MINNA
DEPARTMENT OF ARCHITECTURE
ASSIGNMENT ON
The mat is 3.7m thick, and was constructed in four separate pours totaling 12,500 cubic metres
(m) of concrete. Bauer Spezialtiefbau, with Middle East Foundations, took on much of the
piling work, which required bores to be sunk for cast in-situ piles, to a depth of 43 metres.
Bores for the 192 deep piles were sunk in . Each of them was designed to be cast in situ, and as
such needed to be very deep. Ground conditions at the Burj site were favourable the soft, but
not unstable, soil proved easy to dig into.
For the construction of the tower, a special concrete mix was pumped to a height of more than
600 metres (see Pumping) without segregating. This allowed for a shorter construction time
and gives the building a longer useful life, making it more sustainable. The highest reinforced
concrete corewalls were made using concrete pumped from ground level to a vertical height of
601 metres.
SLAB CONSTRUCTION.
The fastest method which was used to build high rise buildings was used(a process called JUMP
FORMING) . Using an hydraulic jump form system molds were built at the base, re-inforcement
bars were inserted then concrete was poured in. At the point of concrete setting, the moulds were
raised to the next level and on and on till the desired height was reached. Using this process 1
floor was built per week. It climbs up automatically 4metres. With the buttress core, glass
claddings were used to reflect the blazing heat.
Benefits
Self-climbing formwork cuts down the requirement for crane time considerably. By
allowing the crane to be used for other construction work this may reduce the total
number of cranes needed on site.
The formwork is independently supported, so the shear walls and core walls can be
completed ahead of the rest of the main building structure.