. In each case, the compressive force


exerted on the concrete is concentrated over a
small area and a complex state of stress
develops in the concrete in the immediate

SFRC Segmental vicinity of the applied force.


A transition length, approximately equal to
the depth of the section, is required for the
local stress concentration to disperse and for

Tunnel Linings the uniform compressive stress distribution


associated with simple beam theory to
become established. In doing so, the
longitudinal compressive stresses spread out in
a curved trajectory over the transition length.
Arups Owen Francis and Michele Mangione here The compressive stress trajectories are shown
schematically in Figure 1a. The curvature of
describe a new method for limit state design for these compressive stress trajectories result in
steel fibre reinforced concrete segmental linings transverse compression occurring near the
loaded surface and transverse tension over the
remainder of the transition length. The
ADVANCES IN TBM TECHNOLOGY and transfer of concentrated compressive stress to variation of transverse stress at mid depth with
demand for larger underground space has led the segment joints can be significant and may distance from the face is shown in Figure 1b.
to a trend towards larger bored tunnel result in longitudinal cracking and splitting at The case of a rectangular end block loaded
diameters. As a consequence, segmental the joints. The following joint loading scenarios by a stiff centrally located bearing plate was
tunnel linings need to cater for larger forces have been identified as critical and should be originally studied by Guyon (1953), Leonhardt
and segment joints are being subject to higher explicitly considered during detailed design: (1964) and others to determine the elastic
contact stresses. The need for careful (a) Application of ram thrust to the distribution of transverse stress at mid depth
consideration in the design and detailing of circumferential joint for varying ratios of stress concentration, a/d,
the segment joint zones is therefore becoming (b) Transfer of hoop thrust across the radial shown in Figure 2a. It is a relatively
increasingly important. Traditional segment joint straightforward exercise to verify these
joint design is been based on the approach Although there are a number of alternate findings with the results of simple numerical
presented in concrete design codes for segment joint types, including knuckle joints analysis shown in Figure 2b. The resultant
prestressed concrete anchorage zones and and rounded joints, the standard flat joint distributions of transverse tensile stress have
relies on conventional reinforcement to cater shown in Figure 4 has a proven high load been normalised to 0, where 0 is given by
for the effects of concentrated contact stress. capacity, is simplest for mould construction P/d and is the magnitude of the uniform stress
However, this approach is not directly and is typically adopted in practice. The distribution at depth. In these studies the end
applicable for use with steel fibre reinforced methodology described in this paper applies to plate is assumed to extend right across the
concrete (SFRC) segments which are precast concrete segmental linings with flat block in the z-direction to reduce the problem
increasingly being adopted to take advantage joints supporting undrained circular tunnels to two dimensions. For segmental lining joints,
of their potential for production cost savings, excavated by TBM. where the aspect ratio of the applied contact
improved handling robustness and long-term stress in the z-direction is typically > 4, this
durability benefits. This paper presents an Identifying the problem simplification is reasonable.
alternative first principles approach for limit General - For flat joints, the gasket groove Design considerations at segment joints
state design of SFRC segment joints that has and caulking groove reduce the available joint - The local effects arising from the application
been used with success on a number of recent contact width, tj, to less than the full segment of concentrated compressive stress to the joint
projects. It describes an analysis methodology width. In addition, at radial joints, the actual faces that must be considered during detailed
to assess the state of stress at the joints and joint contact width, tj, may be further reduced lining design are summarised in Table 1.
provides a rational basis to justify the as a result of joint rotation associated with The terms bursting and splitting are
elimination or reduction of conventional ovalisation of the lining as shown in Figure 5. generally used to describe the transverse
reinforcement, which may have otherwise As the joint contact width reduces with tension effects arising from the application of
been deemed necessary. respect to the segment thickness, the concentrated compressive stress. Both terms
compressive force to be transferred at the joint are associated with potential longitudinal
Introduction becomes concentrated over the remaining cracking. Bursting is due to the peak
Unlike a mined tunnel lining, which is typically contact width. transverse tensile stress shown in Figure 2 and
cast in place, a segmental tunnel lining is When concentrated compressive stress is occurs just below the loaded face. The
assembled in place from precast component applied to a joint face, either from ram thrust anchorage analogy described in Section 2.2
segments within the tail shield of the machine. on the circumferential joint or from hoop can be extended to show that significant
The unique nature of this type of tunnel thrust on the radial joint, significant transverse transverse tensile stress is also induced at the
construction imposes a number of additional tensile stresses are induced as the loaded face between multiple widely spaced
design considerations when compared to concentrated contact stress distributes to the loads. The corresponding longitudinal
conventional cast-in-place final linings. full width. cracking at the circumferential joint face
In particular, local effects associated with the Anchorage analogy - An analogy can be between the thrust ram shoes is referred to as

22 TUNNELLING JOURNAL
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:38 Page 23

SEGMENTAL LINING

Contact stress distribution incomplete primary grouting or ground


Figure 1: Analogy with bearing For a given contact force, the magnitude of loading with a horizontal to vertical stress ratio
type anchorage for post-tensioned induced bursting stress is strongly influenced 1 and is typically expressed as diametrical
concrete beam by the joint contact width and distribution of distortion. The corresponding theoretical joint
the contact stress. Figure 2 illustrates the opening can be calculated geometrically
Transition length inverse relationship between contact width assuming elliptical deformation of the ring and
and magnitude of peak bursting stress while infinitely stiff segments so that all deformation
Figure 3 shows the positive correlation occurs by rotation of the joints as shown in
between eccentricity of contact stress Figure 5.
distribution and magnitude of peak bursting However, this theoretical geometrical
P 0
stress. opening of the joints is countered to some
For design of segment joints, the joint extent by the closing effect associated with the
contact width and corresponding contact transfer of hoop thrust across the joint. As
stress distribution must be established before hoop load is transferred, the concentrated
(a) Compressive stress trajectories

Table 1: Design considerations for SFRC segment joints

Joint Loading Local effect to be considered


a Tension
Circle (Circumferential) Ram thrust (a) Bearing at contact surface
d x/d
P (b) Bursting beneath the applied contact stress
0.5 1.0 1.5
(c) Splitting at joint surface between rams
Compression
Radial (Longitudinal) Hoop thrust (a) Bearing at contact surface
(b) Bursting beneath the applied contact stress

(b) Transverse stress distribution (or as part of) the analysis to determine the Figure 4: Contact width and stress
bursting and splitting stress.
distribution at circumferential joint
For ram loading, the contact width is
Figure 2: Elastic distribution of defined as the portion of the ram pad which is CL segment
transverse tensile stress (y) for in contact with the available contact width,
e
rectangular end block taking into consideration offset of the rams
and tolerances of the segment position within Ram Pad
0.5 0 the shield. For ram loading, the contact width Nram
0.0 y
0.4 0 a/d=0.1 usually corresponds to the available contact
P tj
0.2 x width as the ram pad width can be sized to
0.3 0 0.3 iint tj/2 iext
0.4 accommodate the expected offset tolerances. t/2

0.5 tj
0.2 0 0.6 The general case is shown in Figure 4.
0.7 Establishing the contact width at radial joints
0.1 0 0.8
tj = MIN[(tj + bp e), tj] Equation (1)
0.9 is more complex due to deformation
tj = contact width
0.0 (ovalisation) of the ring and the accompanying
0 1/8d 1/4d 3/8d 1/2d 5/8d 3/4d 7/8d d tj = available contact width
rigid body rotation of the segments which bp = ram pad width
x
(a) Leonhardt, 1964 results in a slight opening of the joints. e = offset tolerance
Ovalisation can be caused by poor build,
0.5

0.4 a/d=0.1
0.2 Figure 3: Effect of contact stress distribution on magnitude of peak bursting
0.3
0.3 stress: Left - (a) Uniformly distributed contact stress. Right - (b) Linearly varying
/0

0.4
0.5
0.2 0.6 contact stress
0.7
0.1 0.8
0.9
0.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
x/d
(b) Finite element analysis

2.84 MPa
splitting. 2.23 MPa
For the typical range of tensile strengths
associated with steel fibre reinforced concrete
segments, bursting or splitting failure will
generally occur before sufficient contact stress
can be applied to cause a direct bearing
failure. However, direct bearing failure should
always be checked as part of routine design
and has been included in Table 1 for (a) Uniformly distributed contact stress (b) Linearly varying contact stress
completeness.

TUNNELLING JOURNAL 23
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:38 Page 24

Commitment.
7KHGHWDLOZKLFK
PDNHVWKHGLHUHQFH

Mapei Underground Technology Team


Mapei Underground Technology Team is Mapeis answer to the needs of those who work in the world of
underground construction its the result of Mapeis investment into the research & development of specic
products, of Mapeis commitment and devotion of its team who embody professionalism and experience. Because
commitment makes the difference. By your side from the beginning to the completion of the project.

,QWHUYHQWLRQFDSDELOLW\DQ\ZKHUHLQWKHZRUOGZLWKLQKRXUV
3URGXFWLRQLQFUHDVH
&RVWUHGXFWLRQ

0DSHL/HWVWDNHDGHHSHUORRNWRJHWKHUDW
www.utt-mapei.comKTXWW#XWWPDSHLFRP
/mapeispa
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:39 Page 25

SEGMENTAL LINING

joint contact stress produce strains over the cater for the total transverse tension force main effect of the steel fibre reinforcement is
segment length which lead to an increase in which is given by equation 2. an enhancement of the post-crack properties
contact area (closing effect) until a state of For joints subject to eccentric contact stress, of the concrete which leads to more ductile
equilibrium is achieved. The extent of joint conversion to an equivalent rectangular material behaviour. The increased ductility is
closure is a function of lining geometry, contact stress distribution and application of due to the ability of the fibres to transfer
concrete stiffness and magnitude of applied Guyons symmetrical prism as shown in Figure tensile stress across a cracked section and is
hoop load. The corresponding contact width 7 may be adopted to determine the equivalent dependent on the quantity of fibres added as
and stress distribution can be established in geometry for use with equation 2. well as their physical and mechanical
several ways: To control the width of potential bursting properties. The typical post-crack behaviour of
1. Closed form calculation assuming that and spalling cracks, design codes impose stress SFRC is shown in schematically in Figure 8a
the segment acts as a short column and that limits on the bursting and spalling and is characterised by a gradual reduction in
contact stress at any point on the joint contact reinforcement, typically in the range of 150 to tensile strength with increasing crack width
width is related to strain on the basis of a 200MPa. The design is therefore governed by known as strain softening.
simplified bi-linear stress-strain relationship for the serviceability limit state and the required Splitting tensile strength - The splitting
concrete in compression. This approach is area of reinforcement is determined in tensile strength of SFRC can be estimated by
suggested for routine design. Typical linear accordance with equation 3. The applying code formulae for the principal

Figure 5: Radial joint opening due to Figure 6: Contact width and stress Figure 7: Traditional reinforced
assumed elliptical deformation distribution at radial joint concrete design

N = N1 + N2
z CL segment d
1 = a =
p
N1 e e
2 ( )
2 N2 2

tj/3

d = a + 2i
iext T
iint tj/2
tj t/2

Poor build:
Tunnel profile Case 1: Stress diagram for joint closure
y as constructed End point of
segments, joints CL segment 0

Theoretical: z N
Tunnel profile
e T = 0.25 P (1 a/d) Equation (2)
as designed
1
Ast T / fs Equation (3)
b R L
T = total transverse tension force
L
P = applied contact force
c a = equivalent rectangular contact width
iext
iint tj/3 d = depth/width of symmetrical prism
tj t/2
x Ast = Area of reinforcement required
fs = tensile stress limit in reinforcement
a Case 2: Stress diagram for non-joint closure

am contact stress distributions at full and partial


closure of the joint are shown in Figure 6.
reinforcement across the transition zone is
then detailed to comply with the various code
tensile strength of plain concrete or
determined by indirect tensile strength testing
2. 3D numerical analysis of complete rings in specific requirements regarding distribution (Brazil test). Comparison has shown that the
rk in the world of which all segments are modelled with brick and anchorage. splitting tensile strength determined by testing
opment of specic elements, ground stiffness and diametrical is typically higher than that obtained from
deformation are assigned and expected Steel fibre reinforced concrete design code formulae. The SFRC for a segmental
perience. Because loading applied. These models are advanced Design philosophy - Steel fibre reinforced tunnel lining is subject to extensive testing
ject. and can calculate contact area as well as concrete (SFRC) anchorage zones are not during mix design and production to meet
stresses in the concrete but usually require explicitly covered by current concrete design performance requirements. It is recommended
significant modelling and computer processing codes. Consequently, the philosophy adopted that the splitting tensile strength to be used in
time. This approach is suggested in cases of for design of SFRC segment joints is to detailed design be established and confirmed
very onerous joint loading. determine from first principles the transverse on the basis of this testing.
tensile stress induced by the application of the Constitutive model - For cases in which
Traditional reinforced concrete design concentrated compressive loading and the tensile strength is exceeded and the SFRC
For traditionally reinforced concrete segments, demonstrate that this can be accommodated has cracked, it is convenient to model the
the design methodology presented in design by the tensile strength of the SFRC. post-crack strain softening behaviour of the
codes for post-tensioned anchorage zones is Steel fibre reinforced concrete - Steel SFRC with a stress- strain ( - ) relationship so
usually adopted for design of the joints. The fibre reinforced concrete (SFRC) is a cement that non-linear analysis can be carried out.
basic premise is to provide sufficient based composite material reinforced with Due to the practicalities of carrying out direct
reinforcement across the transition zone to discrete randomly distributed steel fibres. The (axial) tensile - tests on concrete

TUNNELLING JOURNAL 25
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:39 Page 26

SEGMENTAL LINING

specimens, a number of methods to determined explicitly if there is significant factored loads shall be used in conjunction
determine the - relationship from the departure from the assumption of uniformly with the characteristic (un-factored)
results of beam bending tests have been distributed central loading on which the constitutive model and a numerical analysis
developed. These include DBV (1992), RILEM established normalised distributions of carried out. For estimating the maximum
TC 162-TDF (2002) and CNR-DT (2006). The transverse tensile stress are based. crack width, all strain between rams is
tensile strength values used in the resultant - The check is considered an ultimate limit translated into a single crack. This result is
relationship are derived from the state check if the analysis is carried out using then used to assess the serviceability of the
corresponding flexural strength using design (factored) loads and the resultant peak gasket. The acceptable crack width limit is
conversion factors which vary depending on bursting stress checked against the design in the order of 0.2 to 0.3mm.
the method adopted. The RILEM - splitting tensile strength which includes the
relationship is shown in Figure 8b. partial material factor for concrete: Conclusion
Elastic Analysis - The simplest approach to *y,p fctd.spl Equation (4) Given the trend towards larger tunnel
determine the peak transverse tensile stress is fctd,spl = fctk,spl /YC Equation (5) diameters, optimised segment thickness and
to set elastic material behaviour to the
concrete, apply the contact stress and carry out
the analysis. The resultant peak bursting stress Table 2: Suggested design procedure for SFRC segment joints
is then checked against the splitting tensile
strength of the concrete. Provided the peak Stage Description
bursting stress does not exceed the splitting 1. Contact stress (a) Establish the joint contact area and contact stress distribution
tensile strength of the concrete, the (b) Check the design bearing stress against the design bearing capacity
assumption of elastic material behaviour is 2. Elastic analysis (a) Carry out elastic analysis of the segment joint zones using factored loads to
considered valid. determine the distribution of transverse tensile stress
Elastic analysis to determine the peak tensile (b) Check the peak bursting stress against the design splitting strength
stress can either be done using the established (c) Check the peak splitting stress against the design splitting strength
elastic distributions of normalised transverse (If the splitting tensile strength is exceeded, the presumption of elastic behaviour is
stress for a rectangular end block available in invalid and non-linear analysis is required)
the literature (Figure 2a) or explicitly by linear
elastic analysis of a simple 2D numerical model 3. Non-linear (a) Carry out non-linear analysis using factored loads and constitutive model.
(Figure 3). For uniform contact stress, the analysis The ULS is satisfied if the factored analysis can converge.
maximum transverse tensile stress predicted (if required) (b) Carry out a non-linear analysis using unfactored loads and constitutive model to
using Figure 2 matches well with explicit 2D satisfy crack width requirements at SLS.
numerical analysis. For non-uniform contact
stress distributions, conversion to an equivalent Provided the design splitting tensile strength is hence increased stress at the joints, careful
rectangular distribution and application of not exceeded, the serviceability limit state will consideration in the design and detailing of the
Guyons symmetrical prism may be adopted so typically be satisfied on the basis that the con- segment joint zones is becoming increasingly
that hand calculation based on Figure 2 can be crete remains uncracked under the application important. This is particularly relevant for SFRC
carried out. However, hand calculation using of the service (unfactored) load. segments where introduction of traditional
these simplifications tends to over-predict the Nonlinear analysis - An elastic analysis will reinforcement solely to cater for tensile stresses
peak bursting stress. It is therefore generally only be successful for bursting at the joints can have significant impact on
checks. Elastic analysis of splitting stress be-
recommended that the peak bursting stress be production time and cost.
tween rams will typically show localised tensile
In many cases, provided the tensile strength
stress at the joint surface in excess of the split-
of the SFRC is properly specified and confirmed
ting strength. If the elastic peak tensile stress
Figure 8: SFRC material model with ongoing production testing and an
exceeds the splitting tensile strength, elastic
appropriate analysis is carried out to determine
analysis is not appropriate and a non-linear
the tensile stress induced at the joints,
Stress analysis is required.
First crack elimination or reduction of bursting
tensile strength
For non-linear analysis, incorporation of the reinforcement at the joints can be justified. The
non-linear strain softening material behaviour suggested design procedure for SFRC segment
Post crack is required to account for the local tensile joints is summarised in Table 2.
tensile strength failure of the concrete. The purpose of this
analysis is to determine whether the excess REFERENCES
transverse tensile stress (bursting or splitting)
can be satisfactorily redistributed once the
1. Leonhardt, F., 1964. Prestressed Concrete
Crack width peak tensile strength has been exceeded and
Design and Construction, English Edition,
(a) Typical strain softening behaviour the concrete has cracked. Non-linear analysis
Wilhelm Ernst , Berlin.
incorporating the strain softening constitutive
2. Mattle, B & John, M., 2009. Analysis and
model described in Section 5.4 may be carried
c design of unreinforced final tunnel linings.
out with finite element software.
Tunel, Vol 1, pp. 73-78.
To check the ultimate limit state, design
1 3. RILEM, 2003. RILEM TC 162-TDF: Test and
2 (factored) loads shall be used in conjunction
3 design methods of steel fibre reinforced
3.5 2.0 with a constitutive model that has been
1 2 3
concrete, --design method. Materials and
reduced by the partial material factor for
c [] Structures, Vol. 36, pp. 560-567.
concrete. The ultimate limit state is satisfied if
4. Warner, R.F., Faulkes, K.A., 1988. Prestressed
the subsequent numerical analysis can achieve
Concrete, 2nd Edition, Longman Cheshire Pty
a stable solution, i.e. the analysis can converge
Ltd, Melbourne.
(b) Simplified - relationship (RILEM)
to equilibrium.
To check the serviceability limit state, un-

26 TUNNELLING JOURNAL
Ground Support Systems

Visit us at WTC 2013,


Geneva, May 31st - June 7th 2013,
Booth no. M1 (Lower floor)

Your partner for tunnel and civil engineering projects

Minova tunnelling and civil business area delivers high performing ground support and consolidation
products and services to people working in tunnelling, infrastructure, construction and repair works. Our
expertise has been developed through growing our people complimented by our long and solid history in
global mining and tunnelling works. We are striving to be the preferred supplier of safe and high
performing products to people working in tunnelling and civil projects, anywhere around the world.

High performance injection resins and resin capsules (Polyurethane, Silicate, Acrylic, Phenolic)

Bolting systems (SDA, GRP, Fore poling system and others)

Professional assistance from experienced engineers

Minova International
Tunnelling & Civils
info@minovaint.com
www.minovainternational.com

A
A member
memberofofthe
theOrica
OricaGroup
Group Ground Support Systems
TJ_0513_ITIG_028.qxd:Feature 21/4/13 12:46 Page 28

RISK REPORT

ITIG 2013 Subsurface


Works Risk Report
NORTH AMERICA, Eastern and Western
The International Tunnelling
Insurers Group (ITIG) is the
author of a Code of Practice for
Risk Management of Tunnel Works, a framework for risk
Europe, Africa and parts of Asia remain less management to assist parties engaged in subsurface construction to
active in the subsurface works arena having
identify the real and special risks associated with their discipline.
not yet recovered from general downturns
associated with the Global Financial Crisis. In ITIG routinely considers the changing World events and
these jurisdictions there remains a higher circumstances which it believes may favourably or unfavourably
pressure from government clients to minimise impact upon schedule, cost, and quality of subsurface works. Here
the price of subsurface infrastructure and
wherever possible implement innovative
ITIG presents its assessment of the Worlds current market condition
construction techniques and simplified and
less expensive designs. Risk mitigation strategies with an emphasis noticeable.
In this environment we are also observing on supervision, quality control, on the job
many new entrants into subsurface training and continuous improvement will Latin America
contracting. The combination of a downward likely be appropriate for managing the altered Continuing strong activities in mining,
pressure on construction prices, innovation risk profiles of projects in these regions. Due to hydropower and infrastructure with domestic
and reduced complexity, with an abundance the availability of capital sovereign, risks and non-domestic contractors bidding and
of capacity in the market, increases the risk associated with cash flow in these projects is delivering. Risk management attitudes and
that projects take on more aggressive considered likely less than in European and procedures are further improved.
construction schedules, involve less North American countries where fiscal policy
experienced contractors and thereby increase remains stretched. Europe
the likelihood of overruns in time and cost and Subsurface activities are not keeping pace with
the production of substandard quality works. Asia economic growth. Central London though
Participants in these markets are urged to Market conditions in Asia vary significantly in remains an active area for tunnelling where
focus on factors such as the actual experience terms of construction activity. robust risk management procedures are being
of contractors and the sufficiency of Some are generally buoyant with a large applied. Central Europe sees a number of
remuneration in the contracts when managing portfolio of projects available to all huge subsurface works on which strict risk
the risks associated with projects in these participants. Although 2013 is depressed by management procedures are applied.
regions. Of particular focus is an emerging pre GFC standards, economic activity remains
desire for clients and projects to self regulate strong. Fully developed countries do not offer Conclusions
critical aspects of the construction, safety and enough projects to their domestic contractors 2013 sees comparatively high levels of activity
engineering as part of their cost saving so a push into other markets can be observed. as many countries embark on demanding
exercises. Lessons from the Heathrow and The emerging risk in these markets is the subsurface infrastructure transportation
Nicoll Highway collapses about the special increased focus on foreign projects thereby projects often as part of economic stimulus
risks of self-regulation should be considered reducing the pool of experienced contractors packages.
when pursuing risk mitigation strategies in for any given regional project. Strategies which The generally tight economic conditions
these projects. address the decrease in availability of coupled with many new entrants into the
experienced practitioners are an appropriate subsurface construction market means that
The Middle East risk mitigation strategy. experienced labour at all levels and in every
The Middle East Gulf Region is generating Hong Kong and Singapore continue to aspect of project construction will be
unprecedented activity in the metro and road assume a special role in the region with stretched.
tunnel sectors of subsurface construction. exemplary procedures. The drive by clients for reduced costs,
2014 will see major projects concurrently As in other parts of the World there are a coupled with the re-emergence in many
begin in Qatar, Abu Dhabi, Saudi Arabia and number of new participants entering the markets of lump sum design and build
Oman. The scale of these projects will likely markets who necessarily require greater contracts, increases the likelihood of severe
stream the top tier contractors and their supervision as part of a prudent risk economic stresses within projects.
experts ability to provide professional services management strategy. Risk mitigation strategies, which focus upon
and supervision. Turkey sees a continued push for large-scale training of comparatively unskilled workers,
Contracting practices in these regions are infrastructure subsurface works with a increasing the effectiveness of supervisory
typically fixed price lump sum design and tendency for JVs formed by local and experts through actions such as collaboratively
build. The combination of the sheer volume of International contractors. sharing information between multiple
work to be constructed, the lack of local contractors concurrently working in the same
expertise and the tight delivery timeframes will United States cities are all mitigation strategies likely to
mean that in this region project risk Compared to the size of its economy increase successful project completion.
management must focus on training subsurface activities are lacking behind Overall 2013 will be a highly productive
comparatively unskilled workforces, optimising expectations with more and more non- year for international subsurface construction
the effectiveness of skilled labour and American contractors seeking opportunities. and marks the continuation of a wave of
supervising contractors whose resources will With their arrival more international increased momentum for the underground
likely be strained by the sheer volume of work. procedures on risk management are construction industry.

34 TUNNELLING JOURNAL
28
Let your skills take off

Aim for the sky with training from Atlas Copco Service
To get results and reach the top you need skill. With Atlas Copcos training products,
operators, technicians and specialists will learn how to master the machines in a
safe and sustainable way.
With our training products, where our sophisticated training simulators hold a key
role, they get to know their new workmate, inside out. Trained people perform
better, find their work more enjoyable and contribute to increased productivity.
Atlas Copcos training products add value to your operation.
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:12 Page 30
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:13 Page 31

WTC 2013

WORLD TUNNEL
CONGRESS 2013
With only a few weeks to go, from 31 May to 7 June, both the WTC 2013
and the 39th general assembly of the International Tunnelling and
Underground Space Association will take place under the motto
Underground the way to the future. The Swiss Tunnelling Society
(STS) is the host in the beautiful Swiss city of Geneva.

SWITZERLAND IS WELL KNOWN for features at this years event. For example, the introduce itself to a larger audience regularly
scenic landscapes and outstanding ITAtech Committee will make a prominent in the context of the presentation forum.
infrastructure as well as its well-developed appearance for the first time at the WTC The presentation forum planned in Geneva
transportation system. The many innovative 2013. On Tuesday afternoon, 4 June 2013, it is located in the exhibit area and offers
solutions employed in the construction of is organising a special session called the exhibitors and participants the opportunity to
Switzerlands numerous tunnels and ITAtech Innovation Session. There, present their newest products, innovative
underground facilities have demonstrated information will be provided about the applications and interesting case studies.
the nations pioneering spirit time and ongoing efforts in the Activity Groups of
again, underscoring its position at the top ITAtech and the first round of guidelines Deminar on sprayable waterproof
of the tunnel construction technology field. developed will be presented. These describe membranes
both the state of the art and best practice A special event within the framework of
ITAtech guidelines with regard to innovations and new technical the WTC 2013 in Geneva is the deminar
Visitors can look forward to many new developments. In addition, ITAtech will on 31 May in the Hagerbach Test Gallery

TUNNELLING JOURNAL 31
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:13 Page 32

WTC 2013

Alphabetical
exhibitor overview
No Company Name
1 AFTES Plant Equipment Branch
2 AGIR Aggregat AG
3 Altamira Information/Subterra
4 Amberg Group
5 Arcadis Geotechnika a.s.
6 ArcelorMittal
7 Astra BAV
8 Atlas Copco Schweiz AG
9 BASF
10 Becker Mining America
11 Bochumer Eisenhutte Heintzmann
12 Brokk AB
13 Caterpillar Tunneling Canada Corporation
14 CBT Brazilian Tunnelling Committee
15 CIFA SpA
16 Dtwyler Sealing Technologies Deutschland GmbH
17 Denka Chemicals GmbH
18 DESOI GmbH
19 Dextra Group
20 DMT GmbH & Co. KG
21 DSI Dywidag-Systems International / Geodata
Ziviltechnikergesellschaft Austria
22 Ein Shemer Rubber Industries Ltd
23 Elkuch Bator AG
24 Fermacell GmbH
25 FiReP Rebar AG
26 FOGTEC Brandschutz
27 Geodata S.p.A., Torino
28 Geokon Inc.
29 germanBelt Systems
30 Giertsen Tunnel AS
31 Halfen GmbH
32 H-Bau Technik GmbH
33 HBI Haerter Consulting Engineers
34 Herrenknecht
35 HIC Corporation
36 Hilti (Schweiz) AG
37 Holcim (Schweiz) AG
38 Implenia AG
39 itech
40 itmsoil on the topic of Sprayable Tunnel Sealing this knowledge to the international
41 Jordahl GmbH Membranes. This deminar will also be tunnelling community. All lectures of the
42 Liebherr-France SAS
43 Lombardi SA organised by ITAtech. Sprayable sealing Swiss Session will be given in German,
44 Maccaferri S.p.A. membranes offer new opportunities in the French, Italian or English and will be
45 Mapei construction of tunnels. Over the past interpreted simultaneously into English or
46 Marti
year, the ITAtech Activity Group Lining German.
47 MATRICS Consult Ltd.
48 Messe Berlin GmbH/InnoTrans and Waterproofing has worked on this
49 Metalliance intensively and has developed a design The upcoming generation Young
50 mineARC Systems guideline for the application of sprayable Swiss Tunnellers
51 Minova MAI GmbH
52 NFM Technologies
waterproof membranes. It will be Students will be offered the opportunity
53 Normet International Ltd. presented in the context of the deminar. of presenting their semester projects and
54 NV Bekaert SA The deminar combines presentations, as diploma theses to a larger audience of
55 Pavemetrics Systems inc. / EUROCONSULT Nuevas are customary in a seminar, with the industry professionals at the WTC 2013.
Technologias, S.A.
56 Pyry Infra AG
unique opportunities afforded by the test This, too, is a premier! The students will
57 Promat AG gallery at Hagerbach to demonstrate the gain insight into the international world
58 Rascor International AG application under realistic conditions. of underground construction, which will
59 RBL-REI France certainly be a valuable experience for
60 Rocksoil S.p.A.
61 ROWA/Belloli Dont miss them: The Swiss Sessions them. The organisers wish to set an
62 S.E.L.I. SpA Every June, the Swiss Tunnel Society holds example with this special session for a
63 Sandvik / Avesco the Swiss Tunnel Congress in Lucerne. In stronger commitment to the promotion of
64 SBV / Infra 2013, it is being moved to Geneva and the upcoming generation.
65 Schauenburg Group / Herco Kuhltechnik
66 SIKA / Putzmeister integrated in the WTC as the Swiss
67 SIREG S.p.A. Session. All WTC 2013 participants are The conclusion on Lake Geneva
68 SPS Consulting free to participate in the Swiss Session. Also on Wednesday evening, 5 June 2013,
69 Stirling Lloyd Polychem Ltd.
On Tuesday afternoon, 4 June 2013, the the traditional concluding banquet will be
70 swiss IT-Factory AG
71 T.R.E. srl Tele-Rilevamento Europa colloquium will take place followed by a held on three large, historic steamships on
72 TAC Corporation day of selected lectures and presenters on Lake Geneva. The special ambience of
73 Terratec, Tasmania Australia Wednesday. The main focus of the Swiss these ships, maintained in original
74 The Norwegian Tunnelling Society NFF
75 The Robbins Company
Session is provided by the experience condition from the Belle Epoque,
76 Trelleborg Ridderkerk BV gained in the construction of the two together with the incomparable landscape
77 Vik rsta AS base tunnels, Ltschberg and Gotthard of Lake Geneva will provide a worthy
78 VMT GmbH through the Alps. The intent is to pass on context for this exceptional occasion.

32 TUNNELLING JOURNAL
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:13 Page 33

www.normet.com
www.taminternational.com

SOLUTIONS FOR
TOUGH JOBS

HIGH QU
QUALITY
ALLIT Y GASKE
GASKETS
TS
International Exp
Experience
perience
Proven longevityy

Reliable tunnel segm


segment
men
sealing gaskets
t monoepdm
monoepdm
t coex
coexslide
slide
t coex
coexswell
swell
t composite blackswe
blackswell
ll
t monoanchored gaskets
gaskets
metro,
for road, railway, metro cable,
o, ca
tunnels
sewage and water tunn nels

www.datwyler.com

TUNNELLING JOURNAL 33
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 34

PROJECT POLITICS

Clearing the Hurdles


Desiree Willis of The Robbins
Company looks at the
sometime complex political
backdrop that accompanies the
realization of many of todays
large scale tunnelling projects

Above: The Robbins EPB at


Lot 1 of the Emisor Oriente
tunnel broke through in
autumn 2012

Left: Mexican President


Felipe Caldern (left) and
Governor Eruviel vila
(right) commemorate the
breakthrough of a Robbins
TBM in September 2012

Right: Mexico Citys Emisor


Oriente Wastewater Tunnel
is an emergency project
being built to prevent
flooding in the downtown
area and boost capacity

BY NOW MANY tunnellers are familiar with construction, but many politicians overlook the generally a government agency with a board
the story of the Access To the Regions Core underground option. Steve Skelhorn, Project consisting of politicians, not engineers. This
(ARC) tunnel in New Jersey, USA. The 14.5km Sponsor at McNally Construction Inc., an makes decision making very time consuming.
tunnel was to be driven below the Hudson experienced contractor, gave his take. Also as it is usually public funds there tends to
River between the states of New Jersey and Committing huge sums of tax payers money be a lot of time and energy diverted to public
New York, and would have doubled commuter for a perceived benefit in say 20 years time is opinion, sometimes at the expense of progress
rail capacity between the two. The project, not necessarily on a politicians agenda. It is of the tunnel. Different procurement processes
however, was short-lived: After spending about often the case that the politicians will go for a that dont only focus on the low bid could
US$600M to begin construction, New Jersey rapid fix a short-term gain option over long- alleviate many of these issues. During the
Governor Chris Christie called for a halt to the term investment. This might be providing new procurement of the SR 99 TBM, for example,
project due to cost overrun concerns. While buses or streetcars over building a subway, for weight was given not only to cost, but also for
some form of the project is still in discussions example. Obviously we cannot get away from technical merit of the design.
and officials are looking to revive it, another politicians on these projects as it is generally Worldwide, political ramifications affect
run at a trans-Hudson tunnel is estimated to be public money, but we can educate politicians projects throughout excavation, not just during
at least a decade away. and the public more. There appears to be a lot startup. Government support can play a key
As projects and their investments become of misinformation surrounding tunnels and the role in a projects success.
larger, politics will have an ever-larger role, with tunnelling industry.
both positive and negative aspects - a Some public shareholder groups, like those Mexicos Emisor Oriente
dichotomy that can make a project complex involved at Seattle, Washington, USAs SR 99 At 63km long, Mexico Citys Emisor Oriente
before anyone even starts digging. Tunnel project have been successful in arguing Wastewater line is a vast undertaking and the
for an underground option over alternatives countrys largest infrastructure project by far.
Political involvement - the pros and cons such as new bridges and surface streets. But The pipeline is being built both to prevent
Political involvement can boost a projects Skelhorn sees an ongoing need for new flooding and to add much needed capacity to
status and place it on the fast track to practices, In large projects, the owner is the areas growing population. Ground

34 TUNNELLING JOURNAL
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 35

PROJECT POLITICS

Above: Multiple EPBs at Phase III of


the New Delhi Metro Extension will
excavate ring lines between Delhi and
two neighbouring suburbs

Left: Lowering of a Robbins EPB


cutterhead at the New Delhi Metro,
where multiple extensions are
expanding the system by 50km

settlement in Mexico City has caused the


existing gravity feed wastewater system, built
in 1975, to lose its slope. Much of the main
pipeline, Emisor Central, is severely corroded
and at high risk of failure - an event that would
cause up to 5m of wastewater to flow into
Mexico Citys surface streets.
Mexicos National Water Commission
(CONAGUA), under direction of then-President
Felipe Caldern, recommended immediate
construction of a new line to help supplement
the struggling system with an additional
150m3/sec capacity. The completed line will

TUNNELLING JOURNAL 35
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 36

PROJECT POLITICS

carry wastewater from Mexico City to several designated Lot 1 site prompted a swift Mexicos current President, Enrique Pea
water treatment plants currently under machine change in 2011. The first piece of Nieto of the Institutional Revolutionary Party,
construction in the state of Hidalgo, where it this project is the critical 10km section at Lot 1. dedicated more funds to the project in 2013 to
will then be recycled for safe use in agriculture. The first Herrenknecht TBM started in shaft 0 in ensure completion of the entire line by its new
The construction of the line was divided into 2009, but was stalled for six months due to a schedule of December 2016. They have a
six lots - Lots 1, 2, and 5 under Mexican flood. In order to finish in time, we brought in positive attitude with us, CONAGUA. They are
contractor Ingenieros Civiles Asociados (ICA) a Robbins TBM originally slated to work on Lot working with us to develop programs to
S.A. de C.V, and Lots 3 and 4 under Carso 5, shaft 20. The TBM bored at Lot 1, shaft 5 in analyze problems and challenges that come
Infraestructura y Construccin, S.A. de C.V. Lot the opposite direction towards the TBM in up, said Carillo.
6 is under construction by Lombardo shaft 0, said David Juarez, then Site Manager Its the best thing that could have
Construcciones and Constructora Estrella. All for ICA. Due to the loss of slope, the Gran happened; we now have more support from
six lots were designated for excavation with Canal at Lot 1 now has a positive vertical government and the opportunity to purchase
8.93m diameter EPBMs, with Robbins alignment below Mexico City and the Ecatepec more equipment. The new administration
supplying three EPB machines and area just outside of the city. Increased volumes wants the project done as fast as possible and
accompanying continuous conveyor systems, of water have the potential to overload current has more than doubled the budget for the
and Herrenknecht supplying three EPBs. pumping stations and send the untreated project, said scar S. Aguilar Prez,
With support from Caldern and water back into the city. Construction Manager for contractor ICA.
CONAGUA, the project began and TBMs were The Robbins TBM completed its 3.5km With the support of the government,
procured in 2010. Prior to the Emisor Oriente tunnel in autumn 2012 after achieving fast contractor, and equipment suppliers, the
there were no tunnels in Mexico for many advance rates up to 592m per month, and is machines are overcoming significantly
years. When the project started, the now being disassembled and sent to its original challenging ground conditions. The three
government and contractors began employing Lot 5. A treatment plant and a pumping station Robbins machines were built to excavate lake
university graduates and people who had at Shaft 5 of Lot 1, is now going online to clays, volcanic rock, and boulders up to
worked on tunnel projects in the 1980s and pump the water diverted into Emisor Oriente 600mm in diameter. The ground conditions
earlier, said Hector Carillo, Machine back into the Gran Canal where the slope has have been identified as some of the most
Superintendent for contractor Carso. not been affected. The finished section has complex in the world - abrasive basalt up to
After repeated flooding of the Gran Canal, been sealed off from the rest of construction. 80MPa UCS is mixed with sections of watery
an untreated waterway at the Lot 1 site, Once Lot 1 was completed, a new President clay that have been compared to a soup, while
governmental agencies declared that section of took office and appointed a new set of officials water pressure is estimated in the range of 4 to
the project a national emergency. at CONAGUA to advise on the project, as these 6bar, some of the highest pressures EPBs have
Although six TBMs were slated to bore at positions at the government agency are worked under.
each lot, problems in shaft 0 at the critically- affiliated with political parties. To tackle the conditions, Robbins engineered

Visit MSD on the 30th International Trade Fair

Hall C3, booth 415/514


Manufacturer for injection technology

Injection systems Maschinen


Stahlbau
and

Mining Dresden
Branch of Herrenknecht AG

Tunneling For whatever reason


Civil engineering
youre tunnelling
Special civil engineering
MSD Maschinen- und Stahlbau Dresden -
your reliable partner for special equipment.

Special device for laying invert segments,


European XFEL, Hamburg, Germany
Hydraulic packer

2K Pneumatic reciprocating pump

DESOI GmbH Phone: +49 6655 9636-0


Gewerbestrae 16 info @ desoi.de | www.desoi.de
D-36148 Kalbach Videos

36 TUNNELLING JOURNAL
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 37

PROJECT POLITICS

some space, as land is not available


everywhere, so we are waiting for the
allotment of land apart from whatever area we
have already. The second problem is utility
diversion; there are many water or sewerage
lines are present, which need diversion.
Monitoring of 26 TBMs at the same time will
definitely be a challenge and for that we are
planning a centralized monitoring system,
which has not yet been finalized but we are
planning to have a centralized server and from
there management information will be
generated. This will help in maintaining
smooth running of all the construction
management.
In addition, traffic management around
Once complete in 2016, Phase III of the New Delhi Metro Extension is projected to multiple jobsites requires detailed planning for
carry 3 million riders annually road closures and service lane closures. When
near residential areas, the jobsites will also be
subject to noise restrictions at night. Mr. Tyagi
the EPBs with mixed ground, back-loading extensive funding from the Central is confident the project will be a great success -
cutterheads. High pressure, tungsten carbide Government as well as international lenders is the new ring lines are projected to carry 3
knife bits can be interchanged with 17-inch fueling its expansion. million riders annually, and the DMRC is not
diameter carbide disc cutters depending on the In the Delhi Metro Extension Phase III, an going to stop there: Planning for Phase IV has
ground conditions. The design also allows for additional 140km will be built throughout begun. The initial tender should be finalized by
bearing and seal removal from either the front Delhi and connecting to neighboring cities 2015.
or back of the cutterhead. Twenty-five injection Haryana, Faridabad, and Bahadurgarh. 50km
ports spaced around the periphery of the of the new ring lines will be built underground. Education is Key
machine are used for injection of various As far as the benefit of Delhi people is Whether the tunnel is in Mexico, the U.S., or
additives depending on ground conditions, and concerned, any mass transit system is a benefit India, political developments can make or
for probe drilling. Additives such as Bentonite to the public. It will decongest many roads, as a break a tunnel project. The key factor,
are being used to condition the muck for large number of people will shift from road to emphasizes Skelhorn, is education:
removal by belt conveyor. metro. Not only that, but the new line will Is there an easier way to boost government
High pressure conditions in concert with provide a great support to the working class coffers than cancelling a billion dollar project?
large boulders additionally necessitated a two- who commute between Delhi and Faridabad he asks. Education of the politicians and public
stage screw conveyor design for the EPBs. An and Bahadurgarh (Haryana), as they can stay in is the best path forward towards greater
initial 900mm diameter ribbon-type screw is those areas where the standard of living is acceptance of the underground option.
capable of transporting boulders up to 600mm quite a bit cheaper than Delhi, said Mr. Tunnelling has its risks and when things go
in diameter up the center shaft for removal Jitender Tyagi, Director Projects for the Delhi wrong they can go very wrong. Unfortunately
through a boulder collecting gate. Metro Rail Corporation. the local media tends to report things going
As of spring 2013, the Lot 5 machine is In planning for this huge project, the DMRC wrong way more than when they go right.
being readied for launch and excavation is has looked to models in Japan, Singapore, There is nothing sensational about a successful
ongoing for the Robbins TBMs at Lots 3 and 4. Hong Kong, and Bangkok in researching their tunnel. Consequently public opinion is swayed
The Lot 3 machine, more than 70m deep, is design, and hope their system will become a by this media and gives more weight towards
excavating at rates of up to 408m per month. model as well. Gradually, we have built our the negatives. Lobby groups within the tunnel
The rates are good in light of excavation in own unique metro system that is getting more community, including associations, can play a
nearly 4km of highly abrasive basalt. The advanced every day. One improvement will be major role in promoting tunnels.
machine encountered this rock after just 78m with ring lines, which encourage connectivity. Skelhorn cites a number of myths that
of boring and required some modifications. Our previous reaches of metro were built in persist in the community as a result of
The excavation at Lot 3 has been the most long radial lines, said Mr. Tyagi. negative press and rumors: As an example I
difficult for us, because of the mixture of sand, The underground portion of rail line was have talked to some people recently and they
clay, and abrasive rock, explained Prez. The proposed for aesthetic reasons and due to the were generally surprised that a tunnel could
third Robbins machine at Lot 4 is experiencing available space in densely populated areas. possibly be driven under a river. They cited a
slower rates due to cutter changes as a result Right now 4 TBMs are currently working but local newspaper report and commented:
of abrasive rock and large boulders being phase III has just started. We can expect 26 Dont those subway people realise that to
encountered. TBMs will be working simultaneously in and build a new subway would mean tunnelling
around 1 year from now, said Mr. Tyagi. The under a river? Everybody knows this is not
Governmental planning - New Delhi ground consists of a mixed face with rock, and possible, they should look at a map before
A model for extensive governmental planning DMRC expects that all tunnelling will be done coming up with plans like this. It is only by
and support is that of the metro extension in with mixed ground EPBs rather than slurry dispelling rumors, promoting success stories,
New Delhi, India. The city of over 16 million is machines. and the benefits and safety of tunnelling, that
home to some of the worlds busiest traffic. In Phase III has a tight construction schedule, public and political opinions can be swayed
answer, the state-owned governmental agency with completion targeted for the end of 2016. towards the positive. While we still have a
Delhi Metro Rail Corporation (DMRC) has built The logistical challenges of launching so many long way to go to overcome the hurdles,
two phases of the Delhi Metro, with a third TBMs simultaneously in order to meet the many projects are navigating the gauntlet of
phase just getting started. Currently the metro schedule, admits Mr. Tyagi, will be many. political opinion, and are having great success
is nearly 190km with 142 stations, and Wherever the TBM is launched, we require as a result.

TUNNELLING JOURNAL 37
TJ_0513_038_039_BTS_Conference_Ad_.qxd:Layout 1 21/4/13 13:40 Page 38

bts
2013
EVENT VENUE:
THE QUEEN ELIZABETH II
CONFERENCE CENTRE,
Broad Sanctuary,
Conference and Ex
Exhibition Westminster, London
SW1P 3EE

Co
BER 23 24, 2013
OCTO nt deliver
ces that simply do
Tired of conferen British
e. Thats why the
on content? We ar ed up
y (BTS) has team
Tunnelling Societ to host
urnal and Brintex
with Tunnelling Jo em ier
ent at Londons pr
this first class ev conference ve nue.

that address
and or ig inal presentations
Fo cu se d tunnelling will
l ch alle nges of modern
the tech nica l standing,
rts of internationa
be given by expe m sessions,
w ith pa ne l debate and foru
com bine d n and the
a tailored exhibitio
the BTS lecture, s most high-
ty to visi t some of London .
po rtu ni truction projects
COPYRIGHT CROSSRAIL LTD

op
profile tunnel cons
elling capital,
in Lo nd on, Europes tunn
So jo in us ing of a new
itness the beginn
this October to w generation of tech
nical
conf erences

,
inform ation ab out the conference contact:
For mo re ase
or spo nsors hip opportunities, ple
exhibit
Gary Tween ion, Speaker an
d
ate R eg istrat
Bill Butler Deleg
the Exhibition portunities
Stand Space at Sponsorship op
720 631
73 6627
Tel: + 44 (0) 20 79 luk.com Tel: + 44 (0) 1622 lingjournal.com
el
Email: b.butler@
hg Email: gary@tunn

Sales please visit: om To


For Dele gate Registration
and Exhibition
w w w.B T S 2 013 .c
TJ_0513_038_039_BTS_Conference_Ad_.qxd:Layout 1 21/4/13 13:41 Page 39

ns and Themes
io
Conference Sess
urement?
DAYn 1 What is the futu
re for tunnel proc K - The Tunneller's Agenda
- Infrastructur U e
1
Sessio tinuity
Keynote lectures Ahead To Ensure Workload Con
ng
ITACUS - Planni
cluding
en ta tio ns w ill cover themes in
Session 1's pres ement strategies
Tunnel procur
TBM procurem
ent ty and risk
oi l m an ag em en t the opportuni
Sp
Logistics and
ur in g in su rance
Proc
actice
- Pu tt in g Design into Pr
rayed Concrete
Li ni ng ent structures
Session 2 Sp tu re of pr im ar y linings as perman
The fu
undaries of SCL e sprayed system
s?
Pushing the bo tly w he re ar e we now with th
- Ex ac
Waterproofing at won't go away
Fi br es - The argument th aterials technolo
gy
Steel v Pl as tic
th e fa ce of SC L with modern m
ngin g a
Materials - Cha from the floor to
on ym ou s 'b al lo t box' questions
g an
l Debate featurin
3 - A 'N ew sn ight' style Pane in in !
Session couraged to jo
. Delegates are en
panel of experts
nks Reception
m ee tin g, fo llowed by a Dri
Monthly BTS

DAYn 2
1 - The Fu tu re fo r TB M s and Segmenta
l Linings
TBM technology
Sessio es in
Recent advanc Ms
ecifications for TB
Performance sp
s explained
Grouting system spoil removal
ce lo ss an d ke eping a check on
Fa
ing roundup
Segmental lin
systems
Muck removal
e Industry?
ri ng Really Taught th
t ha s M on ito ss for design? onths, 18 month
s?
Session 2 - Wha propriate face lo e monitoring, 3 m
What is the ap ca le fo r ba se lin ns ul ta nt or contractor?
eal times the client, co
What is the id rin g co nt ract or -
ocure the monito
Who should pr it rig ht
- getting d processes?
Specification ria te trigger values an
th e ap prop
What are
follow
O pe ra tio ns Information to m the two days
Session 3 - Tu nn el
rin g so m e of th e salient points fro
yle Debate cove
4 - Th e cl os in g 'Newsnight' st
Session

ww.BTS2013.com
To join us visit w
2013.com
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 40

REMEDIATION

THE JUBILEE LINE


REMEDIATION
When water and sand started running into a previously dry tunnel in the
London Underground network, some puzzling questions arose. The operation to
seal the tunnel has helped answer some of those questions and spawned a
revolutionary new monitoring system. Kristina Smith reports.

THIS IS A STORY ABOUT how Londons


unfolding geology caused an unusual
problem in a 35-year old metro tunnel. Its a
story about how a group of engineers and
enthusiasts with different specialities came
together to pioneer a brand new solution,
and how a client and main contractor had the
conviction to go with that solution.
Its also a story with a happy ending and a
few remaining mysteries that may leave the
reader wanting to know more.
It begins in August 2010, when inspectors
in London Undergrounds Jubilee Line tunnel
reported that sand and water were running
into previously dry sections of tunnel near to
Bond Street station. It ends in January 2012
with the successful completion of back
grouting of the tunnels, with wireless real-
time monitoring during the grouting which
saved an estimated 1M compared to
conventional techniques.
In between those dates, every inch of that
section of tunnel was to be monitored,
scrutinised and analysed. And a chance
conversation between Simon Maddison, chief
operating officer of monitoring company
Senceive and Peter Wright, associate director,
tunnels, at Halcrow at a conference in
Cambridge would lead to Senceive
developing its wireless monitoring for this
challenging application.
Real-time monitoring was vital for this
grouting operation because some of the
tunnel rings had moved significantly as the
ground around them changed. The engineers
had to make sure that the grouting didnt
push the deformation too far and damage the
tunnel, or decrease the already tight
clearances for trains.
With the grouting operation taking up most
of the tunnels cross-section, its difficult to see
how measurement techniques such as
extensometers or a total station could ever
have worked. And conventional wired
monitoring would have seen gauges placed
over the entire 400m lengths of the two
affected tunnel sections before any work

40 TUNNELLING JOURNAL
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 41

REMEDIATION

But this was a new monitoring system at Embankment, 300m wide and 12.5m deep
Figure 1: Section of the geology

INE
which required adaptation. It was potentially at its biggest point.
surrounding the Jubilee Line in the a big risk for London Underground and What we dont know is why this once-dry
affected area Costain Laing ORourke to take up, says sand channel now contains water. Analysis of
Wright. I was recommending we go for the the geochemistry of the water in the sand
system. London Underground financed it, channel shows that it is not coming from the
Superficial Deposits Costain Laing ORourke supported it and both surface or from a leaking main, but that it is
parties were prepared to take the risk. probably old groundwater.
30m Jubilee Line tunnels London Clay
The mitigation of that risk came from the Every test showed us it was natural
amount of time spent studying the tunnel, the groundwater, says Wright, who in 2010 was
Sand ground and the monitoring; the combined working for Tube Lines, now Transport for
Channel Lambeth Group competence and sheer brain power of the London, and whose involvement in the project
multi-disciplinary engineering minds continued when he moved to his current role
300m
assembled round the table; and Senceives at Halcrow. It could be recharging from the
confidence in its technology: We knew there chalk aquifer, but at a different location.
were a lot of challenges in there but we were The water table in London has been rising
Figure 2: A possible scenario of very confident that we could do it, says since the 1960s when the city started to lose
what could have happened Maddison. its industries, particularly breweries which were
thirsty customers. In 1992 parties including
Geology unfolding Thames Water, British Telecom, the Association
It seems incredible that the ground beneath of British Insurers and the Corporation of
London, which has more holes in it than a London formed the General Aquifer Research
piece of Emmental cheese, still has mysteries Development and Investigation Team (GARDIT)
to reveal. But indeed it does. Geologist which ultimately resulted in the sinking of a
Jacqueline Skipper of Geotechnical Consulting number of boreholes to pump out water and
Group is helping to unfold some of these artificially maintain a lower water table.
mysteries. At that point it was not realised that there
We have always had simplistic models of was an intermediate aquifer in the Lambeth
the ground in London, says Skipper. What is Group sands, says Skipper. The tunnels
clear now is that it is much more complicated might well have been drier in the 1970s when
than we thought it was. they were constructed, as it was not long after
began, requiring 2,000 gauges and a One complication we are discovering the point of maximum draw down. However it
spaghetti of wiring. includes a small number of deep, sand filled could also have been a short-term climate
The network of wireless gauges also channels in the Lambeth Group, which are effect.
allowed the engineers and geologists to make more common than we realised, and which
decisions about the next night shifts grouting, can only be identified with good quality A unique operation
based on what had happened the previous ground interpretation data. We know for sure that in 2010, the sand
night. Combining the data from the gauges We now know that there is a large sand channel was no longer dry. From September
with information from Bachy Soletanches channel that runs diagonally across the line of that year onwards Tube Lines, which was then
bespoke grouting control software helped Oxford Street, Londons busiest shopping operating the Jubilee Line under a PPP deal,
build a better picture of the ground in that street, its upper surface at 30m below ground had to clear sand from the track bed, an
area. level. It is the size of the current River Thames estimated 0.25 tonnes a week with an

Above left and right: Part of the complex grouting system

TUNNELLING JOURNAL 41
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 42

REMEDIATION

The pumps had to be able to achieve


Figure 3: The intricate lopped supply grout system designed by Kettle accurate and highly controllable flow rates
in the wide range of 60 to 2000 litres per
Surface hour with very tight restrictions on
To drainage
water pump Tunnel level operational grout pressures, which ranged
from two to four bars net pressure behind
the tunnel lining, says Clif Kettle, Principal
PMPU20 Water circuit
Water return
Engineer with Bachy Soletanche.
Surface level The solution saw Bachy Soletanche
Water
tank design, fabricate and trial the computer-
Return Clean water Water from
Grout pump water pump to flush lines tunnel
controlled grout injection pumps in house.
Dirty water
Another challenge was that they had to be
Return grout line
Mixer unit Distribution compact in order to fit into a 1m-wide
manifold
Grout circuit equipment bay in a pedestrian cross
Pressure relief passage.
And while on most jobs, if a bit of kit isnt
quite right you can swap it or add to it, the
Grout injection
circumstances of this job meant that Bachy
Tunnel grout pump Grout Agi tank
Soletanche had to stick with what they
started with. We had one chance to get a
system that was right for what we
Return grout pump encountered, says Spyvee.
Bachy Soletanche did experience some
unexpected problems which had to be
accompanying 400 litres of water. overcome. First, high voltage London
As the workers shovelled sand, the Underground cables interfered with the
engineers examined the monitoring records. computers and control systems. Second, the
Thankfully, there was plenty of monitoring difficulty of isolating the electrical circuits
going on in the area, with co-operative and switchgear from the very fine break dust
owners who were willing to share. generated by the trains.
Monitoring showed us the tunnel was OTB Engineering and Halcrow, both
rising as far as the rails were concerned, and working for Costain Laing ORourke, had
the crown was staying stationary or moving carried out surveys in order to estimate
downwards, says Wright. It was starting grout volumes. They carried out a tapping
to get a little bit alarming. survey of the segments, listening for
Because of this movement and the differences in sound that would suggest
possibility of very significant amounts of voids behind them and then drilled through
sand coming in rapidly, Wright wrote an every five rings and where voids were
emergency preparedness plan, which called suspected to insert a probe and get an
for regular updates and assessments on the estimate of depths. The probes penetrated
condition of the tunnel. An Engineering up to 1.2m with little or no resistance in
Review Panel met weekly to keep its eye on some places.
what was happening, a practice which was Logistics were a challenge with grouting In the event, Bachy Soletanche used less
to continue throughout 2011. equipment needed to be housed in the grout than was estimated. With all the
Tube Lines made an early remediation small diameter cross passage unknowns, this was hardly surprising: the
attempt using expanding polyurethane estimate could only ever be ballpark. The
grout, but that had only limited success. The ground outside the tunnel was much more
ingress stopped for one or two weeks and variation order to the 300M project to complicated than we thought it would be,
then started again. It was clear that we had upgrade Bond Street Station. A Costain even though we had been doing extensive
to embark on a much more significant
grouting project, says Wright.
It was a grouting project unlike any other.
Laing ORourke joint venture is carrying out
the seven-year programme of works that
will create an improved interchange
ground investigation in that area, says
Skipper.
The grout had to come by a tortuous
SU
Back grouting has been done in numerous between the Central and Jubilee Lines and route to find its way to the two running
tunnels but it has never been done on this connection to the new Crossrail lines. tunnels 25m below street level. The mixing
scale whilst maintaining a live railway, says Bachy Soletanche carried out the 4M station was in a small compound at ground
Jonathan Austin, a partner at OTB grouting works. One of the biggest early level in Davies Street; from there the grout
Engineering who oversaw the grouting and challenges, says Bachys Jonathan Spyvee travelled via the UKPN underground
monitoring works. In that respect it is who was deputy project manager for the substation to agitator holding tanks in a
unique. grouting, was sizing the equipment they cross passage between the two tunnels from
Halcrow was tasked with writing the would need down there. where it could be sent to the point of
conceptual design statement (CDS) and with Although we knew something about the injection.It was a case of finding a route
producing the design. But the expertise problem, we did not know how extensive through the various tunnels and
required for such a task couldnt be provided the work would be or where the larger voids passageways down to the tunnels at
by just one organisation, says Wright: It would be, says Spyvee. We had to depth, says Spyvee. Its not the sort of
was a collaborative process, like many develop a system that was fairly flexible. thing you would ever anticipate you need to To order, vi
aspects of tunnelling. Nobody had that gut feel for the volume we do. Clif Kettle who set the project up for us
The grouting project was procured via a would need to be injecting. worked closely with Costain Laing ORourke

42 TUNNELLING JOURNAL
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 43

WTC20it13us
is
... come v 9
at stand L

...AND RECEIVE YOUR


FIRST 3 ISSUES
SUBSCRIBE TODAY... FOR 1.00, 1.20,
US$1.60

SUBSCRIBE NOW!
To order, visit www.tunnellingjournal.com and click on Subscription Offer

TUNNELLING JOURNAL 43
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 44

Constructing a
Sustainable future.
At VINCI Construction Grands Projets, we engineer solutions that are not only
financially competitive, but work sustainably for the planet. It starts with putting
Safety first, always, at all times, on every site. Health & Safety training, policies
and guidelines are all in place, but to generate the best possible results, we go
further with our innovative (A)live on Site programme. We understand that our
people are more reactive to what concerns them directly, we have a team who
visit the site, shoot a short movie and then broadcast it to the team. Each scene
photo credits: MVB, VINCI and subsidiaries photo libraries, Andras Nemeth, Clarence Michel.

is analysed with behaviour experts, underlining the good (and less good) actions.
(A)live on site has been successfully delivered to more than 2,000 people, in 12
languages, across 14 countries, including the UK.
To learn more please visit www.vinci-construction-projects.com/british-isles
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 45

REMEDIATION

and managed to find a route through. need, but that would be a typical to an adjacent one, whatever position or
Kettle came up with an intricate system frequency, says Maddison. Peter wanted sequence they find themselves in, so nodes
of looped supply and return lines for water once a minute. can be moved round to accommodate
and spoil wash-out (see diagram p42). To Speeding up the reporting frequency equipment and even if one were to be
get the grout lines, spoil collector lines and required Senceive to upgrade the damaged, the system could function.
water from the cross passage to the furthest performance of its mesh network. The There were some changes to
point of injection and back, Bachy had to sensors all take readings and talk to each accommodate on the hoof. We had to
devise a low profile ring mains with regular other, with the information finding its way meet some challenges we had not
take off points, compact fittings, and back to a gateway in the case of the anticipated, says Maddison. None of us
removable head assemblies.A big knew exactly what
proportion of the money went on that we would need
grouting system, says Austin. Monitoring the tunnel once we were
The grout itself had an unusual suite of with a trusty laptop down there. It was
properties. It was immiscible with water and a matter
of high solids content so that it could be sometimes of
injected through static or flowing water; it coming off the
had to be sufficiently fluid to act as a shift, writing
contact grout where there were no down the task list,
significant voids, and permit pumping having the team
through long and intricate supply circuits; it work through the
was very low bleed; it had a pot life of day upgrading
between six and 12 hours; and it was and taking it back
sulphate resistant. the following
Bachy Soletanche designed the mix night.
initially in co-operation with BASF, and then One adaptation
refined it in the firms Paris materials came a few shifts
laboratory. The mix comprised water and in, when the
cement grade 11/B with a water cement review team
ratio of 0.56, plus anti-washout agent making the day-
Rheomac UW400, Glenium fluidifier and time decisions to
Delvo stabiliser. steer the night-
In terms of workability, the grout was times work
very good, says Spyvee. It did not give us decided that
issues in pumping the grout into the cross Jubilee Line, a lap top the best way it can. monitoring should continue during the day.
passage and it remained workable for the Sensors are switched on by the network They wanted to see whether the grout had
duration of the shift. only for a short period when reporting in gone off or whether it was still hardening,
Shifts, of course, were not very long. This order to conserve their batteries for years of and the tunnel still moving.
was a live metro with all the work taking life and communicating. If you want to Senceive could not leave laptops down in
place during three-hour night-time report once per minute with 100 nodes, you the tunnels, so installed more nodes to take
maintenance periods. It is quite common run into all kinds of problems with network the signal through a cross passage, up a
that we would have two-and-a-half hours a congestion, says Maddison. We had to do 30m-deep shaft and into a small room in the
night, once the traction current was very ingenious things in order to get the station. It was all done within 10 minutes
discharged and allowing sufficient time to reporting rate up to be able to support 100 of hand-back, says Maddison.
check the track, tunnel clearance and nodes. In the event the day-time monitoring
monitoring data to ensure the tunnel had Another issue was that Senceives tilt showed that the grout had stiffened
stabilised, says Austin. meters were not sensitive enough for this sufficiently before the trains began to
The first task was to get the job. So they integrated a new version that run.We did not use the traffic hours
instrumentation up and running. Fast was 10 times more sensitive. monitoring so much because we found out
deployment of the network was a real Fixing the gauges to the tunnel has also it stopped moving fairly quickly, says
challenge, says Maddison. When you are given rise to an innovative fixing system, Austin.
installing it on a railway bridge it does not patent pending. Maddison and Wright
matter if it takes one hour for the network worked together to develop the fixings Real time monitoring
to settle down. If you are installing it in an using strong magnets, with Wright even The monitoring was crucial to and central to
underground tunnel at 01:10, at 01:30 you testing the sensors while mounted on his the grouting operation. An OTB monitoring
have the grouting engineer shouting When own radiators, discovering they were strong engineer - or more often than he would
can we start? Its a different kettle of fish. enough to take the paint off. have liked, Maddison himself - would be
Before Senceive could deploy its system in Despite the damage to his home, Wright crouching in each tunnel with a laptop,
the tunnels, it had to carry out three months is pleased with the magnets. The network watching the movement of the rings as the
of serious and intense development work. is very simple to install, says Wright. The grout went in.
The five-year old, high-tech start-up operatives down there knew where to put The deformation of each ring had, before
company, a spin-off from University College the nodes. You brush the crud off and stick grouting began, been checked and classified
London more usually monitors civil them on. They were very comfortable in using a laser spot survey. Those rings with
structures using crack gauges and tilt doing that within a couple of shifts. the greatest deformation were assigned the
meters: railway viaducts and other bridges, The simple and robust fixing method smallest trigger level of 2mm; if the ring
retaining walls and embankments. combined with the fact that the monitoring moved by that amount during grouting, the
Monitoring bridge or earthworks require system employs a mesh network made it grouting had to stop. Where rings showed
one reading per hour thats more than you ideal for this application. Any node can talk hardly any deformation, that trigger level

TUNNELLING JOURNAL 45
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 46

REMEDIATION

rose to 20mm. installation of all the many pipework circuits


We knew quite a lot of movement had Figures 4 and 5: Graphs showing with high quality, intrinsically safe
taken place, and we did not want to make it ring deformation and tilt vs time components, and was particularly difficult
any worse, says Wright. (tilt metres were used to monitor because of the anti-wash-out design
There was also a limiting pressure of 4 bar, movement) properties of the grout, says Kettle.
programmed into Bachy Soletanches Ring 1885 Not once did they overrun, and from a
grouting control software. Halcrow had 6 necessarily conservative start, Bachy
determined this pressure in collaboration Soletanche managed to rationalise the
with LU and validated it using a finite 4 number of people on the crew as they
element model. became slicker and more able to predict
So as the grouting crew of around 15 to Movement (mm)
2
how many rings they could grout that shift.
20 people were doing their bit, the Bachy Soletanche was also able to link up
monitoring engineer was looking at the its grout control software to AutoCAD to
change in tunnel deformation and segment 0 create a graphical representation of the
rotations. The monitoring engineer was flat grout volumes and pressures that each
out keeping his eye on the data, says -2 section had experienced, with all the grout
Austin. West Rail interconnections and injection dates
East Rail
Six sensors on each of four rings were Crown attached. Overlaying that with the predicted
-4
sufficient to monitor a 10-ring pack, which Squat (-ve) pattern of geology helped give some more
was the goal for each shift. Once the nights Poly. (Squat (-ve)) clues as to the geology. This helped with
work was complete, all the monitoring -6 predictions for grouting looking ahead.
22/01/10

02/05/10

10/08/10

18/11/10

26/02/11
information, together with the data from It was a work in progress, says Spyvee.
Bachy Soletanches bespoke pumping Towards the end, we perfected it. If you
software went to the day-time Project Time see something graphically, you pick up
Engineering Review Panel (PERP) meeting so things you might miss if you were looking at
that the instructions for the next nights Tilt in mm/1500mm tables of data.
10
work could be defined. 9 Wright, in fact, represented all the
Ring 1-A
Skipper describes this as an observational 8 monitoring information graphically,
7 Ring 1-B
method: You dont just squirt grout in and 6 Ring 1-C preparing a double-sided sheet of A3 for
5 Ring 1-D
then everyone goes home. 4 Ring 1-E
each of the review meetings. This is
Though mostly the grouting took place 3 definitely a practice that he, and others,
Tilt

Ring 1-F
2
from track bed level upwards, this 1 would take on to further jobs.
sometimes varied depending on what the 0 As to whether there will be other jobs just
-1
deformation of that ring was. It was a case -2 like this one, that is another unanswered
-3
of pinpointing where the deformation was -4 question. There are more sand channels,
and working round that problem, says -5 says Skipper, discovered on other current
09/11/2011

09/11/2011
00.57
09/11/2011
01.26
09/11/2011
01.55
09/11/2011
02.24
09/11/2011
02.52
09/11/2011
03.21
09/11/2011
03.50
09/11/2011
04.19
00.28

Skipper. jobs.
There was potential to push the tunnel Skipper is currently working to develop a
back into shape, although we never geological model to find out where the
achieved it due to the limiting pressures, Time channels may be and where there could
says Austin. potentially be risk in the longer-term. The
The tunnel did not move significantly, along the outside of the tunnel until the rising water could have repercussions due to
says Wright. There were some places grout could meet up with an area where the the recharge of hydrostatic pressure in
where the shape was changed fairly rings were completely surrounded by clay. tunnels and especially in escalator shafts,
significantly, but they were areas where the The grouting operation took four months she says.
tunnel was in quite a good shape to start to complete. Over that time, all the For Senceive, the Jubilee Line remediation
with. constituent parts of the engineering jigsaw project has turned out to be just the
The aim for each shift was to grout 10 evolved a little. beginning of the story for tunnel
rings although this varied, depending on Down the tunnels, the grouting gang monitoring. Because the system is so
how much grout each ring took. became more and more efficient. They got flexible, so robust, and after the
Sometimes you would get an area that better and better at judging when to make development work done on this project, so
would take a lot more grout and so you the call to pack up the equipment, says quick to set up, it lends itself perfectly to the
would do less than a 10-ring pack, says Spyvee. With the effect of not finishing on unpredictable environment of tunnel
Spyvee. time being potential delay to the mornings construction and monitoring.
What we did not anticipate was that Jubilee Line service, the stakes were high. The monitoring systems success and
there would be considerable flow of grout This meant Bachy Soletanches logistical potential was recognised in January this year
behind the lining, says Austin. We would planning had to be done with military by the ITA when the team won the Product/
be grouting behind one area but it would precision. Before the possession period Innovation of the Year category in the
take a lot more grout because it would flow began the grout had to be prepared and the International Tunnelling Awards 2012.
behind the back of the lining to another surface and the supply circuits and agitators Its the sort of story that every high-tech
area where there was a void or running in the cross passage charged. start-up company dreams of. Already
sand. Then when you got to an area where Both start-up and shut-down for the Senceive has won several more tunnelling-
there had been running sand and the grout grouting equipment and operations had to related contracts, with developments to
had flowed in the night before, you did not be swift, with the vital task of cleaning out allow remote monitoring via a number of
get anything in. all the circuits and equipment at the end of different routes. From our point of view
Bachy had to grout the rings in sequence, each session. This last task was especially this was a phenomenal opportunity, says
aiming to push the water and flowing sand critical because of the very high cost of Maddison.

46 TUNNELLING JOURNAL
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 47

BARCHIP, REPLACING STE


EEL IN
STEEL
BARCHIP  PRIMARY AND SECONDARY SHOTCRETE LINING

SYNTHETIC FIBRE
 SEGMENTAL LINING
 INVERT SLABS
 CONCRETE TRACK SLAB

REPLACING STEEL 

SHAFT LINING
PORTAL STABILISATION
REINFORCEMENT IN CONCRETE  ROADWAYS

At EPC, weve built our reputation on the strength of our


people and on the quality of our products, which have been
tried and tested by major corporations and engineering
experts worldwide.
BarChip macro synthetic fibre has replaced steel fibre in over
60 major tunnelling projects around the world for road, rail
and water infrastructure. Including;
 A3 Hindhead Road Tunnel - UK
 Devils Slide Road Tunnel - USA
 Ontigola High Speed Rail Tunnel - Spain
 Atlantic Subsea Road Tunnel - Norway

WWW.ELASTOPLASTIC.COM

TUNNELLING JOURNAL 47
Join us at the
World Tunnel Congress 2013
May 31 June 7, 2013
Geneva, Switzerland

Welcome to the land of mountains


and valleys, the land of some of the most
spectacular tunnels and galleries.
Welcome to Switzerland
the host country of the WTC 2013.

World Tunnel Congress 2013


organized by Swiss Tunnelling Society (STS)
Rheinstrasse 4 7320 Sargans Switzerland www.wtc2013.ch
TJ_0513_049_051.qxd:Feature 21/4/13 15:24 Page 49

SUSTAINABILITY

The Future is Smart


and Sustainable
In this article, Dr Benot Jones, Figure 1: The word "sustainable" is unsustainable
(source: www.xkcd.com)
Tunnelling and Underground Space
MSc Course Manager at the The word Sustainable is unsustainable
Frequency of the word Sustainable in US English 1,000%
University of Warwick, UK, discusses text, as a percentage of all words, by year. 2109: All sentences are just the word ?
? ??
?
100% Sustainable repeated over and over.
sustainability.
10%
2061: Sustainable occurs an
SUSTAINABILITY HAS BEEN the watch-word of the 21st Century so far. average of once per sentence.
Source: Google NGrams

1%
Figure 1 says it all:
However, this article will not be the usual yadda-yadda. At least, I 0.1%
havent read anything similar before, and if you have thought the same 2036: Sustainable occurs
0.01% an average of once per page
thoughts then we must meet and compare notes. First, I am going to
Present day
convince you that sustainability is the basis of all good engineering 0.001%
decisions. Then it will obviously follow from this that good engineers have
sustainability embedded in their thought-processes and will automatically 0.0001%

generate sustainable solutions. To make more good engineers who think 0.00001%
sustainably we need to implement a sustainability culture within
organisations and within our profession. 0.000001%
After all that ground work, for those hard-headed people out there Ill
60

80

00

20

40

60

80

00

20

40
19

19

20

20

20

20

20

21

21

21
present the overwhelming business case for sustainability. Finally Ill end Year
with a vision of a smart and sustainable future.

Sustainability is just good engineering the public good and an ethical (and legal) duty footprint, as well as the cost of construction,
The United Nations Brundtland Commission to protect the environment. Therefore, the are all examples of social, environmental and
described sustainable development as impacts on the local community, the health economic considerations that are part of the
meeting the needs of the present without and safety of the workforce, the durability and decisions we make. These issues are all
compromising the ability of future generations longevity of the structure, the need for important and can all be captured under one
to meet their own needs. This doesnt mean, maintenance, the energy use in operation, the of the three pillars, so sustainability gives us a
for example, that we have to stop using non- environmental impacts and the carbon framework that assists us in making good
renewable resources right this minute, because engineering decisions.
that would result in great human suffering, but I hope I have convinced you that
Figure 2: Venn diagram of
we need to be moving away from them and sustainability is not only an important and
sustainable development (United
investing in a sustainable future. To achieve this worthwhile thing to do, but it can be used as
Nations General Assembly, 2005).
we need to take an ethical, long-term, systems- the basis of all good engineering decisions. It is
based approach to the planet. a framework for identifying issues and
A useful framework for understanding measuring the performance of any
sustainability is to consider three pillars social, intervention. It isnt an extra thing we have to
economic and environmental and balancing Social do; it is a way of thinking that should be
these sometimes competing demands will embedded in the way we work. Engineers
result in sustainable development. I prefer the make dozens of decisions every day, and if we
mnemonic people, profit, planet as it is easier think people and planet as well as profit, well
Bearable Equitable
to remember. The three pillars are often make better decisions.
represented visually by the Venn diagram in Since I have just used the words basis for all
Sustainable
Figure 2: engineering decisions, a way of thinking and
Now, what does this have to do with us as embedded in the way we work, it should be
engineers? First off, we should consider what it Environment Economic clear that in order to change the way we make
means to be a professional engineer. It is not Viable decisions, the way we think, and the way we
just about providing cost-effective technical work requires a cultural shift both in
solutions. For instance, the code of conduct of organisational culture and professional culture.
the Institution of Civil Engineers states that civil This sustainability culture is the ideas and
engineers have an overriding responsibility to beliefs that all members of an organisation

TUNNELLING JOURNAL 49
TJ_0513_049_051.qxd:Feature 21/4/13 15:24 Page 50

SUSTAINABILITY

share about sustainability. The challenge of require us to leave about two thirds of it in the technologies to collect data and create
achieving this could be called implementing a ground, resulting in a huge reduction in synergies, for example to reduce energy use,
sustainability culture. demand for oil, a collapse in prices and a pollution or traffic jams.
collapse in the valuation of reserves (HSBC The way we work has been changing rapidly
Implementing a sustainability culture Global Research, 2013). According to HSBC, with technology such as the internet, email,
An example of a cultural shift that has been the market capitalisation of oil companies is social media and smartphones. Work/life
implemented in the past is the way in which overvalued by 40-60%. So clearly people who balance is now difficult to achieve due to a
safety culture has become the norm. are buying shares either assume these climate phenomenon called work/life merge we can
Nowadays, most engineers automatically change targets will not be met, or are taking a now work from home and on the move, and
consider health and safety in every decision short-term view of investment on the scale of this allows more flexible working and better
they make, and this has been the result of a months or years rather than decades. productivity, but it also makes it difficult to
cultural shift. The Confederation of British Companies, however, and particularly separate work time from personal time. This
Industry wrote a seminal report in 1990 titled construction companies, are beginning to take move to communication in the virtual world
Developing a Safety Culture (CBI, 1990). The a long-term view. This is not unselfish, as there implies that geography is less important, but
recommendations of the CBI report could easily is also a strong business case for sustainability. this doesnt appear to be the case. According
be adapted to the implementation of Nowadays, tenders are increasingly being to Rick Robinson, a Smart Cities Architect for
sustainability culture. This is how I would scored with a higher weighting on IBM, the geography of a city is still vital for
summarise the main points: sustainability than cost. So companies with a creativity and collaboration. This means that
crucial importance of the leadership and track record of sustainability are becoming there will still be work for us tunnellers for the
commitment of the Chief Executive leaders more competitive. Competitiveness in non- next few decades at least, but our solutions will
need to walk the talk and put the full energy price factors such as health and safety or need to be smart and sustainable.
of the board behind it sustainability is a no-brainer, particularly as it
depends on the role of line management, doesnt cost much to implement and there are Conclusions
the involvement of all employees and on other benefits as well. Sustainability is not a fad and it is here to stay. It
openness of communication this will A reputation as a responsible corporate is a powerful idea and a useful decision-making
ensure sustainable practices are citizen will benefit any company, both in terms framework, but to gain the greatest benefits
implemented and new ideas are generated of share price, in relationships with we need a cultural shift from thinking of
the importance of demonstrating care and stakeholders, and in attracting and retaining sustainability as an add-on extra to
concern for all those affected by the business staff. At the BASE Birmingham event in April implementing a sustainability culture within our
sustainable businesses have better and 2013, Ian Renhard, head of UK Construction at organisations and within our profession.
more profitable relationships with Interserve said that even in a recession, having
employees, stakeholders, customers and a strong sustainability strategy makes them
REFERENCES
suppliers (Eccles et al., 2011) more resilient. Companies want to work with
a long-term strategy that has to be other companies with similar commitments,
continually reinforced and both Interserve and Jaguar Land Rover 1. CBI (1990). Developing a safety culture.
it must counter the belief that sustainability is have found that their commitment to the local London: Confederation of British Industry.
an add-on, optional extra, or a fad community and to training has strengthened 2. Chouinard, Y. (2006). Let my people go
Concentrating on sustainability culture will not their supply chain, improved planning for surfing: the education of a reluctant
be at the expense of safety culture, since health future skills, made them a more attractive businessman, ISBN 9781101413364. New York:
and safety are part and parcel of sustainability. employer, and improved their corporate Penguin Books.
The key motivating factor used in behavioural- reputation, making their companies stronger as 3. Eccles, R. G., Ioannou, I. & Serafeim, G.
based safety to inspire people to behave in a a result. (2011). The impact of a corporate culture of
safe manner is caring for the health and safety The Stern Review (and Birminghams mini- sustainability on corporate behavior and
of those around us and wanting everyone we Stern Review) demonstrated that almost all of performance. Working Paper 12-035, Harvard
work with to be able to go home unharmed. climate change carbon reduction is wealth- Business School.
The key motivating factor in sustainability generating and improves the quality of peoples 4. Gouldson, A., Kerr, N., Topi, C., Dawkins, E.,
culture could be caring for the planet we live lives (Gouldson et al., 2013). For example, an Kuylenstierna, J. & Pearce, R. (2013). A mini-
on, its ecosystems and its inhabitants, and investment of 3.6bn in reducing Birminghams Stern review of Birmingham and the wider
wanting to leave it in a better state than when carbon footprint would pay for itself in only 3.8 urban area: preliminary findings. Available at:
we arrived. Another motivating factor is years and create 1,650 jobs. It would also http://www.lowcarbonfutures.org/sites/default/f
wanting to do a good job, and for us engineers reduce vulnerability to future energy price iles/Birmingham_Mini-Stern_Review_-
this means building sustainable infrastructure. increases, protect competitiveness, improve _preliminary_findings.pdf [accessed 16th April
public health and slash the carbon footprint. In 2013].
Business case for sustainability fact, given the benefits, even someone who 5. HSBC Global Research (2013). Oil and carbon
The most basic business case for sustainability wont accept the overwhelming evidence that revisited: value at risk from unburnable
is, as Yvon Chouinard, the founder of anthropogenic climate change is happening reserves. HSBC Bank plc, 25th January 2013.
Patagonia, said, there is no business to be would have to agree that carbon reduction is a Available at:
done on a dead planet. This is a long-term good investment. http://gofossilfree.org/files/2013/02/HSBCOilJan
view, and one might wonder whether the The business case for sustainable 13.pdf [accessed 15th April 2013].
markets are set up to think so far ahead development is now not just compelling, but 6. United Nations General Assembly (2005).
(although it is becoming a less long-term view indisputable. 2005 World Summit Outcome, Resolution
as the need to combat climate change A/60/1, adopted by the General Assembly on
becomes ever more urgent). For instance, oil Smart and sustainable 15 September 2005. Available at:
companies are valued based on reserves that if It is difficult to separate smart and http://data.unaids.org/Topics/UniversalAccess/w
exploited fully will result in devastating climate sustainable. Cities are a system of systems, orldsummitoutcome_resolution_24oct2005_en.
change. To have a 50% chance of keeping and making cities sustainable will involve the pdf [accessed 15th April 2013].
climate change below 2 C of warming will integration of systems and the use of smart

50 TUNNELLING JOURNAL
TJ_0513_049_051.qxd:Feature 21/4/13 15:24 Page 51

SOLID
Offering new custom rolling stock
for your project

##!#(*'
# " (#
##$(&!'
& )!#'
" #'(' MINING
( "'
EQUIPMENT
"( (#" %)$!"(
#" 
 
 , + 
 

, www.miningequipmentltd.com

1 mm
mmm$lcj#]cX^$Z[

J^[Z_Wc[j[he\Wdj[ddW[e\j^[YeccedmWif
L[ifkbWLkb]Wh_iWdZj^[WYYkhWYoe\KBIh
6Xi^kZAVhZgIVg\ZiJc^i#
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:40 Page 52

OPERATIONAL

Customising standards
for the emerging tunnel
superpowers
Arnold Dix, Lawyer and Engineer gives some
guidance on regulatory arrangements for subsurface
tunnel risk management from around the world

URBAN PLANNERS AND LEADERS are The regulatory arrangements


increasingly embracing subsurface While all countries demand integrated, safe
transportation as a ready means of reliable subsurface public transport, how it is
breathing new life into ancient cities and achieved varies from country to country. In
setting bold agendas for the super cities of tropical Singapore with its very high water
the future. Legendary cities such as Riyadh, table, and poor quality ground the challenges
& Jeddah, and planned super Cities such as are different to the Gulf States with
Doha are poised for the construction of temperatures in the 50s and the challenges of
entire new Metro systems - from nothing - blown sand. Even the political circumstances
in under a decade. North Africa, West Asia, of a country can impact the achieved result - in
South America and East Asia all appear some Countries foreign experts will be
poised for unprecedented subsurface expected to assume control of key decision
transportation expansion as part of a global making positions, while in others this will be occurs, critics will emerge, and blame for the
revolution to humanise our cities - by actively discouraged. destruction and deaths will be attributed. In
moving transport underground. These The regulatory arrangements must be Taiwan this occurred recently following the
programs are pushing the known sensitive to local conditions - physically, Hsuehshan Tunnel incident in 2012 with many
boundaries of technology, project delivery politically, culturally. The importance of a critics emerging from both within and outside
and operational performance to new limits. customised regulatory environment is easily Taiwan to attribute blame for the deaths.
With a current emphasis on project overlooked during the exciting project Incidents in any country causing multiple
delivery in these regions it is essential that procurement and construction phase. deaths always result in outrage, blame and
the case also be made for timely, efficient Unfortunately it is during this early phase that reform.
regulatory frameworks that convert the the most important decisions about It is easy for critics to conduct a blame
burst of construction into reliable, operational safety, integration and operability exercises following a disaster. The conclusion
integrated, safe public transport systems. are made. At this early stage the excitement of following such an exercise is almost always to
Delivering these outcomes requires much new projects does not easily lend itself to attribute causation of the local incident to the
more than simply transferring a proven discussions about mundane matters of unified differences between what is done to manage
approach from another region - standards regulatory arrangements. safety in the country suffering the disaster and
and practices from one region will not work It is understandable that prior to a serious that which is done elsewhere. Having a robust
the same in another. This impacts how major damage and multiple fatality incident administrative regime to manage the entire
standards are imported into the new occurring in a tunnel it is unusual for local portfolio of subsurface transportation risk is
regions and the importance of translating opinion to even consider seriously the prospect the best approach to managing these risks. It
them into the local technical, social, of a disaster. Usually the systems are new and provides a single point of regulation and
economic and political contexts. This paper significant disasters are not only unlikely, it is accountability - it results in a unified approach
examines road tunnel administrative generally believed they simply won't happen and voice. It usually provides the best
arrangements and engineering standards in here. There can also be more subtle integrated safe system as well.
detail, arguing the broad principles of processes at work - in some cultures there is a
sound leadership and accountability for belief that events in the future can be shaped The European regulatory tunnel safety
safety must mean more than simply by human intervention, and in other cultures arrangement
importing foreign practices. To work it is there is a belief that the future is beyond Administrative Authority - Directive
essential a fresh approach to delivering safe human control. In the area of safety, being 2004/54/EC of the European Parliament and
infrastructure be embraced which draws on sensitive to the local safety culture can be as of the Council of 29 April 2004 on minimum
the best of the rest of the world and important as an understanding of the laws of safety requirements for tunnels in the Trans-
interprets them for application in new physics. European Road Network (EU Directive
regions such as the Middle Eastern context. However, no matter where the disaster 2004/54/EC)[1], provides a useful example of

52 TUNNELLING JOURNAL
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:40 Page 53

OPERATIONAL

both a tunnel safety management structure significant incident or accident. seriously considered in countries with limited
and prescriptive minimum standards for tunnel European Union Safety Officers meet regularly experience of subsurface infrastructure. One of
safety. The Directive was formulated in to share expertise. In this way the EU Safety the important benefits of such an approach is
response to a series of structurally damaging, Officer Strategy is increasingly generating the it encourages training and grooming of local
multi-fatality incidents that crippled European sharing of expertise, contributing further to citizens to assume senior roles as the
economies reliant upon the tunnels. (Table 1) tunnel safety.[3] organization's mature.
Each EU country must designate one or In the case of tunnels that have been Periodic Inspections - EU countries ensure
more administrative authority to take approved at the design stage but which have that inspections, evaluations and tests are
responsibility for tunnel safety, and to take any not been opened to the public by 30 April carried out by inspection entities. These
necessary measures to ensure that the directive 2005, the administrative authority assesses inspection entities are not specified by the EU.
is complied with. The administrative authority their compliance with the EU directive. Practically speaking such inspections are
may be set up at national, regional or local With regard to tunnels that had been carried out by organisations or individuals
level. opened to the public by that date, the known to be expert in such matters.
Prior to commissioning a tunnel the administrative authority had until 30 October One of the roles of the administrative
administrative authority is required to approve 2005 to assess their compliance with the EU authority is to verify that regular inspections
the commissioning of a new tunnel or directive. are carried out by an inspection entity to
rebuilding of an existing one. The By 30 April 2005, EU countries had to ensure that all tunnels falling within the scope
administrative authority has power to suspend submit a report to the Commission on how of the directive comply with its provisions. The
or restrict the operation of a tunnel if the they intend to meet the requirements of the period between two consecutive inspections
safety conditions it imposes are not met. directive, on planned measures, and, where of any given tunnel is mandated not to exceed
The administrative authority must make sure appropriate, on the consequences of opening six years.
the following tasks are performed: or closing the main access roads to the In the authors experience regular inspections
testing and inspecting tunnels on a regular tunnels. by independent experts can be a valuable
basis and drawing up the tunnel specific These staged provisions highlight how a mechanism for ensuring systems and
safety requirements regulatory regime can be introduced procedures are functioning as expected.
putting in place organisational and systematically over an appropriate period of Risk Analysis - A risk analysis, based on a
operational schemes (including emergency time. Such an staged approach should be single methodology defined at national level,
response plans) for the training and
equipping of emergency services
establishing the procedure for immediate Table 1: Fatal Fires in Road Tunnels
closure of a tunnel in case of an emergency
implementing any necessary risk reduction Year Tunnel Length Deaths Dangerous goods
measures
Tunnel Manager - For each tunnel, whether 1978 Velsen, Netherlands 770m 5 No
it is in the design, construction or operating 1979 Nihonzaka, Japan 2,045m 7 Ether (collision)
stage, the administrative authority must 1980 Kajiwara, Japan 740m 1 Paint (collision)
identify a Tunnel Manager whom is
responsible for the management of the tunnel. 1980 Sakai, Japan 459m 5 No, Collision
Any significant incident or accident occurring 1982 Caldecott, Oakland, USA 1,028m 7 Benzene (collision)
in a tunnel must be the subject of an incident 1983 Pecorile, Savona, Italy 600m 9
report prepared by the Tunnel Manager and
1986 LArme, Nice, France 1,105m 3
given to the administrative authority.
Safety Officer - For each tunnel, the Tunnel 1987 Gumefens, Bern, Switzerland 340m 2
Manager, with the prior approval of the 1993 Serra a Ripoli, Italy 442m 4
administrative authority, nominates a Safety 1994 Huguenot, South Africa 3,914m 1 No, Collision
Officer who coordinates all preventive and
1995 Pfander, Austria 6,719m 3
safeguarding measures to ensure the safety of
users and operations staff. The Safety Officer 1996 Isola delle Femmine, Italy 148m 5 LPG (collision)
performs the following tasks: 1999 Mont Blanc, France/Italy 11,600m 39
ensures coordination with the emergency 1999 Tauern, Austria 6,400m 12 Paint/Lacquer (collision)
services and takes part in the preparation of
operational schemes 2001 Gleinalm, Austria 8,320m 5 No, Collision
takes part in the planning, implementation 2001 Gotthard, Switzerland 16,918m 11 No, Collision
and evaluation of emergency operations; 2003 Flyfjell, Norway 3,200m 1
takes part in the definition of safety plans 2004 Baregg, Switzerland 1,100m 1 No, Collision
and the specification of infrastructure
installations 2005 Frejus. France/Italy 12,700m 2
verifies that operational staff and emergency 2006 Viamala, Switzerland 742m 9 No, Collision
services are trained, and takes part in the 2007 Burnley, Melbourne, Australia 3,400m 3 No, Collision
organisation of exercises held at regular
2007 San Martino, Lecco, Italy 4,800m 2 No, Collision
intervals
gives advice on the commissioning of the 2007 Santa Clarita, California, USA 168m 3 ?, Collision
structure, equipment and operation of 2009 Eiksund, Norway 7,765m 5 No, collision
tunnels 2012 Hsuehshan, Taiwan 12,900m 2 No, collision
verifies that the tunnel structure and
equipment are maintained and repaired Total deaths 147
takes part in the evaluation of any (Adapted from John Day, personal communication 2012)

TUNNELLING JOURNAL 53
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 54

OPERATIONAL

prove that the level of risk has changed


Figure 1: (Simplified summary of EU, D and CH Guidelines for unidirectional unacceptably nor does not follow logically
congested tunnels of differing lengths) that such changes are conclusive proof that
Informative summary Tunnel category: Congested undirectional Not mandatory for all tunnels the practices of a country are unsafe, or that
of minimum requirements Final decision appropriate standards have not been met.
Tunnel length (M)
after predetermined
However it does mean that it is a

1200 - 1500m

1500 - 3000m
risk analysis conducted

1000 -1200m
800 - 1000m
400 - 500m

500 - 600m

600 - 800m
Mandatory for all tunnels comparatively simple task to document the
<400m

3000m
Origin of differences between countries and
guideline Category Comment
May be varied if risk assessment
subsequently make assertions about the
Directive Mechanical ventilation
(EU) demonstrates acceptable in special appropriateness of achieved levels of safety
circumstances
Special provisions
after a serious safety incident.
May be varied if risk assessment
(fresh air ducts and/or demonstrates acceptable in special Congested Unidirectional Tunnels
smoke extraction) circumstances Comparative Ventilation EU - Germany
Germany Mechanical ventilation Detailed decisions about smoke
(D) extraction etc driven by requirements (D) - Switzerland (CH) - A simple
of fire case comparative analysis of the German, Swiss and
Special provisions Detailed decisions about smoke
(fresh air ducts and/or extraction etc driven by requirements EU directive for roads tunnels illustrates the
smoke extraction) of fire case variation in requirements in road tunnels
Switzerland Mechanical ventilation Lower risk - Ventilation decisions
(CH) driven by risk analysis
between the Trans European network, and the
domestic laws in Germany and Switzerland.
Higher risk - Ventilation decisions
driven by risk analysis
For illustrative purposes the table
summarises the guidelines for, unidirectional
Special provisions Lower risk - Ventilation decisions congested Tunnels of differing lengths.
(fresh air ducts and/or driven by risk analysis
smoke may extraction) The simplified analysis is tabulated in Figure
Higher risk - Ventilation decisions 1 - Guidelines for unidirectional tunnels of
driven by risk analysis
differing lengths.
It is apparent from the table that there are a
is, at the request of the administrative "experts" may suggest. Within this context a range of requirements between Switzerland,
authority, carried out by an independent body considered approach to managing both user Germany and the EU directive for ventilation.
for a given tunnel, taking into account all safety AND the protection of tunnels The most notable areas of variation of
design factors and traffic conditions that affect themselves from damage can rationally be approach between the EU and both member
safety, notably traffic characteristics and type, developed.[5] states is that in Germany and Switzerland
length and geometry of the tunnel, as well as mechanical ventilation is required in shorter
the projected number of heavy goods vehicles Prescription under the EU Directive tunnels than prescribed by the EU.
per day. The EU Directive is just one set of standards Furthermore detailed risk analysis is critical in
There is still NO mandated risk assessment within Western Europe. Each of the member the ventilation choices particularly in tunnels
methodology, although PIARCs approach has states usually has its own standards too. The less than 1000m long.
gained some considerable favour within the EU Directive is generally considered a As between Germany and Switzerland there
EU.[4] minimum set of requirements. are also differences. For example In Germany
It is to be expected that there will be many the requirement for ventilation commences in The Ra
Risk in perspective differences between what is required under shorter tunnels than in Switzerland, and is the premier in
Before considering the "minimum European Union Road Tunnel requirements Switzerland appears to retain more design underground
underground
o con
requirements" specified (prescribed) within the and that which is required within each of the flexibility for ventilation in non-congested
EU Directive it is important to stress that EU member states and within other countries. longer Tunnels than Germany.
the ttunneling
u neling in
unn
tunnels are inherently safe and do not pose a The reasons for these variations are numerous Under the EU road directive congested Industry
Industr y sectors
s i
disproportionate risk of death to users of the such variations are to be expected and tunnels in excess of one thousand metres nomi
road network. In all the media excitement managed. require mechanical ventilation, and if the
following a tunnel death this fact is often lost. This means that for world travellers a road ventilation type chosen is longitudinal other
A comprehensi
comppreehensi
On the other hand, the value of tunnels is journey may expose them to differing risks in safety measures are required too.
extremely high in terms of economic different countries - even within the EU. As illustrated below under Articles 2.9.3 and most inn
innovative
novatiivve
productivity as is the cost of replacing them. The changes to the risk profile do not 2.9.4 tunnels with congested unidirectional
Furthermore once an incident occurs there is
strong evidence that the consequences of an
incident may be more serious than on a 2.9.2. A mechanical ventilation system shall be installed in all tunnels longer than 1 The meet
meeting
tin
ing will
will also
surface road. This higher level of risk following 000 m with a traffic volume higher than 2 000 vehicles per lane.
the occurrence of an unlikely incident should
Contracting
Contractin ng Practice
Practice
be the focus for avoiding incidents in the first 3 In tunnels with bi-directional and/or congested unidirectional traffic, longitudinal Design and d Planning
Planning
place. It is the confinement of vehicles and ventilation shall be allowed only if a risk analysis according to Article 13 shows it is Difficult G
Ground
Ground
gasses by the tunnel walls and ceilings that acceptable and/or specific measures are taken, such as appropriate traffic manage- DDrill
rill and Blast
B
drives the special risks in tunnels - and ment, shorter emergency exit distances, smoke exhausts at intervals. Environment,
En
nvir
v onmeent, Health
demands special efforts to minimise the Future
Futur
u e Projects
Projects
o
probability of an incident occurring and the 4 Transverse or semi-transverse ventilation systems shall be used in tunnels where a Geotec
Geotechnical
hniical Consid
Consid
specialist response if such an incident occurs. mechanical ventilation system is necessary and longitudinal ventilation is not allowed Ground
Ground S Support
u
uppor t and
The following table highlights the according to 2.9.3. These systems shall be able to exhaust smoke in case of fire.
comparative lack of deaths in road tunnels
from fires. Clause 2.9.2 as extracted from the EU Directive on minimum safety requirements for
Table 1 neatly places road tunnel fire deaths tunnels in the Trans-European Road Network.
in perspective - whatever the media or
For more
m in
303-948
303-948
54 TUNNELLING JOURNAL
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 55

June 23-26, 2013


Marriott Wardman Park Washington, D.C.

The Rapid Excavation and Tunneling Conference (RETC)


is the premier international forum for the exchange and dissemination of developments and advances in
underground
underground
o construction.
const ructtiion. RETC
RETC provides
prrovides innovative
innovatiivve solutions
solu
uttions
i to the unique challenges
chhallleenges associated with
the ttunneling
u neling industry.
unn industr y. Conference
ereencce attendance eexceeds
Conffer xceeds 1,400 professionals
1,4000 pr
rof
ofessionals
e from
from more
morree than 30 countries.
countries.
Industry
Industr y sectors
s include:
include: construction,
constrructtiion, mining,
mining, geotechnical engineering,
geotecchnicall eng ineering, eexploration,
xplor
x n, environmental,
atiion nvvironmental, eco-
en eco-
nomics, manufa
manufacturing,
urin
ctu ng, government, water/wastewaster,
goveernment, land, wate er/wastewasterr, and ttransportation.
ransp portattiion.

A comp
comprehensive
preehensivve eexhibit
xxhibit is held in conjunction
conjuncttiion with the conference.
coonffeerence. The eexhibit
xhibit
x features
u es the industrys
feeatture industr y ss
most inn
innovative
novatiivve and experienced
exxperiienced producers
p
prroducers
o and suppliers. RETC
RETC provides
provides a rare opportunity
rare oppportuunitty to meet key
key
professionals
proffessionals
e from
from around
o d the world.
arround worrlld.

The meet
meeting
tin
ing will
will also ffeature
eat
e ure field trips,
trips, short
short courses and specialt
specialty
ty sp
speakers.
peakers. The pr
program
oggram wil
willl cover:
coover
e:
Contracting
Contractin ng PPractices
ractices and Cost Grouting
Grouting and Ground
Ground Modification
Modification Eastt Coast Projects
Projects
Design and d Planning
Planning Har
Hardd Rock
Rock TBMs
TBMs SEM/NATM
SEM/N
M ATM
Difficult G
Ground
Ground LLarge
arge S
Span
pan TTunnels
unnels an
u and
nd Cav
Caverns
erns Shafts
Shaffts
t and Mining
DDrill
rill and Blast
B Micr
Microtunneling
otunneling and T Trenchless
renchless Tunneling
Tuunneling TTunnel
unn
u nel Rehabilitation
Rehabilitation
Environment,
En
nvir
v onmeent, Health, and S Safety
affet
ey NNew
ew and Inno
Innovative
vativve Technologies
Tec
e hnologies WWater
aater and Gas Control
Control
FFuture
utur
u e Projects
Projects
o PPressure
ressure Face
Face TBM
TBM Case
Caase Histories
Histories Inter
International
rnational PProjects
rojects
Geotec
Geotechnical
hniical Considerations
Considerations PPressure
ressure F
Face
ace T
TBM
BM T Technology
e hnology
ec TTunneling
unn
u neling ffor
or
o Sustainability
Sustainability
Gr
Ground
ound S Support
u
uppor t and Final
Final Lining Risk Management
Management

For more
m information contact:
co
ontact: RETC,
R ETC, www.retc.org,
www.retc.org, meetings@smenet.org,
meetings@
@smenet.org,
303-948-4200,
303-948-4200, 12999
12999 E Adam Aircraft
Aircraft Cir.,
C ., Englewood, CO
Cir CO 80112.
80112.
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 56

OPERATIONAL

traffic are directed not to have longitudinal


Figure 2: (Extract from EU Road Directive)
ventilation unless a prescribe risk assessment
demonstrates such a ventilation system is Mandatory for all tunnels Not mandatory
acceptable given the particular Mandatory with exceptions Recommended
circumstances of a tunnel including traffic Informative summary Traffic 2000 Traffic > 2000 Additional conditions for implementation
management, emergency exit distances and of minimum requirements vehicles per lane vehicles per lane to be mandatory, or comments
500 - >1000m 500 - 1000 - >3000m
smoke exhaust intervals. 1000m 1000m 3000m
The preference is for transverse or semi Lighting Normal lighting 2.8.1
transverse ventilation systems which are Safety lighting 2.8.2

able to exhaust smoke in the case of a fire. Evacuation lighting 2.8.3

Figure 2 extracted from the Road Ventilation Mechanical ventilation 2.9


Special provisions for (semi-) 2.9.5 Mandatory in bi-directional tunnels
Directive which appears at direction 2.1(ix) transverse ventilation where there is a control centre
of the EU Road Tunnel Directive does not Emergency At least every 150m 2.10 Equipped with telephone and 2 extinguishers.
prescribe at what length smoke extraction is staions A maximum interval of 250m is allowed
in existing tunnels
required nor the circumstances in which it Water supply At least every 250m 2.11 If not available, mandatory to provide
would be necessary. sufficient water otherwise
In Germany the requirement for smoke Road signs 2.12 For all safety facilities provided for
tunnel users (see Annex III)
extraction could arise in unidirectional Control centre 2.13 Surveillance of several tunnels may be
tunnels exceeding 600m in length but centralised into a single control centre
would depend upon detailed risk Monitoring Video 2.14 Mandatory where there is a control centre
systems
assessment. Automatic incident detection 2.14 At least one of the two systems is mandatory
and/or fire detection in tunnels with a control centre
Once such tunnels exceed 1200m in Traffic signals before 2.15.1
length smoke extraction using adjustable Equipment the entrances
to close
dampers and a false ceiling would be the tunnel Traffic signals inside the 2.15.2 Recommended if there is a control centre
tunnel at least every 1,000m and the length exceeds 3000m
required (Refer to Figure 1).
In Switzerland smoke extraction would be
required for high risk tunnels over 800m in in guidelines creates a potential regulatory acceptable or unacceptable.
length (or over 1500m in tunnels dilemma.[6] [7] [8] [9] [10] [11] In extreme circumstances minimal
determined to have a lower safety risk). Should the prudent engineer follow the compliance with the EU Directive might not
In Austria the approach taken would be EU Directive because it is comparatively discharge the legal responsibility of Tunnel
similar to that adopted in Germany however recent and compiled as a result of the engineers.
the ultimate decision will be dependent deliberations of many experts from all of By way of further example there could be
upon detailed design aspects of the the EU countries, or should they be unusual HGV traffic using the Trans
proposal including traffic volume, length persuaded by the domestic regulatory European network in that area which
and gradient. environment? rendered the minimum treatment measures
From the brief summary from Germany, The answer as a matter of law is clear. contained within the EU Directive ineffective
Austria and Switzerland noted above it is In order to discharge the engineers from a safety perspective.
apparent that a range of design options professional obligations it is necessary to Likewise circumstances may exist where
could legitimately arise by applying the local turn their expert skills to the question of strict adherence to a countries tunnel
regulation might discharge the engineers
obligations.
It is not uncommon outside the EU However design construction operation of
for neighbouring jurisdictions to these facilities in accordance with the
accepted or prescribed national regulatory
have differing standards. For regime provides strong evidence that the
design in question is appropriate.
example Hong Kong and Mainland There are many cases in all jurisdictions
China, Korea and Japan, Victoria (Countries) which illustrate this point. For
example the highest Australian Court stated
and New South Wales Australia, it early last century as:
New York State and Pittsburgh USA. The mere fact that a defendant follows
common practice does not necessarily show
that he is not negligent, though the general
member countries guidelines. Each of these what is appropriate in the circumstances of practice of prudent men is an important
local design outcomes may legitimately be the particular tunnel. This question must be evidentiary fact. A common practice may be
different to the minimum requirements answered for each country - the Sovereign shown by evidence to be itself negligent
contained in the EU Directive. State - in recognition of her unique Mercer v Commissioner for Road
For an excellent review of the key character and needs. Inexperienced Transport and Tramways (1936) 56 CLR 580
regulatory requirements in Europe there is countries may look to other Countries for per Latham CJ at 589 Lettice v. Council of
currently no better source of data than at guidance but should properly make her the Shire of Muswellbrook[2000]
www.etnfit.net (European Thematic own choices for tunnel safety standards. NSWSC 81
Network on Fire in Tunnels). That source Is There a Correct Engineering Answer? Or more recently:
provides summary documentation and is - While the performance of each of the A finding of want of due care can
continually being updated. design outcomes under the minimum EU properly be made even though the
For the engineer or even Government Directive requirements or those required defendant has obeyed all statutory
responsible for the design, operation or under each country's laws may be different, requirements and followed a common or
refurbishment of road tunnels this variation it does not follow that any of the designs are universal practice.

56 TUNNELLING JOURNAL
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 57

OPERATIONAL

Figure 3: (extracted from the train confirmed to the


Bouwdienst Rijkswaterstaat
Directoraat-Generaal
latest technical standards and all
Rijkswaterstaat Ministry of requirements were fulfilled
Transport, The Netherlands
Sprinklers in Japanese Road Podmore v. Aquatours Pty Ltd (1984) Mainland China, Korea and Japan, Victoria
Tunnels Final Report December NSWLR 111 at p 116 and New South Wales Australia, New York
2001 Chiyoda Engineering Accordingly as engineers there is an State and Pittsburgh USA.
Consultants Co.,Ltd. "F" and Ota obligation to understand and properly apply Figure 3 summarises the requirements for
"L")[12] due professional skill to tunnel safety safety equipment in the Japanese Road
questions. The exact nature of this duty Authorities Jurisdiction.
40,000 varies between legal systems and countries. The first stage of the Japanese process is
Traffic volume (vehicles per day per tube)

30,000 B A AA
25,000 For a Country by Country guide to liability characterisation of the tunnel type. From this
20,000 N.
15,000 N.
L-
40
see reference[9] figure tunnel risks are characterised from a
N. L-
10,000 N.
L- L- 12
x1
06 Divide and Conquer? - There are length/ traffic number perspective.
8,000 3x 4x x1
10 6 10 6 06 differences between the regulatory The Second stage describes what is
4,000 environment the different member states required (Figure 4).
3,000
and countries (often neighbouring each The Japanese approach can readily be
2,000
D C
other), the EU directive and other standards compared to the EU approach which is
1,000 (such as in the United States of America, summarised in Figure 2. It is systematic, and
Taiwan, Japan and Australasia). considered but different to EU and
It is not uncommon outside the EU for member state systems.
0

0
0

0
0

0
10

20
30

50

00

00
00

00

0
,0

neighbouring jurisdictions to have differing There is no correct approach. Each


1,

2,
3,

5,

10

Tunnel length (m)


standards. For example Hong Kong and system will perform differently.
The differences in performance may be
critical for management of a particular event
Figure 4: (extracted from Bouwdienst Rijkswaterstaat Directoraat-Generaal
say a vehicle fire. In a long busy Japanese
Rijkswaterstaat Ministry of Transport, The Netherlands Sprinklers in Japanese
tunnel (AA type) water deluge sprinklers
Road Tunnels Final Report December 2001 Chiyoda Engineering Consultants
are prescribed.
Co.,Ltd.)[12]
Under a range of scenarios the use of
Classification AA A B C D Remarks water deluge sprinklers could impact injury
Safety facility rates and infrastructure damage. The nature
Emergency telephone Not in D-Class tunnels with L < = 20m of the impact will depend upon the scenario.
Information and alarm

Push button The range of potential impacts extends


Fire detector Not in tunnels without ventilation system from positive to negative. If the impact is
Emergency At tunnel entrance Not necessary in tunnels with L > = 200m
negative (i.e. more injuries) it could be
alarm equipment
In tunnel Necessary in A-Class tunnels
argued that prescribing the water deluge
with L > = 3,000m system was wrong.
If no one is injured it is unlikely to be
extinguisher

Fire extinguisher
more than an obscure statistical reference in
Fire

Fire hydrant To be installed in B-Class tunnels


with L < = 1,000m an operator's log book.
Emergency Emergency exit light To be installed in tunnels with evacuation routes Understanding Regulatory Differences -
guidance panel
Guide board (A) To be installed in tunnels with evacuation routes These types of regulatory variations provide
Escape and guidance

Emergency exit sign To be installed in tunnels with evacuation routes an opportunity to argue subsequent to a
Guide board (B) To be installed in tunnels safety event that not only was a particular
without evacuation routes design defective but that had the design
Smoke extractor, Evacuation routes installed in tunnels with L > = 750m practices of another jurisdiction been
evacuation route Smoke extraction installed in tunnels with L > = 750m
Install evacuation routes in AA-Class tunnels and in A-Class tunnels followed injuries would have been avoided.
with L > = 3,000m, with bi-directional traffic and longitudinal ventilation
The impetus for such argument should not
Water supply hydrant To be installed in B-Class tunnels be underestimated and the sentiments and
with L < = 1,000m (water ports near portal)
Leaky feeder system Coaxial cable Necessary in A-Class
dissatisfaction of the public towards a legal
tunnels with L > = 3,000m system which does not find liability
Entrance/exit telephone subsequent to a tragedy are well illustrated
Radio (re-) broadcast Necessary in A-Class by a number of engineering related tragedies
tunnels with L > = 3,000m in recent years.
Other equipment

Loudspeaker system Installed in tunnels with radio (re-broadcasting equipment) The role of standards was recently
Water sprinkler Necessary in bi-directional A-Class highlighted when an Austrian court in
tunnels with L > = 3,000m
and more than 4,000 vehicle a day Salzburg acquitted 16 people of the
Monitoring equipment Type A (20m interval) Installed in tunnels with sprinklers responsibility for the Kaprun ski train blaze
that killed 155 tourists in November 2000.
Type B (at lay-by)
In the determination of the court the Judge
Emergency Installed in tunnels with L > = 200m
lighting equipment noted that:
Emergency Generator Installed in tunnels with L > = 500m the train confirmed to the latest technical
power supply
Uninteruptable power supply Installed in tunnels with L > = 200m standards and all requirements were
fulfilled.
Must be installed Installed if deemed necessary
Importantly the Judge accepted the

TUNNELLING JOURNAL 57
15
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 58

OPERATIONAL

defendants arguments that no-one could


have foreseen the chain of events that lead
The challenge for the Middle East
to the deaths and that none of the
defendants had any reason to suspect that
with its unprecedented tunnel
the heater that started the fire was not up to building program is to formulate
standard.
The importance of considered engineering
regulatory environments that are
decision making underlies all guidelines. respectful and sensitive to local
These guidelines are tools to assist engineers
perform not recipes which guarantee conditions.
success.
attractive to foreign countries because it the directive are more problematic as they
Conclusions separates the executive arm of government imbed within them cultural and technical
The EU Directive on Road tunnel safety from accountability for tunnel safety and prejudices which are not readily discernible -
provides a useful example of both a creates clear lines of expert accountability for translation to other countries unique
regulatory framework and minimum tunnel safety - including named individuals circumstances (such as the Middle East)
prescriptive operating requirements for road and companies. demanding careful considered expert
tunnels. On the other hand the "minimum" analysis.
The regulatory framework is especially requirements for tunnel safety prescribed by A comparative analysis between road
directives and different EU member nation
REFERENCES guidelines readily demonstrates the vast
range of design and operational options
[1] Directive 2004/54/EC of the European Parliament and of the Council of 29 April 2004 on articulated globally with respect to
minimum safety requirements for tunnels in the Trans-European Road Network (EU Directive underground road transportation safety.
2004/54/EC) http://eur-lex.europa.eu/smartapi/cgi/sga_doc?smartapi!celexplus!prod! There is such variation in key safety
DocNumber&lg=en&type_doc=Directive&an_doc=2004&nu_doc=54 parameters such as ventilation, lighting,
emergency evacuation, control systems and
[2] A comparative analysis of the Mont-Blanc, Tauern and Gotthard tunnel fires (2004); Dix, A. . pedestrian ways that expert engineering
Professor. Voeltzel, A. Routes/Roads PIARC. 2004 decisions are still required. The common EU
http://www.piarc.org/en/order-library/5446-en- position as expressed in the EU Tunnel
A%20comparative%20analysis%20of%20the%20Mont-Blanc,%20Tauern%20and%20Gott Directive is an extremely useful articulation of
hard%20tunnel%20fires.htm minimum requirements but is not, and
could never be, the safety standard for the
[3] European Road Tunnel Safety Officers Forum European Union nor any other country in
http://ec.europa.eu/transport/road_safety/eventsarchive/2012_01_18_forum_tunnel_safety_en. the world.
htm The domestic regulations in EU Member
States remain extremely important
[4] Risk evaluation for road tunnels; 2011; Author(s) CLARK Gary / KOHL Bernhard / Dix Arnold documents in determining appropriate
& others; Risk management / Road tunnels; PIARC Ref. RR350-054EN conduct. The variation in approaches
highlighting the importance of providing
[5] Tunnel safety, risk assessment and decision- making; Tunnelling and underground space considered advice no matter what conclusion
technology 25 (2010) 91, 94; http://wenku.baidu.com/view/fa75eac9a1c7aa00b52acb14.html is arrived at following a systematic analysis of
a safety critical issue.
[6] OTA, Y., Japanese Standards and Guidelines for Road Tunnels, Tunnel Management It is the differences between regulatory
International, September 1999, pages 34 37. approaches which highlight the increasing
importance of informed expert decision
[7] Assessment of the Safety of Tunnels Study (IP/A/STOA/FWC/2005-28/SC22/29) European making for professional management of
Parliament underground transportation safety in the
European Union and other regions.
[8] Science and Technology Options Assessment, STOA, Authors/Experts: Beard, Cope, Dix and The challenge for the Middle East with its
others; available at http://www.itas.kit.edu/downloads/etag_beco07a.pdf unprecedented tunnel building program is to
formulate regulatory environments that are
[9] Handbook of Tunnel Fire Safety, 2nd edition; Authors Beard, Carvel, Dix and others; respectful and sensitive to local conditions.
Hardbound ISBN: 978-0-7277-4153-0; Ebook ISBN: 978-0-7277-4193-6; Publication Date: Simple factors such as blown sand and
October 2011; available at http://www.icevirtuallibrary.com/content/book/101179 P525 temperature can play havoc with apparently
sensible practices and standards from other
[10] NFPA 502: Standard for Road Tunnels, Bridges, and Other Limited Access Highway, 2011 parts of the world such as Europe. A unified
Edition; Authors: Brinson,Connell, Dix & others central regulatory framework has its place in
http://www.nfpa.org/catalog/product.asp?pid=50211&icid=B484 regions currently experiencing tunneling
booms such as the Gulf States. Though not
[11] PIARC Road Tunnels Manual; Contributors: Bendelius, Dix, Kabuya and others; superficially as exciting as the construction
http://tunnels.piarc.org/tunnels/ressources/3/257,Chap-8-Equipment-and-systems-EN-v-21.pdf programs themselves such regulatory
frameworks provide the much needed chain
[12] Chiyoda Engineering Consultants, Sprinklers in Japanese Road Tunnels, Report of consistency, responsibility and
commissioned by the Center for Tunnel Safety of the Netherlands Ministry of Transport, accountability during the massive
2001. construction phases of these emerging and
increasingly popular mega projects.

58 TUNNELLING JOURNAL
TJ_0513_059_061.qxd:Feature 21/4/13 15:58 Page 59

OPERATIONAL

Successful tests in
the Trnskog tunnel
in Stockholm
Over the next few years, several
kilometres of tunnels will be or are
being built under Stockholm for both
the Stockholm Bypass and the Northern
Link. They can be expected to carry
A photograph of a free burning test in the Trnskog tunnel, with
high traffic loads, in which an accident
6m/s air velocity. The target vehicle, with combustible material on could have significant consequences.
the side, can be seen on the far side of the flames. The Swedish Transport Administration
has decided to protect the tunnels with
fixed fire fighting systems (sprinklers).
However, the potential for fire
spreading between vehicles is to be
investigated. Here, Glenn Appel,
Haukur Ingason, and Ying Zhen Li of
SP Fire Technology review tests it has
performed in an existing road tunnel to
investigate whether the fire-fighting
system would be capable of preventing
the spread of fire between stationary
vehicles in a queue.

IN CONJUNCTION WITH large fire test hall. Using simple manual flammable materials. The surface of the
Brandskyddslaget and the Swedish calculations and advanced CFD steel was used to measure temperature (a
Transport Administration (STA), specially calculations, we were able to estimate large plate thermometer), so that when
designed nozzles intended to provide what the likely radiation flux on the tunnel the adjacent materials caught fire the
protection against fire in a tunnel has been walls would be and to produce an image temperature of the steel sheet could be
developed. A lot of testing has been done, of which parts of the tunnel needed to be read at the same time.
and a successful design concept has now insulated before the tests. The calculations An advantage of using the target vehicle
been produced. Two different fire-fighting also provided an indication of the distances was that it provided seven positions at
systems have been installed in two sections from the fire at which critical temperatures which the temperature could be measured.
of the existing Trnskog tunnel in order to for the ignition of flammable materials The shape of the target vehicle was that of
simulate as realistic a situation as possible. could be expected. the rear of a van, with two of the
The STA wanted to perform simple tests temperature measurement points on the
that could show that fire would not spread The test arrangement roof and five on the vertical surface facing
between stationary vehicles in a queue SP Fire Technologys LPG tunnel fire towards the fire. This made it possible to
situation. Using real vehicles was not a simulator was used as the fire source. This see where the temperature was the highest
realistic alternative during these tests. simulator has been developed in order to and where the water spray did the most
Instead, a special instrumentation test rig produce a carefully defined heat release use during the tests. The values recorded
was developed, in the form of a target rate. Specially designed burners had been from the target vehicle were comparable
vehicle measuring temperature. The developed for the tests in order to provide with those that could be expected in a real
temperature was measured in order to a good spread of heat even when the vehicle in a fire.
evaluate the risk of fire spread. The fire burner was exposed to the effect of wind.
itself was simulated by a specially The heat release rate that was used Tests under real conditions
developed LPG burner, capable of corresponded to a fast curve (Q = 0.047 * As far as we know, fire-fighting systems
producing different heat release rate t), by which the heat release rate rises have never previously been tested under
curves. from zero up to about 3.5MW in about 4.5 such conditions in an existing tunnel. Two
minutes. This is then followed shortly after different wind velocities were used (6m/s
Initial calculations before the test by a step increase up to about 6MW, and 3m/s) during the tests in order to
In order to be able to make best use of the which is then held constant for a given investigate temperature differences
limited time available in the tunnel, which time. resulting from different distances (2m and
had to be closed to traffic while the tests In addition to the burners, a target 2.8m from the centre of the fire) to the
were being performed, preparatory tests vehicle had been constructed in the form nearest vehicle. An environment such as
were carried out in SP Fire Technologys of a sheet of steel, covered on each side by that in the tunnel is very difficult to

TUNNELLING JOURNAL 59
TJ_0513_059_061.qxd:Feature 21/4/13 15:58 Page 60

OPERATIONAL

Did the fire-fighting system work as


Figure 1: Measured values from the simulated target vehicle exposed to the intended?
fire in a free burning test and with the water spray system in a 6m/s air flow. After having first carried out free burning tests
in which the combustible material caught fire,
experiments were conducted with the fire-
fighting system in operation. This was started
about 30 seconds before the combustible
material was expected to catch fire, after which
the heat release rate rose to 3.5MW and then
step rise to 6MW was performed. No
carbonisation of the combustible material was
seen in most of the tests with the fire-fighting
system in operation, despite the fact that the
material was exposed to radiation from a 6MW
fire for a period of five minutes. The
temperature of the target vehicle was also very
low during most of these tests, as can be
clearly seen from Figure 2. In the particular
case illustrated by Figure 2, the target vehicle
was at a distance of 2.8m from the centre of
the fire, and only about 1.5m from the flames.
The tests described here have shown that
spraying water on an adjacent burning vehicle
effectively keeps the temperature down and
prevents combustible material from catching
fire. This conclusion is an important argument
reproduce in laboratory conditions, due to somewhat over 350 C, which is close to in favour of the use of fire fighting systems in
effects such as the specific geometry of the the ignition temperature. Figure 1 shows queue situations. However, the tests do not
tunnel and the air flows. This is why these the steel temperature from a free burning provide information about the efficacy of fire
experiments are so important. In the free- test with an air velocity of 6m/s in fighting systems when dealing with a fire:
burning tests, the flammable material comparison with a test using the fire this requires further full-scale tests with real
often ignited at a temperature of fighting system. vehicles.

Ministero delle Infrastrutture


e dei Trasporti
Trasporti

Essential reading  get your own copy of Tunnelling Journal

Tunnelling journal

subscribe at:
www.tunnellingjournal.com
60 TUNNELLING JOURNAL
TJ_0513_059_061.qxd:Feature 21/4/13 15:58 Page 61

OPERATIONAL

A new system for water


drainage in tunnels
Water leaks often create problems in tunnels, as they can result in icicles. To prevent this, water is
drained from the tunnel roof and walls down to the ground, where it can be dealt with. Traditionally
sheets of PE foam have been used, but they are difficult to fit and introduce large quantities of
flammable material into the tunnel. A new drainage system, Rockdrain, has now been tested, both
in the laboratory and in full scale in a railway tunnel. The project has been financed by the Swedish
Transport Administration, and performed as a joint project by SP Fire Technology, CBI, IVL, Besab,
Rockdrain and the Traffic Administration. Lars Bostrm of SP Fire Technology explains

ROCKDRAIN IS a new system for drainage


of inwardly leaking water in tunnels, based
on a mesh of ducts secured to the roof and
walls of the tunnel and then sprayed with a
thin layer of conventional permeable
shotcrete. The shotcrete is then covered by
a special layer of sprayed concrete called
Solbruk, which is impermeable to water
leakage and provides better thermal
insulation than conventional shotcrete. The
addition of a small quantity of
polypropylene fibres to the Solbruk
produces a material that can also withstand
fire without spalling.

Full scale trials


The system has undergone full scale testing
in a recently constructed 1.8km long railway
tunnel at Kattleberg, about 40km north
east of Gteborg. The Rockdrain system
was constructed in the tunnel over a length
of about 100m where water leakage has
been observed. The tunnel interior has been
laser scanned after each stage of
application, i.e. first after the channel mesh
was fitted, then after the spraying of Above: The Kattleberg tunnel with the
conventional shotcrete, and finally between draining mesh fitted. Right: Close up of
each sprayed layer of Solbruk. These scans the draining mesh.
have made it possible to determine the
thickness of each sprayed layer with very elements, their durability, the drainage
high accuracy. In addition to enabling the performance and the tolerances required by
drainage performance of the system to be the system for its application, i.e. the
tested on full scale, the work has also maximum distances that can be accepted
revealed practical problems associated with between the mesh and the tunnel wall
application, such as an insufficient thickness without the channels in the mesh being material can be avoided by wet spraying
of Solbruk, which could then be rectified. In blocked by shotcrete. SP Fire Technology has Solbruk with an admixture of 0.5kg/m
addition, energy input and the necessary tested the systems fire resistance using the polypropylene fibres. The tests show that
working time for the application have been hydrocarbon curve (HC) test characteristic, the mesh must be mounted not more than
measured to enable LCC/LCA analyses to be whilst the thermal conductivity and thermal 10mm from the surface of the rock in order
performed. The same measurements and diffusivity of Solbruk have also been to prevent it from being clogged by
comparisons have also been made for determined. shotcrete. The LCA/LCC analysis clearly
insulation of a conventional drainage shows that Rockdrain has definitely less of
system using foamed PE mats. The results an environmental impact, and is cheaper,
The tests that have been performed show than the traditional method of drainage. A
Laboratory tests that, on the whole, Rockdrain works well further important lesson from the project is
An extensive programme of testing has for dealing with drainage in tunnels. Special that good training of operators, thorough
been carried out as part of the project measures may need to be taken to provide knowledge of the system, and proper
work. CBI Betonginstitutet has investigated protection for certain functions such as frost inspections are required to ensure that the
the mechanical properties of the various resistance and fire resistance. Spalling of the system is correctly applied.

TUNNELLING JOURNAL 61
TJ_0513_CONTACTS_062.qxd:Feature 21/4/13 14:41 Page 62

contact US
contributorS
Gary Tween Tris Thomas
Managing Director Editorial Director
Tel: + 44 (0) 1622 720 631 Tel: + 44 (0) 1622 720 631
Mobile: + 44 (0) 7973 205 638 Mobile: + 44 (0) 7812 011 139
gary@tunnellingjournal.com tris@tunnellingjournal.com

Kristina
Smith
Kristina Smith has been writing
about civil engineering and
construction for over 15 years,
Rory Harris Steve Caming having started her career out on
Chairman Publishing Director site as an engineer.
Mobile: + 1 (859) 321 3164 Tel: + 1 (603) 447 1187
rory@tunnelingjournal.com Mobile: + 1 (603) 662 6263
steve@tunnelingjournal.com
tunneling@roadrunner.com

Adrian
Greeman
Mark Piper Peter Bell Adrian Greeman has been
Finance Director Director
writing about international
Tel: + 44 (0) 1672 563 662 Tel: + 44 (0) 1622 720 631
civil engineering projects (in
Mobile: + 44 (0) 7768 554 646 Mobile: + 44 (0) 7770 441 867
particular tunnels, bridges
mark@tunnellingjournal.com peter@tunnellingjournal.com
and highways) for the past
16 years.

Tunnelling journal

Amanda Foley Daniel Lee- TGS Media Ltd


North American Editor PO Box 1261, Maidstone,
Billinghurst Kent, ME14 9HS, UK
amanda@tunnellingjournal.com Sales Consultant
mands.f@hotmail.com Tel: +44 (0) 203 239 6754
Mobile: +44 (0) 7818 422712 488 Allard Hill Road,
daniel@tunnellingjournal.com Conway, NH 03818, USA

The publishers, authors and


printers cannot accept liability
for errors or omissions. All
rights reserved. No part of this
publication may be reproduced
in any form without prior
Pete Beach Peter Lawrence
Illustrator Art Editor permission of the copyright
holder and the publisher,
application for which should
be made to the publisher. TGS
Media Ltd. ISSN Tunnelling
journal (Print) ISSN 2044-
074X, Tunnelling journal
(Online) ISSN 2044-0758

62 TUNNELLING JOURNAL
Untitled-1 1 04/04/2013 11:32:28
NATJ_0513_NAFNTCOVER_001.qxd:cover 21/4/13 21:12 Page 1

Tunneling
north american April/May 2013

www.tunnellingjournal.com
journal

UP EUCLID CREEK
WITH A SOLUTION
THE FIRST OF A SERIES OF NEW TUNNELS
FOR THE CLEAN LAKE PROJECT IS UNDERWAY
SEE PAGE 5 SEE PAGE 14 DETAILS ON PAGES 41-54
OBAMA VISITS BORING FOR RETC VISITS
PORT OF MIAMI BI-COUNTY THE CAPITAL
EGLINTON GEARS TO THE NORTH OF PART ONE OF
UP FOR LAUNCH, AND WASHINGTON DC, NATJS 2013 RETC
OTHER NEWS FROM WSSCS NEW WATER CONFERENCE AND
NORTH AMERICA TUNNEL WINDS UP EXHIBIT PREVIEW
13-02-27_119_ID040_eAz_XXL-Durchmesser_Tunnelling Journal NA_210x297mm_4c_oc_Fassung 01

h e r r e n k n e c h t A G | u tilit y t u nn e lling | T r affi c t u nn e lling

Miami Shanghai Sparvo


12.86m 15.43m 15.55m

WOR LD CHAM PI O N IN XXL-FO RMAT.


Mechanized tunnelling technology Construction companies have successfully excavated some 375 kilometers of tunnel worldwide
for all ground conditions in about 100 projects, using Herrenknecht machines with diameters of more than 10 meters.
Traffic as well as supply and Multi-lane road tunnels, railway tunnels and expansive metro lines provide sufficient capacities
disposal infrastructures for efficient transport systems.
Diameters from 0.10 to 19m The worlds two largest Mixshields (15.43m) have built a double-tube, combined road and
Around 375 kilometers of tunnel metro tunnel beneath the Yangtze River in Shanghai. One of the two machines is currently being
with diameters >10 meters re-used. Together with a smaller Mixshield (14.90m), this giant is currently excavating two
double-tube road tunnels beneath the Huangpu River. The tunnels will connect the districts of
Baoshan and Pudong as well as Minhang and Fengxian. As part of these projects, a total of around
25 kilometers of tunnel with mega-diameters are being built.
For the Miami Port Tunnel, Herrenknecht delivered the largest tunnel boring machine ever
employed in loose rock in the USA. The construction crews celebrated the breakthrough of the
first tunnel by the Herrenknecht EPB Shield S-600 (12.86m) in Florida on July 31, 2012.
The worlds largest tunnel boring machine, the EPB Shield (15.55m), is in operation con-
structing the Sparvo road tunnel in Italy quickly and safely. The first, around 2.5 kilometer long
XXL tube was completed with daily top performances of up to 22 meters on July 26, 2012.
As the only company worldwide, Herrenknecht AG delivers tunnel boring machines for all
ground conditions and in all diameters. The Herrenknecht product range includes tailor-made
machines for transport tunnels, supply and disposal tunnels as well as additional equipment and
service packages.

Herrenknecht Tunnelling
Systems USA, Inc.
1613 132nd Ave E, Suite 200
Sumner, WA 98390
Phone +12534472300
Fax +12538639376
marketing@herrenknecht.com

www.herrenknecht.com

13-02-27_119_ID040_eAz_XXLDurchmesser_TunnellingJournal_210x297_01_RZ.indd 1 28.02.13 10:56


NATJ_0513_COMMENT_003.qxd:Feature 21/4/13 19:06 Page 3

comment contentS
By popular demand 5 North American News
Project, contract & company news
Fire crew tunnel rescues and methane
blasts not withstanding, its been great
to see such positive press on the
9 The Insider
Lessons that can be learned from dragons,
dwarves, wizards, and a white rabbit
tunneling industry this month. From
President Obamas visit to the Port of
Miami Tunnel, in Florida, to promote
public-private partnerships for big-ticket
10 Blue beginnings
The first of four major projects gets under
way for DC Waters Clean Rivers program
infrastructure projects; to Bertha the
worlds largest TBM arriving in Seattle,
Washington, for the Alaskan Way Viaduct Bored Tunnel Replacement; Left: The
national media coverage has at last focused on the great feats being figure of
attempted, and achieved, by tunnelers throughout North America. eight slurry
The most heart-warming story however, was the delight of the San wall shafts
at Blue
Mateo County residents, turned tunnel activists, at the opening
Plains (p10)
ceremony for the Devils Slide Tunnels, in California (p6). Following
Below: The
decades of campaigning which resulted in a tremendous citizen vast caverns
movement to prevent Caltrans proposals for a four-lane overland under NYCs
bypass of this notorious stretch of state Highway 1 and years of Grand Central
construction, some of the pro-tunnel advocates were among the first Terminal (p20)
to drive through the twin tunnels in a parade of classic cars this March.
To aid the celebrations, the Half Moon Bay Brewing Co unveiled a new
beer, Tunnel Vision Ale. I wonder if someone would be willing to
sponsor a tasting at this years RETC conference in Washington DC...

Amanda Foley

Front cover: Up Euclid


Creek with a Solution
The first of a series of new tunnels for the
Clean Lake project is underway
The Euclid Creek Tunnel, a combined sewer
overflow project in Cleveland, Ohio, was
designed and is being built to reduce sewer
overflows to both Euclid Creek and Lake Erie.
14 Boring for WSSCs Bi-County Tunnel
Numerous challenges have been met during
construction of the Bi-County Water Tunnel
The project for the Northeast Ohio Regional Sewer District (NEORSD) is the
first of many tunnels for the NEORSD Clean Lake Project (see p6).
The tunnel is segmentally lined and when complete will be 17,716ft
(5,400m) in length, with a diameter of 23.9ft (7.3m). The contractor,
20 The Grand Central legacy
Production blasting for East Side Access
huge platform caverns draws to a close
McNally/Kiewit JV is excavating the tunnel using a single shield hard rock
TBM. The Euclid Creek Tunnel construction is innovative in the fact that it is
a hard rock tunnel using a
two-component annulus
29 Company News
Career moves and company news

grout. The annulus grout


was developed in BASFs
Technical Center in
30 CAT that gets the cream
Caterpillar Tunneling has been building on
the LOVAT foundation with new investment
Beachwood, Ohio. BASF is and an ambitious R&D program
also supplying alkali-free
set accelerator for
shotcrete application.
Technical support and
34 Meeting the challenges of Coxwell
The final connections have been made on
Torontos Coxwell Trunk Sewer Bypass
expertise is being
provided by the BASF
North American
Underground
41 RETC prepares for the capital
Washington DC is the host city for this years
Rapid Excavation & Tunneling Conference
Construction Group. and Exhibit (RETC)

NORTH AMERICAN TUNNELING JOURNAL 3


NATJ_0513_NEWS_004_007.qxd:Feature 21/4/13 19:18 Page 4

JOBS DONE WELL.


For over 50 years, Kiewits Underground District has
built some of the nations most complex tunneling and
underground facilities.

At the heart of any Kiewit project is a safety minded


workforce, committed to excellence in quality. From our
unique projects to our committed professionals...there is
nothing ordinary about it.

Kiewit Infrastructure Co.


302 South 36th Street, Suite 400, Omaha, NE 68131 | (402) 346-6010

KIEWIT.COM

4 NORTH AMERICAN TUNNELING JOURNAL


NEWS

Bertha arrives in Seattle


Bertha, the worlds largest tunneling largest weighing about 900 tons. Seattle
machine to date, arrived in Seattles Elliott Bay Tunneling Partners (STP JV) crews unloaded
on April 02, following a 5,000-mile journey the pieces and transported them a short
from Hitachi Zosens Sakai Works factory, in distance to the projects 80ft (25m) deep TBM
Osaka, Japan. The 57ft (17.5m) EPB machine launch pit, adjacent to Seattles iconic dock-
will begin excavation of Washington State side sport stadiums, where the machine will
Department of Transportations (WSDOT) be assembled for tunneling.
US$1.35 billion (State Route-99) Alaskan Way Testing at Hitachi Zosens manufacturing
tunnel, beneath downtown Seattle, this plant in Sakai revealed a problem with the
summer. TBMs main drive unit, requiring repairs to the
The five-story-tall machine arrived aboard machine before shipping from Osaka Bay on
the Jumbo Fairpartner in 41 pieces, the March 19. Bertha has since passed all of her
tests, and will officially
become the property of
STP once shes tunneled
approximately 1,000ft
(300m) without any issues.
Crews in Seattle are
about 80% finished with
the launch pit where
Bertha will start her
journey and are currently
preparing the site for TBM
assembly. Work is also
under way at the north
end of the Battery Street
Tunnel to prepare the TBM Left: Jumbo Fiarpartner comes into dock;
reception area. above: Berthas unloading and assembly

Second Avenue Subway worker rescued Methane blast on


after four-hour recovery effort Torontos SeC injures
New Yorks Metropolitan Transportation
Authority (MTA) suspended work on a
four workers
section of the Second Avenue Subway As NATJ was going to press, investigations
project on March 20, following a four-hour were ongoing following a methane explo-
rescue effort to save a worker who became sion on Torontos Southeast Collector (SeC)
trapped in saturated soft ground 75ft Sewer Project. The blast, which occurred
(22m) below ground at the projects 96th around 4.30pm local time on April 10, in-
Street Station Cavern. jured four men working on the projects A2
More than 150 firefighters worked to TBM drive.
free EE Cruz worker, Joseph Barone (age While all four men were admitted to hos-
51), after he lost his footing on plywood pital, two had been released from
sheeting and sunk chest-deep into liquified Markham-Stouffville hospital the same day
clay material as he made his way through and a third man was due to be released on
the 96th Street Station Cavern at about April 11. The fourth man, who was airlifted
8.40pm [EST] on Tuesday, 19 March. to the Sunnybrook Trauma Centre, re-
Barone was given drugs to keep him calm mained in hospital.
and a Fire Department chaplain was Patrick Casey, Director of Corporate Com-
brought to his side during the ordeal. munications for York Region, said contrac-
The worker was eventually pulled from tor Strabag Inc. would be conducting its
the station box by crane at around own investigation into the incident, in ad-
12.30am. Found to be suffering from dition to an on going Ministry of Labour in-
hypothermia and other minor injuries, he vestigation. As it stands now the shaft is
was taken to New York-Presbyterian/Weill invert have been poured with concrete the sealed until the Ministry of Labour investi-
Cornell hospital, in Manhattan. Three area where the worker lost his footing gation is complete, Casey said.
firefighters also suffered minor injuries remains unlined. Although the shaft where the incident
during the rescue operation. The MTA announced new safety occurred [Shaft 10] had been sealed and all
EE Cruz/Tully JV is currently fitting out measures in the wake of the incident. The work there had stopped, work continued
the fully excavated 96th Street station transit agency will now require workers to on other sections of the tunnel, with two
cavern under a $324.6 million MTA wear safety harnesses and mark unlined of the four owner-procured TBMs still in op-
contract. While some stretches of the invert areas with warning cones. eration.

NORTH AMERICAN TUNNELING JOURNAL 5


NEWS

Devils Slide opens to public Crosstown TBMs


Following decades of campaigning and years 1937, this curvy cliff-top stretch of Highway 1
gain a warm
of construction, the $439 million Devils Slide
Tunnel, in San Mateo County, California,
has bedeviled drivers, residents, and Caltrans
engineers, with rockfalls and landslides. Now
reception in Toronto
opened to the public on March 26. The open, the 4,100ft (1250m) tunnels and two
inauguration ceremony for the twin tunnels new 1000ft (300m) bridges steer the route
took place on March 25, with a parade of away from this perilous section of coastline.
classic cars filled with many of the local Caltrans awarded construction of the twin
residents who led the campaign that called tunnels the states first highway tunnel
for the tunnel instead of a four-lane bypass project since the third bore of the Caldecott
being the first to drive through. Tunnel opened in 1964 to Kiewit on January
Kiewit Infrastructure carried out NATM 03, 2007 (see NATJ, April/May 2011, p10).
excavation of the tunnels using roadheaders HNTB was the prime designer, responsible for
and drill & blast excavation through the San the final lining design and the tunnels state-
of-the-art M&E systems. Subconsultant ILF
Consultants was responsible for NATM design
of the initial lining and ground support,
drainage systems and waterproofing. Kiewit
employed Gall Zeidler Consultants to provide
NATM construction support, while a joint
venture of URS and Dr G Sauer Corp was
selected to perform tunnel excavation
inspection and scheduling for Caltrans. (From left) Bruce McCuaig, CEO of
The tunnels will now be known as the Tom Metrolinx, Ontario Transportation Minister
Lantos Tunnels, in honor of the late San Glenn Murray, and Toronto MPP Laura
Pedro Mountain. The works took two years Mateo congressman who secured full federal Albanese
longer than originally expected, in part due to funding for the tunnel. Lantos worked for PHOTO: METROLINX
complex soil conditions being worse than three decades to bring the project to light and
anticipated. But for residents and merchants lived to see the tunnels get underway before On April 09, Ontarios Transportation
of the San Mateo County coast, it was well he died in early 2008. His widow and Minister, Glen Murray, inspected the first
worth the wait. Almost since it opened in daughter were both present at the ceremony. of four owner-procured Caterpillar EPBMs
that will excavate the 11km (6.8-mile)
Downtown tunnel component of the new
Euclid Creek progresses under Erie Eglinton-Scarborough Crosstown LRT, in
Toronto, Canada.
The 27ft (8.2m) diameter Herrenknecht hard The CA$4.9 billion, provincially funded,
rock TBM at work on McNally/Kiewit JVs Eu- LRT will run about 19km (11.8-miles) from
clid Creek Tunnel contract, in Cleveland, Ohio, Black Creek to Kennedy station in the
has completed approximately 50% of its east, and is expected to take about eight
18,050ft (5.5km) drive and is currently mining years to complete.
tunneling beneath Lake Erie. Metrolinx awarded the first of two
The Northeast Ohio Regional Sewer District major tunnelling contracts for the project
(NEORSD) gave McNally/Kiewit JV notice to to Crosstown Transit Constructors
proceed on the $198 million contract in April comprised of Obayashi Canada, Kenny
2011. The Euclid Creek Tunnel is the first of Construction, Kenaidan Contracting and
seven tunnels for the sewer districts Project Technicore Underground in September
Clean Lake, a 25-year plan to protect Lake Erie 2012.
and its tributary rivers and streams from com- veyor system booster stations have also been This first machine will be launched from
bined sewer overflows. installed. the Black Creek Drive Advanced Works
The tunnel, which was designed by Hatch Shafts 1, 4, and 5 have been completely ex- shaft in May, with its twin following a
Mott MacDonald (HMM), is predominantly cavated, and Case Foundation recently com- month later, in June. They will complete
being driven through thinly bedded shales and pleted the 32, 105ft (32m) deep, secant piles the first drives from Black Creek to Allen
interbedded siltstone at an average depth of for Shaft 3, for which soft ground excavation Road, near Eglinton West Station.
200ft (60m). A launch shaft, reception shaft will begin this month. McNally/Kiewits con- Here the machines will be recovered
and three intermediate shafts are also being crete subcontractor, Northstar, has also begun and re-launched on the east side of Allen
built as part of the contract. As the TBM pro- structure and shaft cast-in-place concrete oper- Road, to avoid tunneling under the
gresses a one-pass pre-cast segmental liner, ations at Shafts 4 and 5, along with four addi- existing Spadina Subway. They will
manufactured by CSI Hanson in Macedonia, is tional surface structures. complete their drives at Eglinton Station,
being installed to provide an i.d. of 24ft Jacobs Associates is providing construction just west of Yonge Street.
(7.3m). engineering services for the project, which is The second set of TBMs will be launched
A recent switch to a three-shift mining oper- scheduled for completion in April 2015. The from Laird, in the east currently
ation by the JV is proving to be a success, with launch shaft will be used as part of the Dug- scheduled for May 2014 and drive west
crews having reached record weekly advance way Storage Tunnel, the design of which was back towards Yonge Street. The line will
rates since its inception in early March. Thus recently awarded to MWH in joint venture then run above ground on its own right-
far, three of the projects five continuous con- with HMM. of-way from Laird Road to Kennedy.

6 NORTH AMERICAN TUNNELING JOURNAL


NEWS

Obama visits Port of Miami Tunnel Project


Executive, Louis Brais, told NATJ. President
Obama used his visit to affirm his belief in,
and commitment to, Public Private
Partnerships, using ours as a national model,
and we look forward to partnering with the
public for other great projects.

POM Tunnel Update


Bouygues historic Port of Miami Tunnel
Project was at 69% completion as NATJ went
to press in early April. With a final completion
date less than 15 months away, the Project
Team of now over 500 employees, led by
Project Executive, Louis Brais, is busy at work
on several critical components of the project.
The first of the twin tubes (eastbound
tunnel) was completed on July 31, 2012.
President Barack Obama visited the Port of Harriet, the projects 42ft (12.5m) diameter
Miami Tunnel Project, in Florida, on Friday, Herrenknecht Mixshield TBM, began boring
March 29, to highlight the use of Public- the westbound tunnel on October 29, 2012.
Private partnerships to deliver big-ticket Now more than two thirds into her second
projects such highways, bridges and tunnels, bore, the machine recently successfully
promoting a new plan to rebuild the nations completed the most challenging portion of
roads, bridges and points of commerce a the tunnel alignment.
series of measures that White House officials Extremely porous geology demanded that
argue could appeal to business-minded the Earth Pressure Balance (EPB) TBM be
Republicans. adapted to safely mine without confinement
The Port of Miami Tunnel project, which is
the result of three years of work by more than
6,000 sub-contractors and vendors, will
connect the port to the interstate highway
system and will take over 1.5 million trucks
out of the downtown area per year. The major
infrastructure project, which is being built at
an estimated cost of US$1.3 billion, includes a
-mile (1.1km) long twin-tube highway
tunnel that will connect the MacArthur
Causeway on Watson Island to the Port of
Miami, on Dodge Island.
The tunnel project is a design-build-finance-
operate-and-maintain (DBFOM) Public Private possible? overpressure. The innovative technique used
Partnership (PPP) between public partners the The US President laid out a plan that will to accomplish this was a Water Control
Florida Department of Transportation (FDOT), create jobs while upgrading what businesses Process (WCP) mode (see NATJ September
Miami-Dade County and the City of Miami, need most modern ports; modern pipelines 2012, p10). Harriet is now back in EPB mode
and MAT Concessionaire, which is made up of and tunnels; and modern schools. for the remaining westbound tube excavation,
Meridiam Infrastructure and Bouygues Travaux Called the Partnership to Rebuild America, and is expected to breakthrough later this
Publics. Bouygues Civil Works Florida is the this partnership with the private sector has month (April 2013).
Design-Build Contractor. three main components: creating an Also for the first time ever in Florida,
It is projects like this one, the US independent fund which would leverage ground freezing will be utilized in a
President said in remarks following his tour, private and public capital for infrastructure construction project. Of the five emergency
that will help reignite the true engine of our projects that show the greatest merit; fund cross passages that will link the twin tubes,
economic growth a rising, thriving, middle more projects, at less cost, by establishing cross passages 2 and 3 will be constructed
class. Projects like this create a lot of other new America Fast Forward bonds, which will using ground freezing.
good jobs, too, President Obama explained. give mayors and governors more flexibility and Due to the highly permeable nature of the
You ask any CEO where they would rather power to attract private investment for public soils, pre-treatment is also required. CP1, CP4
locate their business and hire new workers. projects; and strengthening a loan program and CP5 were pre-treated from ground
Are you going to set up shop in a country (the Transportation Infrastructure Finance and surface using an innovative technique, Cutter
thats got raggedy roads, runways that are Innovation Act or TIFIA) that will give cities Soil Mixing (CSM) to form a nearly impervious
pot-holed, and backed-up supply chains? Or and counties better access to funds for monolithic block of soil-cement. Surface
are you going to seek out high-speed rail, infrastructure improvements. restrictions prevented CSM for CPs 2 and 3,
Internet, high-tech schools, new state-of-the- At more than 500 employees, of which so artificial ground freezing via Brine at -30C
art power grids, new bridges, new tunnels, nearly 90% are local hires, Bouygues is proud will be adopted to provide safe support of the
new ports that help you ship products made of the great progress weve made in this very ground during excavation and permanent
in America to the rest of the world as fast as challenging project, Bouygues Project lining.

NORTH AMERICAN TUNNELING JOURNAL 7


NATJ_0513_Buoygues_AD_008.qxd:Ad 21/4/13 19:29 Page 52

PORTMIAMI
TUNNEL

The historic Florida transportation project PortMiami Tunnel will connect the port, Miami-Dade
Countys second largest economic generator, directly to the surrounding highways, improving
access to the port. The technically challenging project, a first in North America for global
conglomerate Bouygues, is comprised of two 11.3 meter internal diameter, 1.27 kilometer long
tunnels bored through the intricate geology of the Biscayne Bay channel, known as Government
Cut. Design-Build Contractor, Bouygues Civil Works Florida, is also a 10% equity partner in
this award-winning Public Private Partnership that U.S. President Barack Obama heralded as a
national model for P3s.

www.Bouygues-Construction.com
FOR MORE INFO ON PORTMIAMI
TUNNEL PROJECT VISIT:
www.portofmiamitunnel.com
Or Contact: L.Weinberg@BCWF-Miami.com
NATJ_0513_Insider_009.qxd:Feature 21/4/13 18:51 Page 9

THE INSIDER

the
insider
Bob Goodfellow, PE, CEng, Senior Vice
President, Aldea Services LLC

WINTER IS OVER and spring is around the harsh to me, regardless of the severity of the and yet contradictory advice. All these characters
corner. The madness of March is upon us, so in surveying error. are supposedly helping poor Alice and Brothers
keeping with the season I thought some Utility location is a well-known problem on Contracting navigate their way through their
thoughts and anecdotes highlighting my own many tunnel projects. In the case of the underground issues when all they want is to get
madness about tunneling and some lessons Chamber of Secrets, Harry Potter locates this out without too much damage.
learned would be fitting for this months Insider. chamber that has lain undiscovered for over 500 We have all heard the expression the more
In writing geotechnical baseline reports (GBRs) years. I would think that a decent set of as-built things change, the more they stay the same.
and attempting to foresee issues and hazards drawings would have solved this mystery long Companies spend millions analyzing industry
that might manifest during projects, I have often ago without all the fuss. trends and discussing how change is good and
opined that if anybody can see into the ground

Through the
ahead of the TBM, they would be very rich
indeed. Imagine my delight then when the
project geologist announced in a recent meeting
that he could see the rock we were going to
encounter just by looking at the mountain.
Alas, his credibility was badly damaged a few
seconds later when he also announced that
there would be no problems.
Another Contractor once told me that when
reviewing a GBR he noted to his chief estimator
that there appeared to be no really bad ground
Looking Glass
Using the appropriate form of contract change must be embraced if we are to succeed,
on the project. When have we had a job with provides the lesson in the Great Escape. Charles but many things are constant in our business.
no really bad ground? he said to his colleague. Bronson as the chief tunnel contractor was not One of these constants is character. The tunnel
They quickly agreed to put 5% of really bad abiding by the minimum support requirements business abounds with extrovert, high
ground into the estimate regardless of what the and caused a serious accident during tunneling maintenance and delightful characters many of
GBR said. under the fences to escape from a prisoner of which would not be out of place in the books or
Lessons are all around us in art and literature war camp, an accident in which he was lucky movies noted above.
that can help us at work. For example, I watched not to be completely buried along with his The mentality and indomitable spirit of tunnel
a movie called Reign of Fire a few years ago. If workers. The Germans in this fine movie were miners is legendary. Many of us have stories to
you havent seen it, I would not exactly drop also clearly unhappy at not being allowed access share, but one I read recently summed up their
everything to rush out and buy it on DVD, but to inspect the works. But you see, it depends attitude perfectly for me. The book was a
the movie begins with a tunneling scene how you set up the contract; and if the fascinating read about military mining during
beneath London. The tunnel excavation breaks specifications rely on self-certification for quality, World War I and how the miners were formed
into a dragons lair disturbing its sleep, which what control do you really have to inspect the into tunneling companies so that large
results in a fiery death for all involved and work and make any changes? The tunnel was underground mines could be placed by
devastation for London and most of the UK. eventually completed and quite a few people tunneling under the opposing forces trenches.
While this movie had great special effects and escaped, so while it wasnt as great an escape as The conditions and courage on both sides to
this was clearly a traumatic event in the history the original plan, we could still call the tunnel pursue such a branch of warfare is a topic for
of my homeland I couldnt help but think project a technical success. another day, but before heading off to face the
blimey, I bet that wasnt in the GBR. That must And then there is my own favorite parody of horrors of the Western Front and join his
be a Type II DSC. I generally try to keep these the tunnel business, Alice in Wonderland. Down tunneling company, a miner from the Northeast
types of thoughts to myself as they are not a rabbit hole Alice goes headlong into the world of England was asked during his medical if he
readily understood by people outside the of tunnel construction, seeing an overexcited was circumcised. He responded with a smile that
industry, but these lessons can be valuable to project sponsor demanding everybodys head be no, that is just fair wear and tear. I know Ive
share with colleagues. cut off when they are not pleased; the rabbit-like worked with people like that guy and I am sure
Alignment control is important in tunneling project manager always concerned with time that even after almost 100 years, many of you
and this importance can be seen in the Lord of and how late they are; the crazy CM calling recognize this brand of miners humor.
the Rings, where the Mines of Moria were meetings (and always with plenty of tea); an There are lessons all around us, if only you are
destroyed when the dwarves delved too deep ever-smiling Cheshire Cat consultant that seems passionate and, yes, crazy enough about tunnels
and released a fearsome beast. This loss of to appear out of thin air whenever there is to take note of them. Stay safe, learn those
vertical alignment resulted in the destruction of trouble; and identical-looking lawyers from the lessons, enjoy the great people in our industry,
their entire community. This does seem a bit firm Tweedledum &Tweedledee giving constant and for goodness sake keep away from dragons!

NORTH AMERICAN TUNNELING JOURNAL 9


NATJ_0513_BLUEPLAINS_010_012.qxd:Feature 21/4/13 19:34 Page 10

The Blue Plains Tunnel is the first of four major


design-build tunnel projects to get underway
for the Clean Rivers Project, in Washington DC.
Amanda Foley, reports

BLUE
beginnings
IN WASHINGTON DC, Traylor/Skanska/Jay- scoring of the technical (35%) and price
Dee JV is currently gearing up for the launch (65%) proposals ultimately resulting in a
of its Herrenknecht EPB machine on the 4.5- combined highest score and lowest bid. EPC
mile (7.3km) long Blue Plains Tunnel Project. Consultants was selected to carry out
The 23ft (7m) diameter machine, which was construction management on the project.
christened Lady Bird during an official The Blue Plains Tunnel is the longest of the
ceremony on April 9, is due to start tunneling four tunnels in the Clean Rivers Program, at
this June. It will be used to excavate the first approximately 24,000ft (7,315m) and includes
phase of The District of Columbia Water and five diaphragm wall shafts that range
Sewer Authoritys (DC Water) $2.6 billion between 50ft (15m) and 132ft (40m) in
Clean Rivers program, which aims to eliminate diameter and 110ft (34m) and 170ft (52m) in
Combined Sewer Overflows (CSOs) into the depth (see map).
Anacostia and Potomac rivers.
Above: Map of the Blue Plains Tunnel After a procurement effort that lasted more Shaft design and construction
Project and the other tunnel projects than a year Traylor/Skanska/Jay-Dee JV (TSJD), Two of these shafts, the 132ft (40m) diameter
in the DC Clean Rivers Program along with its designer Halcrow, was officially Dewatering Pump Station Shaft (DS) and the
awarded the $330.5 million design-build 76ft (23m) diameter Screening Shaft (SS), are
Below: The combined figure eight contract for the Blue Plains Tunnel Project on located at the Blue Plains Advanced Waste
diaphragm wall shaft structure at the May 5, 2011. The contractor was chosen from Water Treatment Plant (BPAWWTP) site and
Blue Plains WWT Plant three short-listed teams, with evaluation and have been designed as a combined figure
eight diaphragm wall structure.
This unique shaft arrangement will
allow the assembly of the TBM
through both shafts, utilizing a
23ft (7m) diameter opening
between the adjoining shaft walls.
The arrangement takes
advantage of the large diameter
shafts to facilitate TBM launch,
explains Traylors Construction
Manager, Brett Zernich. It also
eliminates the need for an
elaborate ground support system
for an interconnecting tunnel
between the two shafts.
Its proved challenging, in
terms of the size and arrangement
of the diaphragm walls, says
Martin Ellis, Halcrows Design
Manager for the project. You
basically end up with some
double-size panels and some Y-
shaped panels where the shafts
interconnect, for which you have
to maintain the excavation.
NATJ_0513_BLUEPLAINS_010_012.qxd:Feature 21/4/13 19:35 Page 11

WASHINGTON DC

TSJD subcontractor Bencor, excavated these


5ft (1.5m) thick, 200ft (60m) deep diaphragm
walls last year. They had to work with some
pretty strict verticality tolerances, which were
dictated by the full depth of the shaft, says
Ellis. Basically, weve had to eke out every bit
of strength from the walls to make the figure
of eight work. The shaft reinforcement
consists of steel cages, with glass fiber
reinforcement for the tunnel eye. Theres also
increased reinforcement locally at the bottom
of the shaft where weve had to take into
consideration the vertical spanning and hoop
stresses in order to gain sufficient strength.
Theres also additional reinforcement around

ngs
the opening between the two shafts, which
transfers the load above and below it.
The shafts, from my viewpoint, are
probably the most complex part of the
project, says Rafael Castro, Design Manager wet. At the other three
of the Blue Plains Tunnel for the Owners shafts sites there is a
Representative Jacobs Associates. Fortunately sandy layer near the base
the JV and its designer have done a very good of the slabs, says Ellis.
job of handling the difficulties associated with So theyll be excavated
their design and construction. There have underwater and the base
been a lot of challenges, but TSJD and slabs will be tremied in
Halcrow have worked through them. From under water.
the shaft design perspective its gone really One of these shafts is
well. The shaft construction itself has gone now being excavated;
fairly well, but weve had some bumps. The while at the other two
requirements for the slurry wall installation locations the diaphragm
were quite stringent and it took a lot of walls have been
finesse to install the slurry wall panels. completed and the shafts
The size and verticality requirements were are ready for excavation.
a challenge, says Zernich. But in the end,
using sophisticated slurry wall technology, Current activity Top left: The projects EPBM is christened in early April
Bencor was able to deliver a world class shaft With TBM assembly now Above: A reinforcement cage is lowered at the DS Shaft
to the client. under way, the JV is
The shafts are now at elevation for the TBM currently preparing for
launch, but once this has taken place the DS the machines launch in mid-June. Were pressure analysis are fairly conservative, says
shaft will be taken down a further 40ft (12m), going to place the shields in the shaft in Ellis. So apart from sensitive structures, such
before the casting of its 23ft (7m) thick May, says Zernich. Weve got several as an 118in high-pressure water main where
dome-shaped base slab takes place. components assembled in the DS Shaft and we will be using full pressures and 24hr
Technically, weve gotten right to the level we are lining the concrete collar of the smaller working, TSJD will be optimizing pressures to
where the shafts are beginning to hold back SS Shaft. Weve got some advantages, minimize any potential ground losses.
some fairly significant loads, however we especially with having such a large shaft. Looking ahead, other program contract
anticipate the diaphragm walls to continue Were able to assemble the machine in an interfaces are a challenge, says Zernich.
performing well for the remainder of the advanced state with four of the gantries in There are several milestone dates on this
excavation, says Castro. line for the launch. Then well have an project, and DC Water has a pretty aggressive
The other tunnel shafts all use the same umbilical feed from gantry five and be able to schedule.
diaphragm wall shaft technique, with the install the decks in order as we launch. We One such interface is the southerly extent
exception that these will be excavated in the will be mining with trains out of the DS Shaft the Anacostia River Tunnel the construction
until were in a sufficient distance, then well of which is due to be awarded next month
stop and re-configure to muck out of the SS where it connects to the Blue Plains Tunnel at
Shaft, and continue excavation of the DS Poplar Point, east of the Anacostia River, with
Shaft to its full depth and cast the base slab. this shaft becoming the reception shaft for
Approximately 9,000ft (2,743m) of the the Anacostia TBM.
tunnels alignment passes below the Potomac There is a very positive vibe on the project
and Anacostia rivers. Running more then however, says Castro. Its running at a very
100ft (30m) below the surface, the alignment fast pace and, as its the first project in the
extends from the Blue Plains Treatment Plant program, DC Water really wants to make sure
along the east bank of the Potomac, adjacent that it makes schedule. So the concentration
to the JBAB joint naval support and air force is all just on getting the job built rather than
base, and then under the Anacostia River to arguing over minor issues. Its a good project
terminate at a reception shaft at DC Water's and its a good program, all the participants
main pumping station. are working well together to achieve the
The volume losses weve used for face projects schedule and quality goals.

NORTH AMERICAN TUNNELING JOURNAL 11


NATJ_0513_BLUEPLAINS_010_012.qxd:Feature 21/4/13 19:35 Page 12

WASHINGTON DC

Blue Plains design features


By Martin Ellis, Design Manager for the Blue Plains Tunnel

The design of the tunnel and shaft the thickness of concrete pours and the will be exposed to sewage effluent.
structures on DC Waters Blue Plains amount of steel reinforcement. Specific durability requirements and
project was performed by Halcrow, now Three other shaft structures utilized careful specification of concrete was
a CH2M Hill company, lead designer for the same diaphragm wall and CIP lining developed to ensure a quality product
the Traylor/Skanska/Jay-Dee JV. A arrangements. These 50ft (15m) and minimize vulnerability to attack by
number of innovative design-build diameter chemicals in the effluent.
solutions were developed for the The lining design incorporates
project including the figure of bolted and doweled joints with cast
eight double shaft and the use of in gaskets and guide rods to assist
steel fiber reinforced segments in ring build. A significant part of the
a one pass lining system for the design challenge was to
tunnel. Halcrow also adopted a accommodate the loading scenario
phased risk based approach to the with larger internal pressures than
assessment of ground movements active ground loading, which
on existing structures and utilities, required a detailed understanding
culminating in detailed numerical of the ground and structure
analysis for at risk structures. From interaction.
this analysis a range of mitigation Ground movements associated
measures were developed to protect with excavation of the tunnels
the integrity of these assets. and shafts were assessed for the
At the Blue Plains Advanced Waste whole of the alignment and a
Water Treatment Plant (BPAWWTP) site comprehensive instrumentation
the Dewatering and Screening shafts scheme designed to monitor the
were designed as a figure of eight works. The shaft sites proved to
structure with the 132ft (40m) and 70ft be the most challenging, due to
(21m) diameter shafts touching each the presence of existing DC
other and sharing a common wall. The Water and third party
diaphragm walls were designed for both infrastructures. Whilst the
temporary and permanent conditions - circular diaphragm wall
the full temporary condition and then method of shaft construction
combined with the cast in place lining to has proven to result in
support the long-term loading. extremely small amounts of
These long-term loads on the shaft ground movement, the
walls were owner specified and assessment of potential
equivalent to the in-situ over- impacts considered the risk of larger
consolidated lateral stresses where shafts were not movements more commonly associated
Ko=1.4 in the Potomac group Clays. de-watered during construction with propped box type excavations.
Other design challenges included and were designed to be excavated in 3D Plaxis models were developed to
meeting the 100-year durability the wet, with tremie base slabs capable fully understand the interaction
requirements for the shaft walls (i.e. the of resisting ground uplift pressures as between existing structures and the
combined diaphragm walls and cast-in- well as potential net downward ground. At the Main Pumping Station
place liner) and dealing with panel pressures associated with the tunnel shaft site, a suite of protection measures
eccentricities associated with tolerance flooding loading scenarios. A radial was developed to mitigate the potential
limits for verticality. arrangement of the reinforcing steel was risks associated with both ground
The verticality tolerance was developed to reduce the quantities used. excavation movements and of the
necessarily very stringent but did prove The tunnel lining has been designed as construction work itself. Numerous
to be achievable. Bearing stresses a 23ft (7m) internal diameter, 14in existing structures were affected with
between panels at the base of the (355mm) thick, precast concrete nine potentially at risk, including 100-
excavation were at the limit for the 5ft segmental lining. It has been configured year old brick lined sewers and timber
(1.5m) thick diaphragm wall panels. 3D with up and down rings in a 6+1 piled underground chambers. Measures
Plaxis analysis was used to confirm the trapezoid-parallelogram segment included installation of steel sets within
distribution of stresses in the complex arrangement to minimize the number of an existing 23 wide outfall sewer tunnel
figure of eight arrangement and also to segments while avoiding any cross joints and soil mixing to stabilize the ground
confirm the acceptability of various and meeting the tight radius criteria of adjacent to shallow sewers prior to the
construction scenarios where excavation the alignment. Steel fiber reinforced excavation of the diaphragm wall
in the two parts of the shaft may not be concrete offers significant cost savings panels. A work site protection slab was
synchronous. The base slabs for the during segment manufacture and gives also required to distribute loads for
double shaft structure were designed as durability advantages over conventional cranes used to install the diaphragm wall
domed shaped arch slabs to minimize steel bars in the one-pass lining, which and for the removal of the TBM.

12 NORTH AMERICAN TUNNELING JOURNAL


Together, Delivering Unparalleled Tunneling Expertise

Strategic Tunnel Enhancement Program,


Abu Dhabi, UAE

University Link, Sound Transit, Seattle, WA Blue Plains Tunnel, DC Water, Washington, DC

CH2M HILL and Halcrow CH2M HILL and Halcrow provide state-of-the-art tunnel expertise that has been
were honored in six
established over a century of understanding and managing the risks associated
categories at the 2012
New Civil Engineer with the development of underground infrastructure.
Tunneling Awards:
T unneling Contractor The combining of these two great companies allows both to leverage best-in-class
of the Year planning, design, program management and construction management skills on the
P roduct/Equipment worlds most complex tunnel projects.
Innovation of the Year
Whatever your tunneling challenges water, rail, transit, highways or utility; soft
T unneling Project
of the Year ground, hard rock or immersed tube; major urban tunneling or underground space
Environmental Initiative development youve discovered the best team in the world.
of the Year
Safety Initiative of the Year For more information, visit ch2mhill.com

2013 CH2M HILL TBG041713052534DEN


NATJ_0513_BICOUNTY_014_019.qxd:Feature 21/4/13 21:42 Page 14

MARYLAND

James Grissom,
Project Manager
for Southland
Contracting,
discusses the
challenges met
during the
construction of
the Washington
Suburban Sanitary
Commissions
(WSSC) Bi-County
Water Tunnel
project, located
in the Maryland
suburbs
immediately north
of Washington DC

Boring for WSSCs


Bi-County Tunnel

14 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_BICOUNTY_014_019.qxd:Feature 21/4/13 21:43 Page 15

Tuckerman n Shaft
Sha t
MARYLAND
(S1) (Start po
point) 355 185
LOCATED IN THE Maryland suburbs, (84m) below surface. The project also
Exis
Existing water
w main
m
immediately north of Washington DC, includes three shafts, one work shaft
the Washington Suburban Sanitary Stoneybro
Stoneybrook
Stoney ook sh
shaft and two end shafts (Figure 1).
(S4) (End
E point)
(E
Commission's (WSSC) 5.3-mile (8.5km) Due to the limited access, a 35ft
long Bi-County Water Tunnel is currently 495 (10.6m) diameter, 165ft (50m) deep
under construction by a joint venture of shaft at Connecticut Avenue was
Conn t Avenue
Connecticut ve
Oscar Renda Contracting, Southland identified as the only place from which a
Contracting and SAK (RSS JV). TBM could be launched and removed.
Mining is currently 98% complete, with The two smaller shafts would be
approximately 590ft (180m) of tunnel constructed at either end of the tunnel,
excavation remaining along the western end at Tuckerman Lane (west) and
of the alignment. Challenges during Stoneybrook Drive (east).
construction included high water inflows at Tunneling was selected from a range
355
one of the shaft locations, areas of poor 97 of horizontal alignment alternatives as
rock quality, and a major TBM Montgomery well as open cut and deeper tunneled
Rockville 95
County
breakdown. Wheaton profiles. Decision-analysis software was
270 used by WSSC and the design team in a
185 Laurel
Project background From the workshop format to select a tunnel
Potomac Bowie
Conceived more than 20 years ago, the Bi- alignment that was favorable in light of
County Water Tunnel will increase supplies of To Prince several factors, including cost, impact to
Georges 495 Upper
clean drinking water to eastern areas of two County Marlboro
the environment, traffic, and the local
counties in Maryland and also Washington Right: Map of the 95 residents. An extensive public outreach
DC. The increased water supply will alleviate Bi-County tunnel campaign proceeded during the early
current capacity limitations from an existing alignment Prince Georges design phase to present the factors
County
4.5ft (1.37m) diameter water main. The tunnel being considered and this campaign was
will also serve as an additional high-pressure Below: A section successful in gaining the consent and
water source during peak-use periods, of steel carrier trust of local residents. The public
droughts, and emergencies. pipe is lowered outreach continued through detailed
Plans for the Bi-County Water Tunnel were
drawn from a long-term water supply project
in the area, which dates back to the 1970s.
Original water tunnels of the same name were
built in 1980 to 1981, using Jarva Kelly-type
TBMs to bore 10ft (3m) diameter tunnels.
These tunnels were built in rock and lined with
shotcrete. Due to leakage rates and rock
competency issues discovered during testing,
the tunnels were not placed into service until
they were lined with a 7.8ft (2.4m) steel pipe
in the early 1990's.
These original tunnels, bored through
quartz, gneiss, schist, and granite, have
provided good capacity in recent decades.
However, the 4.5ft (1.37m) diameter water
main has continued to act as a bottleneck.
Without additional capacity, water pressures
are soon predicted to fall below 2 bar, which
would affect firefighting and emergency
capabilities. To prevent these problems, the
next phase of the plan called for a final tunnel
to tie the two systems together, providing
reliable water supply from the Potomac River
to WSSC customers in Montgomery and
Prince George's Counties.
WSSC hired Black & Veatch to design the
tunnel and its valve vault structures. A joint
venture of Jacobs Associates and Louis Berger
Water Services is providing construction
management services.

Tunnel design
The 5.3-mile (8.5km), 10ft (3m) diameter Bi-
County Water Tunnel route follows the I-270
and I-495 ring roads around Washington DC.
Much of the area is urban and residential,
resulting in limited access and a deep tunnel
alignment between 90ft (27m) and 275ft

NORTH AMERICAN TUNNELING JOURNAL 15


NATJ_0513_BICOUNTY_014_019.qxd:Feature 21/4/13 21:43 Page 16

MARYLAND

Right: Excavation of the drill and blast starter and tail tunnels at the main Connecticut
Avenue S-3 shaft site; Below: The S-3 Shaft utilized liner plate and ring steel in the soil
layer, and rock bolts and shotcrete in the rock layer; Bottom: 72in (1.8m) diameter pipe
installation at the S-4 Stoneybrook Shaft site

design and has been a feature of the


construction. Blasting and extensive truck
traffic movement in an area that is already
subject to heavy traffic has been carried out
without any complaints.
Ground investigation was performed along
the tunnel alignment prior to excavation, with
21 core samples taken from both vertical and
inclined positions. Based on the designers
interpretation of the core samples, three
temporary rock support classes were specified.
These ranged from rock bolts in good quality
Class I ground; to rock bolts, steel channels
and welded wire mesh in Class III ground. The
final liner consists of welded steel carrier pipe
with a protective mortar lining.
The project includes pipeline tie-ins at each
end of the tunnel with valve vault structures.
There is also open cut piping, cathodic
protection and monitoring to be installed.
While lump sum payment was used for
many well-defined components of the project,
such as shafts and the valve chambers, the
main tunnel temporary support was proposed

16 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_BICOUNTY_014_019.qxd:Feature 21/4/13 21:43 Page 17

MARYLAND

make its first push into the hard rock.


The TBM used on the project is one of the
longest-running machines on record. The 10ft
(3m) diameter The Robbins Main Beam TBM
was originally purchased by Affholder, and has
been used on at least ten different projects
between 1973 and 2011; excavating in excess
of 30-miles (48km) of tunnel. For this project,
the machine required more power. Therefore,
SAK installed four new 300hp motors, new
variable frequency drives, PLCs (programmable
logic controllers) and a new lube system at its
Saint Louis facility. The machine was then sent
as unit price payment items for the different to site and assembled with the trailing gear in
classes of rock support. Any variation in the shaft for the eastern reach of tunneling.
support class distribution or amount would be The TBM was launched in July 2010. Due to
covered by the unit prices. This approach has a mechanical issue with one of the drive
worked well for WSSC, with more than motors, the tunnel was excavated with only
anticipated good rock resulting in a slight three drive motors. However, RSS JV
reduction in the overall price for the tunnel. experienced little impact to the schedule and
excavation was completed in November 2010,
Construction works when the TBM made its first hole through at
In August 2009, WSSC awarded the S-4 after finishing the 4,102ft (1.25km) drive.
construction contract for the Bi-County Tunnel Ground support consisted of rock bolts,
to a joint venture of Oscar Renda Contracting, with steel straps and wire mesh being added
Southland Contracting and SAK (RSS JV). The Top: Ventilation line and switch in the in less competent ground. At times, the
winning bid was $113 million, 13% less than starter tunnel at the S-3 Shaft granite was inlaid with quartz and iron pyrite,
the engineer's estimate. and this very abrasive dense material hindered
The main working shaft at Connecticut Above and below: Miss Colleen is one progress. Despite the challenges however,
Avenue S-3 site and the end shaft at of the longest-running machines on average advance rates of 40ft (12m) per 10-
Stoneybrook Drive S-4 site were excavated and record. The 10ft (3m) diameter Robbins hour shift were achieved.
the ground supported using ring steel and Main Beam TBM was originally purchased Once the TBM broke through into the S-4
liner plate in the area of soil and transition. The by Affholder, and has been used on at shaft, RSS JV began operations to remove the
rock zone was then excavated by drill and least ten different projects between 1973 TBMs cutterhead and lift it out of the
blast, installing rock bolts and shotcrete to and 2011; excavating in excess of 30-miles Stoneybrook shaft. The rest of the machine
stabilize the ground as the excavation (48km) of tunnel was then backed out of the tunnel, using the
continued. Excavation of the S-3 shaft started grippers and a specially built frame to make
in September 2009 and was completed in the trailing gear rigid. Once the TBM was back
March 2010. Excavation of the S-4 shaft at the main Connecticut Avenue work shaft,
started in January 2010 and was completed in its components were turned 180 degrees and
October 2010.
Localized dewatering well systems were
installed prior to each of the shafts being
excavated to address potential groundwater
issues due to high groundwater tables at the
S-4 and S-1 shaft sites. It was during the
installation of the de-watering wells at the
Tuckerman S-1 shaft site that RSS JV
determined that water inflows were greater
than expected. A Differing Subsurface
Condition was negotiated and a secant pile
ring wall was installed to prevent groundwater
from affecting the shaft excavation progress.
These secant piles were completed in April
2011 and the shaft was excavated using drill
and blast until its completion in November
2011. The secant pile wall did prove to cut off
the water and with minimal increase to the
overall project costs.
After the completion of the main S-3 work
shaft, RSS JV commenced working on the
starter/launch tunnels for the TBM. The 200ft
(60m) long starter and tail tunnels were
excavated to a diameter of 12ft (3.6m). A
concrete working slab was poured in the invert
of the shaft and the starter tunnels, along with
concrete walls for the TBM to grip against and

NORTH AMERICAN TUNNELING JOURNAL 17


NATJ_0513_BICOUNTY_014_019.qxd:Feature 21/4/13 21:44 Page 18

MARYLAND

pieced back together. Turning the pieces benefit of assisting the tunnel
around, particularly larger bolted-together ventilation particularly when
components, required some maneuvering with mining the western reach.
a crane in the 35ft (10.6m) wide shaft. Cutter wear was higher than
Rebuilding of worn sections of the cutterhead, expected and was significant
including the addition of hardened steel, was given the acceptable tolerances.
also done prior to re-Iaunch. This entire The lifting buckets were showing
process took approximately two months. significant wear due the abrasive
qualities of the rock being mined.
TBM woes and refurbishment While excavation of the
The TBM was re-Iaunched in February 2011. western reach continued,
However, after tunneling for a month, a installation of the 84in (2.1m)
metallurgy failure of a pinion gear caused diameter carrier pipe was being
major damage to TBM drive components that installed in the eastern reach of
included the bull gear. The damage was the tunnel using a hydraulic pipe
extensive and the TBM had to be removed carrier. Each joint had to be
from the tunnel, and the damaged welded to the previous pipe. At
components were shipped to the Robbins every step of the process,
Company factory in Ohio. Repairs to the TBM inspections had to be
as well as some gearbox and motor performed. After all the steel
modifications caused a four-month delay to carrier pipe had been placed, the
the project, however WSSC agreed that this annulus between the pipe and
was beyond the control of RSS JV. the tunnel was grouted.
The TBM was once again re-Iaunched on The grouting was done in
the western drive in July 2011. During multiple lifts, by RSS JV and its
excavation of the western drive RSS JV subcontractor, to minimize any
encountered a few areas of blocky, highly floatation that would be placed
unstable, ground. The ground in these areas on the pipe. RSS JV used a 70%
had to be mined by hand to prevent damage cement and 30% fly ash grout
to the TBM and its conveyors. Top: The SAK-owned Robbins main beam TBM is mix, which was chosen for the
These areas also typically had increased lowered into the S-3 Shaft; Above: the S-3 Shaft at lack of shrinkage shown in
groundwater inflows due to the ground night; Below: View of the S-4 Stoneybrook Shaft after testing prior to placement of the
conditions. At some locations where the an annulus grout pour grout. Close attention was paid
unstable ground was encountered flows to the each lift.
observed were as high as 150gpm and
resulted in steady state flows that were still any reoccurrences. These areas were Current progress
within acceptable criteria. The first area negotiated using a modified class of support When tunneling of the western reach is
encountered in the western reach was and was priced as an equitable adjustment to completed (due as NATJ was about to go to
approximately 40ft (12m) long and resulted in the contract. press), the same method of pipe placement
a large void over and in front of the TBM. During excavation of the tunnel, four welding and annulus grouting will be used
RSS JV evaluated the ground conditions and cathodic monitoring shafts had to be drilled throughout the western reach of the tunnel.
recommended the installation of steel ring sets into the tunnel excavation. In the long term Overall the unit price approach has stood up
to support the ground as crews moved slowly they will be used to monitor the tunnel liner very well during construction and water
through the unstable areas. Extra sets were and the corrosion of the pipe over time, but inflows have been well within the advertised
ordered and stored at the site to be ready for during construction have provided the added baseline amounts. That coupled with the lack
of negative impact to the surrounding
neighborhoods means that, despite the
numerous challenges encountered during
tunnel construction, this has been a highly
successful project so far for WSSC.
RSS JV approached this project like others in
the past and worked with the project team to
maintain open communication. When
problems came up, RSS JV took a proactive
approach to move forward instead of waiting
sometimes for decisions to go through the
usual channels, which can result in delays and
additional costs to the project. Sometimes risks
were taken and RSS was not always sure if it
would recover those risks financially, but the JV
moved forward with good faith, working
with its partners in coming to meet the various
challenges. This cooperation between partners
has kept this project fluid.
Project completion is currently anticipated in
Spring 2014 with tunneling due for
completion at the end of April 2013.

18 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_BICOUNTY_014_019.qxd:Feature 21/4/13 21:44 Page 19

DIFFICULT ACCESS GEOTECH DRILLING.

Booth 610
www.cruxsub.com/RETC

CDM Smith is a Proud Sponsor


of the 2013 RETC Conference

cdmsmith.com
Offices worldwide

NORTH AMERICAN TUNNELING JOURNAL 19


NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:33 Page 20

GRAND
CENTRAL
LEGACY
BELOW NEW YORKS iconic Grand
Central Terminal the backdrop for many
a film scene two different, but equally
impressive, underground spaces have
been created. While commuters and
visitors have continued unhindered on
their journeys at ground level, contractor
New Yorks East Side Access project will provide Dragados-Judlau JV, working for the
Metropolitan Transportation Authoritys
the citys first new major railway terminal in over Capital Construction Company (MTACC)
has been carving out two vast caverns,
a hundred years. As the huge platform caverns each around 52ft (16m) wide, by 61ft
carved from the rock beneath the citys iconic (19m) high, and 1,200ft (370m) long.
The caverns are important elements of
Grand Central Terminal near completion, NATJs the complex megaproject that is East
Side Access, now with an estimated price
Kristina Smith looks at the story of their creation tag of $8.24 billion. Designed by a tri-

20 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:33 Page 21

NEW YORK

Opposite and above: The caverns that will


house the future LIRR concourse.
Left: One of the hard rock running tunnels
(All photos: MTA/Patrick Cashin)

venture of Parsons Brinckerhoff, STV and


Parsons Transportation, excavation works
for the East Side Access project are now
complete and the route has been formed
to carry Long Island Rail Road (LIRR) trains
underground from the Sunnyside Rail
Yard, in Queens, to a brand new terminus
under Grand Central Terminal, in
Manhattan (see Figure 1, p25).
LIRR trains currently share Penn Station
with two other rail companies, Amtrak
and New Jersey Transit. Penn Station,
built in the late 1800s to serve a through-
train service is hugely congested; and
with half of LIRRs passengers destined
for the East Side of Manhattan, it makes
perfect sense for the railroad to have a
new terminal there.
Each cavern will house four platforms
on two levels, with a mezzanine level for
pedestrian access sandwiched between.
Passengers will travel to and from the
platforms via a vast underground
concourse, the contract for which has yet
to be let.

NORTH AMERICAN TUNNELING JOURNAL 21


NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:33 Page 22

NEW YORK

The most expensive tunnel ever?


Schiavone/Kiewit would excavate the Northern Boulevard
crossing at the opposite end was not finished, due to the fact
that the contract to construct it had been defaulted.
At Granite/Traylor/Frontier Kemper s end of the Q-tip shaped
box, the area was full of soil and also despite slurry walls
having been installed full of water. Although bracing was in
place, Schiavone/Kiewits access area at
Left: Underpinning the western end of the box, looked more
of the Northern like a swimming pool.
Boulevard The ultimate solution to the leaking
Right: Final lining slurry walls was a jet grouting program
of the crossing conducted at the interface between the
slurry walls and the rock, creating jet
grout columns between 15ft and 25ft high. Using panel records
At $1 million per linear foot, the section of tunnel that passes as guidance, GTF JV oversaw the grouting of all areas where
under the Northern Boulevard, on the Queens side of the East there was any concern. There were doubts from some quarters
Side Access project, may be the most expensive tunnel ever whether this approach would be effective, says Thompson, but
built. In a project with several demanding underground it was. Though the entire length of the 2,500 linear feet of
contracts, this short 125ft (38m) section of SEM tunnel has the slurry wall wasnt grouted, the ultimate cost was $17 million.
accolade of being the most technically challenging. Once the leaks had been fixed, Schiavone/Kiewit installed
Providing the final link between Dragados-Judlaus open-cut temporary underpinning for the elevated transit line and
shaft at the Queens end of the existing 63rd Street tunnel, and drilled grout holes to fill voids below the subway structure;
the vast 760ft (230m) long open-cut TBM launch box for the 58,000 gallons of grout was pumped in. As well as the ground
four new soft ground tunnels under the Sunnyside Rail Yard, freezing holes, heat pipes also had to be installed around the
this short section of tunnel passes through glacial deposits with
a very high water table. It also passes beneath a triple-level
transit corridor, consisting of a five-track subway, a major Figure 1a: Northern Boulevard construction sequence
surface-level highway, and elevated rail tracks (see Figure 1a).
Joint venture contractor Schiavone-Kiewit won contract Elevated BMT Subway (N, W lines)
CQ039 to construct the Northern Boulevard crossing. A
number of options were considered, and a number of N. Blv. Roadway
consultants were consulted, says Andy Thompson of Hatch 13
Mott MacDonald, Senior Program Manager for MTACCs

IND Subway
(E, V lines)
Construction Management team. But the answer came back Existing IND
the same each time: ground freezing an arch above the crown 20
Subway invert
of the oval-shaped tunnel was the only feasible option.
Lowering the groundwater through dewatering wasnt
Ground
possible due to the polluted water bodies in the area that cant freezing arch
be disturbed. Vertical drilling from the surface or from the 3
Drift
subway structure also wasnt logistically possible. Final liner 1 2 Temporary
Drift Drift shotcrete
This is an unusual application for ground freezing: You 6
55
wouldnt normally horizontally freeze a partial arch, drilling 4 Drift 5
Drift Drift Top of rock
125ft-long holes in that kind of ground, says Thompson.
Schiavone-Kiewit started on the back foot. The large open-
cut slurry wall box from which Granite/Traylor/Frontier
Kemper (GTF) JV would launch its Herrenknecht Slurry shields
80
eastwards under the rail yard (see NATJ, April/May 2012), and

[Continued from p21] Dragados-Judlaus which also won the contract to construct four The only evidence of what lies beneath are
contract has suffered from delays. However, hard rock TBM running tunnels (totaling the construction sites for the four ventilation
construction of the caverns can be counted as 25,100ft (7.65km) in length) through buildings, shoehorned into very compact sites.
a success for Manhattans commuters and Manhattan Schist, had to bring everything in City residents have only been troubled by the
visitors, who have suffered no disruption to and out from Queens via the existing 63rd trucks servicing these areas. However, even
Grand Central Terminal or its trains. The last of Street East River immersed tube tunnel. these limited disruptions have been noted.
the 2,500 structural blasts required to create The problem with East Side Access is that We drilled holes into the tunnels and
the caverns was carried out in early March, all the tunneling work has been mobilized out caverns and fed concrete in from the surface
with construction methods reducing the of Queens, so you have an extremely long though pipes, which has proven to be a
number of planned blasts by more than half. supply line, says Andy Thompson of Hatch challenge, says Thompson. We have to
The cloistered nature of the caverns Mott MacDonald, Senior Program Manager coordinate with the DoT for street closures.
construction is one of the factors that has for MTACCs Construction Management And building owners are not very happy when
made underground construction on this side team. There are no reception or drive shafts a concrete truck is parked outside their
of the river so challenging. Dragados-Judlau, in Manhattan. building for three years.

22 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:33 Page 23

ever?
PHOTO COURTESY OF MORETRENCH

top of the arch. These were to control the outward spread


of the freeze and limit heave. The ground at the crossing
includes bulls liver soils, which are rapidly dilatant silts in
which ice lenses can form, causing vertical heave. The
preparation work took around two years, four times longer
than the tunneling, says Thompson. The tunneling itself
took five months, with two months to install the final liner.
Schiavone/Kiewit constructed the tunnel using sequential
excavation methods (SEM). Throughout all the operations
the structures were carefully monitored for movement,
using automated total stations and prisms in the subway
box and manual survey readings on the elevated structures.
Groundwater levels were also closely monitored.
We were most worried about the box structure
moving, says Thompson. The elevated structure will be
supported off the tunnel lining: so the tunnel becomes the
foundation for the elevated subway. Soil extraction holes
had also been drilled, so that if the box structure suffered
from heave, soil could be removed from directly underneath
it. However these were not required as the subway moved Above: Workers carry
upwards by just 1.25in (32mm). out inspections in
Now that the groundfreeze which was conducted by one of the East Side
specialist sub-contractor Moretrench has been taken off, Access hard rock
the soil extraction holes can be used for compensation running tunnels
grouting if required. It will take a year for the freeze to
dissipate, but in the mean time, Thompson classifies the Right: Concreting
tunnel as a qualified success. We have contingency plans works underway in
in place to deal with any movement, he says. one of the caverns
With the completion of the tunneling works beneath the
Northern Boulevard, the entire length of the East Side Below: An Atlas
Access tunnels are now in place. We can now go from 43rd Copco Boomer E2C is
Street in Queens to 38th Street in Manhattan entirely used to drill 1.5in
underground, says Thompson. diameter holes into
Though tunneling and cavern construction is now the mica-inflected
complete, East Side Access still has plenty of technical granite Schist that
challenges ahead. Not least of these will be rebuilding the forms the bedrock of
Harold Interlocking, with its 800 trains a day. Midtown Manhattan

Only one bidder


Dragados-Judlau was awarded Contract
CM019 at a price of $734 million to construct
the two caverns, complete the Manhattan
hard rock running tunnels, together with
excavation of the tunnel wyes that lead into
the caverns, cross-passages, escalator shafts
and vertical shafts, in February 2008. The JV
was the only bidder for the negotiated
contract. The main reason for this was that
Dragados-Judlau had already won contract
CM009, back in 2006, to construct the
running tunnels on the Manhattan side of the
East River. Running from the end of 63rd
7-Line Tail Tunnel, Manhattan, NY:
Limited Cover Ground Freezing

Dewatering &
Groundwater Control

Ground Freezing

Earth Retention & Anchors

Deep Foundations

Underpinning Systems

Grouting &
Ground Improvement

Environmental Remediation

Industrial Construction Northern Blvd. NATM Crossing


Queens, NY: Jet Grouting

www.moretrench.com
Geotechnical Construction Coast to Coast 800-394-MORE
NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:32 Page 25

NEW YORK

used by New York City Transit for the F line


and the lower levels reserved for the future
East Side Access project. Had designers
started from scratch, they may not have
chosen that crossing point today. Back in the
1960s, the East Side Access project looked
quite different, says Thompson.
Having the same contractor working on
both the cavern and rock tunnel contracts
made sense for the construction of the
caverns. It meant that four running tunnels
could be cut through each cavern and then
enlarged to create the caverns, one of the
factors that contributed to halving the
number of planned production blasts.
Having tunnelled through the rock in the
cavern locations, designers were also able to
modify the initial support based on more
detailed knowledge of the rock. Steel ribs
were eliminated and the size and spacing of
rock bolts were also adjusted.
Above: Lining of an escalator shaft that Large explosions became a sensitive subject
will connect the LIRR concourse to the in New York following 9/11, which occurred
main level of the terminal; Left: Escalator during the design phase for East Side Access.
pits in the base of one of the caverns; Metro North Railroad (MNR), which operates
Below left: Drill holes are loaded with Grand Central Terminal, was also concerned
Emulex explosives; Below right: Rockbolt that its 100-year-old building might suffer
support in an unlined rock running tunnel damage due to ground bourne vibrations
caused by the blasts, disrupting train services.
Street to the caverns, the cost of constructing The East Side Access team employed
the 38,000 linear feet of hard rock tunnels vibration experts to verify that the historic
was then $428 million. Access was always terminal would be unscathed. When the first
going to be an issue, says Thompson. blast in was made on March 7th, 2008, there
Whoever controlled the Queens access, was still some trepidation from Metro North,
controlled the price of the cavern contract. with 20 representatives standing by to witness
800,000 cubic yards of rock had to come out the event. Six years to the day later, on March
of the tunnels and travel by conveyor to 7th, 2013, as the last production blast took
Queens where it was stockpiled and then place, all fear of damage or disruption to the
moved out by truck. Timing was another terminal had evaporated.
factor, says Thompson: in late 2007 the Face drilling was carried out using four Atlas
market was much more buoyant than it is Copco E2C Face Drills and two L2C Boomers.
now, with few tunneling contractors able to Both types of rig utilize Atlas Copcos
take on such a large contract. computerized rig and boom control systems,
The river crossing from Queens to providing increased drilling accuracy. This
Manhattan already existed. Back in the 1960s, resulted in less overbreak, and as a result less
the 63rd Street immersed tube tunnel was backfill concrete, in the caverns.
built as a bi-level structure with the upper level However, due to the strict permissions and
NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:32 Page 26

Figure 1: Map showing the alignment New Yorks East Side Access project

AK
Blvd
29th Ave
Clockwise from top: Supply trains travel in

TR
hern
Metro-North

Nort

AM
Railroad

N
from Queens to support excavation; One LIRR
Central Port gton
of the running tunnel wyes; Inspection of Park hin
Wasranch
. .) B
the Schist; View into one of the caverns
8,600ft 0ft ft
(17,200 Linear Ft.) 5,50 inear Yard
(11,200 L id
e
63rd Street Tunnel ys
63rd St nn
41st Ave Su
checks required for blasting, each blast took Blvd
g

ens
in

Que
ck
(31,300 Linear Ft.)

rlo

time. The sequence of events was: Get Queensborough Bridge


te

Mid-Day
In
lt Island

Storage Yard
ol

permission once the shots were wired up;


7,200ft.

ar
H
vd

QUEENS
Bl

complete the blast; inspect the blast influence


Rooseve

53rd St
rn
e
rth

Arch Street Yard


zone in the train shed; then clear the trains.
No

50th St
& Shop Facility
ss way
That meant we tried to do the excavation in MANHATTAN Long
Island
Expre
Grand
other ways, said Thompson. Central
495
495
42nd St Terminal LIR
Dragados-Judlaus solution was to employ Queens-
Midto R
Tunnel wn Mo
Sandvik roadheaders. Though Manhattan 38th St n ta
uk Branch
Penn
Schist is relatively hard, at 14,000psi (97MPa) Station
Lexington Ave

East
Madison Ave

and at the upper end of the roadheaders BROOKLYN


Park Ave

2nd Ave
3rd Ave
8th Ave

7th Ave

6th Ave

5th Ave

capability, the method worked well, says


R

Existing LIRR Tunnel Structure (17,200 LF)


ive

Thompson. The contractor first tried out


r

Manhattan - 8 Tunnels Excavated (31,300 LF)


roadheaders in 2009. The first of its two rock Queens - 4 Tunnels Excavated (11,200 LF)
TBMs, a refurbished Robbins Main-Beam,
having completed its first run, had been
pulled back to the point where the tunnel drives into four spilt-level bores through the
splits into two. Blasting the wye at that point caverns used an alternative method, which
(directly beneath newly installed MNR signal prevented the need for either blasting or
equipment) was proving lengthy and roadheader excavation. Using a method
problematic, due to concerns regarding the remembered from the Chicago TARP project,
effects of vibration on the equipment, so Dragados-Judlau backfilled the tunnels with
Dragados-Judlau decided to try the concrete so that the TBMs had something to
roadheaders. Though there were issues with grip against as they steered off on a new
the machines sinking into the excavated course to create the wyes.
muck, the operation showed that the In each of the caverns, the roadheaders
roadheaders could cope with the rock. The excavated the side enlargements from the
problem of them vibrating into the muck was upper TBM bores. The central pillars were
solved with plastic mats. blasted and the roadheaders completed the
Subsequent TBM re-launches to split the profile of the top headings. At that point, the

26 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:32 Page 27

NEW YORK

JV put in the permanent concrete arch. This planned to be precast elements. There were the open-cut advance works contract (see
made sense from a safety perspective, and two reasons for this choice: To achieve a box), the Queens tunnels have been a major
reassured Metro North that Grand Central, uniform, high-quality finish and to minimize success for the project, says Thompson.
35ft (10.5m) above, would remain secure. future maintenance. Though short, the four soft ground tunnels,
It was more practical approach, says MTA first put the lining contract, CM12, totaling 10,500ft (3,200m) in length, were
Thompson. These caverns are 60ft (18m) out to tender before its re-negotiations with excavated through mixed face conditions that
high. Think of building formwork 60ft in the Dragados-Judlau, but pulled it back until the included boulders, manmade obstacles, a high
air, thats a major task. This way, we were deal was complete. When the contract was water table, low overburden, and the nation's
doing it from 30ft (9m). It also meant that re-tendered, there were four bids, all of which busiest railroad interlocking overhead.
top heading construction could take place were far higher than MTAs estimates had Control of ground movement was so good,
whilst the lower TBM drives were underway. suggested. Right now we are evaluating our however, that GTF elected to drive one of its

Using roadheaders also reduced the volume packaging options to ensure that we maintain two 22.5ft (6.8m) diameter Mixshield
of primary liner concrete required. Using this our schedule and budget, says Thompson. machines above the watertable almost to the
method meant we got a better profile, with Likely to be split, the new lining packages surface, rather than use the originally
less overbreak and initial support, which will be out to tender soon, says Thompson. intended open-cut TBM recovery method.
meant less backfill concrete, says Thompson. The caverns will remain a hybrid between in- We drove four tunnels underneath the
Once the arches were in place, the contractor situ and precast concrete, with some of the railroad interlocking and caused no settlement
dropped the benches into the tunnels below. less conspicuous locations that had initially and no disruption to the railroad, says
been designed with precast liners, changed to Thompson. We actually brought one of the
End in sight in-situ. It is important that the caverns look drives to within 6ft (1.8m) of the surface, until
By June this year, all excavation work will be good. Together with the 350,000ft2 we couldnt mine any further.
complete. At the time of writing, Dragados- underground concourse a contract which The decision to mine so close to the surface
Judlau still had some minor blasts to carry out, will be let next year these structures convey was taken to minimize disruption and co-
to perfect the profile, and had to finish the the spirit of New Yorks newest terminal. ordination issues for the railroad. The Harold
escalator pits in the floors of the caverns. With Grand Central and Penn, the only Interlocking is the USs busiest interlocking
Though the two caverns will be by far the major stations currently in operation, this will carrying over 800 trains a day. But there was
most impressive of the contractors be New Yorks first new terminal in over 100 so little movement that a switch that was
excavations, they are just part of the story for years. One of the mandates we were given taken out of service for three weeks while a
the Manhattan work. All in all, there have was that this was to be a new gateway to TBM tunnelled below it was put immediately
been 63 separate work headings. The sheer New York, says Thompson. The architects back into service without requiring
size of the works is in itself demanding. want it to look impressive. They are aiming to adjustment. The slurry machines were really
At one time they had almost 1,000 people echo and compliment the various elements of controllable, says Thompson. We had half
working on the job over three shifts, says Grand Central Terminals design. an inch of heave and between quarter- and
Thompson. Thats a lot of people to half-an inch of settlement, which is well
manage. Early reports on the progress of Meanwhile, on the East side... within the railroads operational parameters.
Dragados-Judlaus contracts highlighted that While Dragados-Judlau has battled with the When the travelling public starts to use the
the contractor was unfamiliar with the logistical challenges in Manhattan, tunneling new line in 2019, pushed back from an
practices of New Yorks highly unionized contractors on the Queens side have had their original opening date of this year, they will
workforce. The contractor did fall behind, and own battles to fight. Granite/Traylor/Frontier know nothing of the triumphs of the slurry
this resulted in MTA re-negotiating Dragados- Kemper (GTF) JV has successfully completed drives or the technical engineering feats that
Judlaus package of work, in January 2011, to its CQ031 soft ground tunnels contract, using enabled tunneling under the Northern
remove much of the lining works, while slurry machines for the first time in New York Boulevard. They will, however, at least be able
playing to its strengths by ensuring that all and only the fifth time in the US (see NATJ, to admire the new caverns, which will
excavation works were in its package. April/May 2012, p11). Though the contract ultimately become the centerpiece of this
Around half of the caverns final lining is finished five months late, due to issues with much-anticipated extension of the LIRR.

NORTH AMERICAN TUNNELING JOURNAL 27


RAPID EXCAVATION AND
TUNNELING June 23-26, 2013
CONFERENCE
RAPID
Marriott EXCAVATION
Wardman Park AND
Washington, D.C.
TUNNELING CONFERENCE

The Rapid Excavation and Tunneling Conference (RETC)


is the premier international forum for the exchange and dissemination of developments and advances in
underground construction. RETC provides innovative solutions to the unique challenges associated with
the tunneling industry. Conference attendance exceeds 1,400 professionals from more than 30 countries.
Industry sectors include: construction, mining, geotechnical engineering, exploration, environmental, eco-
nomics, manufacturing, government, land, water/wastewaster, and transportation.

A comprehensive exhibit is held in conjunction with the conference. The exhibit features the industrys
most innovative and experienced producers and suppliers. RETC provides a rare opportunity to meet key
professionals from around the world.

The meeting will also feature field trips, short courses and specialty speakers. The program will cover:
Contracting Practices and Cost Grouting and Ground Modification East Coast Projects
Design and Planning Hard Rock TBMs SEM/NATM
Difficult Ground Large Span Tunnels and Caverns Shafts and Mining
Drill and Blast Microtunneling and Trenchless Tunneling Tunnel Rehabilitation
Environment, Health, and Safety New and Innovative Technologies Water and Gas Control
Future Projects Pressure Face TBM Case Histories International Projects
Geotechnical Considerations Pressure Face TBM Technology Tunneling for Sustainability
Ground Support and Final Lining Risk Management

For more information contact: RETC, www.retc.org, meetings@smenet.org,


303-948-4200, 12999 E Adam Aircraft Cir., Englewood, CO 80112.

RETC_2013_TunnellingJournal.indd 1 12/6/12 11:00 AM


NATJ_0513_COMPANY_NEWS_029.qxd:Feature 21/4/13 18:59 Page 29

www.tunnelingjournal.com - breaking industry news first! COMPANY NEWS

Hayward Baker acquires Geo-Foundations


Hayward Baker has announced that it has acquired Geo-Foundations Among current projects, Geo-Foundations is
Contractors, a Canadian-based specialty geotechnical construction firm. providing micropiles for excavation support as part
Geo-Foundations is now a subsidiary of Hayward Baker Canada, but of the highly visible Union Station rehabilitation
retains the Geo-Foundations name. Todd Edmunds, Founder and leader and expansion initiative in Downtown Toronto.
of the business since 2001, will continue his active association with the Commenting on the acquisition Edmunds said,
enterprise as President of the new subsidiary. This is an exciting opportunity for the Geo team.
Geo-Foundations serves the heavy civil, industrial, commercial, After interacting with Hayward Baker on several JV
institutional and transportation infrastructure sectors of the Canadian projects, it became apparent that both companies Todd Edmunds
construction industry. It specializes in foundation support, ground shared similar values and business focus. The
improvement and ground treatment projects. The firm is also opportunity to become part of an international organization further
recognized for its small-diameter drilling capabilities to create effective enhances our abilities to provide superior engineering and technology
rock and soil anchors, as well as its sophisticated jet grouting skills. services to clients and meet the growing demands of our industry.

Devils Slide earns


Engineering Project
Achievement Award
As part of the National Engineers
Week Awards Banquet, the Devils
Slide Tunnels Project in San Mateo
County, California, has earned an
Engineering Project Achievement
From left: Headland, Younis, Fabian and Yousefzadeh Award from Orange County
Engineering Council. HNTB
Aldea: New partners, projects and office Corporation is lead designer on the
project for the California Department
Aldea Services continues to of design- and engineering management, of Transportation.
expand, adding two new construction-related design, and consultation. Winners of this years awards were
partners to keep up with issues, said Senior VP, Bob Mohamed has managed announced at a ceremony hosted in
the rising demand for Goodfellow. and lead the design for Fullerton, California, on February 22.
specialized services offered Paul Headland joins the major tunneling projects The OCEC event honored the
by the firm. Mohamed Maryland operation as Vice including Dubai Metro, accomplishments, quality and
Younis and Paul Headland President of Geological WSSC Bi-County Water diversity of engineering and related
join Bob Goodfellow and Services and offers over 20 Tunnel, and Kolkata Metro. scientific communities in Southern
Gina Goodfellow in the years of experience in Aldea has also added California.
ownership group. tunneling and mining. Paul two engineers to their To be recognized by the OCEC is a
With vast international is well known in the North staff: recent Colorado tremendous honor for Caltrans,
experience in underground American tunnel industry School of Mines graduate, HNTB and all the firms that have
design, construction and has specialized Guadalupe Monge provided engineering services on
management and risk expertise in microtunneling Fabian, has joined the Devils Slide, said Yung-Nien Wang,
assessment, the firm has and trenchless design and Columbus, OH office; and HNTB project manager and structural
quickly become an construction as well as Roozbeh Yousefzadeh, lead in Southern California.
established force in the ground behavior and P.E., has joined as a The $430 million project represents
underground industry geological characterization structural engineer in the the first road tunnel constructed by
Paul, Mohamed and I for all types of tunnels. new Frederick, MD office. Caltrans in more than 50 years, and
have worked together for Mohamed Younis The newly established when it officially opened to traffic
over 10 years and this becomes Vice President of Frederick, MD office on March 26, the tunnel became the
familiarity along with our Tunnel & Geotechnical provides us with another second longest road tunnels in
complementary strengths Engineering. Mohamed solid base for operations to California. HNTB worked closely with
and experience make us has over 20 years of North support our projects all Caltrans to fully explore alternative
well-suited to helping our American and international over the world, designs and construction methods
clients with a wide range experience in tunnel Goodfellow added. for the twin NATM tunnels (see p5).

New locos prove to be a hit on OSIS


The JV of Kenny and Obayashi took delivery last year of three Mining Equipment flagship
locomotives. The new ME Locomotives weigh 25 metric tonnes and are powered by Cummins
engines that are coupled to powershift transmissions and planetary drive axels. Combined with
wet disc brakes, this results in a low maintenance unit that is in keeping with the Mining
Equipment philosophy make it strong and keep it simple. The project is for the construction
of a 23,317ft (7km) deep rock storm water overflow and relief sewer for the City of Columbus
in Ohio. Mining Equipment says the project and the locomotives are rolling along nicely.

NORTH AMERICAN TUNNELING JOURNAL 29


NATJ_0513_CAT_030_032.qxd:Feature 22/4/13 21:38 Page 30

CAT that gets


the cream
Caterpillar Tunneling is building on the foundation laid
down by the family-run Lovat TBM business. With the
company now fully merged into Caterpillars global
organization, the focus is on manufacturing operations,
improved logistics, and leveraging research and
development resources. Amanda Foley reports
FOLLOWING ITS ACQUISITION of LOVAT in At the time of Caterpillars acquisition in Mining, in Dortmund, Germany. In his new
2008, Caterpillar Tunneling Canada Corps 2008, Richards son, Rick Lovat, then President role Ukens will be responsible for shaping
goal has been to build on the solid foundation and CEO of the business, described the move Caterpillars global underground mining
laid down by the family-run TBM company. as a victory in terms of resources for a strategy. His position at Caterpillar Tunneling
Committed to growing the business through company that needed to double in size[1]. The Canada has now been divided into two
strategic investment, the construction and acquisition would provide customers with the separate roles, with 16-year LOVAT veteran
mining equipment giant has spent millions of benefit of Caterpillars global purchasing Craig Bournes taking up the position of
dollars expanding its manufacturing and re- power and its wealth of experience in large- Director of Sales; and long-term Caterpillar
manufacturing facilities, improving logistics, scale equipment manufacture. marketing and product support specialist, Nick
purchasing state-of-the-art equipment, and The transition was completed in 2009, Natale, assuming the position of Director of
conducting research and development. when Rick officially stepped down in order to Marketing & Product Support.
The Canadian TBM supplier was founded in make way for Dick Cooper, a 40-year The key reason for this move has been the
1972 by tunneling industry icon Richard Lovat, Caterpillar veteran, to take full leadership of strategic expansion of Caterpillars mining
whose passion and dedication for the industry the company. By 2011, the TBM business had operations. Following its $8.8 billion purchase
drove an impressive array of technology been re-branded and fully integrated into of mining equipment giant Bucyrus, in 2011,
innovations. As a pioneer and global leader of Caterpillars global operation. Along with the Caterpillar effectively also acquired an
soft ground TBM technology, LOVAT grew name change, to Caterpillar Tunneling underground mining division. Klaus, with his
into a multi-million dollar company building Canada Corporation, several members of experience here, has gone to head up the our
more than 250 TBMs, and performing over LOVATs senior management team also parted new corporate underground strategy and lead
150 full refurbishments, for more than 700 ways with the company. the integration of the new equipment
tunneling projects worldwide. However, in Most recently, in October 2012, after more portfolio into Caterpillar, explains Natale.
order to keep pace with the ever-increasing than two years as Vice President of Marketing Along with these underground mining
global demand for TBMs, the company and Sales at Caterpillar Tunneling Canada, products which primarily consist of long wall
needed to grow substantially and that would Klaus Ukens has left the tunneling business, and continuous mining equipment comes
require significant capital investment. having accepted a position within Caterpillar access to new conveyor systems technology

30 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_CAT_030_032.qxd:Feature 22/4/13 21:38 Page 31

COMPANY PROFILE

and even the current development of new Clockwise from far left: Holey was the first of four 6.13m (20.1ft) diameter Cat EPBMs to
underground drilling jumbos. Its part of the finish work on Torontos Spadina (TYSSE) Subway extension; Views of the exterior and
wider corporate strategy, to determine how interior of the Manufacturing & Logistics Center; The Cat Tunneling team in the main facility
these equipment portfolios interact and what
resources we can leverage in the future to having a clean shop floor. Most of these
expand our product ranges. explains Natale things are logical, but when theyre put
together they provide a more productive
Manufacturing and logistics facility and a better working environment.
One of the first actions taken by Caterpillar, Caterpillar again expanded its facilities in
back in 2009, was the rental of a new 2011, with the fabrication of a new 15,000ft2
180,000ft2 building about 2.5-miles (4kms) dedicated re-manufacturing facility beside its
from the existing manufacturing plant at main Carlingview plant. This is being used to
Carlingview Drive, near Pearson International refurbish utility sized TBMs up to 5m (16ft) in
Airport, in Toronto. Caterpillar spent millions diameter from minor repairs to complete
of dollars outfitting this Manufacturing & overhauls and upgrades once more freeing
Logistic Centre (MLC) to handle all its light up further space on the main shop floor.
manufacturing operations, warehousing of One of the problems we have is when a
spare parts and equipment, and relocated machine comes back for refurbishment from a
office space. This instantly improved logistics jobsite. We open up the container and can
and freed up a large amount of space on the find contaminated soil and other unwanted
main shop floor to enable expansion. pests, which can be an issue, especially with
Many of the improved logistics here are the Ministry of Environment, says Walter
the result of processes that are pretty standard Trisi, Caterpillars North American Area Sales
at Caterpillar, says Natale. We have the Manager. Now we can lift machines straight
Caterpillar Production System, similar to the off the truck with a new crane that extends
Toyota Way, that looks at how material flows outside the building, and lower them straight
throughout each facility. This includes where into the big wash bay, where the run-off is
everything is placed, how each technicians collected. The same crane then transports the
workstation is set up, even simple things like TBM into the building for refurbishment.

Top left: Two of the


four 3.62m (12ft)
diameter Cat EPBMs
currently at work on
Torontos Southeast
Collector Sewer

Above left: The main


facilitys brand new
Waldrich Coburg
vertical lathe

Left: Machine testing


underway in the
main facility

NORTH AMERICAN TUNNELING JOURNAL 31


NATJ_0513_CAT_030_032.qxd:Feature 22/4/13 21:38 Page 32

COMPANY PROFILE

One of Cats major development goals has


always been to increase its product offering to
encompass larger diameter TBMs. Even
though the company has designed proposed
TBMs of up to 15m (49ft) in diameter, until
recently the biggest machine it could actually
produce in-house was 12m (39ft) in diameter.
Now, with significant equipment investment,
including a newly installed state-of-the-art
automated Waldrich Coburg vertical lathe, a The new dedicated re-manufacturing facility, with its wash bay and crane
Union horizontal milling machine, and a 200t system, located on the grounds of the main facility at Carlingview Drive
crane system, the ability to produce these
larger diameter TBMs is a reality.
In addition, the new machinery also at the time. At the moment we have enough analysis, forensic investigations, machine/soil
facilitates increased production volume. We volume here for the business end of the interactions, virtual product development and
have an old Craven Brothers vertical lathe that TBMs, so it makes more sense to out-source advanced manufacturing improvements.[2]
we use for large diameter milling. But the less complex manufacturing. In particular, the company has done a lot of
previously, whenever we put a large piece on research on proprietary cutting tools, utilizing
there it would create a major bottleneck in the Research & Development Cat Tough Steel, which has been developed to
factory, because it can only take one piece at In addition to substantially improved buying improve the durability of Cats disc cutters.
a time, explains Trisi. Now, with this new power, with a supply chain around the world Weve been working to selectively leverage
that provides improved those Caterpillar differentiators from other
production efficiency and product lines especially in the cutter tool area.
quality, another major Caterpillar Tough Steel is a proprietary
advantage gained since the metallurgy with unique heat treatment
transition to Caterpillar is process, which was originally developed for
access to the vast tractor sprockets. After realizing such an
engineering community improved wear life in the original tractor
within the corporation. application Caterpillar Tunneling started
There is a great fit utilizing the material in disc cutter rings and
between earth moving we are now seeing upwards of 30%
equipment and TBMs, says increased ring wear life.
Glenn Mongillo, The next phase of Caterpillar Tunnelings
Engineering Manager and disc cutter innovation also comes from tractor
Head of Projects, for undercarriage technology. Using track idler
Caterpillar Tunneling technology, the company has developed a
Canada. With this product simplified disc cutter that requires no internal
synergy comes engineering servicing, but does accept replacement rings
Above: TBMs for the City East Cable Tunnel (left), in Sydney, synergy. We have been able to elongate the life of the assembly.
Australia, and the Eglinton Crosstown LRT, in Toronto. to take advantage of a While these disc cutter assemblies are
Below: The Port Mann Tunnel EPBM, destined for Vancouver number of Caterpillar backwards compatible, the heart of the
products in our design, enabling technology lies in the bearing, shafts
including hoses and and Caterpillar proprietary sealing systems.
equipment, weve removed that bottleneck. couplings, Caterpillar steel and generators. It The lower rolling resistance is said to deliver
We can mill parts of up to 8m (26ft) diameter has also enabled us to advance development 40% lower operating temperatures and with
on the Waldrich Coburg and we can still programs involving cutting tools, materials, no internal disassembly during cutter repairs.
produce diameters of up to 12m (39ft) on the software and analysis. With the extensive This translates into faster changes with more
old Craven. For anything bigger than 12m, we facilities at the Caterpillar Technical Center up-time. The new disc cutters continue to
can also mill machined parts on the Union. [the home of Cats Product Development and utilize Tough Steel and are the latest in
In order to increase its production capacity, Global Technology Division], in Peoria, Illinois, Caterpillar Tunnelings pursuits to tap their
Caterpillar has not only invested in tooling, we can conduct advanced metallurgical broader company resources.
but it has also formed a strategic partnership
for its back-up gantry manufacturing. This is
now being done under contract by global
manufacturing solutions provider Valiant.
Theyve got an extremely long facility where
they can fully assemble and test the back-up
systems, says Natale. Its a question of
capacity, what we have going on in our facility

REFERENCES

1. Wallis, S. A powerful partner for pushing


forward, Tunneltalk, April 2008.
2. Wright, J. Behind The Scenes at The
Caterpillar Technical Center, May 2012.
http://www.peoriamagazines.com

32 NORTH AMERICAN TUNNELING JOURNAL


Cutting_Edge_Ad.qxd:Layout 1 5/9/12 23:53 Page 1

cutting edge
November 3-5, 2013
The Westin Seattle,
Seattle, Washington

E ON MEGAPROJECTS
C
2013 CONFEREN

ly successful
Following the high
on Pressurized
2012 Conference
in Miami, North
TBM Tunneling,
eling Journal an
d
American Tunn d
are again please
the UCA of SME
y conference
to present a timel s.
ern megaproject
focused on mod
will again feature
The conference
tions from
critical presenta
rts, panel
international expe
open mic
discussions, and
ith a tailored
sessions along w
ique opportunity
exhibit and the un
Alaskan Way
to visit the SR-99
oject.
Bored Tunnel Pr

ar today!
Mark your calend

t will be
ts from this even
10% of the profi Stud ent
A of SMEs
donated to the UC
Scholarship Fund

ence,
m ore in fo rm at io n about the conferplease contact:
For rship opportunitie
s,
exhibit or sponso Steve Caming
7 1187
Tel: + 1 (603) 44 elingjournal.com
Amanda Foley nn
7577 Email: steve@tu
Tel: +1 (603) 452 nnelingjournal.com
tu
Email: amanda@
journal.com
www.tunnelling
rg
www.smenet.o
NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:39 Page 34

TORONTO

Meeting the
challenges of
COXWELL

The slurry walls of the exit shaft

34 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:39 Page 35

The Coxwell Trunk


Sewer Bypass Tunnel is
a small but interesting
job, north of Torontos
city center, in Canada.
McNally Project Sponsor,
Steve Skelhorn, provides
an update on the project
and describes the final
sewer connections

A construction crew inspects the damaged section of the Coxwell Trunk Sewer, following
ON A COLD NIGHT THIS FEBRUARY, as completion of the Bypass last month. This will soon be backfilled and then abandoned
residents to the north of Torontos city center
slept, the final stages of the Coxwell Sewer
Emergency Bypass were completed. Weeks of the existing sewer at either end (Figure 1). Tunnel depths were up to 45m (150ft) and
preparation, and endless planning, culminated A previous article on the Coxwell tunnel, compressed air was utilised as support.
in a single night of strategic activity. published in the October/November 2010 More recently, due to the citys current
Installing a Bypass into a live sewer is never edition of NATJ, primarily focussed on the population expansion and the critical nature of
easy, but when the sewer is one of Torontos shafts and tunnels for this project. This article this particular trunk, it has become necessary
main trunk sewers (servicing approximately serves as an update on project and describes to twin the system to provide increased
750,000 residents); has flows in excess of 6m3 the final connections at each of the shafts. capacity and options for maintenance. As part
per second; and with no contingency plan, the environmental assessment for this future
other than diverting the entire sewer into the Project background expansion work, video inspections discovered
Don River; the task became the critical activity In the late 1950s, to facilitate the expansion of a damaged section within the Coxwell Trunk
in this small, but challenging, project. the city of Toronto a 2.6m (8.5ft) i.d. trunk Sewer. With the damaged section in such
A simple outline of the Coxwell Bypass sewer was installed connecting northern close proximity to residential properties, it was
Tunnel project would be the sinking of two sections of the city to the treatment works by of obvious concern to the City of Toronto,
shafts either side of a damaged section of the lake. At that time, this was a tricky particularly in terms of potential sewer failure,
existing sewer, driving a tunnel around this undertaking, with excavation undertaken by blockage, and ground subsidence.
damaged section, and live connections into hand through water-bearing alluvial materials. The City of Toronto therefore considered it
prudent to affect a repair to this section as
quickly as possible. With the system running
Figure 1: Map of the Coxwell Trunk Sewer Bypass
close to capacity, it was not possible to enter
Taylor Creek Park the sewer and effect repairs in a reliable and
Ea ewe

r line
reek sewe
s

Massey c
st r l

cost-effective manner, and consequently, an


Do ine

emergency bypass tunnel was designed.


n

The Coxwell Emergency Bypass is a short


Depth of sewer line in valley: 12.5 metres section of equivalent size tunnel that runs
tor
cep Entry shaft 500m (1,640ft) around the damaged section
ri nter
ive of sewer. On February 23, 2010, following a
D on R
0 50 100m unique bid process with 80% weighting on
the technical requirements and 20% on price
res.
McNally Construction, with Aecom Canada
a ra C as its designer, was the successful proponent
B ar b
Bypass sewer for the CA$30 million design-build contract
.
tunnel lvd with both the highest technical rating and the
ell B lowest price. As McNally already owned a
xw 3.3m (9.8ft) diameter Lovat EPB TBM and
Co
segment moulds for a 2.744m (9ft) i.d. tunnel
Approximate location of
damaged section of sewer (utilized on Torontos Bathurst/Langstaff and
19th Avenue tunnels), its proposal was based
Exit shaft on this size of tunnel.
Tre

The tunnel route leads from the base of a


a
Co

or Dr. ravine to the top, with the tunnel invert


dw

OConn
xw

ay

Depth of sewer line at varying in depth from 9m (30ft) at the


ell

Blv

street level: 40.5 metres entry/launch shaft to a depth of 42m (138ft) at


Av

d
e.

the exit shaft on Coxwell Avenue. The Bypass

NORTH AMERICAN TUNNELING JOURNAL 35


NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:39 Page 36
NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:40 Page 37

TORONTO

shafts, and allow excavation around and


under the sewer.
On exposure of the upper half of the sewer,
the top was cut away using concrete wire
saws. The saddle of the tunnel was then
removed allowing the flume to be lowered
into place. Hydraulic jacks incorporated into
the flumes were then actuated to expand the
flume into the sewer either side.
Seals at each end of the flume were then
inflated to form the seal. This temporary
flume was installed in live flow conditions.
Night work was carried out to benefit from
the low flow, albeit the low flow was still only
just below spring line of the existing tunnel.
The flumes proved highly effective and
Figure 2: Schematic of the entry shaft were installed without a hitch in around two
hours. The hydraulic rams were remotely
Secant piles build activated, which allowed the flumes to be
above the pipe installed without exposing crews to the flows.

Figure 3: Sketch of the temporary flume


Secant
pile shaft
Lubricated Hydraulic
nipples jacks

External
telescopic
pipe
New Tunnel
by TBM
Lips with
anchor
bolts

Existing sewer pipe

had to meet the hydraulic performance of the property and 6m (20ft) of an arterial road.
existing section of sewer, which only has The 500m (1640ft) long section of new
300mm (12in) of fall over its length. Therefore bypass tunnel running around the damaged
the new 500m (1640ft) long tunnel bends section of sewer was driven in full EPB mode. Inflatable
around the damaged section in a sweeping On completion of the tunnelling, excavations Centralized seal
curve, and consequently results in a longer were carried out around the existing sewer at teeth
Internal
tunnel section. This alignment required the each shaft ready for the connections. telescopic pipe
tunnel to negotiate a 150m (490ft) radius While progress went very well on the entry
curve. To achieve this it was necessary to shaft and the tunnel, production was delayed
modify the existing segment moulds to on the exit shaft due to some complex ground
increase the taper from 20mm (0.8in) to conditions around the existing sewer. A
40mm (1.6in). The use of an articulating tail systematic program of jet grouting, sodium
can was also required to negotiate the curve. silicate grouting, dewatering and cementitious
grouting was ultimately required to fully seal
Shaft and tunnel construction around the sewer and allow the excavation to
Work on the Emergency Bypass commenced be completed.
in March 2010. Two shafts were constructed The entry shaft flume was installed in
over the existing live sewer. The upstream October 2011 with the exit flume following
shaft (or entry shaft) was a 10m x 17m (33ft x one year later in October of 2012.
55ft) interlocking secant pile shaft
approximately 8m (26ft) deep (see Figure 2). Temporary flumes
The downstream shaft (exit shaft) consisted of As discussed, the bypass connects directly into
a 10m (33ft) diameter, 45m (150ft) deep, the existing live Coxwell Trunk Sewer, which
octagonal slurry wall shaft. The deeper shaft (under wet weather flow) can surcharge to
was complicated by its location. Situated on a 3m (10ft) above the tunnel. Therefore, Above: The temporary flume in place within
postage stamp size compound, the shaft specially fabricated hydraulic flume pipes were the entry shaft
walls were within 3m (10ft) of a residential designed to bridge the sewer through the Top left: The completed bypass tunnel

NORTH AMERICAN TUNNELING JOURNAL 37


NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:40 Page 38

TORONTO

The final connection minimum flows in the sewer and on the removed the sewage entered the new
The final permanent connection involved the evening of February 19, 2013, the connection bypass at the downstream end but also
removal of the temporary flumes and the work commenced. The sequence of the sewer continued to flow down its original
installation of permanent elbows. Consisting connection was as follows: course.
of mortar lined steel pipe the elbows were

1 2
fabricated ahead of time (before the shafts Starting work at around 11pm (after The crew relocated to the entry shaft
were excavated). Consequently concrete was the flows within the sewer dipped and repeated the process removing the
required in the shafts once the temporary below spring line), the downstream upstream temporary flume. Again this
flumes were installed to match the shaft temporary hydraulic flume was went smoothly with the flume
concrete to the elbows. removed (with the flumes being removed by 1am. Despite the flows
After the concrete was cast in each shaft, hydraulically actuated this was possible being at thier lowest levels, a
split flanges were fabricated and the lower without men present at the base of the considerable amount of flow was
half of each flange was bolted to the shaft). This operation went very witnessed through the shaft. This
respective concrete wall. This flange would smoothly and within 40 minutes the resulted in sewage flowing through
provide the fit for the elbows during flume was on the surface. Once both tunnels.
installation. Once the elbows were lowered
into position, the upper flanges could be
bolted in place to finally secure the elbow.
The procedure for removing the flume was
the focus of much debate. Several methods
were looked into for diverting or reducing the
flows to allow for the permanent flume
installation. Unfortunately due to high flows,
access restrictions, and surcharge limits, the
only viable option was to carry out all the
work under live flow.
Night time work was selected to ensure

Right: The temporary flume in place


within the exit shaft. Below: The
connection elbow for the exit shaft

38 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:40 Page 39

TORONTO

The live flow connections were a huge


success and much credit must go to all those
involved from the concept stage, through
planning and design and down to execution.

4
At 4.45am the final connection was visibility within the shaft dropped to
completed with installation of the minimal. With the second elbow in
elbow at the exit shaft. By 6am the place the flow was successfully diverted
upper flanges were also in place. through the new bypass.
Complicating the process at the exit

5
shaft was the temperature with an air The following day the sewage within
Retracting the temporary flume temperature of around -14C (6.8F) as each shaft was pumped out. A new
soon as the flume was removed access was created at each connection
to allow for this and also to permit
entry for future inspections.

6
The final stage will be to mass fill
around each elbow with concrete to
seal the pipes in place. At the time of
writing this article, work was ongoing
and the site is expected to be cleared
and fully restored by early summer.

With the bypass now in place the section of


damaged sewer is to be backfilled and
abandoned.

Summary
The Coxwell Emergency Bypass was a very
challenging job, but not necessarily due to the
usual issues encountered on a tunnelling
project. The live flow connections were a
huge success and much credit must go to all
those involved from the concept stage,
Removal of the flume in the entry shaft through planning and design and down to
execution.

3
At 1.45am lowering of the permanent
elbow at the entry shaft commenced.
Prior balancing at the surface ensured
the elbow remained level. Once in place
all the flow was diverted into the new
bypass. Once in place all the flow was
now diverted into the new bypass and
the upper sections of the retaining ring
were bolted on before the crew moved
back to the exit shaft.

Lowering the entry shaft elbow The elbow in place within the exit shaft

NORTH AMERICAN TUNNELING JOURNAL 39


NATJ_0513_040_042_RETCintro.qxd:Feature 21/4/13 20:54 Page 40

ROCK & CONCRETE GRINDERS ROADHEADERS TUNNEL SUPPORT SYSTEMS

ANTRAQUIP
Experienced, Innovative & Reliable
758 Bowman Ave., Hagerstown, MD 21740, USA
ph: +1 301.665.1165 . info@antraquip.net
www.antraquip.net

#1 IN ROCK CUTTING
Arch Canopy and Barrel Vault System, Lattice Girders, Steel Ribs and Diamond Saw Attachments

High Performance, Delivered

o u t w hy we are so
d
C 2013! Fin P
We wil l be at RET
ED U
U M P
P OOTH #2108.
visit us in B

Amix Systems Ltd., designs and manufactures


TC 2013
grout and backfill mixing systems, Visit us at RuEt your projects, and
hear abo ducts
We want to to se rvice and pro
and custom equipment for civil, environmental, share our ap
p ro a ch
m e, hasssle, an
d money.
o m e rs ti
ur cust
that saves o
mining, and construction projects.
#21
08
B OOTH
Learn more about the dedicated, Contact: Dennis Arbour
experienced team, and the innovative products at: Dennis@AmixSystems.com
Phone:1-604-746-0555
www.AmixSystems.com.

40 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_040_042_RETCintro.qxd:Feature 21/4/13 20:54 Page 41

RETC PREVIEW

RETC PREPARES
FOR THE CAPITAL

JUNE 23-26, 2013 - MARRIOTT EXHIBIT HOURS


WARDMAN PARK, WASHINGTON DC Monday, June 24
5.00pm 7.00pm:
Exhibit Hall Reception
WASHINGTON DC IS THE HOST CITY for place on Sunday, June 23.
this years Rapid Excavation & Tunneling In addition, Sunday afternoon
Conference & Exhibit (RETC) and with also sees two strong Special Tuesday, June 25
numerous major projects currently ongoing Program sessions on Contracting 11.00am 2.00pm
in the region, the RETC Organizing Practices and Risk Management. 11.30am 1.00pm: Exhibit Hall Lunch
Committee is sure to attract record numbers On Monday morning the four- 4.00pm 6.00pm: Exhibit Hall Reception
of delegates to the nations captial, from track conference program gets into
both home and abroad. full swing, providing a wealth of Wednesday, June 26
DC Waters Clean Rivers Project is now in papers on subjects including
9.00am Noon
full swing, and a conference site visit to the Difficult Ground, Geotechnical
Blue Plains Tunnel offers attendees the Considerations, New and
opportunity to tour the longest of Innovative Technologies,
the four design-build tunnel Pressure Face TBM Case will present the UCAs current activities and
projects in the scheme (see Histories, Instrumentation and announce this years Scholarship Recipients.
p10). Traylor/Skanska/Jay Dee Settlement Control, and The induction of incoming UCA Chair, Bill
JVs 26ft (7.9m) diameter Large Span Caverns. Edgerton, will also take place.
Herrenknect TBM will be in Victor Mendez, of the Another full day of technical conference
the shaft and almost ready to Federal Highway sessions including Ground Stabilization,
launch on the 4.5-mile (7.3km) Administraton, will host the Hard Rock Tunneling, Precast Linings,
project by the time the RETC tour RETC Welcoming Luncheon; SEM/NATM, Grouting & Water Control, and
takes place on Wednesday, June 26. and, later in the day, the Exhibit Shafts will be followed by an Exhibit Hall
As for the conference itself, four Short Hall Drinks Reception will mark the drinks reception, and the RETC Dinner.
Courses kick off this years RETC program, opening of more than 130 exhibit booths Wednesday morning wraps up the
with sessions on Grouting in Underground for delegates to tour while catching up with Technical Sessions, with papers on Design &
Construction, Tunnel Lining Design, friends and colleagues over a beer. Planning, Major and Future Projects. All in
Microtunneling, and Understanding Risk, At the UCA of SME Breakfast on Tuesday all, its set to be an event to remember, and
Uncertanties and Hard Decisions, all taking morning outgoing UCA Chair, Jeff Petersen we look forward to seeing you there!

NORTH AMERICAN TUNNELING JOURNAL 41


NATJ_0513_040_042_RETCintro.qxd:Feature 21/4/13 20:54 Page 42

RETC PREVIEW

EXH
1200 1202 1204 1206 1210 1212 1214 1216 1220 1222 901 903 905 907
NO EXIT

IB
ITOR
1201 1203 1205 1207 1211 1213 1215 1217 1221 1223 1225

SER
1300 1304 1310 1312 1314 1316 1320 1322 1324 LOUNGE

VICE
CEN
TRE
808 810
703 709 711
NO EXIT

The 2013 RETC Exhibit kicks


off at 5pm on Monday, June LOUNGE 700 702 704 706 710
2325
24, during the Exhibit Hall
1430
Drinks Reception. Meet the 2323 601 603 605 607 611 613
NATJ team at booth 600! 1428
1601 1603 2321
1426 600 602 604 606 610 612 614
1700 1609 2319
1424 501 503 505 507 511 513 515

1422 1701 1703 1705 1707


508 510 514

SALES
1800 1802 1804 1806 1808
403 415 417
409 411

&
1801 1803 1807

OPS EX
408 410
1900 1902 1904 1906 2309
1414

HIBIT
303 315
309 311
1412 2307
1901 1903 1905 1907 1909

1410 2000 2004 2006 2008 306 308


2303 300 302 312 314
1408 201 203 207 209 213 215
2001 2007 2008 2301
1406
2100 2106 2108 ENTRANCE 200 202 204 206

1402 101 103 105 107 109

2103
1400

2201 2203 2207

RETC 2011 EXHIBITORS & BOOTHS


ABC Industries 808 David R. Klug & Associates 300 Kaydon Corp Bearings Division 706 Rocscience 2009
ABC Ventilation Systems 2000 Delcan 103 King Shotcrete 614 RST Instruments 215
Agru America 1701 DeNeef Construction Chemicals 505 Lachel & Associates 510 Ruen Drilling 601
Akkerman 2001 Derrick Equipment Co 2307 Langan Engineering & Environmental 312 S&B Industrial Minerals (NA) 709
Alpine Equipment 1414 Dibit Measuring Technique USA 607 Layne Geo 1324 Sandvik Mining and Construction 2319
Amberg Engineering (NA) 2301 Dr. Sauer & Partners Corp 513 Line Power 303 Schauenburg Flexadux Corp 201
Amberg Technologies 2303 DSI/American Commercial 315 Maccaferri 1900 Schnabel Foundation Co 1400
American Chemical Technologies 2006 Elasto Plastic Concrete 1802 Malcolm Drilling Co 1904 Schwing Bioset 1220
American Mine Research 204 Everest Equipment Co 1322 McDowell Equipment 2106 SELI SPA 206
Amix Systems 2108 Fibercon International 1402 MCT Murer Consult 710 Shaft Drillers International 1221
Antraquip Corp 1707 Gall Zeidler Consultants 1806 Messinger Bearings 1807 Shannon & Wilson 2004
Arup 2201 Geocomp/GeoTesting Express 1803 Midwest Industrial Supply 604 Shotcrete Technologies 603
Atkins North America 1424 Geo-Instruments 101 MineARC Systems 2207 Shurjoint Piping Products 1907
Atlas Copco CMT-USA 1304 Geokon 1428 Mining Equipment 2100 Sika Corporation 2323
Avanti International 700 Givens International Drilling Supplies 109 Mining Technologies International 2203 SOLDATA 1217
Babendererde Engineers 511 GMS Mine Repair & Maintenace 1223 Moretrench 508 Spendrup Fan Co 408
Ballard Diving & Hyperbaric Services 611 Gomez International 1302 MWH Global 1601 Stirling Lloyd Products 1225
Baroid Industrial Drilling Products 409 Grindex Pumps 1406 Naylor Pipe Co 203 Surecrete 507
BASF Construction Chemicals 1609 Halfen Anchoring Systems 901 Nexans AmerCable 1426 tacs 905
Becker Mining America 514 Hatch Mott MacDonald 308 Nicholson Construction Co 602 Team Mixing Technologies 1316
Bekaert Corp 704 Hayward Baker 1705 Normet Americas 1800 Technical Tunnelling Components 314
Boart Longyear E&I Drilling Services 1314 Heintzmann Corp 1906 North American Tunneling Journal 600 TEI Rock Drills 309
Brokk 311 Helix: Micro-Rebar 711 Orica USA 1702 Tenbusch 903
Brookville Equipment Corp 2008 Herrenknecht USA 403 Pacchiosi Drill USA 1312 The Euclid Chemical Co 1909
Cambria County Assn for Blind & HIC Fibers 606 Parsons Brinckerhoff 501 The Robbins Co 2103
Handicapped 209 Hitachi Zosen Corporation 1300 Parsons Corp 1422 TLT-Babcock Process Fan Group 1901
Caterpillar Tunneling Canada Corp 703 HNTB 2321 Paul C. Rizzo Associates 1410 Trelleborg Ridderkerk 1902
CDM Smith 702 Hobas Pipe USA 1703 Permalok Corporation 213 Tunnel Business Magazine 1903
Cellular Concrete Solutions 1603 Hughes Brothers 1905 Plaxis 810 URS Corp 1430
CETCO 417 ILF Consultants 605 Powerking Corporation 202 VMT 1310
ChemGrout 411 Irwin Car and Equipment 1412 Pultrall 1216 W. R. Grace & Co 503
Cosella-Dorken Products 1801 Itasca Consulting Group 515 Putzmeister Shotcrete Technology 2325 Williams Form Engineering Corp 612
Crux Subsurface 610 J. H. Fletcher & Co 200 QSP Packers 410 Wisko America 1222
CTS Cement Manufacturing Corp 302 Jacobs Associates 2309 Rasa Corp 2007 World Tunnelling 1804
Daigh Company 1808 JADCO Manufacturing 1408 Reimers Systems 907 Xypex Chemical Corp 105
Datwyler Sealing Technologies 306 Jennmar Corp 613 Richway Industries 207 Zed Tunnel Guidance 1320

42 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:48 Page 43

RETC PREVIEW

ABC Industries ventilation systems efficiency. Its oval


shape also allows for more headroom
ABC Industries is using RETC 2013 to in confined spaces and accommodates
showcase its recently launched TruOval higher profile underground equipment.
MineVent line of layflat blower ducting ABC Industries also claims that
for the mine, tunnel, and underground TruOvals welded construction reduces
construction industries. TruOvals the air loss, weakening, and premature
patent-pending design is engineered failure associated with conventional
with suspension cables spaced sewn ducting. The durable RipStop
intermittently through the ducting to substrate prevents small tears from
maintain the ductings oval shape. By becoming major holes. All TruOval
utilizing an internal cable suspension MineVent fabrics have been tested and
system and eliminating the fabric approved by the Mine Safety and
divider typically seen in oval layflat Health Administration Standards
ducting, TruOval minimizes the amount (MSHA).
of air-flow friction and maximizes the RETC Booth 808

Akkerman Amberg Engineering (North


Pipe jacking and tunneling America)
equipment specialist Having been
Akkerman has developed a developing
range of products that geotechnical
accurately install a variety of underground infrastructure. Over the solutions for
years, the firm has introduced manned pipe jacking, more than 40
microtunneling, guided boring and earth pressure balance years, Ambergs
systems to expand the range of sizes, ground conditions and work to date
complexities in which its systems perform. culminated in
RETC Booth 2001 the lead design
and project
management
for major parts
Alpine Equipment of the 35.4
mile Gotthard
Alpine Equipment is a market leader in Base Tunnel.
roadheaders, shaft sinkers and hydraulic cutter Amberg typically integrates
head attachments. The firm can specify equipment all requirements from the design. Other services
for tunneling, mining, scaling, excavating and any geological and geotechnical include: support materials;
other rock cutting or grinding project. New and analysis with the owners underground excavation
refurbished roadheaders are available and ready to clearance profile to design services and equipment; and
work or to be customized for specific jobs excavation methods, material ventilation systems, materials
requirements. Alpine also specializes in transverse handling aspects, ventilation, and equipment.
rotary cutter attachments with models ranging final lining and structural RETC Booth 2301
from 20-190hp to fit most carrier vehicles. Alpines
team can assist in equipping projects, engineering
custom solutions or supplying spare parts (MSHA).
RETC Booth 1414 American Chemical
Technologies
American Chemical same requirements for
Technologies (ACT) demanding industrial
manufactures and applications. Additionally,
distributes biodegradable, UCON Trident & Neptune
fire-resistant, and water offer a non-sheening,
soluble lubricants for 100% water-solubility, and
Tunnel Boring Machines an excellent aquatic
across the globe. EcoSafe toxicity profile; score in
FR hydraulic fluid & the practically non-toxic
EcoGear gear oil category according to the
technology represents a U.S. Fish and Wildlife
significant advancement in Classification.
synthetic, fire-resistance, ACT commits to setting
and biodegradability. new standards for product
UCON Trident AW performance and "Pride in
hydraulic fluids & Neptune Personal Service."
gear lubricants meet the RETC booth 2006

NORTH AMERICAN TUNNELING JOURNAL 43


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:48 Page 44

RETC PREVIEW

protocol further offers


American Mine Research underground
connectivity to the
Founded in 1975 and located in Rocky monitoring, control and communications Internet, e-mail, PBX-
Gap, VA, American Mine Research (AMR) electronics for the surface and coupling (land line
will be promoting its complete line of underground mining, aggregates and access), video streaming,
tunneling industries at RETC 2013. AMRs etc. Available in
new Mine Net Mesh System is a Modbus Ethernet
completely wireless system based on 802. or Wi-Fi versions,
11 Wi-Fi protocol for use in underground AMRs line of fixed
mines and tunnels. The Mesh System mount gas sensors
consists of wireless access points, IP- can simultaneously
addressable tracking tags, VOIP Smart monitor up to four
Phones, and a Master Station (surface gases such as CO,
computer). It offers wireless personnel CH4, O2, NO,
and asset tracking, atmospheric NO2, H2, H2S, and
monitoring and voice, text, and push-to- SO2.
talk communications. The systems open RETC booth 204

Beyond Tunnels

Antraquip Corp
Antraquip is a designer, manufacturer
and supplier of roadheaders, hydraulic
rock grinders, shaft sinkers, special
tracked machines with a variety of
boom options, and tunnel support
systems. Antraquip roadheaders and
rock grinders are being used all over
the world in a variety of civil
engineering and mining projects.
Our expertise goes beyond tunnels. Antraquip offers not only standard
roadheaders in the 12 80 ton
weight class, but is extremely flexible
We also deliver cut-and-cover and sequentially excavated in offering project-oriented
structures, caverns, portals, slopes, and embankments. engineering solutions. The firm also
Anytime youre faced with underground risk, Jacobs Associates supplies lattice girders, steel sets and
arch roof canopy systems for projects
is your partner for design, construction management, and throughout North America. The ability
dispute resolution. to provide a wide range of tunneling
equipment and services makes
Antraquip not only a leading
manufacturer but also an experienced
partner to utilize for any tunneling
JACOBS SF.COM and mining project. Visit Antraquip at
RETC Show Booth 1707.

44 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:49 Page 45

RETC PREVIEW

Arup Ballard Diving & Hyperbaric Services


Global engineering BDHS is a market leader in Hyperbaric Support Services for
consultancy Arup the worlds tunnel projects. By providing specialty turnkey
zplaces strong multidisciplinary technical solutions to contractors requiring hyperbaric equipment,
engineering teams into projects to assist client personnel and commercial diving services, BDHS says it has
organizations, joint venture partners and become a preferred international provider. The firms
contractors to deliver excellence. The firm experienced
seeks challenging work across the full range of supervisory personnel
tunneling activities. This has led us to global include Compressed
portfolio of tunneling work with a Air Workers, Dive
construction value of more than US$225 Medical Technicians,
billion. Much of this is being delivered in Hyperbaric Nurses, Hyperbaric Physician
cooperation with other firms, demonstrating Assistants and other specialty personnel.
our belief in inclusivity. In recognition of its Projects that BDHS have worked on
tunneling capabilities, Arup was awarded include: Alaskan Way Viaduct
Tunnel Designer of the Year at the 2012 Replacement, Lake Mead Intake Tunnel,
International Tunneling Awards. Port Mann Tunnel, OARS Deep Sewer
RETC booth 2201. Tunnel, and the New York Harbor Siphon.
Booth Number: 611

Atlas Copco CMT USA Baroid Industrial Drilling Products


Atlas Copco Construction Mining Technique USA is Baroid Industrial Drilling Products (IDP) is a product service line of
responsible for the sales, aftersales service and Halliburton. Since 1958, Baroid IDP has been providing drilling
rental of equipment for surface and underground fluid products and service to a variety of markets in the industrial
rock excavation, civil works and infrastructure drilling industry. Tunneling and drilling fluid additives, bentonite
projects, exploration drilling, rock reinforcement, grouts, and specialty chemicals with customized training and job-
and ground engineering. The company is site expertise are available for the tunneling industry. Baroid IDP
headquartered in the has a dedicated research & development laboratory which
US near Denver, continues to seek new technology & methods
Colorado. Employing that will support the industry and assist end-
approximately 450 users. Baroid IDP products are available through
people, it extends its a global distribution network.
reach through a RETC booth 409
nationwide network
of sales and service
stores and specialist
drilling distributors.
RETC booth 1304. BASF Construction Chemicals
Part of the German chemical giant, BASF Underground
Construction Group is a leading worldwide construction
chemicals supplier. The firm supplies a range of soil
conditioning foams, anti-clay agents and polymers, and
Babendererde TBM products as well as technologies for sprayed
Engineers concrete, precast and cast-in place concrete. As many
underground projects attract international contractor
Babendererde Engineers and design teams, the firm claims its global presence
is an independent supports seamless transfer of technology and services to
engineering company specializing in underground tunneling. any project, anywhere in
Together with its sister company, Babendererde Engineers of Bad the world.
Schwartau, Germany, the firm focuses on tunnel design, project Booth 1609
development, construction management and process engineering,
as well as independent expert assistance on contractual disputes.
Additionally, Babendererde Engineers offers Tunneling Processing
Control (TPC)
software, which is a
unique software
system that facilitates
data management
with multiple features,
and can be easily
tailored by the user for
a specific purpose.
Visit the team at
RETC booth 511.

NORTH AMERICAN TUNNELING JOURNAL 45


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:49 Page 46

Tunnel

Trenchless

Geotechnical

Shaft 4 OARS Phase II, Trumbull Corporation, Columbus, OH


Geostructural

Engineering & Design

Contact:
AJ McGinn 315.434.8885
Alan Howard 925.247.9000
Gregg Sherry 303.703.1405

Colorado | New York | California | Texas | Illinois


tE,D

46 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:49 Page 47

RETC PREVIEW

Brookville Equipment
Corporation
Rail support equipment specialist Brookville
Equipment Corporation will be showcasing its latest
innovations in high-height diesel and battery
locomotives and personnel carriers at RETC 2013.
These customizable personnel carriers provide
comfortable cushioned seating for four to 20 workers
Caterpillar Tunneling
and the option to also function as an eight to 25 ton Caterpillar Tunneling custom designs and manufactures tunnel boring
locomotive. With 95 years of experience machines (TBMs) and other support equipment to the unique needs of
manufacturing customized rail-mounted powered the most extreme global tunneling challenges. CAT soft/mixed ground
transportation solutions, Brookvilles tunneling and rock TBMs are widely used today across various industry
portfolio includes four to 45 ton battery or diesel- segments: metro, rail, transportation, hydropower, sewer, cable and
powered locomotives featuring heavy duty frames, pipelines. The firm will custom tailor a solution to ensure a projects
planetary drive axles, liquid-cooled wet disc brakes, success. CATs customers also enjoy product support from launch to
optional explosion proofing for improved safety and breakthrough and products that are built to be rebuilt.
climate controlled cabs for optimum operator comfort. RETC booth Number 703
These tunneling units have been used on some of the
industrys most notable projects, include the Traylor
Brothers East Side Access Project in New York City and
the Stillwater Mine in Nye, Montana. Datwyler Sealing
RETC booth 2008
Technologies
Datwyler, Division Sealing Technologies, is the world
CDM Smith leading provider of tunneling gaskets. With the newly
acquired Phoenix PDT Profiles business, Datwyler
CDM Smith is a consulting, features currently successful references in more than 450
engineering, construction and tunnels on all five continents. The company offers many
operations firm with an underground construction team that gasket profiles and material options, all designed and
includes geotechnical, structural, and civil engineers and geologists. offered on a project specific basis, to meet any
The firms tunnel-related work includes planning, feasibility and hydrostatic and/or environmental conditions that may be
design, including both 2D and 3D FEM analyses. The firm offers encountered. Datwyler now manufactures five types of
construction services including construction and program gaskets to meet a wide range of tunnel applications:
management, inspection and geotechnical instrumentation mono EPDM, hydrophilic, Co-ex Swell and Composite
monitoring and interpretation for soft ground and rock tunnels. Black Swell and the new anchored gasket. The anchored
Design and construction services cover all types of ground gasket as the new generation for segmental tunneling
modifications including ground freezing, grouting, and dewatering. gasket is now being used in the first USA tunnel projects.
CDM Smiths field equipment includes geotechnical RETC booth 306
instrumentation and construction data acquisition equipment.
RETC booth 702

Crux Subsurface
Geotechnical construction and exploration specialist Crux
subsurface has provided solutions to some of the most difficult-
access, geologically-challenging and environmentally-sensitive
David R. Klug &
projects in the United States. Specialties include long-range Associates
deviation-controlled horizontal core holes, borehole surveying, David R. Klug & Associates provides international and
optical and acoustical televiewer services, high-quality national manufacturer representative services to the
sampling, and instrument underground heavy civil and mine construction
installation. Pre- industries. The company specializes in the
excavation stabilization coordination of products, equipment and services
services include for NATM, soft ground, precast segmental and
dewatering, permeation conventional tunnel construction. This includes
and compaction initial support systems, GFRP bolts and soft-eye
grouting, tube arch structures, flexible membrane waterproofing
canopies, and cased systems, prefabricated final lining reinforcement
horizontal boreholes. The products, steel moulds, connectors and gasket
firm provides design sealing systems for one pass precast tunnel
build services and a fleet linings, tunnel profiling / scanning equipment
of custom-designed and associated site services, design and supply of
equipment to ensure that project specific material handling systems, and
project needs are met. complex final lining forming systems.
Booth 610 Booth 300

NORTH AMERICAN TUNNELING JOURNAL 47


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:49 Page 48

RETC PREVIEW

Fibercon International Gomez International


Fibercon is one of the worlds leading manufacturers of Specializing in consulting,
steel fiber reinforcement products. The company will engineering, equipment
be using its booth at RETC 2013 to showcase its new manufacturing, rebuild and
CAR35EDM steel fiber (Carbon-35mm-End Deformed sales, Gomez International
Mild) with 2SD2 design for shotcrete applications. This can assist in project design,
new fiber is the latest in the firms long history of steel estimating, equipment-
fibers that have been proven to improve the material procurement,
performance of fiber reinforced shotcrete (SFRS). These submittal preparation, through
ASTM A820 Type II steel fibers have been designed to project completion. Specializing
specifically to meet the challenges of the ever- in TBM excavation methods; the design and
increasing performance requirements of SFRS in todays application of conveyor haulage systems;
market. Fibercom fibers are made in the USA and are dewatering; muck removal; electrical
members of ASA, ACI, and FRCA. instrumentation, controls (inc. PLCs); low, medium,
RETC Booth 1402 high voltage electrical distribution up to 115kV; rock
support methods; segment lining; ventilation; data
collection, back-up/trailing floor, auxiliary support;
communication; and rolling stock. Equipment sales,
Geokon lease, manufacturing and rebuild: Tunnel
locomotives, tunnel excavators, rolling stock,
Monitoring specialist Geokon designs and manufactures ventilation fans, generators, transformers, power
a full range of geotechnical instrumentation suitable for systems, etc.
monitoring the safety and stability of civil engineering RETC booth 1302
structures including tunnels, mines and foundations.
Geokon's product line includes piezometers, pressure
cells, strain gages, inclinometers, load cells,
displacement gages, settlement systems, local and web-
based data-acquisition systems, as well as custom
instruments for specialized applications. Tunnel-specific
instruments include NATM-style concrete pressure cells,
convergence meters, multiple-point extensometers,
instrumented rockbolts, and tape extensometers.
Geokon, Inc. has been awarded ISO 9001:2008
registration from both ANSIANAB, USA and UKAS of
Great Britain.
RETC Booth 1428

Grindex demanding applications


imaginable. Thanks to
Pumps built-in motor protection
and air valves, pumps can
Hatch Mott MacDonald Grindex, a specialist in run unsupervised and
electrical submersible even dry for long periods
Engineering pump technology, offers a without damage. With
consultancy Hatch Mott complete line of highly SMART motor protection,
MacDonald provides efficient and reliable Grindex Pumps will not
tunnel design and submersible pumps run backwards, will not
engineering solutions designed for heavy-duty single phase and are
for rail and transit, road, water/wastewater conveyance, CSO drainage, sludge and protected against
storage, and cable and communications. The firm works to slurry applications. overheating. Both single
identify practical approaches to tunneling, equipment Stainless steel, MSHA and and three phase pumps
selection, and contracting approaches. Expertise includes soft explosion proof pumps can be equipped with
ground and rock tunneling, cut and cover, underground are also available. On built in float switches and
caverns, immersed tube tunnels, jacked tunnels and micro- construction sites, in other options. Pump
tunneling. Complimentary skills in technical areas include mines and various designs range between
tunnel rehabilitation, ground stabilization and treatment, industrial applications, 0.6 to 140 HP and deliver
tunnel systems, ventilation, and life safety and security. The Grindex submersible up to 5,000 gallons per
firm has a staff of 2,400 and over 70+ offices throughout pumps are constantly minute with pressures of
North America. being put to the test in up to 750 feet. Visit us at
RETC booth 308 some of the most booth number 1406

48 NORTH AMERICAN TUNNELLING JOURNAL


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:49 Page 49

RETC PREVIEW

Itasca
Itasca is dedicated to providing its clients better insight into the
Herrenknecht around by 180 degrees and
is now excavating the
behavior of the engineered earth environments where they
operate. To do so, it maintains a staff of leading engineers in the
Tunnelling second section to final fields of rock mechanics, hydrology, hydrogeology, geochemistry,
breakthrough. mining engineering, petroleum engineering, geophysics, and
Systems USA Herrenknecht delivers software engineering. The state-of-the-art numerical modeling
Construction companies cutting-edge tunnel boring codes that Itasca uses and sells for solving problems in
have successfully excavated machines for all ground geomechanics and hydrology are among the most widely used,
around 2,300 kilometers of conditions and all widely respected tools of their kind. Operating as both
traffic tunnel with diameters diameters. Together with consultants and software developers creates dynamic interplay:
of more than 4.2 meters the Groups innovative the technical capabilities of the consultancy are extended via
using Herrenknecht specialists, Herrenknecht is direct access to the internals of the software tools it uses. In
technology. able to offer integrated turn, the software is continuously developed, improved, and
In Miami, a Herrenknecht solutions around tunnel proven in the real-world problem-solving environment of the
EPB Shield recently construction at all times. consulting practice. Visit Itasca at RETC booth number 515.
successfully finished one With 77 international
tunnel of the twin-tubed companies the
Port of Miami Tunnel. The
machine concept with
Herrenknecht Group
provides a comprehensive
Jacobs Associates
slurryfier box mastered the range of additional Consulting engineers Jacobs construction management
water-bearing geology with equipment and services Associates provides solutions for capabilities. It also offers the
bravura in only 9 months. close to the project site difficult underground projects broader heavy civil construction
After the first breakthrough, and the customer. industry a robust
the EPB Shield was turned RETC booth 403 package of claims
and dispute
resolution services.
Jacobs Associates is
HNTB an award-winning
HNTB specialises in design and support services for tunnel firm with 13 offices
structures. The firms experts have the insight and in the United States,
knowledge to provide solutions on a wide range of tunnels, Australia, New
from small-diameter excavations to the largest machine- Zealand, and
bored tunnel in the world. Their work cuts across the Canada. Services
highways, transit, rail, aviation and water sectors. HNTB include: geological,
staffs experience includes tunnel design, tunnel boring geotechnical Services
machine construction, access shaft design, program and equipment;
management, project funding, cut and cover tunnels, civil, and excels in the water, tunnel boring equipment;
hydraulic and drainage design, construction, geotechnical wastewater, and transportation underground excavation services
reports and analysis, ATM and CIP and pre-cast segmental sectors. With an emphasis on and equipment; engineering
tunnel liners. tunnels and shafts, Jacobs offers design and services for tunnels.
RETC booth 2321 a full range of design and RETC booth 2309

Hughes Brothers
At RETC 2013 Hughes Brothers Inc will be
displaying various Fiber Reinforced Polymer
products that facilitate TBM launch and
reception chambers, removable FRP Soil Nails
and earth anchors, GFRP bars for face
stabilization in sequential excavation methods breakouts projects worldwide. Recently,
and GFRP rock bolts. The firms Aslan FRP bars extensive use was made of Aslan bars in the
are uniquely suited to the tunneling and mining diaphragm walls for the Seattle SR99 Alaska Way
industry as they are very high strength, Viaduct replacement tunnel. Aslan FRP materials
lightweight, and non-corroding but are easily are also used in situations where encroachment
consumed by mining equipment or tunnel or future use issues require consumable or
boring machines. The Aslan 100 GFRP rebar has removable anchors or methods.
been used in over 300 TBM launch and RETC booth 1905

NORTH AMERICAN TUNNELING JOURNAL 49


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:49 Page 50

RETC PREVIEW

Let
Le
JADCO Manufacturing Maccaferri
As part of a worldwide industrial group, Maccaferri has over 130
For more than 30 years years of experience and expertise that includes solutions in retaining

n
JADCO has been a global wall systems, reinforcement of steep slopes, embankments,
leader in solving the toughest drainage systems, rockfall protection, soil erosion protection,
wear, impact, and abrasion coastal protection, and solutions in mining. The firm offers a wide
challenges in the tunneling, range of solutions for use in tunneling projects range from Wirand
mining, steel, construction, steel fibers and FibroMac synthetic fibers for improving the
power generation, recycling, performance of
and other major industries. At concrete, to specialized
RETC the company will display tunneling products
its premier lines of including: self-drilling
CHROMEWELD Overlay Plate bolts and steel anchors,

y
that outlast virtually any material in high-abrasion fiberglass reinforcement
applications; and QT-Plus Wear Steels that provide bars, drainage tubes and
10X the wear life of conventional offerings. In ceramic final linings.
addition, the ISO 9001:2008-certified manufacturer Maccaferris team of
will exhibit its HARDGUARD wear blocks that defeat professionals is available to
the harshest, most abrasive operating conditions. offer specialized technical
RETC booth 1408 support, project analysis,
design, and product
selection.
RETC Booth 1900
J.H. Fletcher
& Co
J.H. Fletcher & Co has provided mobile underground mining
Malcolm Drilling Company
equipment to the industry for over 75 years. Fletcher was a Malcolm's list of core services in tunneling and
pioneer in the production of roof bolters, and design of the
automated temporary roof support system (ATRS) and
geotechnical construction includes drilled shafts,
excavation support systems, cutoff and secant pile walls, Narrow Fle
continues to provide a wide range of equipment that focuses jet grouting, deep soil mixing, cutter soil mixing and
on worker safety and productivity in underground mines. dewatering. These combined services have routinely is design
designed
Fletchers world-renowned roof bolters are accompanied by an been applied on numerous complex tunneling projects
entire product line including: scalers, powder loaders, and drill throughout North America. The firm says its large and bac
backed
jumbos. Fletcher also continues its legacy of custom-built equipment fleet and highly skilled personnel allows it to
equipment, with a Fletcher machine customers are assured a comply with the most rigorous schedule compression. mining eexper
machine built specific for their application and job. Malcolms experience facilitates a Design/Build approach
Fletcher will be represented at RETC this year, located in to projects and allows for timely collaboration with expanding
expand
booth 200. Visitors will be provided information regarding owners and contractors. The
the entire product line, and also have the ability to interact
with Fletcher powerpoints, videos and animations.
firm provides these services
nationwide through regional
custome
customer s
offices.
RETC Booth 1904
QGLQJ SDUWV
QGLQJ
Layne GEO more co conven
Layne GEO is one of six
divisions of global water
Customizatio
Customi
management,
construction and drilling
maintenanc
maintena anc
company Layne Christensen Company, which provides solutions
for water, mineral, and energy challenges. With Laynes ability to
components
compone
p ents
leverage resources, GEO is an important link in providing total
project solutions for our clients by offering an array of choice simps
underground construction expertise, and providing specialized
services within the fields of ground improvement, deep ORRN DW
DW WK
WKH
KH E
foundations, earth retention, and customized geotechnical
equipment design and fabrication. has to prov p
GEOs solutions are geared towards heavy civil, industrial and
commercial construction markets that are focused primarily on soil your de decis
ecis
stabilization and subterranean structural support during the
construction or rehabilitation of dams/levees, tunnels, shafts, water easy.. Rel
easy Reliab
liab
lines, subways, highways and marine facilities. Services offered
include jet grouting, diaphragm and slurry cutoff walls, cement the answer
answeer is
and chemical grouting, drilled piles, vibratory ground
improvement/stone columns and installation of ground anchors.
RETC Booth 1324 ZZZMKH
ZZZ
ZMMKH
M
J.H. Fletc
Fletcher
cher & Co. can
cannot
nnot antic
uct. Proper
per use
use, mainten
maintenance
nance an
50 NORTH AMERICAN TUNNELING JOURNAL
NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 51

Fletcher
er

Let
Le
n a r r ow
w
your mine
e
Narrow Fletcher J151-DE
a little.
is design
designed for a long life,
and backed
bac by 75 years of
mining experience.
e Fletchers
expanding world-wide
expand
custome
customer support, makes
QGLQJ SDUWV  GLVWULEXWRUV
QGLQJ
more co convenient than ever.
Customization options, low
Customi J.H. Fletcher & Co
maintenance
maintena ance and prov
proven
ven P.O.
P.O
. . Bo
Box
x 218
2187
87
Huntington,, WV 25722
257222
components,
compone
p ents,, makes the Scan here
here to discover
disco
over our w
website
ebsitte
choice simple.
s Once youy
DW WK
ORRN DW WKH )OHWFKHU
KH EHQHWV )OHWF
FKHU

has to provide,
p narrowing
narrowwing
your de decision
ecision becomes
becom mes
easy.. Reliable
easy Relliable and dura
durable-
able-
answeer is always Fletc
the answer herr.
Fletcher.
ZZZMKHWFKHUFRP
ZZZ
ZMMKHWFKHU
M UFRP
FRP 304 525 7811
304.525.7811 VDOHV#MKHWFKHUFRP
VDOHV#MKHWF
# FKHUUFRP
FRP
J.H. Fletc
Fletcher
cher & Co. can
cannot
nnot anticipate every mine hazard
d that mmay
ay develop during use off these products
products.s. Follow your
our mine plan and/or roof control
con
ntrol plan
p prior
p to use of the prod-
prod-
uct. Proper
per use
use, mainten
maintenance
nance and continued use of (OEM)
(OE origi
original
nal equipment parts will be essential forr maximum operating results. 2013 J.H. FFletcher & Co. All rights reserved.
NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 52

Geotechnical,
Mineral Exploration
and Horizontal Coring

Horizontal Coring for Tunnel Investigation


P.O. Box 267 2320 River Road,
Clark Fork, Idaho, USA 83811
Phone 208-266-1151 USA
Fax 208-266-1379 Modesto, California, Phone 209-988-4261
RIFH#UXHQGULOOLQJFRP Bozeman, Montana, Phone 406-586-6266

www.ruendrilling.com

...AND RECEIVE YOUR

SUBSCRIBE TODAY... FIRST 3 ISSUES


FOR US$1.60, 1.20,
1.00

SUBSCRIBE NOW!
To order, visit www.tunnellingjournal.com and click on Subscription Offer
52 NORTH AMERICAN TUNNELING JOURNAL
NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 53

RETC PREVIEW

MineARC Systems Nicholson Construction Co


Established in 1999, MineARC Systems is now the global leader in the Founded in 1955, Nicholson is a leader in geotechnical
manufacture and supply of emergency safe-refuge systems to the construction, providing a wide range of deep foundations,
underground mining, tunneling, and chemical processing industries. In earth retention, ground treatment, and ground
an industrial emergency, when evacuation is improvement services on projects throughout the United
no-longer safe or practical, MineARC refuge States. For tunnels, Nicholson constructs access shafts with
chambers are designed to provide a safe diaphragm walls and jet grout columns and the company
and secure go-to area for personnel to supports operations with a wide variety of grouting and
gather and await extraction. earth retention techniques. Nicholson has offices around the
MineARC refuge chambers have been country to address each region's unique geotechnical
successfully used around the world in construction needs. Visit Nicholson at booth 602.
multiple mine and tunneling emergencies to
save lives. Today MineARC has offices and
manufacturing facilities in Perth, Western
Australia; Santiago, Chile; Beijing, China;
Gauteng in South Africa and Dallas in the Parsons Brinckerhoff
United States, as well as a strong Consulting engineer
distribution network worldwide. MineARC Parsons Brinckerhoff
refuge chambers are present in over 100 offers multidisciplinary
operations in over 40 countries. All skills for the
MineARC refuge chambers comply with the development of all
highest international industry regulations and guidelines. modes of infrastructure
Booth number 2207 across the globe
including
transportation, power,
mining and
Mining Equipment water/wastewater. The
firms Geotechnical and
Mining Equipment has been supplying the mining and tunneling Tunneling group
industries with rebuilt underground equipment for more than 30 years. provides a full range of
The business has grown to encompass new ventilation equipment, engineering, planning,
Jetair fans, and new rolling stock, C.S. Card and Moran Engineering. and construction
Mining Equipment, Jetair and Mine Hoists International are currently management services
doing business in North and South America, Australia, Asia, Africa and that have resulted in
Europe. Products include: concrete mixing and award-winning tunnels, caverns, underground storage
transportation equipment; hoists and facilities and below-ground structures. Parsons
headframes; mining equipment; mucking Brinckerhoff received the award for Tunnel Design Firm
systems; tunnel haulage systems; ventilation of the Year in 2010 and was named Programme
systems, materials and equipment. Manager of the Year in 2011 in New Civil Engineers
RETC Booth 2100 International Tunnelling Awards.
RETC Booth 501

Moretrench
Geotechnical contractor Moretrench
specializes in design/build and turnkey
solutions for challenging construction
requirements and subsurface conditions. Credited with
Parsons
developing the first practical wellpoint system in 1924, the
company has dewatered sites for subway and underground Since 1944, Parsons
station construction across the country. With the development of has worked on
other specialty geotechnical methods, Moretrench moved some of the largest,
beyond dewatering to also utilize ground freezing for deep most complex
shaft construction and connector tunnels, and various grouting tunneling and
methods, including jet, permeation, compaction and underground
compensation grouting, for other tunneling-related challenges construction projects
such as soil stabilization, in the United States
groundwater control and and around the world. The firms tunnel professionals have
rock consolidation. These completed more than 60 recent projects, with specific
services are available expertise in planning, design, construction (design-build
nationwide through full and alternative delivery), construction management,
service offices in New Jersey, program management, and the operation of water,
New York, Florida, wastewater, and transportation tunnels. Experienced with
Massachusetts, Pennsylvania, soft-ground, rock, and mixed-faced conditions, the firm says
and Washington D.C. it is committed to delivering rapid, safe, economical
RETC Booth 508 tunneling.
RETC Booth 1422

NORTH AMERICAN TUNNELING JOURNAL 53


NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 54

RETC PREVIEW

Ruen Drilling The Robbins Company


TBM manufacturer The Robbins Company provides
Ruen Drilling provides drilling services including surface, solutions to some of the worlds most challenging
underground, and horizontal directional core drilling for tunneling
the geotechnical, exploration and geothermal industries. projects.
Drilling equipment includes truck, track, skid, and With its
helicopter supported core drills. Crews are all trained in Onsite First
achieving a high degree of core recovery for the client. Time
Recent projects include: Devils Slide Tunnel, Irvington Assembly
Tunnel, Caldecott Tunnel 4th bore, Route 9 Tunnel in (OFTA)
Hong Kong, Highway 53 Tunnel in Puerto Rico. method,
RETC Booth 601 The Robbins
Company in
2013
launched
hard rock and Earth Pressure Balance (EPB) TBMs four
to five months earlier than comparable shop
Shannon & Wilson assemblies. In Mexico City, a trio of Robbins EPBs and
continuous conveyors are making impressive headway,
With a reputation in tunnel design earned by achieving high speeds under high pressure, mixed
developing innovative solutions to specific site ground conditions.
conditions, Shannon & Wilson's projects have included: RETC Booth 2103
the worlds largest diameter soft ground tunnel; the
worlds first and only vertical, continuously spiral lined
shaft; components of
major transit systems; VMT
and instrumentation of Based in
major tunnel Germany with
installations. The firms subsidiaries in
staff is experienced in Russia, Australia,
designing and managing USA and China, VMT has supplied best-selling tunnel navigation
a wide range of and optimization systems worldwide since 1994. Additional
tunneling techniques solutions boost productivity by automating and monitoring
including drill and blast, processes. For segmental lined tunnels, the firm provides
roadheader, tunnel systems to measure the dimensional geometrical tolerances,
boring machine, earth track segments during production, storage and installation
pressure balance enabling storage optimization with reduced storage and
machine, slurry machine, personnel costs. Software for the calculation of the best ring
microtunneling, pipejacking, and directional drilling sequence as well as equipment for monitoring of ring
methods. Its services include: route selection; subsurface deformation is also offered. VMTs information and risk
exploration programs; design recommendations (soil management system enables correlation of the differing data
and rock); tunnel and liner methods selection; plans, sources on a typical project.
specifications, and engineer's construction estimates; RETC Booth 1310
construction management; construction monitoring;
tunnel condition assessment; and tunnel rehabilitation.
RETC Booth 2004
Zed Tunnel Guidance
A technological engineering company, ZED develops and
Team Mixing Technologies manufactures TBM guidance systems for installation on
For over 40 years Team Mixing Technologies has most types of machine and used by contractors worldwide.
provided fully automated material handling systems for The component units are designed and constructed to the
TBM bi-component grouts, bentonite slurries and grout highest standards, allowing clients to mount them directly
injection as well as for shotcrete, concrete and mining into one of the most hostile environments, without the
backfill. TMT manufactures colloidal mixers, pumping need for protective operator cabins. The equipment
and delivery systems, as well as the automated controls. undergoes continuous, but controlled redesign,
Concepts are specifically tailored to the customers needs incorporating the latest and most appropriate advances
and include complete engineering, design and made in electronic technology and manufacturing
fabrication of all mechanical, structural and electrical techniques to improve reliability and robustness i.e. low
systems. Services range from preliminary engineering power surface mount components. The OS is Windows
and case studies through to hands-on commissioning Embedded Standard 7 which, with ZEDs specific build
and field training with complete CAD documentation configuration, provides good stability with protection
and follow-up. Other services include ground against file corruption due to mains power instability, giving
improvement equipment, grouting materials and pumps a reliable platform on which to run the suite of software
and pumping equipment. applications.
RETC Booth 1316 RETC Booth 1320

54 NORTH AMERICAN TUNNELING JOURNAL


NATJ_0513_ADS_INSERT_055.qxd:Feature 21/4/13 22:02 Page 55

CONCEPT TO COMPLETION
AUTOMATED GROUT & SLURRY SYSTEMS
Featuring high shear colloidal mills
with new Mk IV mechanical seals
Fully Automated
Self Cleaning
Containerized Plants
Lo-Prole Plants
Foam & Admix Systems

Used in major tunnelling


projects world-wide including
the Brisbane Australia Airport
Link megaproject

www.teammixing.com
sales@teammixing.com
Ph: 1.604.556.7225

PROVEN
Offering new and used tunneling equipment
for more than 25 years.

##!#(*'
# " (#
##$(&!'
& )!#'
" #'(' MINING
( "'
EQUIPMENT
"( (#" %)$!"(
#" 
 
 , + 
 

, www.miningequipmentltd.com

S-ar putea să vă placă și