Safe Plan of Action

HSEP 2.16f1
Project No. 60034/35

Activity/Task: Washing, Chipping, Grinding, and Painting Works Work Area: GD Atlantis Date ________
2012

Steps of Activity/Task Hazard/Reaction to Change Safe Plan Resources


Preparation of equipment Electric Shock Access and egress going to SPA Briefing Provided
and materials needed to Finger and hand injury crane clear from any PPE: Safety harness, Safety
task Personnel fall from height obstacle and obstructed glass, Respiratory mask,
Washing of the deck crane materials Hardhat, Hand gloves,
Slips and trips
or boom Cable routing of power tools Safety shoes, Face shield
Damage to eye
Chipping of damage old and inspection for wear and and Coverall
Inhalation of dust and paint
paint tear
fumes
Grinding brush of area to be Materials and tools must be
Splashing of paints Emergency Contact
painted securely tight to prevent
Falling of materials Number: 0619189706
Painting works on the area from falling
of the deck or boom Mandatory wearing of PPE
which is suited for the task
Adequate supervision of the
supervisor during working at
height
Supervisor will instruct
personnel on the procedures
and precautions to be
followed when working at
heights