Documente Academic
Documente Profesional
Documente Cultură
Tunnelling
www.tunnellingjournal.com April/May 2013
SEGMENTAL
LININGS IN FOCUS
THE KORALMS SEGMENT
TRACKING SYSTEM
ROBBINS CONVEYORS SET THE PACE
High speed tunneling demands high speed muck removalwith maximum
capacity, minimal hands-on labor, and controlled operating costs.
contentS
5 Editors comment
6 Snapshots of
www.tunnellingjournal.com news
52 Customising Standards
Arnold Dix, Lawyer and Engineer gives
some guidance on regulatory
arrangements for subsurface tunnel risk
management from around the world
Above: The politics of
many a large scale
tunnelling project are
59 Successful tests in the Trnskog
Tunnel
SP Fire Technology reviews recent fire
becoming ever more tests carried out in the Trnskog road
complex (p34) tunnel in Stockholm
Left: SP Fire Technology
describe recent fire tests
carried out in the
61 A new system for water drainage
SP Fire Technology describe Rockdrain, a
new method and material used to control
Trnskog Tunnel in water leakage in a tunnel
Stockholm, Sweden
62 Contacts
TUNNELLING JOURNAL 3
Sika
Innovative
Solutions
The building owner expects timely completion of a project in high You have clear demands regarding economical rock support and
quality, also in consideration of local conditions. We provide you durable lining system, the concept of the waterproofing system
with system solutions that meet these demands and ensure you and of the sustainability of products and solutions used. Sika
competent service and punctual delivery of high quality products. provides quality products to meet your requirements, including
those for unforeseen circumstances.
editorScomment
Priced out?
ITS INTERESTING TO READ the time, rather than US$350M once,
International Tunnelling Insurers then US$100M in claims, and
Group (ITIG) world market then another US$350M trying to
outlook report on p28 of this fix the damn thing.
issue of TJ. Although brief, it It seems totally incongruous to
certainly packs a punch and got me at the present time. I really
me thinking about where the believe the established industry
insurers see the strengths and is, within itself, trying everything
weaknesses of the industry. One possible to turn opinions around
area of particular concern is the and to push technology to a new
continued pressure from clients to level at an unprecedented scale.
push prices as low as possible, But it is sad to see that innovation
whilst showing an almost may well only be acceptable to
immovable reluctance to clients in terms of how much it
implement, or even try out any can cut cost, not in terms of
form of innovation in both design enhancing quality and
and construction methodology. revolutionizing civil engineering.
Reading between the lines, and The real problem is in our
adding a few of my own, makes modern world everything comes
for a worrying picture where down to hard money, and its very
spend thrift clients are awarding difficult to argue against a lower
contracts to alarmingly low bids bidder unless the client really
tendered by the new wave of understands where the lowest bid
worryingly inexperienced may take him!
contractors entering the market But lets not get too down; Ive
naively believing it to be both only focused on one negative
easy and lucrative. Cut to the aspect just to flag it up. There is
chase, and these in-experienced
contractors are exactly NOT the
type of companies you would
plenty to be positive about, and it
looks like tunnelling is still on the
up and the future looks very
The real problem
is in our modern
world everything
want to try innovation with, and bright indeed, despite our
in some case you wouldnt even dreadful few years at the mercy comes down to hard
want to try standard tunnelling of dodgy bank practices. And, as
practices with. There simply isnt for our in-experienced low
money, and its very
the in-house experience there to bidders, it really wouldnt surprise difficult to argue
allow it and consequently little me if many of them exit as fast as against a lower
new gets tried out and the same they arrived once they really
mistakes are repeated over and understand the risk and returns bidder unless the
over. Criminally, the established involved in underground client really
contractors with a wealth of construction. Having your fingers
experience in the locker room are burnt once in the tunnelling understands where
essentially being priced out of arena can spell the end for many the lowest bid may
new work by these crazy low a would be contractor! And if
bids. What a false economy on a
grand scale, indeed the
expression, buy cheap, buy
some are still here in ten years,
they will absolutely deserve to be
and good luck to them. After all,
take him!
twice instantly springs to mind. everybody has to start
Its not rocket science better to somewhere!
spend US$500M once on a
project that stands the test of Tris Thomas
TUNNELLING JOURNAL 5
NEWS FROM THE WEB
6 TUNNELLING JOURNAL
NEWS FROM THE WEB
TUNNELLING JOURNAL 7
NEWS FROM THE WEB
8 TUNNELLING JOURNAL
Safety aspects are one of those high
priorities in equipment selection choice at
our company.When we looked at the types
of machines that could not only support our
project but also handle all the conditions
and the huge size of the tunnel we were
going to undertake, the Sandvik range
offered exactly what we needed.
Kim Bailey
Plant Manager
Leighton Contractors (Asia) Ltd.
Hong Kong
Expertise in crushing
Understanding
underground
For decades, Sandvik has worked with various tunneling methods at customer sites Meet us at
around the world, creating expertise that results in intelligent cutting-edge technology.
As the only manufacturer with its own underground R&D center at the factory, Sandvik
continues to be the clear forerunner in the tunneling equipment industry. Always striving
to serve you with the best possible solution for your application at hand.
www.construction.sandvik.com
SEGMENTAL LINING
km
17.1
Ne
km
TBM II
KAT
0.7
6km
l 10.
TM
unne
or y t
NA
rat
xplo
TM/e
NA Shaft: 60m
West portal III
KAT NATM: 4.4km
TBM: 32.8km
10 TUNNELLING JOURNAL
TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:33 Page 11
SEGMENTAL LINING
KORALM TUNNEL
SEGMENTS -
complex monitoring
and management
Strict quality control and tracking requirements
are being met with the SDS computerised
production control system for the segments going
into the new Koralm tunnel in Austria. Adrian
Greeman visited the site and files this report
DRIVES FOR THE MAIN sections of the segments have been set by the client BB-
Koralm high speed railway tunnel project Infrastruktur, the capital works division of
began work at the beginning of this year, two Austrian state railways. As well as tight quality
9.9m diameter TBM hard rock bores of 15.7km assurances it wants full traceability of the
and 17.1km length respectively form the lines components in the segments to allow for
on the north and south sides of the alignment. easier trouble-shooting and investigation in the
They will take around three years to complete event of damage or failure within the tunnels.
their eastwards progress, meeting eventually The requirements arise particularly from
with 12km and 10km drives coming the other caution about potential difficulties in the rock
way by another contractor. and particularly in the first seven or so
The Strabag-Jgerbau joint venture kilometres of the drives through striated gneiss
contractor for the central and largest section of with significant slip surfaces in the rock. For this
the project, Lot 2, is pleased with the start it section there is also a very unusual requirement
has made on the TBM sections. The first for an in situ lining.
machine began in February on the southern The TBM will install a basic segmental lining
bore and the second machine starting work and then we will follow on with a waterproof
earlier than expected, just before Easter. drainage membrane and in situ inner shell cast
Meanwhile in its first two years, the using a travelling formwork as you would in a
contractor has already made some 4.4km of conventional tunnel, says Strabag project
tunnel by conventional methods in soft ground director for the joint venture Wolfgang Lehner.
near the western end. But the hard rock drives In the later harder gneiss section the tunnel
are the key part of its 600M contract. will use simply the plain segmental lining.
A key element of its work in the initial period All these segments must be produced on
of the contract has been setting up and site. The client ruled out segment production
preparing for the segment production and elsewhere and delivery to site because of the
delivery to the machines which will consume potential disruption it would cause. The area is
eventually some 103,500 segments for the a pleasant rolling landscape of farmland,
rings and another 17,250 larger invert vineyards and small townships.
segments. These 13.4t pieces are for a flat floor The delivery of so many segments by trucks
which is installed immediately behind the over a three year period would have been
machine and to which are bolted twin railway impossible, says Andreas Lange, segment
tracks for personnel carriers, logistics and production manager. He says that it would also
machine supply of segments and grout. have been difficult to bring them in by rail,
Strict requirements for quality of the because although there is a line to the site,
TUNNELLING JOURNAL 11
ENVIRONMENTAL
MONITORING
AND MACHINE
CONTROL: FROM
BREAKING GROUND
TO BREAKING
THROUGH.
SEE THE LIGHT
SEGMENTAL LINING
installed as part of the mobilisation, it does not tolerances, says Nod Clarke-Hackston,
have sufficient capacity. It is needed for international sales manager for VMT, and
supplies like the pea gravel, grout and so forth even a fraction of a millimetre can set it out.
and for removal of spoil, he say. The system uses input from modern laser
But producing so many segments on site has scanners, two of which in fixed positions can
its own difficulties, most of all the space. be used either to scan the interior of a steel
Within a tightly constrained area the contractor form or the final segments once removed. The
must have not only its tunnel access and spoil factories at Koralm have a measuring space
disposal handling but also two segment fitted with Faro scanners.
factories and a storage area. That is very These can work in minutes compared to
small, says Lange. For his purposes, he has a painstaking day long checking with total
yard stretching approximately 150m in each stations required in the past. A 3-d best-fit
direction from the central tunnel access shafts, volume model is produced. VMT has specific
and just 50m wide. Within this enough software, TubGeo for this purpose.
segments must be stored to allow for 28 days Scans are carried out on a regular basis to
of hardening and supply to the machines. A check the forms and also on the output of
supplementary area is available to the back of segments with a specified procedure to check
the site but it is not much. the first ten from each model, then to sample
one-in ten and dropping to one in 500 if no
Different rings deviations are being picked up.
Complicating the picture is the need to The SDS also comes with a tagging and
produce various types of ring segment. There is recording system using bar codes in this case,
a basic ring, and then a high strength ring with though RFID mini-chips can also be embedded
more reinforcement and a stronger mix design for automated work. The various inputs into a
for the concrete. A third type of specially segment are all tagged with their own
reinforced ring is needed for the points in the Above: the invert. Top left: segments individual identifiers barcodes.
tunnel where the tunnel lining will be broken delivered to the base of the shaft. Top At Koralm there are two factories for
through to form cross passages, every 500m. right: segment installation at the TBM segments each using Herrenknecht made
These have more steel still and heavy 100mm forms, moving around a production carousel
diameter dowel bars at three points to connect with a seven-hour heat curing oven. There is a
to the next ring, to give the lining stability once of its first full outings at Koralm. separate batching plant for each factory fitted
some segments are broken out. It works with two main elements, firstly a with Liebherr pan mixers. An upper floor is
The big 4m long invert sections also have to labelling and tagging system to trap and then used to assemble the steel segment
be made and stored. They use a different enter information and then a relational reinforcement cages.
concrete mix still. database taking advantage of the ways that Deliveries of cement, additives and in some
The invert sections mean you need extra data can be added together, cross referenced cases, aggregate, are by rail, says engineer
space for those to have their own areas even if and queried to bring up all the pertinent Robert Goliasch, on a line we built for the
sometimes it is left empty, says Lange. information about any particular item. project from the main line.
The solution to these problems, both Management audits, reports, and other The various component streams into a
tracking and checking elements and then information can be drawn out in myriad forms. segment each have a bar code, including the
storing and locating them has been a relatively VMT has also developed software within the concrete batch, the steel form itself, and the
complex database and tagging system system for highly accurate measurement and reinforcement cage. Tags are heavy duty
developed by TBM guidance system maker virtual 3-d modelling of segments and the weatherproof plastic stuck on the outside or in
VMT. Called rather prosaically the Segment mould they are produced in. the case of the reinforcement cages, are like
Documentation System it has been given one Modern segments are made to exacting airline baggage tags around one of the bars,
14 TUNNELLING JOURNAL
TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:36 Page 15
SEGMENTAL LINING
Above left: a partial Koralm Tunnel ring. Above right: barcoding of each individual segment modern Smartphones, with touch screens to
call up the appropriate menu, explains Lange.
The final segment gets a new barcode as it
also in heavy plastic. Each barcode number scanners to record the particular barcodes as leaves the mould, made up of the form code,
references data on the particular elements such they go through the process and enter further the reinforcement and the concrete, and this
as details of time and date of mixing, water details. Mould preparation, moulding, then allows its progress to be traced.
content, cement content and aggregate for the concreting, de-moulding, initial indoor curing That code is used to follow the segment
concrete, the rebar design for the cages or the storage for 24hours, and outside storage all through to the machine. The segment erection
particular mould and its laser scan details. see data entry. procedure at the machine also uses barcode
The workers in the factory have hand held The scanners are quite easy to use, like readers so that the exact segment installed in
Self-Drilling
lf D illi System
S t S
Solutions
l ti
AT Pipe
Pipe U
Umbrella
m b r ella S
Support
u p por t S
System
ys te m Quick - Safe - Reliable
Thee fastest
fastest and
and most most accurate
accurate c cased
ase d
drilling
ing system
system
Advanced
vanced drilling
d r illi n g u
unit
nit ffor
or a allll g
ground
round cconditions:
onditions:
from
m clay
clay to
to g
granite
ranite
Various
ious innovative
innovative p pipe
ip e c connections
onnections ffor or a
allll ffields
ields ofof application
ap
Unique
que AAutomation
utomation Un U
Unit it ffor
or u underground
nderground d drilling
rilling rrigs
igs
www.dsi-tunneling.com
TUNNELLING JOURNAL 15
TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:37 Page 16
the exact position in the tunnel is detailed. Preparation and arranging of the cages and the Herrenknecht Formwork segment factory
It means that very precise information is
available on every ring of the tunnel lining if
any issues develop, says Lehner. That allows
for a high level of fault diagnosis. Was there a
problem with the temperature, the concrete
mix, the rebar etc?
The individual segment tracking system has
another function too, in storage of the
segments. Because of the tight limits on space
Lange wants to avoid leaving empty voids in
the storage racks. But usually, to know where
segments are, and equally to access them
quickly, requires ordering then by type and age.
But the database can track very precisely
where a segment has been stored within the
yard, says Lange. That means the segments
can be piled up close and then to find any
particular type of segment and especially to
locate segments sufficiently aged for concrete
strength, the database is queried.
The 60t capacity Knz portal cranes used in
the yard work with such database storage
16 TUNNELLING JOURNAL
Seli_Pub_tj_II.qxp:Layout 1 19/03/13 11:48 Page 1
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 18
SEGMENTAL LINING
Pre-cast segments
The segments must achieve a minimum
strength of 15MPa before they are demoulded
and handled.
To ensure the segments wont be
damaged, the first thing is to have the correct
curing of the concrete, says Praut. If you
want to control and to set the same standard
for every single segment, you must have a
repetitive environment in terms of temperature
and humidity. You cannot do that with static
moulds.
Minimum strength assured, the next step is
to arrange every stage of the handling process
so that damage to the segments is avoided.
On New Zealands Waterview project, where
the segments weigh in at 10.6 tonnes, Wilson
Tunnelling has invested in all the latest
The Alaskan Way Ring handling and storage equipment in order to
assembled in all its glory achieve maximum efficiency, says Praut.
Handling and the logistics inside the
precast yard is a key issue, he says. You can
MOULD MANUFACTURER CBE GROUP can a narrower tolerance with a bigger surface. waste a lot of time by handling, moving and
now boast a hat-trick of mega-tunnels. Its The challenge is amplified, says Praut. turning these big segments. Wilson wanted to
latest contract in this family is the Bosphorous Imagine having the same tolerance over a have the most productive equipment for these
Strait Road Crossing in Istanbul, requiring rings 4m length as over a 2m length: its a very big big segments.
with an outer diameter of 13.2m. difference. They wanted to set a high standard for
The Istanbul project joins the Alaskan Way in Achieving those tighter tolerances requires producing segments in New Zealand. And
Seattle, with its 17m outer diameter rings and three things, says Praut: more man hours, the they may perhaps re-use the equipment for a
the Waterview project in New Zealand (see right equipment and a strict checking regime project following on from Waterview.
photo caption) which has a 14m outer using laser scanners. The equipment was manufactured by CBE
diameter. Though Alaskan Way is the big The extra time spent in making these Group company Acimex, which in February
brother of the trio, all these projects require moulds for mega-tunnels comes from the relocated from Paris to St Avertin next door to
the same, particular approach to mould iterative adjustments which have to be made its parent. Acimex supplied Waterview with
manufacture, casting and installation. to get the mould within those tight tolerances. equipment including a demoulding vacuum
The issue is precision, every step of the way, Laser scanning, which CBE has been using for lifter, a hydraulic turning device which restrains
says CBEs sales director Alain Praut: the last seven years, is a key tool in checking the segment on every access whilst rotating it
Because all of these tunnels are in seismic this. through 180 degrees and hydraulic trolleys
areas, the precision of the segments is a main Machinery is important too, says Praut. For deliver the segments automatically from inside
concern. example, the CNC machines which are used to the factory to the external storage yard.
In areas of seismic activity, the contact face machine the end faces of the moulds, which Due to the size of the segments, the
between segments is very significant. That will create the contact faces of the segments, equipment is pretty big, requiring a lot of
means any wrong positioning of the ring, must be big enough. design and a lot of complex systems such as
which can come when the TBM places the We have the capacity internally to machine the PLC and hydraulic controls, says Praut.
segments or due to the ring geometry, can the 8m-long sides in a single pass because we
break the segment, creating weakness or have the correct equipment to do it, says And so to site
failure in the ring. Praut. It means that we can guarantee the The theme of precision must continue once
This is something of which the tunnels geometry of that face and increase the the segments are on site, being placed behind
owners are very aware, says Praut. The accuracy. the TBM. During the boring process when
clients specifications are much more precise Once the moulds have been honed to the cylinders are pushing on the segments, the
than, say, for a 6m-diameter subway tunnel, perfection and delivered to the precast force required for these big TBMs is very
he says. On these projects control is very segment casting company, the next challenges high, says Praut. This means the position of
strict, very rigid. are how to produce accurate, identical the segments in relation to the previous rings
Insurance premiums on tunnels in this type segments and how to avoid damage during must be perfect. Otherwise the force from the
of geology are high, says Praut. The insurance demoulding, moving and storing. The only cylinders which are supplying the torque to the
companies demand more controls to reduce approach here, says Praut, is to create a cutting head can destroy the segment which
the premiums. manufacturing facility more akin to a car has just been installed.
production line. Human input is very limited A saving grace is that the advancement of
Precision, precision to avoid introducing stresses and to reduce the such large diameter machines will be slower
Avoiding the situation of an imperfect ring all change of mishaps, he says. than for a standard diameter TBM. The
starts with the manufacture of the moulds. For segments of this size, the only option is boring wont be very fast, so they will have
The challenge in making the moulds is having the controlled environment of the carousel. time to adjust the segments, says Praut.
18 TUNNELLING JOURNAL
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 19
SEGMENTAL LINING
TUNNELLING JOURNAL 19
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 20
SEGMENTAL LINING
of a typical multi-
33
layer system. And
second, the inte-
grated gasket
means build time
is speeded up
Herrenknecht
says by up to
50%. 8
20
Designed for
20 TUNNELLING JOURNAL
TJ_0513_ROUNDUP_018_021.qxd:Feature 21/4/13 12:27 Page 21
SEGMENTAL LINING
sewage, stormwater and sea water tunnels, whereas with pDCPD it isnt likely to. that you will wait for the panels.
Herrenknecht started to show this version of There are two main steps in the manufac- Producing them on site will bring big ben-
Combisegments to its customers around six ture of Combisegments using pDCPD. The efits of time and cost. If you want to use a
months ago. Although the target diameter is first is to create the pDCPD liner using simple PE pipe for lining the concrete seg-
the typical utility tunnel diameter of 2m to Reaction Injection Moulding (RIM). ments in a second step, you have to ship it all
5m, there is no limit as to what size could be The EDPM gasket, handling sockets and over the world. That means a lot of transport
the system for anchoring time and costs.
the liner into the concrete - With pDCPD, the raw materials are shipped
a polypropylene honey- to site, taking up far less space. The polymer
comb structure - are placed is created by mixing two liquid resin compo-
into the mould. Once the nents, supplied by Telene, which combine in a
mould is closed, the injec- chemical reaction.
tion process takes a maxi- Though pDCPD will be new to most tun-
mum of 20 seconds. nelling markets, it has been used in sewage
The second step sees the and water tunnels in Japan on 12 projects
resin liner simply laid in the since 1995. There, the process is different,
bottom of the concrete with sheets of pDCPD laid into the moulds,
mould. Reinforcement can which means that the joints must be sealed
be added as required, and after the segments have been installed.
the concrete cast in the Japans experience has provided useful for
usual way. Herrenknecht which has visited projects
In February 2013, where pDCPD have been used earlier this
Herrenknecht Formwork year. We were impressed by the quality of
built the first ever structure the tunnels, says Riechers. Test data from
using the second-genera- the Japanese Institute of Wastewater Engi-
tion Combisegments: a neering Technology has also served to corrob-
vertical test section at its orate Herrenknechts findings.
factory in Schwanau, In Germany, tests by the German Institute
Germany. Five rings and of Underground Infrastructures (IKT) are also
4m high with an internal underway, with the manufacture aiming to
diameter of 2m, the manu- have national approval by the end of this
facturer is inviting potential year. The segments are being put through
customers to come and their paces, with properties from water tight-
inspect it. ness to pull-out strength of the anchoring
system being tested.
Sights on site This is a big development for us, says
Herrenknecht Formworks Riechers. People have heard of Combiseg-
Above: The Combisegments test ring in goal is that the segments ments but they havent heard about this new
the Herrenknecht factory in Schwanau be made on site. We are planning right now version with this new material. I think it could
to be able to produce Combisegments on make a big difference in the market.
site, says Riechers. When you produce pan-
produced, says Riechers. Already, els in Europe and ship them to the Middle
Herrenknecht is in discussion about East, there will probably be increased costs Below: Tests being carried out by the
Combisegments use on a number of projects due to shipment and there is always a risk German Infrastructure Institute
around the world.
Roots in Russia
Herrenknecht launched its first GRP version of
Combisegments in 2007, with the first and
only - use on the Yuzhny Sewage Pipeline in
Tzariayno, Moscow in 2009. Although this
project was counted as a success, GRP offers
challenges during both the manufacture and
installation phases, so Herrenknecht began to
research alternative materials around three
years ago.
GRP is very rigid, says Riechers. It takes
a lot of effort to put it into moulds and to fix
the gasket.
pDCPD, on the other hand, is not rigid. It
has good impact resistance; some of its com-
mon uses are for bumpers on trucks or fend-
ers on agricultural and construction plant.
This property brings benefits during
construction too. If someone drops a hammer
onto the GRP lining it is likely to break,
TUNNELLING JOURNAL 21
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:38 Page 22
SEGMENTAL LINING
22 TUNNELLING JOURNAL
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:38 Page 23
SEGMENTAL LINING
(b) Transverse stress distribution (or as part of) the analysis to determine the Figure 4: Contact width and stress
bursting and splitting stress.
distribution at circumferential joint
For ram loading, the contact width is
Figure 2: Elastic distribution of defined as the portion of the ram pad which is CL segment
transverse tensile stress (y) for in contact with the available contact width,
e
rectangular end block taking into consideration offset of the rams
and tolerances of the segment position within Ram Pad
0.5 0 the shield. For ram loading, the contact width Nram
0.0 y
0.4 0 a/d=0.1 usually corresponds to the available contact
P tj
0.2 x width as the ram pad width can be sized to
0.3 0 0.3 iint tj/2 iext
0.4 accommodate the expected offset tolerances. t/2
0.5 tj
0.2 0 0.6 The general case is shown in Figure 4.
0.7 Establishing the contact width at radial joints
0.1 0 0.8
tj = MIN[(tj + bp e), tj] Equation (1)
0.9 is more complex due to deformation
tj = contact width
0.0 (ovalisation) of the ring and the accompanying
0 1/8d 1/4d 3/8d 1/2d 5/8d 3/4d 7/8d d tj = available contact width
rigid body rotation of the segments which bp = ram pad width
x
(a) Leonhardt, 1964 results in a slight opening of the joints. e = offset tolerance
Ovalisation can be caused by poor build,
0.5
0.4 a/d=0.1
0.2 Figure 3: Effect of contact stress distribution on magnitude of peak bursting
0.3
0.3 stress: Left - (a) Uniformly distributed contact stress. Right - (b) Linearly varying
/0
0.4
0.5
0.2 0.6 contact stress
0.7
0.1 0.8
0.9
0.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
x/d
(b) Finite element analysis
2.84 MPa
splitting. 2.23 MPa
For the typical range of tensile strengths
associated with steel fibre reinforced concrete
segments, bursting or splitting failure will
generally occur before sufficient contact stress
can be applied to cause a direct bearing
failure. However, direct bearing failure should
always be checked as part of routine design
and has been included in Table 1 for (a) Uniformly distributed contact stress (b) Linearly varying contact stress
completeness.
TUNNELLING JOURNAL 23
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:38 Page 24
Commitment.
7KHGHWDLOZKLFK
PDNHVWKHGLHUHQFH
,QWHUYHQWLRQFDSDELOLW\DQ\ZKHUHLQWKHZRUOGZLWKLQKRXUV
3URGXFWLRQLQFUHDVH
&RVWUHGXFWLRQ
0DSHL/HWVWDNHDGHHSHUORRNWRJHWKHUDW
www.utt-mapei.comKTXWW#XWWPDSHLFRP
/mapeispa
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:39 Page 25
SEGMENTAL LINING
joint contact stress produce strains over the cater for the total transverse tension force main effect of the steel fibre reinforcement is
segment length which lead to an increase in which is given by equation 2. an enhancement of the post-crack properties
contact area (closing effect) until a state of For joints subject to eccentric contact stress, of the concrete which leads to more ductile
equilibrium is achieved. The extent of joint conversion to an equivalent rectangular material behaviour. The increased ductility is
closure is a function of lining geometry, contact stress distribution and application of due to the ability of the fibres to transfer
concrete stiffness and magnitude of applied Guyons symmetrical prism as shown in Figure tensile stress across a cracked section and is
hoop load. The corresponding contact width 7 may be adopted to determine the equivalent dependent on the quantity of fibres added as
and stress distribution can be established in geometry for use with equation 2. well as their physical and mechanical
several ways: To control the width of potential bursting properties. The typical post-crack behaviour of
1. Closed form calculation assuming that and spalling cracks, design codes impose stress SFRC is shown in schematically in Figure 8a
the segment acts as a short column and that limits on the bursting and spalling and is characterised by a gradual reduction in
contact stress at any point on the joint contact reinforcement, typically in the range of 150 to tensile strength with increasing crack width
width is related to strain on the basis of a 200MPa. The design is therefore governed by known as strain softening.
simplified bi-linear stress-strain relationship for the serviceability limit state and the required Splitting tensile strength - The splitting
concrete in compression. This approach is area of reinforcement is determined in tensile strength of SFRC can be estimated by
suggested for routine design. Typical linear accordance with equation 3. The applying code formulae for the principal
Figure 5: Radial joint opening due to Figure 6: Contact width and stress Figure 7: Traditional reinforced
assumed elliptical deformation distribution at radial joint concrete design
N = N1 + N2
z CL segment d
1 = a =
p
N1 e e
2 ( )
2 N2 2
tj/3
d = a + 2i
iext T
iint tj/2
tj t/2
Poor build:
Tunnel profile Case 1: Stress diagram for joint closure
y as constructed End point of
segments, joints CL segment 0
Theoretical: z N
Tunnel profile
e T = 0.25 P (1 a/d) Equation (2)
as designed
1
Ast T / fs Equation (3)
b R L
T = total transverse tension force
L
P = applied contact force
c a = equivalent rectangular contact width
iext
iint tj/3 d = depth/width of symmetrical prism
tj t/2
x Ast = Area of reinforcement required
fs = tensile stress limit in reinforcement
a Case 2: Stress diagram for non-joint closure
TUNNELLING JOURNAL 25
TJ_0513_ARUP_022_026.qxd:Feature 21/4/13 12:39 Page 26
SEGMENTAL LINING
specimens, a number of methods to determined explicitly if there is significant factored loads shall be used in conjunction
determine the - relationship from the departure from the assumption of uniformly with the characteristic (un-factored)
results of beam bending tests have been distributed central loading on which the constitutive model and a numerical analysis
developed. These include DBV (1992), RILEM established normalised distributions of carried out. For estimating the maximum
TC 162-TDF (2002) and CNR-DT (2006). The transverse tensile stress are based. crack width, all strain between rams is
tensile strength values used in the resultant - The check is considered an ultimate limit translated into a single crack. This result is
relationship are derived from the state check if the analysis is carried out using then used to assess the serviceability of the
corresponding flexural strength using design (factored) loads and the resultant peak gasket. The acceptable crack width limit is
conversion factors which vary depending on bursting stress checked against the design in the order of 0.2 to 0.3mm.
the method adopted. The RILEM - splitting tensile strength which includes the
relationship is shown in Figure 8b. partial material factor for concrete: Conclusion
Elastic Analysis - The simplest approach to *y,p fctd.spl Equation (4) Given the trend towards larger tunnel
determine the peak transverse tensile stress is fctd,spl = fctk,spl /YC Equation (5) diameters, optimised segment thickness and
to set elastic material behaviour to the
concrete, apply the contact stress and carry out
the analysis. The resultant peak bursting stress Table 2: Suggested design procedure for SFRC segment joints
is then checked against the splitting tensile
strength of the concrete. Provided the peak Stage Description
bursting stress does not exceed the splitting 1. Contact stress (a) Establish the joint contact area and contact stress distribution
tensile strength of the concrete, the (b) Check the design bearing stress against the design bearing capacity
assumption of elastic material behaviour is 2. Elastic analysis (a) Carry out elastic analysis of the segment joint zones using factored loads to
considered valid. determine the distribution of transverse tensile stress
Elastic analysis to determine the peak tensile (b) Check the peak bursting stress against the design splitting strength
stress can either be done using the established (c) Check the peak splitting stress against the design splitting strength
elastic distributions of normalised transverse (If the splitting tensile strength is exceeded, the presumption of elastic behaviour is
stress for a rectangular end block available in invalid and non-linear analysis is required)
the literature (Figure 2a) or explicitly by linear
elastic analysis of a simple 2D numerical model 3. Non-linear (a) Carry out non-linear analysis using factored loads and constitutive model.
(Figure 3). For uniform contact stress, the analysis The ULS is satisfied if the factored analysis can converge.
maximum transverse tensile stress predicted (if required) (b) Carry out a non-linear analysis using unfactored loads and constitutive model to
using Figure 2 matches well with explicit 2D satisfy crack width requirements at SLS.
numerical analysis. For non-uniform contact
stress distributions, conversion to an equivalent Provided the design splitting tensile strength is hence increased stress at the joints, careful
rectangular distribution and application of not exceeded, the serviceability limit state will consideration in the design and detailing of the
Guyons symmetrical prism may be adopted so typically be satisfied on the basis that the con- segment joint zones is becoming increasingly
that hand calculation based on Figure 2 can be crete remains uncracked under the application important. This is particularly relevant for SFRC
carried out. However, hand calculation using of the service (unfactored) load. segments where introduction of traditional
these simplifications tends to over-predict the Nonlinear analysis - An elastic analysis will reinforcement solely to cater for tensile stresses
peak bursting stress. It is therefore generally only be successful for bursting at the joints can have significant impact on
checks. Elastic analysis of splitting stress be-
recommended that the peak bursting stress be production time and cost.
tween rams will typically show localised tensile
In many cases, provided the tensile strength
stress at the joint surface in excess of the split-
of the SFRC is properly specified and confirmed
ting strength. If the elastic peak tensile stress
Figure 8: SFRC material model with ongoing production testing and an
exceeds the splitting tensile strength, elastic
appropriate analysis is carried out to determine
analysis is not appropriate and a non-linear
the tensile stress induced at the joints,
Stress analysis is required.
First crack elimination or reduction of bursting
tensile strength
For non-linear analysis, incorporation of the reinforcement at the joints can be justified. The
non-linear strain softening material behaviour suggested design procedure for SFRC segment
Post crack is required to account for the local tensile joints is summarised in Table 2.
tensile strength failure of the concrete. The purpose of this
analysis is to determine whether the excess REFERENCES
transverse tensile stress (bursting or splitting)
can be satisfactorily redistributed once the
1. Leonhardt, F., 1964. Prestressed Concrete
Crack width peak tensile strength has been exceeded and
Design and Construction, English Edition,
(a) Typical strain softening behaviour the concrete has cracked. Non-linear analysis
Wilhelm Ernst , Berlin.
incorporating the strain softening constitutive
2. Mattle, B & John, M., 2009. Analysis and
model described in Section 5.4 may be carried
c design of unreinforced final tunnel linings.
out with finite element software.
Tunel, Vol 1, pp. 73-78.
To check the ultimate limit state, design
1 3. RILEM, 2003. RILEM TC 162-TDF: Test and
2 (factored) loads shall be used in conjunction
3 design methods of steel fibre reinforced
3.5 2.0 with a constitutive model that has been
1 2 3
concrete, --design method. Materials and
reduced by the partial material factor for
c [] Structures, Vol. 36, pp. 560-567.
concrete. The ultimate limit state is satisfied if
4. Warner, R.F., Faulkes, K.A., 1988. Prestressed
the subsequent numerical analysis can achieve
Concrete, 2nd Edition, Longman Cheshire Pty
a stable solution, i.e. the analysis can converge
Ltd, Melbourne.
(b) Simplified - relationship (RILEM)
to equilibrium.
To check the serviceability limit state, un-
26 TUNNELLING JOURNAL
Ground Support Systems
Minova tunnelling and civil business area delivers high performing ground support and consolidation
products and services to people working in tunnelling, infrastructure, construction and repair works. Our
expertise has been developed through growing our people complimented by our long and solid history in
global mining and tunnelling works. We are striving to be the preferred supplier of safe and high
performing products to people working in tunnelling and civil projects, anywhere around the world.
High performance injection resins and resin capsules (Polyurethane, Silicate, Acrylic, Phenolic)
Minova International
Tunnelling & Civils
info@minovaint.com
www.minovainternational.com
A
A member
memberofofthe
theOrica
OricaGroup
Group Ground Support Systems
TJ_0513_ITIG_028.qxd:Feature 21/4/13 12:46 Page 28
RISK REPORT
34 TUNNELLING JOURNAL
28
Let your skills take off
Aim for the sky with training from Atlas Copco Service
To get results and reach the top you need skill. With Atlas Copcos training products,
operators, technicians and specialists will learn how to master the machines in a
safe and sustainable way.
With our training products, where our sophisticated training simulators hold a key
role, they get to know their new workmate, inside out. Trained people perform
better, find their work more enjoyable and contribute to increased productivity.
Atlas Copcos training products add value to your operation.
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:12 Page 30
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:13 Page 31
WTC 2013
WORLD TUNNEL
CONGRESS 2013
With only a few weeks to go, from 31 May to 7 June, both the WTC 2013
and the 39th general assembly of the International Tunnelling and
Underground Space Association will take place under the motto
Underground the way to the future. The Swiss Tunnelling Society
(STS) is the host in the beautiful Swiss city of Geneva.
SWITZERLAND IS WELL KNOWN for features at this years event. For example, the introduce itself to a larger audience regularly
scenic landscapes and outstanding ITAtech Committee will make a prominent in the context of the presentation forum.
infrastructure as well as its well-developed appearance for the first time at the WTC The presentation forum planned in Geneva
transportation system. The many innovative 2013. On Tuesday afternoon, 4 June 2013, it is located in the exhibit area and offers
solutions employed in the construction of is organising a special session called the exhibitors and participants the opportunity to
Switzerlands numerous tunnels and ITAtech Innovation Session. There, present their newest products, innovative
underground facilities have demonstrated information will be provided about the applications and interesting case studies.
the nations pioneering spirit time and ongoing efforts in the Activity Groups of
again, underscoring its position at the top ITAtech and the first round of guidelines Deminar on sprayable waterproof
of the tunnel construction technology field. developed will be presented. These describe membranes
both the state of the art and best practice A special event within the framework of
ITAtech guidelines with regard to innovations and new technical the WTC 2013 in Geneva is the deminar
Visitors can look forward to many new developments. In addition, ITAtech will on 31 May in the Hagerbach Test Gallery
TUNNELLING JOURNAL 31
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:13 Page 32
WTC 2013
Alphabetical
exhibitor overview
No Company Name
1 AFTES Plant Equipment Branch
2 AGIR Aggregat AG
3 Altamira Information/Subterra
4 Amberg Group
5 Arcadis Geotechnika a.s.
6 ArcelorMittal
7 Astra BAV
8 Atlas Copco Schweiz AG
9 BASF
10 Becker Mining America
11 Bochumer Eisenhutte Heintzmann
12 Brokk AB
13 Caterpillar Tunneling Canada Corporation
14 CBT Brazilian Tunnelling Committee
15 CIFA SpA
16 Dtwyler Sealing Technologies Deutschland GmbH
17 Denka Chemicals GmbH
18 DESOI GmbH
19 Dextra Group
20 DMT GmbH & Co. KG
21 DSI Dywidag-Systems International / Geodata
Ziviltechnikergesellschaft Austria
22 Ein Shemer Rubber Industries Ltd
23 Elkuch Bator AG
24 Fermacell GmbH
25 FiReP Rebar AG
26 FOGTEC Brandschutz
27 Geodata S.p.A., Torino
28 Geokon Inc.
29 germanBelt Systems
30 Giertsen Tunnel AS
31 Halfen GmbH
32 H-Bau Technik GmbH
33 HBI Haerter Consulting Engineers
34 Herrenknecht
35 HIC Corporation
36 Hilti (Schweiz) AG
37 Holcim (Schweiz) AG
38 Implenia AG
39 itech
40 itmsoil on the topic of Sprayable Tunnel Sealing this knowledge to the international
41 Jordahl GmbH Membranes. This deminar will also be tunnelling community. All lectures of the
42 Liebherr-France SAS
43 Lombardi SA organised by ITAtech. Sprayable sealing Swiss Session will be given in German,
44 Maccaferri S.p.A. membranes offer new opportunities in the French, Italian or English and will be
45 Mapei construction of tunnels. Over the past interpreted simultaneously into English or
46 Marti
year, the ITAtech Activity Group Lining German.
47 MATRICS Consult Ltd.
48 Messe Berlin GmbH/InnoTrans and Waterproofing has worked on this
49 Metalliance intensively and has developed a design The upcoming generation Young
50 mineARC Systems guideline for the application of sprayable Swiss Tunnellers
51 Minova MAI GmbH
52 NFM Technologies
waterproof membranes. It will be Students will be offered the opportunity
53 Normet International Ltd. presented in the context of the deminar. of presenting their semester projects and
54 NV Bekaert SA The deminar combines presentations, as diploma theses to a larger audience of
55 Pavemetrics Systems inc. / EUROCONSULT Nuevas are customary in a seminar, with the industry professionals at the WTC 2013.
Technologias, S.A.
56 Pyry Infra AG
unique opportunities afforded by the test This, too, is a premier! The students will
57 Promat AG gallery at Hagerbach to demonstrate the gain insight into the international world
58 Rascor International AG application under realistic conditions. of underground construction, which will
59 RBL-REI France certainly be a valuable experience for
60 Rocksoil S.p.A.
61 ROWA/Belloli Dont miss them: The Swiss Sessions them. The organisers wish to set an
62 S.E.L.I. SpA Every June, the Swiss Tunnel Society holds example with this special session for a
63 Sandvik / Avesco the Swiss Tunnel Congress in Lucerne. In stronger commitment to the promotion of
64 SBV / Infra 2013, it is being moved to Geneva and the upcoming generation.
65 Schauenburg Group / Herco Kuhltechnik
66 SIKA / Putzmeister integrated in the WTC as the Swiss
67 SIREG S.p.A. Session. All WTC 2013 participants are The conclusion on Lake Geneva
68 SPS Consulting free to participate in the Swiss Session. Also on Wednesday evening, 5 June 2013,
69 Stirling Lloyd Polychem Ltd.
On Tuesday afternoon, 4 June 2013, the the traditional concluding banquet will be
70 swiss IT-Factory AG
71 T.R.E. srl Tele-Rilevamento Europa colloquium will take place followed by a held on three large, historic steamships on
72 TAC Corporation day of selected lectures and presenters on Lake Geneva. The special ambience of
73 Terratec, Tasmania Australia Wednesday. The main focus of the Swiss these ships, maintained in original
74 The Norwegian Tunnelling Society NFF
75 The Robbins Company
Session is provided by the experience condition from the Belle Epoque,
76 Trelleborg Ridderkerk BV gained in the construction of the two together with the incomparable landscape
77 Vik rsta AS base tunnels, Ltschberg and Gotthard of Lake Geneva will provide a worthy
78 VMT GmbH through the Alps. The intent is to pass on context for this exceptional occasion.
32 TUNNELLING JOURNAL
TJ_0513_WTC_030_033.qxd:Feature 21/4/13 13:13 Page 33
www.normet.com
www.taminternational.com
SOLUTIONS FOR
TOUGH JOBS
HIGH QU
QUALITY
ALLIT Y GASKE
GASKETS
TS
International Exp
Experience
perience
Proven longevityy
www.datwyler.com
TUNNELLING JOURNAL 33
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 34
PROJECT POLITICS
BY NOW MANY tunnellers are familiar with construction, but many politicians overlook the generally a government agency with a board
the story of the Access To the Regions Core underground option. Steve Skelhorn, Project consisting of politicians, not engineers. This
(ARC) tunnel in New Jersey, USA. The 14.5km Sponsor at McNally Construction Inc., an makes decision making very time consuming.
tunnel was to be driven below the Hudson experienced contractor, gave his take. Also as it is usually public funds there tends to
River between the states of New Jersey and Committing huge sums of tax payers money be a lot of time and energy diverted to public
New York, and would have doubled commuter for a perceived benefit in say 20 years time is opinion, sometimes at the expense of progress
rail capacity between the two. The project, not necessarily on a politicians agenda. It is of the tunnel. Different procurement processes
however, was short-lived: After spending about often the case that the politicians will go for a that dont only focus on the low bid could
US$600M to begin construction, New Jersey rapid fix a short-term gain option over long- alleviate many of these issues. During the
Governor Chris Christie called for a halt to the term investment. This might be providing new procurement of the SR 99 TBM, for example,
project due to cost overrun concerns. While buses or streetcars over building a subway, for weight was given not only to cost, but also for
some form of the project is still in discussions example. Obviously we cannot get away from technical merit of the design.
and officials are looking to revive it, another politicians on these projects as it is generally Worldwide, political ramifications affect
run at a trans-Hudson tunnel is estimated to be public money, but we can educate politicians projects throughout excavation, not just during
at least a decade away. and the public more. There appears to be a lot startup. Government support can play a key
As projects and their investments become of misinformation surrounding tunnels and the role in a projects success.
larger, politics will have an ever-larger role, with tunnelling industry.
both positive and negative aspects - a Some public shareholder groups, like those Mexicos Emisor Oriente
dichotomy that can make a project complex involved at Seattle, Washington, USAs SR 99 At 63km long, Mexico Citys Emisor Oriente
before anyone even starts digging. Tunnel project have been successful in arguing Wastewater line is a vast undertaking and the
for an underground option over alternatives countrys largest infrastructure project by far.
Political involvement - the pros and cons such as new bridges and surface streets. But The pipeline is being built both to prevent
Political involvement can boost a projects Skelhorn sees an ongoing need for new flooding and to add much needed capacity to
status and place it on the fast track to practices, In large projects, the owner is the areas growing population. Ground
34 TUNNELLING JOURNAL
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 35
PROJECT POLITICS
TUNNELLING JOURNAL 35
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 36
PROJECT POLITICS
carry wastewater from Mexico City to several designated Lot 1 site prompted a swift Mexicos current President, Enrique Pea
water treatment plants currently under machine change in 2011. The first piece of Nieto of the Institutional Revolutionary Party,
construction in the state of Hidalgo, where it this project is the critical 10km section at Lot 1. dedicated more funds to the project in 2013 to
will then be recycled for safe use in agriculture. The first Herrenknecht TBM started in shaft 0 in ensure completion of the entire line by its new
The construction of the line was divided into 2009, but was stalled for six months due to a schedule of December 2016. They have a
six lots - Lots 1, 2, and 5 under Mexican flood. In order to finish in time, we brought in positive attitude with us, CONAGUA. They are
contractor Ingenieros Civiles Asociados (ICA) a Robbins TBM originally slated to work on Lot working with us to develop programs to
S.A. de C.V, and Lots 3 and 4 under Carso 5, shaft 20. The TBM bored at Lot 1, shaft 5 in analyze problems and challenges that come
Infraestructura y Construccin, S.A. de C.V. Lot the opposite direction towards the TBM in up, said Carillo.
6 is under construction by Lombardo shaft 0, said David Juarez, then Site Manager Its the best thing that could have
Construcciones and Constructora Estrella. All for ICA. Due to the loss of slope, the Gran happened; we now have more support from
six lots were designated for excavation with Canal at Lot 1 now has a positive vertical government and the opportunity to purchase
8.93m diameter EPBMs, with Robbins alignment below Mexico City and the Ecatepec more equipment. The new administration
supplying three EPB machines and area just outside of the city. Increased volumes wants the project done as fast as possible and
accompanying continuous conveyor systems, of water have the potential to overload current has more than doubled the budget for the
and Herrenknecht supplying three EPBs. pumping stations and send the untreated project, said scar S. Aguilar Prez,
With support from Caldern and water back into the city. Construction Manager for contractor ICA.
CONAGUA, the project began and TBMs were The Robbins TBM completed its 3.5km With the support of the government,
procured in 2010. Prior to the Emisor Oriente tunnel in autumn 2012 after achieving fast contractor, and equipment suppliers, the
there were no tunnels in Mexico for many advance rates up to 592m per month, and is machines are overcoming significantly
years. When the project started, the now being disassembled and sent to its original challenging ground conditions. The three
government and contractors began employing Lot 5. A treatment plant and a pumping station Robbins machines were built to excavate lake
university graduates and people who had at Shaft 5 of Lot 1, is now going online to clays, volcanic rock, and boulders up to
worked on tunnel projects in the 1980s and pump the water diverted into Emisor Oriente 600mm in diameter. The ground conditions
earlier, said Hector Carillo, Machine back into the Gran Canal where the slope has have been identified as some of the most
Superintendent for contractor Carso. not been affected. The finished section has complex in the world - abrasive basalt up to
After repeated flooding of the Gran Canal, been sealed off from the rest of construction. 80MPa UCS is mixed with sections of watery
an untreated waterway at the Lot 1 site, Once Lot 1 was completed, a new President clay that have been compared to a soup, while
governmental agencies declared that section of took office and appointed a new set of officials water pressure is estimated in the range of 4 to
the project a national emergency. at CONAGUA to advise on the project, as these 6bar, some of the highest pressures EPBs have
Although six TBMs were slated to bore at positions at the government agency are worked under.
each lot, problems in shaft 0 at the critically- affiliated with political parties. To tackle the conditions, Robbins engineered
Mining Dresden
Branch of Herrenknecht AG
36 TUNNELLING JOURNAL
TJ_0513_DESIREE_034_037.qxd:Feature 21/4/13 16:41 Page 37
PROJECT POLITICS
TUNNELLING JOURNAL 37
TJ_0513_038_039_BTS_Conference_Ad_.qxd:Layout 1 21/4/13 13:40 Page 38
bts
2013
EVENT VENUE:
THE QUEEN ELIZABETH II
CONFERENCE CENTRE,
Broad Sanctuary,
Conference and Ex
Exhibition Westminster, London
SW1P 3EE
Co
BER 23 24, 2013
OCTO nt deliver
ces that simply do
Tired of conferen British
e. Thats why the
on content? We ar ed up
y (BTS) has team
Tunnelling Societ to host
urnal and Brintex
with Tunnelling Jo em ier
ent at Londons pr
this first class ev conference ve nue.
that address
and or ig inal presentations
Fo cu se d tunnelling will
l ch alle nges of modern
the tech nica l standing,
rts of internationa
be given by expe m sessions,
w ith pa ne l debate and foru
com bine d n and the
a tailored exhibitio
the BTS lecture, s most high-
ty to visi t some of London .
po rtu ni truction projects
COPYRIGHT CROSSRAIL LTD
op
profile tunnel cons
elling capital,
in Lo nd on, Europes tunn
So jo in us ing of a new
itness the beginn
this October to w generation of tech
nical
conf erences
,
inform ation ab out the conference contact:
For mo re ase
or spo nsors hip opportunities, ple
exhibit
Gary Tween ion, Speaker an
d
ate R eg istrat
Bill Butler Deleg
the Exhibition portunities
Stand Space at Sponsorship op
720 631
73 6627
Tel: + 44 (0) 20 79 luk.com Tel: + 44 (0) 1622 lingjournal.com
el
Email: b.butler@
hg Email: gary@tunn
ns and Themes
io
Conference Sess
urement?
DAYn 1 What is the futu
re for tunnel proc K - The Tunneller's Agenda
- Infrastructur U e
1
Sessio tinuity
Keynote lectures Ahead To Ensure Workload Con
ng
ITACUS - Planni
cluding
en ta tio ns w ill cover themes in
Session 1's pres ement strategies
Tunnel procur
TBM procurem
ent ty and risk
oi l m an ag em en t the opportuni
Sp
Logistics and
ur in g in su rance
Proc
actice
- Pu tt in g Design into Pr
rayed Concrete
Li ni ng ent structures
Session 2 Sp tu re of pr im ar y linings as perman
The fu
undaries of SCL e sprayed system
s?
Pushing the bo tly w he re ar e we now with th
- Ex ac
Waterproofing at won't go away
Fi br es - The argument th aterials technolo
gy
Steel v Pl as tic
th e fa ce of SC L with modern m
ngin g a
Materials - Cha from the floor to
on ym ou s 'b al lo t box' questions
g an
l Debate featurin
3 - A 'N ew sn ight' style Pane in in !
Session couraged to jo
. Delegates are en
panel of experts
nks Reception
m ee tin g, fo llowed by a Dri
Monthly BTS
DAYn 2
1 - The Fu tu re fo r TB M s and Segmenta
l Linings
TBM technology
Sessio es in
Recent advanc Ms
ecifications for TB
Performance sp
s explained
Grouting system spoil removal
ce lo ss an d ke eping a check on
Fa
ing roundup
Segmental lin
systems
Muck removal
e Industry?
ri ng Really Taught th
t ha s M on ito ss for design? onths, 18 month
s?
Session 2 - Wha propriate face lo e monitoring, 3 m
What is the ap ca le fo r ba se lin ns ul ta nt or contractor?
eal times the client, co
What is the id rin g co nt ract or -
ocure the monito
Who should pr it rig ht
- getting d processes?
Specification ria te trigger values an
th e ap prop
What are
follow
O pe ra tio ns Information to m the two days
Session 3 - Tu nn el
rin g so m e of th e salient points fro
yle Debate cove
4 - Th e cl os in g 'Newsnight' st
Session
ww.BTS2013.com
To join us visit w
2013.com
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 40
REMEDIATION
40 TUNNELLING JOURNAL
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 41
REMEDIATION
But this was a new monitoring system at Embankment, 300m wide and 12.5m deep
Figure 1: Section of the geology
INE
which required adaptation. It was potentially at its biggest point.
surrounding the Jubilee Line in the a big risk for London Underground and What we dont know is why this once-dry
affected area Costain Laing ORourke to take up, says sand channel now contains water. Analysis of
Wright. I was recommending we go for the the geochemistry of the water in the sand
system. London Underground financed it, channel shows that it is not coming from the
Superficial Deposits Costain Laing ORourke supported it and both surface or from a leaking main, but that it is
parties were prepared to take the risk. probably old groundwater.
30m Jubilee Line tunnels London Clay
The mitigation of that risk came from the Every test showed us it was natural
amount of time spent studying the tunnel, the groundwater, says Wright, who in 2010 was
Sand ground and the monitoring; the combined working for Tube Lines, now Transport for
Channel Lambeth Group competence and sheer brain power of the London, and whose involvement in the project
multi-disciplinary engineering minds continued when he moved to his current role
300m
assembled round the table; and Senceives at Halcrow. It could be recharging from the
confidence in its technology: We knew there chalk aquifer, but at a different location.
were a lot of challenges in there but we were The water table in London has been rising
Figure 2: A possible scenario of very confident that we could do it, says since the 1960s when the city started to lose
what could have happened Maddison. its industries, particularly breweries which were
thirsty customers. In 1992 parties including
Geology unfolding Thames Water, British Telecom, the Association
It seems incredible that the ground beneath of British Insurers and the Corporation of
London, which has more holes in it than a London formed the General Aquifer Research
piece of Emmental cheese, still has mysteries Development and Investigation Team (GARDIT)
to reveal. But indeed it does. Geologist which ultimately resulted in the sinking of a
Jacqueline Skipper of Geotechnical Consulting number of boreholes to pump out water and
Group is helping to unfold some of these artificially maintain a lower water table.
mysteries. At that point it was not realised that there
We have always had simplistic models of was an intermediate aquifer in the Lambeth
the ground in London, says Skipper. What is Group sands, says Skipper. The tunnels
clear now is that it is much more complicated might well have been drier in the 1970s when
than we thought it was. they were constructed, as it was not long after
began, requiring 2,000 gauges and a One complication we are discovering the point of maximum draw down. However it
spaghetti of wiring. includes a small number of deep, sand filled could also have been a short-term climate
The network of wireless gauges also channels in the Lambeth Group, which are effect.
allowed the engineers and geologists to make more common than we realised, and which
decisions about the next night shifts grouting, can only be identified with good quality A unique operation
based on what had happened the previous ground interpretation data. We know for sure that in 2010, the sand
night. Combining the data from the gauges We now know that there is a large sand channel was no longer dry. From September
with information from Bachy Soletanches channel that runs diagonally across the line of that year onwards Tube Lines, which was then
bespoke grouting control software helped Oxford Street, Londons busiest shopping operating the Jubilee Line under a PPP deal,
build a better picture of the ground in that street, its upper surface at 30m below ground had to clear sand from the track bed, an
area. level. It is the size of the current River Thames estimated 0.25 tonnes a week with an
TUNNELLING JOURNAL 41
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 42
REMEDIATION
42 TUNNELLING JOURNAL
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:34 Page 43
WTC20it13us
is
... come v 9
at stand L
SUBSCRIBE NOW!
To order, visit www.tunnellingjournal.com and click on Subscription Offer
TUNNELLING JOURNAL 43
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 44
Constructing a
Sustainable future.
At VINCI Construction Grands Projets, we engineer solutions that are not only
financially competitive, but work sustainably for the planet. It starts with putting
Safety first, always, at all times, on every site. Health & Safety training, policies
and guidelines are all in place, but to generate the best possible results, we go
further with our innovative (A)live on Site programme. We understand that our
people are more reactive to what concerns them directly, we have a team who
visit the site, shoot a short movie and then broadcast it to the team. Each scene
photo credits: MVB, VINCI and subsidiaries photo libraries, Andras Nemeth, Clarence Michel.
is analysed with behaviour experts, underlining the good (and less good) actions.
(A)live on site has been successfully delivered to more than 2,000 people, in 12
languages, across 14 countries, including the UK.
To learn more please visit www.vinci-construction-projects.com/british-isles
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 45
REMEDIATION
and managed to find a route through. need, but that would be a typical to an adjacent one, whatever position or
Kettle came up with an intricate system frequency, says Maddison. Peter wanted sequence they find themselves in, so nodes
of looped supply and return lines for water once a minute. can be moved round to accommodate
and spoil wash-out (see diagram p42). To Speeding up the reporting frequency equipment and even if one were to be
get the grout lines, spoil collector lines and required Senceive to upgrade the damaged, the system could function.
water from the cross passage to the furthest performance of its mesh network. The There were some changes to
point of injection and back, Bachy had to sensors all take readings and talk to each accommodate on the hoof. We had to
devise a low profile ring mains with regular other, with the information finding its way meet some challenges we had not
take off points, compact fittings, and back to a gateway in the case of the anticipated, says Maddison. None of us
removable head assemblies.A big knew exactly what
proportion of the money went on that we would need
grouting system, says Austin. Monitoring the tunnel once we were
The grout itself had an unusual suite of with a trusty laptop down there. It was
properties. It was immiscible with water and a matter
of high solids content so that it could be sometimes of
injected through static or flowing water; it coming off the
had to be sufficiently fluid to act as a shift, writing
contact grout where there were no down the task list,
significant voids, and permit pumping having the team
through long and intricate supply circuits; it work through the
was very low bleed; it had a pot life of day upgrading
between six and 12 hours; and it was and taking it back
sulphate resistant. the following
Bachy Soletanche designed the mix night.
initially in co-operation with BASF, and then One adaptation
refined it in the firms Paris materials came a few shifts
laboratory. The mix comprised water and in, when the
cement grade 11/B with a water cement review team
ratio of 0.56, plus anti-washout agent making the day-
Rheomac UW400, Glenium fluidifier and time decisions to
Delvo stabiliser. steer the night-
In terms of workability, the grout was times work
very good, says Spyvee. It did not give us decided that
issues in pumping the grout into the cross Jubilee Line, a lap top the best way it can. monitoring should continue during the day.
passage and it remained workable for the Sensors are switched on by the network They wanted to see whether the grout had
duration of the shift. only for a short period when reporting in gone off or whether it was still hardening,
Shifts, of course, were not very long. This order to conserve their batteries for years of and the tunnel still moving.
was a live metro with all the work taking life and communicating. If you want to Senceive could not leave laptops down in
place during three-hour night-time report once per minute with 100 nodes, you the tunnels, so installed more nodes to take
maintenance periods. It is quite common run into all kinds of problems with network the signal through a cross passage, up a
that we would have two-and-a-half hours a congestion, says Maddison. We had to do 30m-deep shaft and into a small room in the
night, once the traction current was very ingenious things in order to get the station. It was all done within 10 minutes
discharged and allowing sufficient time to reporting rate up to be able to support 100 of hand-back, says Maddison.
check the track, tunnel clearance and nodes. In the event the day-time monitoring
monitoring data to ensure the tunnel had Another issue was that Senceives tilt showed that the grout had stiffened
stabilised, says Austin. meters were not sensitive enough for this sufficiently before the trains began to
The first task was to get the job. So they integrated a new version that run.We did not use the traffic hours
instrumentation up and running. Fast was 10 times more sensitive. monitoring so much because we found out
deployment of the network was a real Fixing the gauges to the tunnel has also it stopped moving fairly quickly, says
challenge, says Maddison. When you are given rise to an innovative fixing system, Austin.
installing it on a railway bridge it does not patent pending. Maddison and Wright
matter if it takes one hour for the network worked together to develop the fixings Real time monitoring
to settle down. If you are installing it in an using strong magnets, with Wright even The monitoring was crucial to and central to
underground tunnel at 01:10, at 01:30 you testing the sensors while mounted on his the grouting operation. An OTB monitoring
have the grouting engineer shouting When own radiators, discovering they were strong engineer - or more often than he would
can we start? Its a different kettle of fish. enough to take the paint off. have liked, Maddison himself - would be
Before Senceive could deploy its system in Despite the damage to his home, Wright crouching in each tunnel with a laptop,
the tunnels, it had to carry out three months is pleased with the magnets. The network watching the movement of the rings as the
of serious and intense development work. is very simple to install, says Wright. The grout went in.
The five-year old, high-tech start-up operatives down there knew where to put The deformation of each ring had, before
company, a spin-off from University College the nodes. You brush the crud off and stick grouting began, been checked and classified
London more usually monitors civil them on. They were very comfortable in using a laser spot survey. Those rings with
structures using crack gauges and tilt doing that within a couple of shifts. the greatest deformation were assigned the
meters: railway viaducts and other bridges, The simple and robust fixing method smallest trigger level of 2mm; if the ring
retaining walls and embankments. combined with the fact that the monitoring moved by that amount during grouting, the
Monitoring bridge or earthworks require system employs a mesh network made it grouting had to stop. Where rings showed
one reading per hour thats more than you ideal for this application. Any node can talk hardly any deformation, that trigger level
TUNNELLING JOURNAL 45
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 46
REMEDIATION
02/05/10
10/08/10
18/11/10
26/02/11
information, together with the data from It was a work in progress, says Spyvee.
Bachy Soletanches bespoke pumping Towards the end, we perfected it. If you
software went to the day-time Project Time see something graphically, you pick up
Engineering Review Panel (PERP) meeting so things you might miss if you were looking at
that the instructions for the next nights Tilt in mm/1500mm tables of data.
10
work could be defined. 9 Wright, in fact, represented all the
Ring 1-A
Skipper describes this as an observational 8 monitoring information graphically,
7 Ring 1-B
method: You dont just squirt grout in and 6 Ring 1-C preparing a double-sided sheet of A3 for
5 Ring 1-D
then everyone goes home. 4 Ring 1-E
each of the review meetings. This is
Though mostly the grouting took place 3 definitely a practice that he, and others,
Tilt
Ring 1-F
2
from track bed level upwards, this 1 would take on to further jobs.
sometimes varied depending on what the 0 As to whether there will be other jobs just
-1
deformation of that ring was. It was a case -2 like this one, that is another unanswered
-3
of pinpointing where the deformation was -4 question. There are more sand channels,
and working round that problem, says -5 says Skipper, discovered on other current
09/11/2011
09/11/2011
00.57
09/11/2011
01.26
09/11/2011
01.55
09/11/2011
02.24
09/11/2011
02.52
09/11/2011
03.21
09/11/2011
03.50
09/11/2011
04.19
00.28
Skipper. jobs.
There was potential to push the tunnel Skipper is currently working to develop a
back into shape, although we never geological model to find out where the
achieved it due to the limiting pressures, Time channels may be and where there could
says Austin. potentially be risk in the longer-term. The
The tunnel did not move significantly, along the outside of the tunnel until the rising water could have repercussions due to
says Wright. There were some places grout could meet up with an area where the the recharge of hydrostatic pressure in
where the shape was changed fairly rings were completely surrounded by clay. tunnels and especially in escalator shafts,
significantly, but they were areas where the The grouting operation took four months she says.
tunnel was in quite a good shape to start to complete. Over that time, all the For Senceive, the Jubilee Line remediation
with. constituent parts of the engineering jigsaw project has turned out to be just the
The aim for each shift was to grout 10 evolved a little. beginning of the story for tunnel
rings although this varied, depending on Down the tunnels, the grouting gang monitoring. Because the system is so
how much grout each ring took. became more and more efficient. They got flexible, so robust, and after the
Sometimes you would get an area that better and better at judging when to make development work done on this project, so
would take a lot more grout and so you the call to pack up the equipment, says quick to set up, it lends itself perfectly to the
would do less than a 10-ring pack, says Spyvee. With the effect of not finishing on unpredictable environment of tunnel
Spyvee. time being potential delay to the mornings construction and monitoring.
What we did not anticipate was that Jubilee Line service, the stakes were high. The monitoring systems success and
there would be considerable flow of grout This meant Bachy Soletanches logistical potential was recognised in January this year
behind the lining, says Austin. We would planning had to be done with military by the ITA when the team won the Product/
be grouting behind one area but it would precision. Before the possession period Innovation of the Year category in the
take a lot more grout because it would flow began the grout had to be prepared and the International Tunnelling Awards 2012.
behind the back of the lining to another surface and the supply circuits and agitators Its the sort of story that every high-tech
area where there was a void or running in the cross passage charged. start-up company dreams of. Already
sand. Then when you got to an area where Both start-up and shut-down for the Senceive has won several more tunnelling-
there had been running sand and the grout grouting equipment and operations had to related contracts, with developments to
had flowed in the night before, you did not be swift, with the vital task of cleaning out allow remote monitoring via a number of
get anything in. all the circuits and equipment at the end of different routes. From our point of view
Bachy had to grout the rings in sequence, each session. This last task was especially this was a phenomenal opportunity, says
aiming to push the water and flowing sand critical because of the very high cost of Maddison.
46 TUNNELLING JOURNAL
TJ_0513_JUBILEE_040_047.qxd:Feature 21/4/13 14:35 Page 47
SYNTHETIC FIBRE
SEGMENTAL LINING
INVERT SLABS
CONCRETE TRACK SLAB
REPLACING STEEL
SHAFT LINING
PORTAL STABILISATION
REINFORCEMENT IN CONCRETE ROADWAYS
WWW.ELASTOPLASTIC.COM
TUNNELLING JOURNAL 47
Join us at the
World Tunnel Congress 2013
May 31 June 7, 2013
Geneva, Switzerland
SUSTAINABILITY
1%
Figure 1 says it all:
However, this article will not be the usual yadda-yadda. At least, I 0.1%
havent read anything similar before, and if you have thought the same 2036: Sustainable occurs
0.01% an average of once per page
thoughts then we must meet and compare notes. First, I am going to
Present day
convince you that sustainability is the basis of all good engineering 0.001%
decisions. Then it will obviously follow from this that good engineers have
sustainability embedded in their thought-processes and will automatically 0.0001%
generate sustainable solutions. To make more good engineers who think 0.00001%
sustainably we need to implement a sustainability culture within
organisations and within our profession. 0.000001%
After all that ground work, for those hard-headed people out there Ill
60
80
00
20
40
60
80
00
20
40
19
19
20
20
20
20
20
21
21
21
present the overwhelming business case for sustainability. Finally Ill end Year
with a vision of a smart and sustainable future.
Sustainability is just good engineering the public good and an ethical (and legal) duty footprint, as well as the cost of construction,
The United Nations Brundtland Commission to protect the environment. Therefore, the are all examples of social, environmental and
described sustainable development as impacts on the local community, the health economic considerations that are part of the
meeting the needs of the present without and safety of the workforce, the durability and decisions we make. These issues are all
compromising the ability of future generations longevity of the structure, the need for important and can all be captured under one
to meet their own needs. This doesnt mean, maintenance, the energy use in operation, the of the three pillars, so sustainability gives us a
for example, that we have to stop using non- environmental impacts and the carbon framework that assists us in making good
renewable resources right this minute, because engineering decisions.
that would result in great human suffering, but I hope I have convinced you that
Figure 2: Venn diagram of
we need to be moving away from them and sustainability is not only an important and
sustainable development (United
investing in a sustainable future. To achieve this worthwhile thing to do, but it can be used as
Nations General Assembly, 2005).
we need to take an ethical, long-term, systems- the basis of all good engineering decisions. It is
based approach to the planet. a framework for identifying issues and
A useful framework for understanding measuring the performance of any
sustainability is to consider three pillars social, intervention. It isnt an extra thing we have to
economic and environmental and balancing Social do; it is a way of thinking that should be
these sometimes competing demands will embedded in the way we work. Engineers
result in sustainable development. I prefer the make dozens of decisions every day, and if we
mnemonic people, profit, planet as it is easier think people and planet as well as profit, well
Bearable Equitable
to remember. The three pillars are often make better decisions.
represented visually by the Venn diagram in Since I have just used the words basis for all
Sustainable
Figure 2: engineering decisions, a way of thinking and
Now, what does this have to do with us as embedded in the way we work, it should be
engineers? First off, we should consider what it Environment Economic clear that in order to change the way we make
means to be a professional engineer. It is not Viable decisions, the way we think, and the way we
just about providing cost-effective technical work requires a cultural shift both in
solutions. For instance, the code of conduct of organisational culture and professional culture.
the Institution of Civil Engineers states that civil This sustainability culture is the ideas and
engineers have an overriding responsibility to beliefs that all members of an organisation
TUNNELLING JOURNAL 49
TJ_0513_049_051.qxd:Feature 21/4/13 15:24 Page 50
SUSTAINABILITY
share about sustainability. The challenge of require us to leave about two thirds of it in the technologies to collect data and create
achieving this could be called implementing a ground, resulting in a huge reduction in synergies, for example to reduce energy use,
sustainability culture. demand for oil, a collapse in prices and a pollution or traffic jams.
collapse in the valuation of reserves (HSBC The way we work has been changing rapidly
Implementing a sustainability culture Global Research, 2013). According to HSBC, with technology such as the internet, email,
An example of a cultural shift that has been the market capitalisation of oil companies is social media and smartphones. Work/life
implemented in the past is the way in which overvalued by 40-60%. So clearly people who balance is now difficult to achieve due to a
safety culture has become the norm. are buying shares either assume these climate phenomenon called work/life merge we can
Nowadays, most engineers automatically change targets will not be met, or are taking a now work from home and on the move, and
consider health and safety in every decision short-term view of investment on the scale of this allows more flexible working and better
they make, and this has been the result of a months or years rather than decades. productivity, but it also makes it difficult to
cultural shift. The Confederation of British Companies, however, and particularly separate work time from personal time. This
Industry wrote a seminal report in 1990 titled construction companies, are beginning to take move to communication in the virtual world
Developing a Safety Culture (CBI, 1990). The a long-term view. This is not unselfish, as there implies that geography is less important, but
recommendations of the CBI report could easily is also a strong business case for sustainability. this doesnt appear to be the case. According
be adapted to the implementation of Nowadays, tenders are increasingly being to Rick Robinson, a Smart Cities Architect for
sustainability culture. This is how I would scored with a higher weighting on IBM, the geography of a city is still vital for
summarise the main points: sustainability than cost. So companies with a creativity and collaboration. This means that
crucial importance of the leadership and track record of sustainability are becoming there will still be work for us tunnellers for the
commitment of the Chief Executive leaders more competitive. Competitiveness in non- next few decades at least, but our solutions will
need to walk the talk and put the full energy price factors such as health and safety or need to be smart and sustainable.
of the board behind it sustainability is a no-brainer, particularly as it
depends on the role of line management, doesnt cost much to implement and there are Conclusions
the involvement of all employees and on other benefits as well. Sustainability is not a fad and it is here to stay. It
openness of communication this will A reputation as a responsible corporate is a powerful idea and a useful decision-making
ensure sustainable practices are citizen will benefit any company, both in terms framework, but to gain the greatest benefits
implemented and new ideas are generated of share price, in relationships with we need a cultural shift from thinking of
the importance of demonstrating care and stakeholders, and in attracting and retaining sustainability as an add-on extra to
concern for all those affected by the business staff. At the BASE Birmingham event in April implementing a sustainability culture within our
sustainable businesses have better and 2013, Ian Renhard, head of UK Construction at organisations and within our profession.
more profitable relationships with Interserve said that even in a recession, having
employees, stakeholders, customers and a strong sustainability strategy makes them
REFERENCES
suppliers (Eccles et al., 2011) more resilient. Companies want to work with
a long-term strategy that has to be other companies with similar commitments,
continually reinforced and both Interserve and Jaguar Land Rover 1. CBI (1990). Developing a safety culture.
it must counter the belief that sustainability is have found that their commitment to the local London: Confederation of British Industry.
an add-on, optional extra, or a fad community and to training has strengthened 2. Chouinard, Y. (2006). Let my people go
Concentrating on sustainability culture will not their supply chain, improved planning for surfing: the education of a reluctant
be at the expense of safety culture, since health future skills, made them a more attractive businessman, ISBN 9781101413364. New York:
and safety are part and parcel of sustainability. employer, and improved their corporate Penguin Books.
The key motivating factor used in behavioural- reputation, making their companies stronger as 3. Eccles, R. G., Ioannou, I. & Serafeim, G.
based safety to inspire people to behave in a a result. (2011). The impact of a corporate culture of
safe manner is caring for the health and safety The Stern Review (and Birminghams mini- sustainability on corporate behavior and
of those around us and wanting everyone we Stern Review) demonstrated that almost all of performance. Working Paper 12-035, Harvard
work with to be able to go home unharmed. climate change carbon reduction is wealth- Business School.
The key motivating factor in sustainability generating and improves the quality of peoples 4. Gouldson, A., Kerr, N., Topi, C., Dawkins, E.,
culture could be caring for the planet we live lives (Gouldson et al., 2013). For example, an Kuylenstierna, J. & Pearce, R. (2013). A mini-
on, its ecosystems and its inhabitants, and investment of 3.6bn in reducing Birminghams Stern review of Birmingham and the wider
wanting to leave it in a better state than when carbon footprint would pay for itself in only 3.8 urban area: preliminary findings. Available at:
we arrived. Another motivating factor is years and create 1,650 jobs. It would also http://www.lowcarbonfutures.org/sites/default/f
wanting to do a good job, and for us engineers reduce vulnerability to future energy price iles/Birmingham_Mini-Stern_Review_-
this means building sustainable infrastructure. increases, protect competitiveness, improve _preliminary_findings.pdf [accessed 16th April
public health and slash the carbon footprint. In 2013].
Business case for sustainability fact, given the benefits, even someone who 5. HSBC Global Research (2013). Oil and carbon
The most basic business case for sustainability wont accept the overwhelming evidence that revisited: value at risk from unburnable
is, as Yvon Chouinard, the founder of anthropogenic climate change is happening reserves. HSBC Bank plc, 25th January 2013.
Patagonia, said, there is no business to be would have to agree that carbon reduction is a Available at:
done on a dead planet. This is a long-term good investment. http://gofossilfree.org/files/2013/02/HSBCOilJan
view, and one might wonder whether the The business case for sustainable 13.pdf [accessed 15th April 2013].
markets are set up to think so far ahead development is now not just compelling, but 6. United Nations General Assembly (2005).
(although it is becoming a less long-term view indisputable. 2005 World Summit Outcome, Resolution
as the need to combat climate change A/60/1, adopted by the General Assembly on
becomes ever more urgent). For instance, oil Smart and sustainable 15 September 2005. Available at:
companies are valued based on reserves that if It is difficult to separate smart and http://data.unaids.org/Topics/UniversalAccess/w
exploited fully will result in devastating climate sustainable. Cities are a system of systems, orldsummitoutcome_resolution_24oct2005_en.
change. To have a 50% chance of keeping and making cities sustainable will involve the pdf [accessed 15th April 2013].
climate change below 2 C of warming will integration of systems and the use of smart
50 TUNNELLING JOURNAL
TJ_0513_049_051.qxd:Feature 21/4/13 15:24 Page 51
SOLID
Offering new custom rolling stock
for your project
##!#(*'
# " (#
##$(&!'
& )!#'
" #'(' MINING
( "'
EQUIPMENT
"( (#"
%)$!"(
#"
, +
, www.miningequipmentltd.com
1 mm
mmm$lcj#]cX^$Z[
J^[Z_Wc[j[he\Wdj[ddW[e\j^[YeccedmWif
L[ifkbWLkb]Wh_iWdZj^[WYYkhWYoe\KBIh
6Xi^kZAVhZgIVg\ZiJc^i#
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:40 Page 52
OPERATIONAL
Customising standards
for the emerging tunnel
superpowers
Arnold Dix, Lawyer and Engineer gives some
guidance on regulatory arrangements for subsurface
tunnel risk management from around the world
52 TUNNELLING JOURNAL
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:40 Page 53
OPERATIONAL
both a tunnel safety management structure significant incident or accident. seriously considered in countries with limited
and prescriptive minimum standards for tunnel European Union Safety Officers meet regularly experience of subsurface infrastructure. One of
safety. The Directive was formulated in to share expertise. In this way the EU Safety the important benefits of such an approach is
response to a series of structurally damaging, Officer Strategy is increasingly generating the it encourages training and grooming of local
multi-fatality incidents that crippled European sharing of expertise, contributing further to citizens to assume senior roles as the
economies reliant upon the tunnels. (Table 1) tunnel safety.[3] organization's mature.
Each EU country must designate one or In the case of tunnels that have been Periodic Inspections - EU countries ensure
more administrative authority to take approved at the design stage but which have that inspections, evaluations and tests are
responsibility for tunnel safety, and to take any not been opened to the public by 30 April carried out by inspection entities. These
necessary measures to ensure that the directive 2005, the administrative authority assesses inspection entities are not specified by the EU.
is complied with. The administrative authority their compliance with the EU directive. Practically speaking such inspections are
may be set up at national, regional or local With regard to tunnels that had been carried out by organisations or individuals
level. opened to the public by that date, the known to be expert in such matters.
Prior to commissioning a tunnel the administrative authority had until 30 October One of the roles of the administrative
administrative authority is required to approve 2005 to assess their compliance with the EU authority is to verify that regular inspections
the commissioning of a new tunnel or directive. are carried out by an inspection entity to
rebuilding of an existing one. The By 30 April 2005, EU countries had to ensure that all tunnels falling within the scope
administrative authority has power to suspend submit a report to the Commission on how of the directive comply with its provisions. The
or restrict the operation of a tunnel if the they intend to meet the requirements of the period between two consecutive inspections
safety conditions it imposes are not met. directive, on planned measures, and, where of any given tunnel is mandated not to exceed
The administrative authority must make sure appropriate, on the consequences of opening six years.
the following tasks are performed: or closing the main access roads to the In the authors experience regular inspections
testing and inspecting tunnels on a regular tunnels. by independent experts can be a valuable
basis and drawing up the tunnel specific These staged provisions highlight how a mechanism for ensuring systems and
safety requirements regulatory regime can be introduced procedures are functioning as expected.
putting in place organisational and systematically over an appropriate period of Risk Analysis - A risk analysis, based on a
operational schemes (including emergency time. Such an staged approach should be single methodology defined at national level,
response plans) for the training and
equipping of emergency services
establishing the procedure for immediate Table 1: Fatal Fires in Road Tunnels
closure of a tunnel in case of an emergency
implementing any necessary risk reduction Year Tunnel Length Deaths Dangerous goods
measures
Tunnel Manager - For each tunnel, whether 1978 Velsen, Netherlands 770m 5 No
it is in the design, construction or operating 1979 Nihonzaka, Japan 2,045m 7 Ether (collision)
stage, the administrative authority must 1980 Kajiwara, Japan 740m 1 Paint (collision)
identify a Tunnel Manager whom is
responsible for the management of the tunnel. 1980 Sakai, Japan 459m 5 No, Collision
Any significant incident or accident occurring 1982 Caldecott, Oakland, USA 1,028m 7 Benzene (collision)
in a tunnel must be the subject of an incident 1983 Pecorile, Savona, Italy 600m 9
report prepared by the Tunnel Manager and
1986 LArme, Nice, France 1,105m 3
given to the administrative authority.
Safety Officer - For each tunnel, the Tunnel 1987 Gumefens, Bern, Switzerland 340m 2
Manager, with the prior approval of the 1993 Serra a Ripoli, Italy 442m 4
administrative authority, nominates a Safety 1994 Huguenot, South Africa 3,914m 1 No, Collision
Officer who coordinates all preventive and
1995 Pfander, Austria 6,719m 3
safeguarding measures to ensure the safety of
users and operations staff. The Safety Officer 1996 Isola delle Femmine, Italy 148m 5 LPG (collision)
performs the following tasks: 1999 Mont Blanc, France/Italy 11,600m 39
ensures coordination with the emergency 1999 Tauern, Austria 6,400m 12 Paint/Lacquer (collision)
services and takes part in the preparation of
operational schemes 2001 Gleinalm, Austria 8,320m 5 No, Collision
takes part in the planning, implementation 2001 Gotthard, Switzerland 16,918m 11 No, Collision
and evaluation of emergency operations; 2003 Flyfjell, Norway 3,200m 1
takes part in the definition of safety plans 2004 Baregg, Switzerland 1,100m 1 No, Collision
and the specification of infrastructure
installations 2005 Frejus. France/Italy 12,700m 2
verifies that operational staff and emergency 2006 Viamala, Switzerland 742m 9 No, Collision
services are trained, and takes part in the 2007 Burnley, Melbourne, Australia 3,400m 3 No, Collision
organisation of exercises held at regular
2007 San Martino, Lecco, Italy 4,800m 2 No, Collision
intervals
gives advice on the commissioning of the 2007 Santa Clarita, California, USA 168m 3 ?, Collision
structure, equipment and operation of 2009 Eiksund, Norway 7,765m 5 No, collision
tunnels 2012 Hsuehshan, Taiwan 12,900m 2 No, collision
verifies that the tunnel structure and
equipment are maintained and repaired Total deaths 147
takes part in the evaluation of any (Adapted from John Day, personal communication 2012)
TUNNELLING JOURNAL 53
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 54
OPERATIONAL
1200 - 1500m
1500 - 3000m
risk analysis conducted
1000 -1200m
800 - 1000m
400 - 500m
500 - 600m
600 - 800m
Mandatory for all tunnels comparatively simple task to document the
<400m
3000m
Origin of differences between countries and
guideline Category Comment
May be varied if risk assessment
subsequently make assertions about the
Directive Mechanical ventilation
(EU) demonstrates acceptable in special appropriateness of achieved levels of safety
circumstances
Special provisions
after a serious safety incident.
May be varied if risk assessment
(fresh air ducts and/or demonstrates acceptable in special Congested Unidirectional Tunnels
smoke extraction) circumstances Comparative Ventilation EU - Germany
Germany Mechanical ventilation Detailed decisions about smoke
(D) extraction etc driven by requirements (D) - Switzerland (CH) - A simple
of fire case comparative analysis of the German, Swiss and
Special provisions Detailed decisions about smoke
(fresh air ducts and/or extraction etc driven by requirements EU directive for roads tunnels illustrates the
smoke extraction) of fire case variation in requirements in road tunnels
Switzerland Mechanical ventilation Lower risk - Ventilation decisions
(CH) driven by risk analysis
between the Trans European network, and the
domestic laws in Germany and Switzerland.
Higher risk - Ventilation decisions
driven by risk analysis
For illustrative purposes the table
summarises the guidelines for, unidirectional
Special provisions Lower risk - Ventilation decisions congested Tunnels of differing lengths.
(fresh air ducts and/or driven by risk analysis
smoke may extraction) The simplified analysis is tabulated in Figure
Higher risk - Ventilation decisions 1 - Guidelines for unidirectional tunnels of
driven by risk analysis
differing lengths.
It is apparent from the table that there are a
is, at the request of the administrative "experts" may suggest. Within this context a range of requirements between Switzerland,
authority, carried out by an independent body considered approach to managing both user Germany and the EU directive for ventilation.
for a given tunnel, taking into account all safety AND the protection of tunnels The most notable areas of variation of
design factors and traffic conditions that affect themselves from damage can rationally be approach between the EU and both member
safety, notably traffic characteristics and type, developed.[5] states is that in Germany and Switzerland
length and geometry of the tunnel, as well as mechanical ventilation is required in shorter
the projected number of heavy goods vehicles Prescription under the EU Directive tunnels than prescribed by the EU.
per day. The EU Directive is just one set of standards Furthermore detailed risk analysis is critical in
There is still NO mandated risk assessment within Western Europe. Each of the member the ventilation choices particularly in tunnels
methodology, although PIARCs approach has states usually has its own standards too. The less than 1000m long.
gained some considerable favour within the EU Directive is generally considered a As between Germany and Switzerland there
EU.[4] minimum set of requirements. are also differences. For example In Germany
It is to be expected that there will be many the requirement for ventilation commences in The Ra
Risk in perspective differences between what is required under shorter tunnels than in Switzerland, and is the premier in
Before considering the "minimum European Union Road Tunnel requirements Switzerland appears to retain more design underground
underground
o con
requirements" specified (prescribed) within the and that which is required within each of the flexibility for ventilation in non-congested
EU Directive it is important to stress that EU member states and within other countries. longer Tunnels than Germany.
the ttunneling
u neling in
unn
tunnels are inherently safe and do not pose a The reasons for these variations are numerous Under the EU road directive congested Industry
Industr y sectors
s i
disproportionate risk of death to users of the such variations are to be expected and tunnels in excess of one thousand metres nomi
road network. In all the media excitement managed. require mechanical ventilation, and if the
following a tunnel death this fact is often lost. This means that for world travellers a road ventilation type chosen is longitudinal other
A comprehensi
comppreehensi
On the other hand, the value of tunnels is journey may expose them to differing risks in safety measures are required too.
extremely high in terms of economic different countries - even within the EU. As illustrated below under Articles 2.9.3 and most inn
innovative
novatiivve
productivity as is the cost of replacing them. The changes to the risk profile do not 2.9.4 tunnels with congested unidirectional
Furthermore once an incident occurs there is
strong evidence that the consequences of an
incident may be more serious than on a 2.9.2. A mechanical ventilation system shall be installed in all tunnels longer than 1 The meet
meeting
tin
ing will
will also
surface road. This higher level of risk following 000 m with a traffic volume higher than 2 000 vehicles per lane.
the occurrence of an unlikely incident should
Contracting
Contractin ng Practice
Practice
be the focus for avoiding incidents in the first 3 In tunnels with bi-directional and/or congested unidirectional traffic, longitudinal Design and d Planning
Planning
place. It is the confinement of vehicles and ventilation shall be allowed only if a risk analysis according to Article 13 shows it is Difficult G
Ground
Ground
gasses by the tunnel walls and ceilings that acceptable and/or specific measures are taken, such as appropriate traffic manage- DDrill
rill and Blast
B
drives the special risks in tunnels - and ment, shorter emergency exit distances, smoke exhausts at intervals. Environment,
En
nvir
v onmeent, Health
demands special efforts to minimise the Future
Futur
u e Projects
Projects
o
probability of an incident occurring and the 4 Transverse or semi-transverse ventilation systems shall be used in tunnels where a Geotec
Geotechnical
hniical Consid
Consid
specialist response if such an incident occurs. mechanical ventilation system is necessary and longitudinal ventilation is not allowed Ground
Ground S Support
u
uppor t and
The following table highlights the according to 2.9.3. These systems shall be able to exhaust smoke in case of fire.
comparative lack of deaths in road tunnels
from fires. Clause 2.9.2 as extracted from the EU Directive on minimum safety requirements for
Table 1 neatly places road tunnel fire deaths tunnels in the Trans-European Road Network.
in perspective - whatever the media or
For more
m in
303-948
303-948
54 TUNNELLING JOURNAL
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 55
A comp
comprehensive
preehensivve eexhibit
xxhibit is held in conjunction
conjuncttiion with the conference.
coonffeerence. The eexhibit
xhibit
x features
u es the industrys
feeatture industr y ss
most inn
innovative
novatiivve and experienced
exxperiienced producers
p
prroducers
o and suppliers. RETC
RETC provides
provides a rare opportunity
rare oppportuunitty to meet key
key
professionals
proffessionals
e from
from around
o d the world.
arround worrlld.
The meet
meeting
tin
ing will
will also ffeature
eat
e ure field trips,
trips, short
short courses and specialt
specialty
ty sp
speakers.
peakers. The pr
program
oggram wil
willl cover:
coover
e:
Contracting
Contractin ng PPractices
ractices and Cost Grouting
Grouting and Ground
Ground Modification
Modification Eastt Coast Projects
Projects
Design and d Planning
Planning Har
Hardd Rock
Rock TBMs
TBMs SEM/NATM
SEM/N
M ATM
Difficult G
Ground
Ground LLarge
arge S
Span
pan TTunnels
unnels an
u and
nd Cav
Caverns
erns Shafts
Shaffts
t and Mining
DDrill
rill and Blast
B Micr
Microtunneling
otunneling and T Trenchless
renchless Tunneling
Tuunneling TTunnel
unn
u nel Rehabilitation
Rehabilitation
Environment,
En
nvir
v onmeent, Health, and S Safety
affet
ey NNew
ew and Inno
Innovative
vativve Technologies
Tec
e hnologies WWater
aater and Gas Control
Control
FFuture
utur
u e Projects
Projects
o PPressure
ressure Face
Face TBM
TBM Case
Caase Histories
Histories Inter
International
rnational PProjects
rojects
Geotec
Geotechnical
hniical Considerations
Considerations PPressure
ressure F
Face
ace T
TBM
BM T Technology
e hnology
ec TTunneling
unn
u neling ffor
or
o Sustainability
Sustainability
Gr
Ground
ound S Support
u
uppor t and Final
Final Lining Risk Management
Management
For more
m information contact:
co
ontact: RETC,
R ETC, www.retc.org,
www.retc.org, meetings@smenet.org,
meetings@
@smenet.org,
303-948-4200,
303-948-4200, 12999
12999 E Adam Aircraft
Aircraft Cir.,
C ., Englewood, CO
Cir CO 80112.
80112.
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 56
OPERATIONAL
56 TUNNELLING JOURNAL
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 57
OPERATIONAL
30,000 B A AA
25,000 For a Country by Country guide to liability characterisation of the tunnel type. From this
20,000 N.
15,000 N.
L-
40
see reference[9] figure tunnel risks are characterised from a
N. L-
10,000 N.
L- L- 12
x1
06 Divide and Conquer? - There are length/ traffic number perspective.
8,000 3x 4x x1
10 6 10 6 06 differences between the regulatory The Second stage describes what is
4,000 environment the different member states required (Figure 4).
3,000
and countries (often neighbouring each The Japanese approach can readily be
2,000
D C
other), the EU directive and other standards compared to the EU approach which is
1,000 (such as in the United States of America, summarised in Figure 2. It is systematic, and
Taiwan, Japan and Australasia). considered but different to EU and
It is not uncommon outside the EU for member state systems.
0
0
0
0
0
0
10
20
30
50
00
00
00
00
0
,0
2,
3,
5,
10
Fire extinguisher
more than an obscure statistical reference in
Fire
Emergency exit sign To be installed in tunnels with evacuation routes an opportunity to argue subsequent to a
Guide board (B) To be installed in tunnels safety event that not only was a particular
without evacuation routes design defective but that had the design
Smoke extractor, Evacuation routes installed in tunnels with L > = 750m practices of another jurisdiction been
evacuation route Smoke extraction installed in tunnels with L > = 750m
Install evacuation routes in AA-Class tunnels and in A-Class tunnels followed injuries would have been avoided.
with L > = 3,000m, with bi-directional traffic and longitudinal ventilation
The impetus for such argument should not
Water supply hydrant To be installed in B-Class tunnels be underestimated and the sentiments and
with L < = 1,000m (water ports near portal)
Leaky feeder system Coaxial cable Necessary in A-Class
dissatisfaction of the public towards a legal
tunnels with L > = 3,000m system which does not find liability
Entrance/exit telephone subsequent to a tragedy are well illustrated
Radio (re-) broadcast Necessary in A-Class by a number of engineering related tragedies
tunnels with L > = 3,000m in recent years.
Other equipment
Loudspeaker system Installed in tunnels with radio (re-broadcasting equipment) The role of standards was recently
Water sprinkler Necessary in bi-directional A-Class highlighted when an Austrian court in
tunnels with L > = 3,000m
and more than 4,000 vehicle a day Salzburg acquitted 16 people of the
Monitoring equipment Type A (20m interval) Installed in tunnels with sprinklers responsibility for the Kaprun ski train blaze
that killed 155 tourists in November 2000.
Type B (at lay-by)
In the determination of the court the Judge
Emergency Installed in tunnels with L > = 200m
lighting equipment noted that:
Emergency Generator Installed in tunnels with L > = 500m the train confirmed to the latest technical
power supply
Uninteruptable power supply Installed in tunnels with L > = 200m standards and all requirements were
fulfilled.
Must be installed Installed if deemed necessary
Importantly the Judge accepted the
TUNNELLING JOURNAL 57
15
TJ_0513_ARNOLD_052_058.qxd:Feature 21/4/13 15:41 Page 58
OPERATIONAL
58 TUNNELLING JOURNAL
TJ_0513_059_061.qxd:Feature 21/4/13 15:58 Page 59
OPERATIONAL
Successful tests in
the Trnskog tunnel
in Stockholm
Over the next few years, several
kilometres of tunnels will be or are
being built under Stockholm for both
the Stockholm Bypass and the Northern
Link. They can be expected to carry
A photograph of a free burning test in the Trnskog tunnel, with
high traffic loads, in which an accident
6m/s air velocity. The target vehicle, with combustible material on could have significant consequences.
the side, can be seen on the far side of the flames. The Swedish Transport Administration
has decided to protect the tunnels with
fixed fire fighting systems (sprinklers).
However, the potential for fire
spreading between vehicles is to be
investigated. Here, Glenn Appel,
Haukur Ingason, and Ying Zhen Li of
SP Fire Technology review tests it has
performed in an existing road tunnel to
investigate whether the fire-fighting
system would be capable of preventing
the spread of fire between stationary
vehicles in a queue.
IN CONJUNCTION WITH large fire test hall. Using simple manual flammable materials. The surface of the
Brandskyddslaget and the Swedish calculations and advanced CFD steel was used to measure temperature (a
Transport Administration (STA), specially calculations, we were able to estimate large plate thermometer), so that when
designed nozzles intended to provide what the likely radiation flux on the tunnel the adjacent materials caught fire the
protection against fire in a tunnel has been walls would be and to produce an image temperature of the steel sheet could be
developed. A lot of testing has been done, of which parts of the tunnel needed to be read at the same time.
and a successful design concept has now insulated before the tests. The calculations An advantage of using the target vehicle
been produced. Two different fire-fighting also provided an indication of the distances was that it provided seven positions at
systems have been installed in two sections from the fire at which critical temperatures which the temperature could be measured.
of the existing Trnskog tunnel in order to for the ignition of flammable materials The shape of the target vehicle was that of
simulate as realistic a situation as possible. could be expected. the rear of a van, with two of the
The STA wanted to perform simple tests temperature measurement points on the
that could show that fire would not spread The test arrangement roof and five on the vertical surface facing
between stationary vehicles in a queue SP Fire Technologys LPG tunnel fire towards the fire. This made it possible to
situation. Using real vehicles was not a simulator was used as the fire source. This see where the temperature was the highest
realistic alternative during these tests. simulator has been developed in order to and where the water spray did the most
Instead, a special instrumentation test rig produce a carefully defined heat release use during the tests. The values recorded
was developed, in the form of a target rate. Specially designed burners had been from the target vehicle were comparable
vehicle measuring temperature. The developed for the tests in order to provide with those that could be expected in a real
temperature was measured in order to a good spread of heat even when the vehicle in a fire.
evaluate the risk of fire spread. The fire burner was exposed to the effect of wind.
itself was simulated by a specially The heat release rate that was used Tests under real conditions
developed LPG burner, capable of corresponded to a fast curve (Q = 0.047 * As far as we know, fire-fighting systems
producing different heat release rate t), by which the heat release rate rises have never previously been tested under
curves. from zero up to about 3.5MW in about 4.5 such conditions in an existing tunnel. Two
minutes. This is then followed shortly after different wind velocities were used (6m/s
Initial calculations before the test by a step increase up to about 6MW, and 3m/s) during the tests in order to
In order to be able to make best use of the which is then held constant for a given investigate temperature differences
limited time available in the tunnel, which time. resulting from different distances (2m and
had to be closed to traffic while the tests In addition to the burners, a target 2.8m from the centre of the fire) to the
were being performed, preparatory tests vehicle had been constructed in the form nearest vehicle. An environment such as
were carried out in SP Fire Technologys of a sheet of steel, covered on each side by that in the tunnel is very difficult to
TUNNELLING JOURNAL 59
TJ_0513_059_061.qxd:Feature 21/4/13 15:58 Page 60
OPERATIONAL
Tunnelling journal
subscribe at:
www.tunnellingjournal.com
60 TUNNELLING JOURNAL
TJ_0513_059_061.qxd:Feature 21/4/13 15:58 Page 61
OPERATIONAL
TUNNELLING JOURNAL 61
TJ_0513_CONTACTS_062.qxd:Feature 21/4/13 14:41 Page 62
contact US
contributorS
Gary Tween Tris Thomas
Managing Director Editorial Director
Tel: + 44 (0) 1622 720 631 Tel: + 44 (0) 1622 720 631
Mobile: + 44 (0) 7973 205 638 Mobile: + 44 (0) 7812 011 139
gary@tunnellingjournal.com tris@tunnellingjournal.com
Kristina
Smith
Kristina Smith has been writing
about civil engineering and
construction for over 15 years,
Rory Harris Steve Caming having started her career out on
Chairman Publishing Director site as an engineer.
Mobile: + 1 (859) 321 3164 Tel: + 1 (603) 447 1187
rory@tunnelingjournal.com Mobile: + 1 (603) 662 6263
steve@tunnelingjournal.com
tunneling@roadrunner.com
Adrian
Greeman
Mark Piper Peter Bell Adrian Greeman has been
Finance Director Director
writing about international
Tel: + 44 (0) 1672 563 662 Tel: + 44 (0) 1622 720 631
civil engineering projects (in
Mobile: + 44 (0) 7768 554 646 Mobile: + 44 (0) 7770 441 867
particular tunnels, bridges
mark@tunnellingjournal.com peter@tunnellingjournal.com
and highways) for the past
16 years.
Tunnelling journal
62 TUNNELLING JOURNAL
Untitled-1 1 04/04/2013 11:32:28
NATJ_0513_NAFNTCOVER_001.qxd:cover 21/4/13 21:12 Page 1
Tunneling
north american April/May 2013
www.tunnellingjournal.com
journal
UP EUCLID CREEK
WITH A SOLUTION
THE FIRST OF A SERIES OF NEW TUNNELS
FOR THE CLEAN LAKE PROJECT IS UNDERWAY
SEE PAGE 5 SEE PAGE 14 DETAILS ON PAGES 41-54
OBAMA VISITS BORING FOR RETC VISITS
PORT OF MIAMI BI-COUNTY THE CAPITAL
EGLINTON GEARS TO THE NORTH OF PART ONE OF
UP FOR LAUNCH, AND WASHINGTON DC, NATJS 2013 RETC
OTHER NEWS FROM WSSCS NEW WATER CONFERENCE AND
NORTH AMERICA TUNNEL WINDS UP EXHIBIT PREVIEW
13-02-27_119_ID040_eAz_XXL-Durchmesser_Tunnelling Journal NA_210x297mm_4c_oc_Fassung 01
Herrenknecht Tunnelling
Systems USA, Inc.
1613 132nd Ave E, Suite 200
Sumner, WA 98390
Phone +12534472300
Fax +12538639376
marketing@herrenknecht.com
www.herrenknecht.com
comment contentS
By popular demand 5 North American News
Project, contract & company news
Fire crew tunnel rescues and methane
blasts not withstanding, its been great
to see such positive press on the
9 The Insider
Lessons that can be learned from dragons,
dwarves, wizards, and a white rabbit
tunneling industry this month. From
President Obamas visit to the Port of
Miami Tunnel, in Florida, to promote
public-private partnerships for big-ticket
10 Blue beginnings
The first of four major projects gets under
way for DC Waters Clean Rivers program
infrastructure projects; to Bertha the
worlds largest TBM arriving in Seattle,
Washington, for the Alaskan Way Viaduct Bored Tunnel Replacement; Left: The
national media coverage has at last focused on the great feats being figure of
attempted, and achieved, by tunnelers throughout North America. eight slurry
The most heart-warming story however, was the delight of the San wall shafts
at Blue
Mateo County residents, turned tunnel activists, at the opening
Plains (p10)
ceremony for the Devils Slide Tunnels, in California (p6). Following
Below: The
decades of campaigning which resulted in a tremendous citizen vast caverns
movement to prevent Caltrans proposals for a four-lane overland under NYCs
bypass of this notorious stretch of state Highway 1 and years of Grand Central
construction, some of the pro-tunnel advocates were among the first Terminal (p20)
to drive through the twin tunnels in a parade of classic cars this March.
To aid the celebrations, the Half Moon Bay Brewing Co unveiled a new
beer, Tunnel Vision Ale. I wonder if someone would be willing to
sponsor a tasting at this years RETC conference in Washington DC...
Amanda Foley
KIEWIT.COM
PORTMIAMI
TUNNEL
The historic Florida transportation project PortMiami Tunnel will connect the port, Miami-Dade
Countys second largest economic generator, directly to the surrounding highways, improving
access to the port. The technically challenging project, a first in North America for global
conglomerate Bouygues, is comprised of two 11.3 meter internal diameter, 1.27 kilometer long
tunnels bored through the intricate geology of the Biscayne Bay channel, known as Government
Cut. Design-Build Contractor, Bouygues Civil Works Florida, is also a 10% equity partner in
this award-winning Public Private Partnership that U.S. President Barack Obama heralded as a
national model for P3s.
www.Bouygues-Construction.com
FOR MORE INFO ON PORTMIAMI
TUNNEL PROJECT VISIT:
www.portofmiamitunnel.com
Or Contact: L.Weinberg@BCWF-Miami.com
NATJ_0513_Insider_009.qxd:Feature 21/4/13 18:51 Page 9
THE INSIDER
the
insider
Bob Goodfellow, PE, CEng, Senior Vice
President, Aldea Services LLC
WINTER IS OVER and spring is around the harsh to me, regardless of the severity of the and yet contradictory advice. All these characters
corner. The madness of March is upon us, so in surveying error. are supposedly helping poor Alice and Brothers
keeping with the season I thought some Utility location is a well-known problem on Contracting navigate their way through their
thoughts and anecdotes highlighting my own many tunnel projects. In the case of the underground issues when all they want is to get
madness about tunneling and some lessons Chamber of Secrets, Harry Potter locates this out without too much damage.
learned would be fitting for this months Insider. chamber that has lain undiscovered for over 500 We have all heard the expression the more
In writing geotechnical baseline reports (GBRs) years. I would think that a decent set of as-built things change, the more they stay the same.
and attempting to foresee issues and hazards drawings would have solved this mystery long Companies spend millions analyzing industry
that might manifest during projects, I have often ago without all the fuss. trends and discussing how change is good and
opined that if anybody can see into the ground
Through the
ahead of the TBM, they would be very rich
indeed. Imagine my delight then when the
project geologist announced in a recent meeting
that he could see the rock we were going to
encounter just by looking at the mountain.
Alas, his credibility was badly damaged a few
seconds later when he also announced that
there would be no problems.
Another Contractor once told me that when
reviewing a GBR he noted to his chief estimator
that there appeared to be no really bad ground
Looking Glass
Using the appropriate form of contract change must be embraced if we are to succeed,
on the project. When have we had a job with provides the lesson in the Great Escape. Charles but many things are constant in our business.
no really bad ground? he said to his colleague. Bronson as the chief tunnel contractor was not One of these constants is character. The tunnel
They quickly agreed to put 5% of really bad abiding by the minimum support requirements business abounds with extrovert, high
ground into the estimate regardless of what the and caused a serious accident during tunneling maintenance and delightful characters many of
GBR said. under the fences to escape from a prisoner of which would not be out of place in the books or
Lessons are all around us in art and literature war camp, an accident in which he was lucky movies noted above.
that can help us at work. For example, I watched not to be completely buried along with his The mentality and indomitable spirit of tunnel
a movie called Reign of Fire a few years ago. If workers. The Germans in this fine movie were miners is legendary. Many of us have stories to
you havent seen it, I would not exactly drop also clearly unhappy at not being allowed access share, but one I read recently summed up their
everything to rush out and buy it on DVD, but to inspect the works. But you see, it depends attitude perfectly for me. The book was a
the movie begins with a tunneling scene how you set up the contract; and if the fascinating read about military mining during
beneath London. The tunnel excavation breaks specifications rely on self-certification for quality, World War I and how the miners were formed
into a dragons lair disturbing its sleep, which what control do you really have to inspect the into tunneling companies so that large
results in a fiery death for all involved and work and make any changes? The tunnel was underground mines could be placed by
devastation for London and most of the UK. eventually completed and quite a few people tunneling under the opposing forces trenches.
While this movie had great special effects and escaped, so while it wasnt as great an escape as The conditions and courage on both sides to
this was clearly a traumatic event in the history the original plan, we could still call the tunnel pursue such a branch of warfare is a topic for
of my homeland I couldnt help but think project a technical success. another day, but before heading off to face the
blimey, I bet that wasnt in the GBR. That must And then there is my own favorite parody of horrors of the Western Front and join his
be a Type II DSC. I generally try to keep these the tunnel business, Alice in Wonderland. Down tunneling company, a miner from the Northeast
types of thoughts to myself as they are not a rabbit hole Alice goes headlong into the world of England was asked during his medical if he
readily understood by people outside the of tunnel construction, seeing an overexcited was circumcised. He responded with a smile that
industry, but these lessons can be valuable to project sponsor demanding everybodys head be no, that is just fair wear and tear. I know Ive
share with colleagues. cut off when they are not pleased; the rabbit-like worked with people like that guy and I am sure
Alignment control is important in tunneling project manager always concerned with time that even after almost 100 years, many of you
and this importance can be seen in the Lord of and how late they are; the crazy CM calling recognize this brand of miners humor.
the Rings, where the Mines of Moria were meetings (and always with plenty of tea); an There are lessons all around us, if only you are
destroyed when the dwarves delved too deep ever-smiling Cheshire Cat consultant that seems passionate and, yes, crazy enough about tunnels
and released a fearsome beast. This loss of to appear out of thin air whenever there is to take note of them. Stay safe, learn those
vertical alignment resulted in the destruction of trouble; and identical-looking lawyers from the lessons, enjoy the great people in our industry,
their entire community. This does seem a bit firm Tweedledum &Tweedledee giving constant and for goodness sake keep away from dragons!
BLUE
beginnings
IN WASHINGTON DC, Traylor/Skanska/Jay- scoring of the technical (35%) and price
Dee JV is currently gearing up for the launch (65%) proposals ultimately resulting in a
of its Herrenknecht EPB machine on the 4.5- combined highest score and lowest bid. EPC
mile (7.3km) long Blue Plains Tunnel Project. Consultants was selected to carry out
The 23ft (7m) diameter machine, which was construction management on the project.
christened Lady Bird during an official The Blue Plains Tunnel is the longest of the
ceremony on April 9, is due to start tunneling four tunnels in the Clean Rivers Program, at
this June. It will be used to excavate the first approximately 24,000ft (7,315m) and includes
phase of The District of Columbia Water and five diaphragm wall shafts that range
Sewer Authoritys (DC Water) $2.6 billion between 50ft (15m) and 132ft (40m) in
Clean Rivers program, which aims to eliminate diameter and 110ft (34m) and 170ft (52m) in
Combined Sewer Overflows (CSOs) into the depth (see map).
Anacostia and Potomac rivers.
Above: Map of the Blue Plains Tunnel After a procurement effort that lasted more Shaft design and construction
Project and the other tunnel projects than a year Traylor/Skanska/Jay-Dee JV (TSJD), Two of these shafts, the 132ft (40m) diameter
in the DC Clean Rivers Program along with its designer Halcrow, was officially Dewatering Pump Station Shaft (DS) and the
awarded the $330.5 million design-build 76ft (23m) diameter Screening Shaft (SS), are
Below: The combined figure eight contract for the Blue Plains Tunnel Project on located at the Blue Plains Advanced Waste
diaphragm wall shaft structure at the May 5, 2011. The contractor was chosen from Water Treatment Plant (BPAWWTP) site and
Blue Plains WWT Plant three short-listed teams, with evaluation and have been designed as a combined figure
eight diaphragm wall structure.
This unique shaft arrangement will
allow the assembly of the TBM
through both shafts, utilizing a
23ft (7m) diameter opening
between the adjoining shaft walls.
The arrangement takes
advantage of the large diameter
shafts to facilitate TBM launch,
explains Traylors Construction
Manager, Brett Zernich. It also
eliminates the need for an
elaborate ground support system
for an interconnecting tunnel
between the two shafts.
Its proved challenging, in
terms of the size and arrangement
of the diaphragm walls, says
Martin Ellis, Halcrows Design
Manager for the project. You
basically end up with some
double-size panels and some Y-
shaped panels where the shafts
interconnect, for which you have
to maintain the excavation.
NATJ_0513_BLUEPLAINS_010_012.qxd:Feature 21/4/13 19:35 Page 11
WASHINGTON DC
ngs
the opening between the two shafts, which
transfers the load above and below it.
The shafts, from my viewpoint, are
probably the most complex part of the
project, says Rafael Castro, Design Manager wet. At the other three
of the Blue Plains Tunnel for the Owners shafts sites there is a
Representative Jacobs Associates. Fortunately sandy layer near the base
the JV and its designer have done a very good of the slabs, says Ellis.
job of handling the difficulties associated with So theyll be excavated
their design and construction. There have underwater and the base
been a lot of challenges, but TSJD and slabs will be tremied in
Halcrow have worked through them. From under water.
the shaft design perspective its gone really One of these shafts is
well. The shaft construction itself has gone now being excavated;
fairly well, but weve had some bumps. The while at the other two
requirements for the slurry wall installation locations the diaphragm
were quite stringent and it took a lot of walls have been
finesse to install the slurry wall panels. completed and the shafts
The size and verticality requirements were are ready for excavation.
a challenge, says Zernich. But in the end,
using sophisticated slurry wall technology, Current activity Top left: The projects EPBM is christened in early April
Bencor was able to deliver a world class shaft With TBM assembly now Above: A reinforcement cage is lowered at the DS Shaft
to the client. under way, the JV is
The shafts are now at elevation for the TBM currently preparing for
launch, but once this has taken place the DS the machines launch in mid-June. Were pressure analysis are fairly conservative, says
shaft will be taken down a further 40ft (12m), going to place the shields in the shaft in Ellis. So apart from sensitive structures, such
before the casting of its 23ft (7m) thick May, says Zernich. Weve got several as an 118in high-pressure water main where
dome-shaped base slab takes place. components assembled in the DS Shaft and we will be using full pressures and 24hr
Technically, weve gotten right to the level we are lining the concrete collar of the smaller working, TSJD will be optimizing pressures to
where the shafts are beginning to hold back SS Shaft. Weve got some advantages, minimize any potential ground losses.
some fairly significant loads, however we especially with having such a large shaft. Looking ahead, other program contract
anticipate the diaphragm walls to continue Were able to assemble the machine in an interfaces are a challenge, says Zernich.
performing well for the remainder of the advanced state with four of the gantries in There are several milestone dates on this
excavation, says Castro. line for the launch. Then well have an project, and DC Water has a pretty aggressive
The other tunnel shafts all use the same umbilical feed from gantry five and be able to schedule.
diaphragm wall shaft technique, with the install the decks in order as we launch. We One such interface is the southerly extent
exception that these will be excavated in the will be mining with trains out of the DS Shaft the Anacostia River Tunnel the construction
until were in a sufficient distance, then well of which is due to be awarded next month
stop and re-configure to muck out of the SS where it connects to the Blue Plains Tunnel at
Shaft, and continue excavation of the DS Poplar Point, east of the Anacostia River, with
Shaft to its full depth and cast the base slab. this shaft becoming the reception shaft for
Approximately 9,000ft (2,743m) of the the Anacostia TBM.
tunnels alignment passes below the Potomac There is a very positive vibe on the project
and Anacostia rivers. Running more then however, says Castro. Its running at a very
100ft (30m) below the surface, the alignment fast pace and, as its the first project in the
extends from the Blue Plains Treatment Plant program, DC Water really wants to make sure
along the east bank of the Potomac, adjacent that it makes schedule. So the concentration
to the JBAB joint naval support and air force is all just on getting the job built rather than
base, and then under the Anacostia River to arguing over minor issues. Its a good project
terminate at a reception shaft at DC Water's and its a good program, all the participants
main pumping station. are working well together to achieve the
The volume losses weve used for face projects schedule and quality goals.
WASHINGTON DC
The design of the tunnel and shaft the thickness of concrete pours and the will be exposed to sewage effluent.
structures on DC Waters Blue Plains amount of steel reinforcement. Specific durability requirements and
project was performed by Halcrow, now Three other shaft structures utilized careful specification of concrete was
a CH2M Hill company, lead designer for the same diaphragm wall and CIP lining developed to ensure a quality product
the Traylor/Skanska/Jay-Dee JV. A arrangements. These 50ft (15m) and minimize vulnerability to attack by
number of innovative design-build diameter chemicals in the effluent.
solutions were developed for the The lining design incorporates
project including the figure of bolted and doweled joints with cast
eight double shaft and the use of in gaskets and guide rods to assist
steel fiber reinforced segments in ring build. A significant part of the
a one pass lining system for the design challenge was to
tunnel. Halcrow also adopted a accommodate the loading scenario
phased risk based approach to the with larger internal pressures than
assessment of ground movements active ground loading, which
on existing structures and utilities, required a detailed understanding
culminating in detailed numerical of the ground and structure
analysis for at risk structures. From interaction.
this analysis a range of mitigation Ground movements associated
measures were developed to protect with excavation of the tunnels
the integrity of these assets. and shafts were assessed for the
At the Blue Plains Advanced Waste whole of the alignment and a
Water Treatment Plant (BPAWWTP) site comprehensive instrumentation
the Dewatering and Screening shafts scheme designed to monitor the
were designed as a figure of eight works. The shaft sites proved to
structure with the 132ft (40m) and 70ft be the most challenging, due to
(21m) diameter shafts touching each the presence of existing DC
other and sharing a common wall. The Water and third party
diaphragm walls were designed for both infrastructures. Whilst the
temporary and permanent conditions - circular diaphragm wall
the full temporary condition and then method of shaft construction
combined with the cast in place lining to has proven to result in
support the long-term loading. extremely small amounts of
These long-term loads on the shaft ground movement, the
walls were owner specified and assessment of potential
equivalent to the in-situ over- impacts considered the risk of larger
consolidated lateral stresses where shafts were not movements more commonly associated
Ko=1.4 in the Potomac group Clays. de-watered during construction with propped box type excavations.
Other design challenges included and were designed to be excavated in 3D Plaxis models were developed to
meeting the 100-year durability the wet, with tremie base slabs capable fully understand the interaction
requirements for the shaft walls (i.e. the of resisting ground uplift pressures as between existing structures and the
combined diaphragm walls and cast-in- well as potential net downward ground. At the Main Pumping Station
place liner) and dealing with panel pressures associated with the tunnel shaft site, a suite of protection measures
eccentricities associated with tolerance flooding loading scenarios. A radial was developed to mitigate the potential
limits for verticality. arrangement of the reinforcing steel was risks associated with both ground
The verticality tolerance was developed to reduce the quantities used. excavation movements and of the
necessarily very stringent but did prove The tunnel lining has been designed as construction work itself. Numerous
to be achievable. Bearing stresses a 23ft (7m) internal diameter, 14in existing structures were affected with
between panels at the base of the (355mm) thick, precast concrete nine potentially at risk, including 100-
excavation were at the limit for the 5ft segmental lining. It has been configured year old brick lined sewers and timber
(1.5m) thick diaphragm wall panels. 3D with up and down rings in a 6+1 piled underground chambers. Measures
Plaxis analysis was used to confirm the trapezoid-parallelogram segment included installation of steel sets within
distribution of stresses in the complex arrangement to minimize the number of an existing 23 wide outfall sewer tunnel
figure of eight arrangement and also to segments while avoiding any cross joints and soil mixing to stabilize the ground
confirm the acceptability of various and meeting the tight radius criteria of adjacent to shallow sewers prior to the
construction scenarios where excavation the alignment. Steel fiber reinforced excavation of the diaphragm wall
in the two parts of the shaft may not be concrete offers significant cost savings panels. A work site protection slab was
synchronous. The base slabs for the during segment manufacture and gives also required to distribute loads for
double shaft structure were designed as durability advantages over conventional cranes used to install the diaphragm wall
domed shaped arch slabs to minimize steel bars in the one-pass lining, which and for the removal of the TBM.
University Link, Sound Transit, Seattle, WA Blue Plains Tunnel, DC Water, Washington, DC
CH2M HILL and Halcrow CH2M HILL and Halcrow provide state-of-the-art tunnel expertise that has been
were honored in six
established over a century of understanding and managing the risks associated
categories at the 2012
New Civil Engineer with the development of underground infrastructure.
Tunneling Awards:
T unneling Contractor The combining of these two great companies allows both to leverage best-in-class
of the Year planning, design, program management and construction management skills on the
P roduct/Equipment worlds most complex tunnel projects.
Innovation of the Year
Whatever your tunneling challenges water, rail, transit, highways or utility; soft
T unneling Project
of the Year ground, hard rock or immersed tube; major urban tunneling or underground space
Environmental Initiative development youve discovered the best team in the world.
of the Year
Safety Initiative of the Year For more information, visit ch2mhill.com
MARYLAND
James Grissom,
Project Manager
for Southland
Contracting,
discusses the
challenges met
during the
construction of
the Washington
Suburban Sanitary
Commissions
(WSSC) Bi-County
Water Tunnel
project, located
in the Maryland
suburbs
immediately north
of Washington DC
Tuckerman n Shaft
Sha t
MARYLAND
(S1) (Start po
point) 355 185
LOCATED IN THE Maryland suburbs, (84m) below surface. The project also
Exis
Existing water
w main
m
immediately north of Washington DC, includes three shafts, one work shaft
the Washington Suburban Sanitary Stoneybro
Stoneybrook
Stoney ook sh
shaft and two end shafts (Figure 1).
(S4) (End
E point)
(E
Commission's (WSSC) 5.3-mile (8.5km) Due to the limited access, a 35ft
long Bi-County Water Tunnel is currently 495 (10.6m) diameter, 165ft (50m) deep
under construction by a joint venture of shaft at Connecticut Avenue was
Conn t Avenue
Connecticut ve
Oscar Renda Contracting, Southland identified as the only place from which a
Contracting and SAK (RSS JV). TBM could be launched and removed.
Mining is currently 98% complete, with The two smaller shafts would be
approximately 590ft (180m) of tunnel constructed at either end of the tunnel,
excavation remaining along the western end at Tuckerman Lane (west) and
of the alignment. Challenges during Stoneybrook Drive (east).
construction included high water inflows at Tunneling was selected from a range
355
one of the shaft locations, areas of poor 97 of horizontal alignment alternatives as
rock quality, and a major TBM Montgomery well as open cut and deeper tunneled
Rockville 95
County
breakdown. Wheaton profiles. Decision-analysis software was
270 used by WSSC and the design team in a
185 Laurel
Project background From the workshop format to select a tunnel
Potomac Bowie
Conceived more than 20 years ago, the Bi- alignment that was favorable in light of
County Water Tunnel will increase supplies of To Prince several factors, including cost, impact to
Georges 495 Upper
clean drinking water to eastern areas of two County Marlboro
the environment, traffic, and the local
counties in Maryland and also Washington Right: Map of the 95 residents. An extensive public outreach
DC. The increased water supply will alleviate Bi-County tunnel campaign proceeded during the early
current capacity limitations from an existing alignment Prince Georges design phase to present the factors
County
4.5ft (1.37m) diameter water main. The tunnel being considered and this campaign was
will also serve as an additional high-pressure Below: A section successful in gaining the consent and
water source during peak-use periods, of steel carrier trust of local residents. The public
droughts, and emergencies. pipe is lowered outreach continued through detailed
Plans for the Bi-County Water Tunnel were
drawn from a long-term water supply project
in the area, which dates back to the 1970s.
Original water tunnels of the same name were
built in 1980 to 1981, using Jarva Kelly-type
TBMs to bore 10ft (3m) diameter tunnels.
These tunnels were built in rock and lined with
shotcrete. Due to leakage rates and rock
competency issues discovered during testing,
the tunnels were not placed into service until
they were lined with a 7.8ft (2.4m) steel pipe
in the early 1990's.
These original tunnels, bored through
quartz, gneiss, schist, and granite, have
provided good capacity in recent decades.
However, the 4.5ft (1.37m) diameter water
main has continued to act as a bottleneck.
Without additional capacity, water pressures
are soon predicted to fall below 2 bar, which
would affect firefighting and emergency
capabilities. To prevent these problems, the
next phase of the plan called for a final tunnel
to tie the two systems together, providing
reliable water supply from the Potomac River
to WSSC customers in Montgomery and
Prince George's Counties.
WSSC hired Black & Veatch to design the
tunnel and its valve vault structures. A joint
venture of Jacobs Associates and Louis Berger
Water Services is providing construction
management services.
Tunnel design
The 5.3-mile (8.5km), 10ft (3m) diameter Bi-
County Water Tunnel route follows the I-270
and I-495 ring roads around Washington DC.
Much of the area is urban and residential,
resulting in limited access and a deep tunnel
alignment between 90ft (27m) and 275ft
MARYLAND
Right: Excavation of the drill and blast starter and tail tunnels at the main Connecticut
Avenue S-3 shaft site; Below: The S-3 Shaft utilized liner plate and ring steel in the soil
layer, and rock bolts and shotcrete in the rock layer; Bottom: 72in (1.8m) diameter pipe
installation at the S-4 Stoneybrook Shaft site
MARYLAND
MARYLAND
pieced back together. Turning the pieces benefit of assisting the tunnel
around, particularly larger bolted-together ventilation particularly when
components, required some maneuvering with mining the western reach.
a crane in the 35ft (10.6m) wide shaft. Cutter wear was higher than
Rebuilding of worn sections of the cutterhead, expected and was significant
including the addition of hardened steel, was given the acceptable tolerances.
also done prior to re-Iaunch. This entire The lifting buckets were showing
process took approximately two months. significant wear due the abrasive
qualities of the rock being mined.
TBM woes and refurbishment While excavation of the
The TBM was re-Iaunched in February 2011. western reach continued,
However, after tunneling for a month, a installation of the 84in (2.1m)
metallurgy failure of a pinion gear caused diameter carrier pipe was being
major damage to TBM drive components that installed in the eastern reach of
included the bull gear. The damage was the tunnel using a hydraulic pipe
extensive and the TBM had to be removed carrier. Each joint had to be
from the tunnel, and the damaged welded to the previous pipe. At
components were shipped to the Robbins every step of the process,
Company factory in Ohio. Repairs to the TBM inspections had to be
as well as some gearbox and motor performed. After all the steel
modifications caused a four-month delay to carrier pipe had been placed, the
the project, however WSSC agreed that this annulus between the pipe and
was beyond the control of RSS JV. the tunnel was grouted.
The TBM was once again re-Iaunched on The grouting was done in
the western drive in July 2011. During multiple lifts, by RSS JV and its
excavation of the western drive RSS JV subcontractor, to minimize any
encountered a few areas of blocky, highly floatation that would be placed
unstable, ground. The ground in these areas on the pipe. RSS JV used a 70%
had to be mined by hand to prevent damage cement and 30% fly ash grout
to the TBM and its conveyors. Top: The SAK-owned Robbins main beam TBM is mix, which was chosen for the
These areas also typically had increased lowered into the S-3 Shaft; Above: the S-3 Shaft at lack of shrinkage shown in
groundwater inflows due to the ground night; Below: View of the S-4 Stoneybrook Shaft after testing prior to placement of the
conditions. At some locations where the an annulus grout pour grout. Close attention was paid
unstable ground was encountered flows to the each lift.
observed were as high as 150gpm and
resulted in steady state flows that were still any reoccurrences. These areas were Current progress
within acceptable criteria. The first area negotiated using a modified class of support When tunneling of the western reach is
encountered in the western reach was and was priced as an equitable adjustment to completed (due as NATJ was about to go to
approximately 40ft (12m) long and resulted in the contract. press), the same method of pipe placement
a large void over and in front of the TBM. During excavation of the tunnel, four welding and annulus grouting will be used
RSS JV evaluated the ground conditions and cathodic monitoring shafts had to be drilled throughout the western reach of the tunnel.
recommended the installation of steel ring sets into the tunnel excavation. In the long term Overall the unit price approach has stood up
to support the ground as crews moved slowly they will be used to monitor the tunnel liner very well during construction and water
through the unstable areas. Extra sets were and the corrosion of the pipe over time, but inflows have been well within the advertised
ordered and stored at the site to be ready for during construction have provided the added baseline amounts. That coupled with the lack
of negative impact to the surrounding
neighborhoods means that, despite the
numerous challenges encountered during
tunnel construction, this has been a highly
successful project so far for WSSC.
RSS JV approached this project like others in
the past and worked with the project team to
maintain open communication. When
problems came up, RSS JV took a proactive
approach to move forward instead of waiting
sometimes for decisions to go through the
usual channels, which can result in delays and
additional costs to the project. Sometimes risks
were taken and RSS was not always sure if it
would recover those risks financially, but the JV
moved forward with good faith, working
with its partners in coming to meet the various
challenges. This cooperation between partners
has kept this project fluid.
Project completion is currently anticipated in
Spring 2014 with tunneling due for
completion at the end of April 2013.
Booth 610
www.cruxsub.com/RETC
cdmsmith.com
Offices worldwide
GRAND
CENTRAL
LEGACY
BELOW NEW YORKS iconic Grand
Central Terminal the backdrop for many
a film scene two different, but equally
impressive, underground spaces have
been created. While commuters and
visitors have continued unhindered on
their journeys at ground level, contractor
New Yorks East Side Access project will provide Dragados-Judlau JV, working for the
Metropolitan Transportation Authoritys
the citys first new major railway terminal in over Capital Construction Company (MTACC)
has been carving out two vast caverns,
a hundred years. As the huge platform caverns each around 52ft (16m) wide, by 61ft
carved from the rock beneath the citys iconic (19m) high, and 1,200ft (370m) long.
The caverns are important elements of
Grand Central Terminal near completion, NATJs the complex megaproject that is East
Side Access, now with an estimated price
Kristina Smith looks at the story of their creation tag of $8.24 billion. Designed by a tri-
NEW YORK
NEW YORK
IND Subway
(E, V lines)
Construction Management team. But the answer came back Existing IND
the same each time: ground freezing an arch above the crown 20
Subway invert
of the oval-shaped tunnel was the only feasible option.
Lowering the groundwater through dewatering wasnt
Ground
possible due to the polluted water bodies in the area that cant freezing arch
be disturbed. Vertical drilling from the surface or from the 3
Drift
subway structure also wasnt logistically possible. Final liner 1 2 Temporary
Drift Drift shotcrete
This is an unusual application for ground freezing: You 6
55
wouldnt normally horizontally freeze a partial arch, drilling 4 Drift 5
Drift Drift Top of rock
125ft-long holes in that kind of ground, says Thompson.
Schiavone-Kiewit started on the back foot. The large open-
cut slurry wall box from which Granite/Traylor/Frontier
Kemper (GTF) JV would launch its Herrenknecht Slurry shields
80
eastwards under the rail yard (see NATJ, April/May 2012), and
[Continued from p21] Dragados-Judlaus which also won the contract to construct four The only evidence of what lies beneath are
contract has suffered from delays. However, hard rock TBM running tunnels (totaling the construction sites for the four ventilation
construction of the caverns can be counted as 25,100ft (7.65km) in length) through buildings, shoehorned into very compact sites.
a success for Manhattans commuters and Manhattan Schist, had to bring everything in City residents have only been troubled by the
visitors, who have suffered no disruption to and out from Queens via the existing 63rd trucks servicing these areas. However, even
Grand Central Terminal or its trains. The last of Street East River immersed tube tunnel. these limited disruptions have been noted.
the 2,500 structural blasts required to create The problem with East Side Access is that We drilled holes into the tunnels and
the caverns was carried out in early March, all the tunneling work has been mobilized out caverns and fed concrete in from the surface
with construction methods reducing the of Queens, so you have an extremely long though pipes, which has proven to be a
number of planned blasts by more than half. supply line, says Andy Thompson of Hatch challenge, says Thompson. We have to
The cloistered nature of the caverns Mott MacDonald, Senior Program Manager coordinate with the DoT for street closures.
construction is one of the factors that has for MTACCs Construction Management And building owners are not very happy when
made underground construction on this side team. There are no reception or drive shafts a concrete truck is parked outside their
of the river so challenging. Dragados-Judlau, in Manhattan. building for three years.
ever?
PHOTO COURTESY OF MORETRENCH
Dewatering &
Groundwater Control
Ground Freezing
Deep Foundations
Underpinning Systems
Grouting &
Ground Improvement
Environmental Remediation
www.moretrench.com
Geotechnical Construction Coast to Coast 800-394-MORE
NATJ_0513_EASTSIDE_020_027.qxd:Feature 21/4/13 23:32 Page 25
NEW YORK
Figure 1: Map showing the alignment New Yorks East Side Access project
AK
Blvd
29th Ave
Clockwise from top: Supply trains travel in
TR
hern
Metro-North
Nort
AM
Railroad
N
from Queens to support excavation; One LIRR
Central Port gton
of the running tunnel wyes; Inspection of Park hin
Wasranch
. .) B
the Schist; View into one of the caverns
8,600ft 0ft ft
(17,200 Linear Ft.) 5,50 inear Yard
(11,200 L id
e
63rd Street Tunnel ys
63rd St nn
41st Ave Su
checks required for blasting, each blast took Blvd
g
ens
in
Que
ck
(31,300 Linear Ft.)
rlo
Mid-Day
In
lt Island
Storage Yard
ol
ar
H
vd
QUEENS
Bl
53rd St
rn
e
rth
50th St
& Shop Facility
ss way
That meant we tried to do the excavation in MANHATTAN Long
Island
Expre
Grand
other ways, said Thompson. Central
495
495
42nd St Terminal LIR
Dragados-Judlaus solution was to employ Queens-
Midto R
Tunnel wn Mo
Sandvik roadheaders. Though Manhattan 38th St n ta
uk Branch
Penn
Schist is relatively hard, at 14,000psi (97MPa) Station
Lexington Ave
East
Madison Ave
2nd Ave
3rd Ave
8th Ave
7th Ave
6th Ave
5th Ave
NEW YORK
JV put in the permanent concrete arch. This planned to be precast elements. There were the open-cut advance works contract (see
made sense from a safety perspective, and two reasons for this choice: To achieve a box), the Queens tunnels have been a major
reassured Metro North that Grand Central, uniform, high-quality finish and to minimize success for the project, says Thompson.
35ft (10.5m) above, would remain secure. future maintenance. Though short, the four soft ground tunnels,
It was more practical approach, says MTA first put the lining contract, CM12, totaling 10,500ft (3,200m) in length, were
Thompson. These caverns are 60ft (18m) out to tender before its re-negotiations with excavated through mixed face conditions that
high. Think of building formwork 60ft in the Dragados-Judlau, but pulled it back until the included boulders, manmade obstacles, a high
air, thats a major task. This way, we were deal was complete. When the contract was water table, low overburden, and the nation's
doing it from 30ft (9m). It also meant that re-tendered, there were four bids, all of which busiest railroad interlocking overhead.
top heading construction could take place were far higher than MTAs estimates had Control of ground movement was so good,
whilst the lower TBM drives were underway. suggested. Right now we are evaluating our however, that GTF elected to drive one of its
Using roadheaders also reduced the volume packaging options to ensure that we maintain two 22.5ft (6.8m) diameter Mixshield
of primary liner concrete required. Using this our schedule and budget, says Thompson. machines above the watertable almost to the
method meant we got a better profile, with Likely to be split, the new lining packages surface, rather than use the originally
less overbreak and initial support, which will be out to tender soon, says Thompson. intended open-cut TBM recovery method.
meant less backfill concrete, says Thompson. The caverns will remain a hybrid between in- We drove four tunnels underneath the
Once the arches were in place, the contractor situ and precast concrete, with some of the railroad interlocking and caused no settlement
dropped the benches into the tunnels below. less conspicuous locations that had initially and no disruption to the railroad, says
been designed with precast liners, changed to Thompson. We actually brought one of the
End in sight in-situ. It is important that the caverns look drives to within 6ft (1.8m) of the surface, until
By June this year, all excavation work will be good. Together with the 350,000ft2 we couldnt mine any further.
complete. At the time of writing, Dragados- underground concourse a contract which The decision to mine so close to the surface
Judlau still had some minor blasts to carry out, will be let next year these structures convey was taken to minimize disruption and co-
to perfect the profile, and had to finish the the spirit of New Yorks newest terminal. ordination issues for the railroad. The Harold
escalator pits in the floors of the caverns. With Grand Central and Penn, the only Interlocking is the USs busiest interlocking
Though the two caverns will be by far the major stations currently in operation, this will carrying over 800 trains a day. But there was
most impressive of the contractors be New Yorks first new terminal in over 100 so little movement that a switch that was
excavations, they are just part of the story for years. One of the mandates we were given taken out of service for three weeks while a
the Manhattan work. All in all, there have was that this was to be a new gateway to TBM tunnelled below it was put immediately
been 63 separate work headings. The sheer New York, says Thompson. The architects back into service without requiring
size of the works is in itself demanding. want it to look impressive. They are aiming to adjustment. The slurry machines were really
At one time they had almost 1,000 people echo and compliment the various elements of controllable, says Thompson. We had half
working on the job over three shifts, says Grand Central Terminals design. an inch of heave and between quarter- and
Thompson. Thats a lot of people to half-an inch of settlement, which is well
manage. Early reports on the progress of Meanwhile, on the East side... within the railroads operational parameters.
Dragados-Judlaus contracts highlighted that While Dragados-Judlau has battled with the When the travelling public starts to use the
the contractor was unfamiliar with the logistical challenges in Manhattan, tunneling new line in 2019, pushed back from an
practices of New Yorks highly unionized contractors on the Queens side have had their original opening date of this year, they will
workforce. The contractor did fall behind, and own battles to fight. Granite/Traylor/Frontier know nothing of the triumphs of the slurry
this resulted in MTA re-negotiating Dragados- Kemper (GTF) JV has successfully completed drives or the technical engineering feats that
Judlaus package of work, in January 2011, to its CQ031 soft ground tunnels contract, using enabled tunneling under the Northern
remove much of the lining works, while slurry machines for the first time in New York Boulevard. They will, however, at least be able
playing to its strengths by ensuring that all and only the fifth time in the US (see NATJ, to admire the new caverns, which will
excavation works were in its package. April/May 2012, p11). Though the contract ultimately become the centerpiece of this
Around half of the caverns final lining is finished five months late, due to issues with much-anticipated extension of the LIRR.
A comprehensive exhibit is held in conjunction with the conference. The exhibit features the industrys
most innovative and experienced producers and suppliers. RETC provides a rare opportunity to meet key
professionals from around the world.
The meeting will also feature field trips, short courses and specialty speakers. The program will cover:
Contracting Practices and Cost Grouting and Ground Modification East Coast Projects
Design and Planning Hard Rock TBMs SEM/NATM
Difficult Ground Large Span Tunnels and Caverns Shafts and Mining
Drill and Blast Microtunneling and Trenchless Tunneling Tunnel Rehabilitation
Environment, Health, and Safety New and Innovative Technologies Water and Gas Control
Future Projects Pressure Face TBM Case Histories International Projects
Geotechnical Considerations Pressure Face TBM Technology Tunneling for Sustainability
Ground Support and Final Lining Risk Management
COMPANY PROFILE
and even the current development of new Clockwise from far left: Holey was the first of four 6.13m (20.1ft) diameter Cat EPBMs to
underground drilling jumbos. Its part of the finish work on Torontos Spadina (TYSSE) Subway extension; Views of the exterior and
wider corporate strategy, to determine how interior of the Manufacturing & Logistics Center; The Cat Tunneling team in the main facility
these equipment portfolios interact and what
resources we can leverage in the future to having a clean shop floor. Most of these
expand our product ranges. explains Natale things are logical, but when theyre put
together they provide a more productive
Manufacturing and logistics facility and a better working environment.
One of the first actions taken by Caterpillar, Caterpillar again expanded its facilities in
back in 2009, was the rental of a new 2011, with the fabrication of a new 15,000ft2
180,000ft2 building about 2.5-miles (4kms) dedicated re-manufacturing facility beside its
from the existing manufacturing plant at main Carlingview plant. This is being used to
Carlingview Drive, near Pearson International refurbish utility sized TBMs up to 5m (16ft) in
Airport, in Toronto. Caterpillar spent millions diameter from minor repairs to complete
of dollars outfitting this Manufacturing & overhauls and upgrades once more freeing
Logistic Centre (MLC) to handle all its light up further space on the main shop floor.
manufacturing operations, warehousing of One of the problems we have is when a
spare parts and equipment, and relocated machine comes back for refurbishment from a
office space. This instantly improved logistics jobsite. We open up the container and can
and freed up a large amount of space on the find contaminated soil and other unwanted
main shop floor to enable expansion. pests, which can be an issue, especially with
Many of the improved logistics here are the Ministry of Environment, says Walter
the result of processes that are pretty standard Trisi, Caterpillars North American Area Sales
at Caterpillar, says Natale. We have the Manager. Now we can lift machines straight
Caterpillar Production System, similar to the off the truck with a new crane that extends
Toyota Way, that looks at how material flows outside the building, and lower them straight
throughout each facility. This includes where into the big wash bay, where the run-off is
everything is placed, how each technicians collected. The same crane then transports the
workstation is set up, even simple things like TBM into the building for refurbishment.
COMPANY PROFILE
REFERENCES
cutting edge
November 3-5, 2013
The Westin Seattle,
Seattle, Washington
E ON MEGAPROJECTS
C
2013 CONFEREN
ly successful
Following the high
on Pressurized
2012 Conference
in Miami, North
TBM Tunneling,
eling Journal an
d
American Tunn d
are again please
the UCA of SME
y conference
to present a timel s.
ern megaproject
focused on mod
will again feature
The conference
tions from
critical presenta
rts, panel
international expe
open mic
discussions, and
ith a tailored
sessions along w
ique opportunity
exhibit and the un
Alaskan Way
to visit the SR-99
oject.
Bored Tunnel Pr
ar today!
Mark your calend
t will be
ts from this even
10% of the profi Stud ent
A of SMEs
donated to the UC
Scholarship Fund
ence,
m ore in fo rm at io n about the conferplease contact:
For rship opportunitie
s,
exhibit or sponso Steve Caming
7 1187
Tel: + 1 (603) 44 elingjournal.com
Amanda Foley nn
7577 Email: steve@tu
Tel: +1 (603) 452 nnelingjournal.com
tu
Email: amanda@
journal.com
www.tunnelling
rg
www.smenet.o
NATJ_0513_COXWELL_034_039.qxd:Feature 21/4/13 17:39 Page 34
TORONTO
Meeting the
challenges of
COXWELL
A construction crew inspects the damaged section of the Coxwell Trunk Sewer, following
ON A COLD NIGHT THIS FEBRUARY, as completion of the Bypass last month. This will soon be backfilled and then abandoned
residents to the north of Torontos city center
slept, the final stages of the Coxwell Sewer
Emergency Bypass were completed. Weeks of the existing sewer at either end (Figure 1). Tunnel depths were up to 45m (150ft) and
preparation, and endless planning, culminated A previous article on the Coxwell tunnel, compressed air was utilised as support.
in a single night of strategic activity. published in the October/November 2010 More recently, due to the citys current
Installing a Bypass into a live sewer is never edition of NATJ, primarily focussed on the population expansion and the critical nature of
easy, but when the sewer is one of Torontos shafts and tunnels for this project. This article this particular trunk, it has become necessary
main trunk sewers (servicing approximately serves as an update on project and describes to twin the system to provide increased
750,000 residents); has flows in excess of 6m3 the final connections at each of the shafts. capacity and options for maintenance. As part
per second; and with no contingency plan, the environmental assessment for this future
other than diverting the entire sewer into the Project background expansion work, video inspections discovered
Don River; the task became the critical activity In the late 1950s, to facilitate the expansion of a damaged section within the Coxwell Trunk
in this small, but challenging, project. the city of Toronto a 2.6m (8.5ft) i.d. trunk Sewer. With the damaged section in such
A simple outline of the Coxwell Bypass sewer was installed connecting northern close proximity to residential properties, it was
Tunnel project would be the sinking of two sections of the city to the treatment works by of obvious concern to the City of Toronto,
shafts either side of a damaged section of the lake. At that time, this was a tricky particularly in terms of potential sewer failure,
existing sewer, driving a tunnel around this undertaking, with excavation undertaken by blockage, and ground subsidence.
damaged section, and live connections into hand through water-bearing alluvial materials. The City of Toronto therefore considered it
prudent to affect a repair to this section as
quickly as possible. With the system running
Figure 1: Map of the Coxwell Trunk Sewer Bypass
close to capacity, it was not possible to enter
Taylor Creek Park the sewer and effect repairs in a reliable and
Ea ewe
r line
reek sewe
s
Massey c
st r l
OConn
xw
ay
Blv
d
e.
TORONTO
External
telescopic
pipe
New Tunnel
by TBM
Lips with
anchor
bolts
had to meet the hydraulic performance of the property and 6m (20ft) of an arterial road.
existing section of sewer, which only has The 500m (1640ft) long section of new
300mm (12in) of fall over its length. Therefore bypass tunnel running around the damaged
the new 500m (1640ft) long tunnel bends section of sewer was driven in full EPB mode. Inflatable
around the damaged section in a sweeping On completion of the tunnelling, excavations Centralized seal
curve, and consequently results in a longer were carried out around the existing sewer at teeth
Internal
tunnel section. This alignment required the each shaft ready for the connections. telescopic pipe
tunnel to negotiate a 150m (490ft) radius While progress went very well on the entry
curve. To achieve this it was necessary to shaft and the tunnel, production was delayed
modify the existing segment moulds to on the exit shaft due to some complex ground
increase the taper from 20mm (0.8in) to conditions around the existing sewer. A
40mm (1.6in). The use of an articulating tail systematic program of jet grouting, sodium
can was also required to negotiate the curve. silicate grouting, dewatering and cementitious
grouting was ultimately required to fully seal
Shaft and tunnel construction around the sewer and allow the excavation to
Work on the Emergency Bypass commenced be completed.
in March 2010. Two shafts were constructed The entry shaft flume was installed in
over the existing live sewer. The upstream October 2011 with the exit flume following
shaft (or entry shaft) was a 10m x 17m (33ft x one year later in October of 2012.
55ft) interlocking secant pile shaft
approximately 8m (26ft) deep (see Figure 2). Temporary flumes
The downstream shaft (exit shaft) consisted of As discussed, the bypass connects directly into
a 10m (33ft) diameter, 45m (150ft) deep, the existing live Coxwell Trunk Sewer, which
octagonal slurry wall shaft. The deeper shaft (under wet weather flow) can surcharge to
was complicated by its location. Situated on a 3m (10ft) above the tunnel. Therefore, Above: The temporary flume in place within
postage stamp size compound, the shaft specially fabricated hydraulic flume pipes were the entry shaft
walls were within 3m (10ft) of a residential designed to bridge the sewer through the Top left: The completed bypass tunnel
TORONTO
The final connection minimum flows in the sewer and on the removed the sewage entered the new
The final permanent connection involved the evening of February 19, 2013, the connection bypass at the downstream end but also
removal of the temporary flumes and the work commenced. The sequence of the sewer continued to flow down its original
installation of permanent elbows. Consisting connection was as follows: course.
of mortar lined steel pipe the elbows were
1 2
fabricated ahead of time (before the shafts Starting work at around 11pm (after The crew relocated to the entry shaft
were excavated). Consequently concrete was the flows within the sewer dipped and repeated the process removing the
required in the shafts once the temporary below spring line), the downstream upstream temporary flume. Again this
flumes were installed to match the shaft temporary hydraulic flume was went smoothly with the flume
concrete to the elbows. removed (with the flumes being removed by 1am. Despite the flows
After the concrete was cast in each shaft, hydraulically actuated this was possible being at thier lowest levels, a
split flanges were fabricated and the lower without men present at the base of the considerable amount of flow was
half of each flange was bolted to the shaft). This operation went very witnessed through the shaft. This
respective concrete wall. This flange would smoothly and within 40 minutes the resulted in sewage flowing through
provide the fit for the elbows during flume was on the surface. Once both tunnels.
installation. Once the elbows were lowered
into position, the upper flanges could be
bolted in place to finally secure the elbow.
The procedure for removing the flume was
the focus of much debate. Several methods
were looked into for diverting or reducing the
flows to allow for the permanent flume
installation. Unfortunately due to high flows,
access restrictions, and surcharge limits, the
only viable option was to carry out all the
work under live flow.
Night time work was selected to ensure
TORONTO
4
At 4.45am the final connection was visibility within the shaft dropped to
completed with installation of the minimal. With the second elbow in
elbow at the exit shaft. By 6am the place the flow was successfully diverted
upper flanges were also in place. through the new bypass.
Complicating the process at the exit
5
shaft was the temperature with an air The following day the sewage within
Retracting the temporary flume temperature of around -14C (6.8F) as each shaft was pumped out. A new
soon as the flume was removed access was created at each connection
to allow for this and also to permit
entry for future inspections.
6
The final stage will be to mass fill
around each elbow with concrete to
seal the pipes in place. At the time of
writing this article, work was ongoing
and the site is expected to be cleared
and fully restored by early summer.
Summary
The Coxwell Emergency Bypass was a very
challenging job, but not necessarily due to the
usual issues encountered on a tunnelling
project. The live flow connections were a
huge success and much credit must go to all
those involved from the concept stage,
Removal of the flume in the entry shaft through planning and design and down to
execution.
3
At 1.45am lowering of the permanent
elbow at the entry shaft commenced.
Prior balancing at the surface ensured
the elbow remained level. Once in place
all the flow was diverted into the new
bypass. Once in place all the flow was
now diverted into the new bypass and
the upper sections of the retaining ring
were bolted on before the crew moved
back to the exit shaft.
Lowering the entry shaft elbow The elbow in place within the exit shaft
ANTRAQUIP
Experienced, Innovative & Reliable
758 Bowman Ave., Hagerstown, MD 21740, USA
ph: +1 301.665.1165 . info@antraquip.net
www.antraquip.net
#1 IN ROCK CUTTING
Arch Canopy and Barrel Vault System, Lattice Girders, Steel Ribs and Diamond Saw Attachments
o u t w hy we are so
d
C 2013! Fin P
We wil l be at RET
ED U
U M P
P OOTH #2108.
visit us in B
RETC PREVIEW
RETC PREPARES
FOR THE CAPITAL
RETC PREVIEW
EXH
1200 1202 1204 1206 1210 1212 1214 1216 1220 1222 901 903 905 907
NO EXIT
IB
ITOR
1201 1203 1205 1207 1211 1213 1215 1217 1221 1223 1225
SER
1300 1304 1310 1312 1314 1316 1320 1322 1324 LOUNGE
VICE
CEN
TRE
808 810
703 709 711
NO EXIT
SALES
1800 1802 1804 1806 1808
403 415 417
409 411
&
1801 1803 1807
OPS EX
408 410
1900 1902 1904 1906 2309
1414
HIBIT
303 315
309 311
1412 2307
1901 1903 1905 1907 1909
2103
1400
RETC PREVIEW
RETC PREVIEW
Beyond Tunnels
Antraquip Corp
Antraquip is a designer, manufacturer
and supplier of roadheaders, hydraulic
rock grinders, shaft sinkers, special
tracked machines with a variety of
boom options, and tunnel support
systems. Antraquip roadheaders and
rock grinders are being used all over
the world in a variety of civil
engineering and mining projects.
Our expertise goes beyond tunnels. Antraquip offers not only standard
roadheaders in the 12 80 ton
weight class, but is extremely flexible
We also deliver cut-and-cover and sequentially excavated in offering project-oriented
structures, caverns, portals, slopes, and embankments. engineering solutions. The firm also
Anytime youre faced with underground risk, Jacobs Associates supplies lattice girders, steel sets and
arch roof canopy systems for projects
is your partner for design, construction management, and throughout North America. The ability
dispute resolution. to provide a wide range of tunneling
equipment and services makes
Antraquip not only a leading
manufacturer but also an experienced
partner to utilize for any tunneling
JACOBS SF.COM and mining project. Visit Antraquip at
RETC Show Booth 1707.
RETC PREVIEW
Tunnel
Trenchless
Geotechnical
Contact:
AJ McGinn 315.434.8885
Alan Howard 925.247.9000
Gregg Sherry 303.703.1405
RETC PREVIEW
Brookville Equipment
Corporation
Rail support equipment specialist Brookville
Equipment Corporation will be showcasing its latest
innovations in high-height diesel and battery
locomotives and personnel carriers at RETC 2013.
These customizable personnel carriers provide
comfortable cushioned seating for four to 20 workers
Caterpillar Tunneling
and the option to also function as an eight to 25 ton Caterpillar Tunneling custom designs and manufactures tunnel boring
locomotive. With 95 years of experience machines (TBMs) and other support equipment to the unique needs of
manufacturing customized rail-mounted powered the most extreme global tunneling challenges. CAT soft/mixed ground
transportation solutions, Brookvilles tunneling and rock TBMs are widely used today across various industry
portfolio includes four to 45 ton battery or diesel- segments: metro, rail, transportation, hydropower, sewer, cable and
powered locomotives featuring heavy duty frames, pipelines. The firm will custom tailor a solution to ensure a projects
planetary drive axles, liquid-cooled wet disc brakes, success. CATs customers also enjoy product support from launch to
optional explosion proofing for improved safety and breakthrough and products that are built to be rebuilt.
climate controlled cabs for optimum operator comfort. RETC booth Number 703
These tunneling units have been used on some of the
industrys most notable projects, include the Traylor
Brothers East Side Access Project in New York City and
the Stillwater Mine in Nye, Montana. Datwyler Sealing
RETC booth 2008
Technologies
Datwyler, Division Sealing Technologies, is the world
CDM Smith leading provider of tunneling gaskets. With the newly
acquired Phoenix PDT Profiles business, Datwyler
CDM Smith is a consulting, features currently successful references in more than 450
engineering, construction and tunnels on all five continents. The company offers many
operations firm with an underground construction team that gasket profiles and material options, all designed and
includes geotechnical, structural, and civil engineers and geologists. offered on a project specific basis, to meet any
The firms tunnel-related work includes planning, feasibility and hydrostatic and/or environmental conditions that may be
design, including both 2D and 3D FEM analyses. The firm offers encountered. Datwyler now manufactures five types of
construction services including construction and program gaskets to meet a wide range of tunnel applications:
management, inspection and geotechnical instrumentation mono EPDM, hydrophilic, Co-ex Swell and Composite
monitoring and interpretation for soft ground and rock tunnels. Black Swell and the new anchored gasket. The anchored
Design and construction services cover all types of ground gasket as the new generation for segmental tunneling
modifications including ground freezing, grouting, and dewatering. gasket is now being used in the first USA tunnel projects.
CDM Smiths field equipment includes geotechnical RETC booth 306
instrumentation and construction data acquisition equipment.
RETC booth 702
Crux Subsurface
Geotechnical construction and exploration specialist Crux
subsurface has provided solutions to some of the most difficult-
access, geologically-challenging and environmentally-sensitive
David R. Klug &
projects in the United States. Specialties include long-range Associates
deviation-controlled horizontal core holes, borehole surveying, David R. Klug & Associates provides international and
optical and acoustical televiewer services, high-quality national manufacturer representative services to the
sampling, and instrument underground heavy civil and mine construction
installation. Pre- industries. The company specializes in the
excavation stabilization coordination of products, equipment and services
services include for NATM, soft ground, precast segmental and
dewatering, permeation conventional tunnel construction. This includes
and compaction initial support systems, GFRP bolts and soft-eye
grouting, tube arch structures, flexible membrane waterproofing
canopies, and cased systems, prefabricated final lining reinforcement
horizontal boreholes. The products, steel moulds, connectors and gasket
firm provides design sealing systems for one pass precast tunnel
build services and a fleet linings, tunnel profiling / scanning equipment
of custom-designed and associated site services, design and supply of
equipment to ensure that project specific material handling systems, and
project needs are met. complex final lining forming systems.
Booth 610 Booth 300
RETC PREVIEW
RETC PREVIEW
Itasca
Itasca is dedicated to providing its clients better insight into the
Herrenknecht around by 180 degrees and
is now excavating the
behavior of the engineered earth environments where they
operate. To do so, it maintains a staff of leading engineers in the
Tunnelling second section to final fields of rock mechanics, hydrology, hydrogeology, geochemistry,
breakthrough. mining engineering, petroleum engineering, geophysics, and
Systems USA Herrenknecht delivers software engineering. The state-of-the-art numerical modeling
Construction companies cutting-edge tunnel boring codes that Itasca uses and sells for solving problems in
have successfully excavated machines for all ground geomechanics and hydrology are among the most widely used,
around 2,300 kilometers of conditions and all widely respected tools of their kind. Operating as both
traffic tunnel with diameters diameters. Together with consultants and software developers creates dynamic interplay:
of more than 4.2 meters the Groups innovative the technical capabilities of the consultancy are extended via
using Herrenknecht specialists, Herrenknecht is direct access to the internals of the software tools it uses. In
technology. able to offer integrated turn, the software is continuously developed, improved, and
In Miami, a Herrenknecht solutions around tunnel proven in the real-world problem-solving environment of the
EPB Shield recently construction at all times. consulting practice. Visit Itasca at RETC booth number 515.
successfully finished one With 77 international
tunnel of the twin-tubed companies the
Port of Miami Tunnel. The
machine concept with
Herrenknecht Group
provides a comprehensive
Jacobs Associates
slurryfier box mastered the range of additional Consulting engineers Jacobs construction management
water-bearing geology with equipment and services Associates provides solutions for capabilities. It also offers the
bravura in only 9 months. close to the project site difficult underground projects broader heavy civil construction
After the first breakthrough, and the customer. industry a robust
the EPB Shield was turned RETC booth 403 package of claims
and dispute
resolution services.
Jacobs Associates is
HNTB an award-winning
HNTB specialises in design and support services for tunnel firm with 13 offices
structures. The firms experts have the insight and in the United States,
knowledge to provide solutions on a wide range of tunnels, Australia, New
from small-diameter excavations to the largest machine- Zealand, and
bored tunnel in the world. Their work cuts across the Canada. Services
highways, transit, rail, aviation and water sectors. HNTB include: geological,
staffs experience includes tunnel design, tunnel boring geotechnical Services
machine construction, access shaft design, program and equipment;
management, project funding, cut and cover tunnels, civil, and excels in the water, tunnel boring equipment;
hydraulic and drainage design, construction, geotechnical wastewater, and transportation underground excavation services
reports and analysis, ATM and CIP and pre-cast segmental sectors. With an emphasis on and equipment; engineering
tunnel liners. tunnels and shafts, Jacobs offers design and services for tunnels.
RETC booth 2321 a full range of design and RETC booth 2309
Hughes Brothers
At RETC 2013 Hughes Brothers Inc will be
displaying various Fiber Reinforced Polymer
products that facilitate TBM launch and
reception chambers, removable FRP Soil Nails
and earth anchors, GFRP bars for face
stabilization in sequential excavation methods breakouts projects worldwide. Recently,
and GFRP rock bolts. The firms Aslan FRP bars extensive use was made of Aslan bars in the
are uniquely suited to the tunneling and mining diaphragm walls for the Seattle SR99 Alaska Way
industry as they are very high strength, Viaduct replacement tunnel. Aslan FRP materials
lightweight, and non-corroding but are easily are also used in situations where encroachment
consumed by mining equipment or tunnel or future use issues require consumable or
boring machines. The Aslan 100 GFRP rebar has removable anchors or methods.
been used in over 300 TBM launch and RETC booth 1905
RETC PREVIEW
Let
Le
JADCO Manufacturing Maccaferri
As part of a worldwide industrial group, Maccaferri has over 130
For more than 30 years years of experience and expertise that includes solutions in retaining
n
JADCO has been a global wall systems, reinforcement of steep slopes, embankments,
leader in solving the toughest drainage systems, rockfall protection, soil erosion protection,
wear, impact, and abrasion coastal protection, and solutions in mining. The firm offers a wide
challenges in the tunneling, range of solutions for use in tunneling projects range from Wirand
mining, steel, construction, steel fibers and FibroMac synthetic fibers for improving the
power generation, recycling, performance of
and other major industries. At concrete, to specialized
RETC the company will display tunneling products
its premier lines of including: self-drilling
CHROMEWELD Overlay Plate bolts and steel anchors,
y
that outlast virtually any material in high-abrasion fiberglass reinforcement
applications; and QT-Plus Wear Steels that provide bars, drainage tubes and
10X the wear life of conventional offerings. In ceramic final linings.
addition, the ISO 9001:2008-certified manufacturer Maccaferris team of
will exhibit its HARDGUARD wear blocks that defeat professionals is available to
the harshest, most abrasive operating conditions. offer specialized technical
RETC booth 1408 support, project analysis,
design, and product
selection.
RETC Booth 1900
J.H. Fletcher
& Co
J.H. Fletcher & Co has provided mobile underground mining
Malcolm Drilling Company
equipment to the industry for over 75 years. Fletcher was a Malcolm's list of core services in tunneling and
pioneer in the production of roof bolters, and design of the
automated temporary roof support system (ATRS) and
geotechnical construction includes drilled shafts,
excavation support systems, cutoff and secant pile walls, Narrow Fle
continues to provide a wide range of equipment that focuses jet grouting, deep soil mixing, cutter soil mixing and
on worker safety and productivity in underground mines. dewatering. These combined services have routinely is design
designed
Fletchers world-renowned roof bolters are accompanied by an been applied on numerous complex tunneling projects
entire product line including: scalers, powder loaders, and drill throughout North America. The firm says its large and bac
backed
jumbos. Fletcher also continues its legacy of custom-built equipment fleet and highly skilled personnel allows it to
equipment, with a Fletcher machine customers are assured a comply with the most rigorous schedule compression. mining eexper
machine built specific for their application and job. Malcolms experience facilitates a Design/Build approach
Fletcher will be represented at RETC this year, located in to projects and allows for timely collaboration with expanding
expand
booth 200. Visitors will be provided information regarding owners and contractors. The
the entire product line, and also have the ability to interact
with Fletcher powerpoints, videos and animations.
firm provides these services
nationwide through regional
custome
customer s
offices.
RETC Booth 1904
QGLQJ SDUWV
QGLQJ
Layne GEO more co conven
Layne GEO is one of six
divisions of global water
Customizatio
Customi
management,
construction and drilling
maintenanc
maintena anc
company Layne Christensen Company, which provides solutions
for water, mineral, and energy challenges. With Laynes ability to
components
compone
p ents
leverage resources, GEO is an important link in providing total
project solutions for our clients by offering an array of choice simps
underground construction expertise, and providing specialized
services within the fields of ground improvement, deep ORRN DW
DW WK
WKH
KH E
foundations, earth retention, and customized geotechnical
equipment design and fabrication. has to prov p
GEOs solutions are geared towards heavy civil, industrial and
commercial construction markets that are focused primarily on soil your de decis
ecis
stabilization and subterranean structural support during the
construction or rehabilitation of dams/levees, tunnels, shafts, water easy.. Rel
easy Reliab
liab
lines, subways, highways and marine facilities. Services offered
include jet grouting, diaphragm and slurry cutoff walls, cement the answer
answeer is
and chemical grouting, drilled piles, vibratory ground
improvement/stone columns and installation of ground anchors.
RETC Booth 1324 ZZZMKH
ZZZ
ZMMKH
M
J.H. Fletc
Fletcher
cher & Co. can
cannot
nnot antic
uct. Proper
per use
use, mainten
maintenance
nance an
50 NORTH AMERICAN TUNNELING JOURNAL
NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 51
Fletcher
er
Let
Le
n a r r ow
w
your mine
e
Narrow Fletcher J151-DE
a little.
is design
designed for a long life,
and backed
bac by 75 years of
mining experience.
e Fletchers
expanding world-wide
expand
custome
customer support, makes
QGLQJ SDUWV GLVWULEXWRUV
QGLQJ
more co convenient than ever.
Customization options, low
Customi J.H. Fletcher & Co
maintenance
maintena ance and prov
proven
ven P.O.
P.O
. . Bo
Box
x 218
2187
87
Huntington,, WV 25722
257222
components,
compone
p ents,, makes the Scan here
here to discover
disco
over our w
website
ebsitte
choice simple.
s Once youy
DW WK
ORRN DW WKH )OHWFKHU
KH EHQHWV )OHWF
FKHU
has to provide,
p narrowing
narrowwing
your de decision
ecision becomes
becom mes
easy.. Reliable
easy Relliable and dura
durable-
able-
answeer is always Fletc
the answer herr.
Fletcher.
ZZZMKHWFKHUFRP
ZZZ
ZMMKHWFKHU
M UFRP
FRP 304 525 7811
304.525.7811 VDOHV#MKHWFKHUFRP
VDOHV#MKHWF
# FKHUUFRP
FRP
J.H. Fletc
Fletcher
cher & Co. can
cannot
nnot anticipate every mine hazard
d that mmay
ay develop during use off these products
products.s. Follow your
our mine plan and/or roof control
con
ntrol plan
p prior
p to use of the prod-
prod-
uct. Proper
per use
use, mainten
maintenance
nance and continued use of (OEM)
(OE origi
original
nal equipment parts will be essential forr maximum operating results. 2013 J.H. FFletcher & Co. All rights reserved.
NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 52
Geotechnical,
Mineral Exploration
and Horizontal Coring
www.ruendrilling.com
SUBSCRIBE NOW!
To order, visit www.tunnellingjournal.com and click on Subscription Offer
52 NORTH AMERICAN TUNNELING JOURNAL
NATJ_0513_RETC_043_054.qxd:Feature 22/4/13 21:50 Page 53
RETC PREVIEW
Moretrench
Geotechnical contractor Moretrench
specializes in design/build and turnkey
solutions for challenging construction
requirements and subsurface conditions. Credited with
Parsons
developing the first practical wellpoint system in 1924, the
company has dewatered sites for subway and underground Since 1944, Parsons
station construction across the country. With the development of has worked on
other specialty geotechnical methods, Moretrench moved some of the largest,
beyond dewatering to also utilize ground freezing for deep most complex
shaft construction and connector tunnels, and various grouting tunneling and
methods, including jet, permeation, compaction and underground
compensation grouting, for other tunneling-related challenges construction projects
such as soil stabilization, in the United States
groundwater control and and around the world. The firms tunnel professionals have
rock consolidation. These completed more than 60 recent projects, with specific
services are available expertise in planning, design, construction (design-build
nationwide through full and alternative delivery), construction management,
service offices in New Jersey, program management, and the operation of water,
New York, Florida, wastewater, and transportation tunnels. Experienced with
Massachusetts, Pennsylvania, soft-ground, rock, and mixed-faced conditions, the firm says
and Washington D.C. it is committed to delivering rapid, safe, economical
RETC Booth 508 tunneling.
RETC Booth 1422
RETC PREVIEW
CONCEPT TO COMPLETION
AUTOMATED GROUT & SLURRY SYSTEMS
Featuring high shear colloidal mills
with new Mk IV mechanical seals
Fully Automated
Self Cleaning
Containerized Plants
Lo-Prole Plants
Foam & Admix Systems
www.teammixing.com
sales@teammixing.com
Ph: 1.604.556.7225
PROVEN
Offering new and used tunneling equipment
for more than 25 years.
##!#(*'
# " (#
##$(&!'
& )!#'
" #'(' MINING
( "'
EQUIPMENT
"( (#"
%)$!"(
#"
, +
, www.miningequipmentltd.com