Sunteți pe pagina 1din 1

ID Task Task Name Duration Start Finish Predecessors Aug 28, '16 Sep 18, '16 Oct 9, '16

Predecessors Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17
Mode S S M T W T F S S M T W T F S S M T W T F
0 Industrial shed 125 days Sun 9/11/16 Fri 1/13/17 Industrial shed

125 days

1 Excavation 4 days Sun 9/11/16 Wed 9/14/16 Excavation

4 days
2 Excavation and 4 days Sun 9/11/16 Wed 9/14/16 Excavation and Dressing
Dressing 4 days

3 P.C.C Bed 9 days Thu 9/15/16 Fri 9/23/16 2 P.C.C Bed

9 days

4 Shuttering 3 days Thu 9/15/16 Sat 9/17/16 2 Shuttering


3 days

5 Laying and 3 days Sun 9/18/16 Tue 9/20/16 4 Laying and Compaction
Compaction 3 days

6 Curing 8 days Fri 9/16/16 Fri 9/23/16 4SS+1 day Curing


8 days

7 Concrete Footing 27 days Sat 9/24/16 Thu 10/20/16 6 Concrete Footing

27 days
8 Reinforcement and 8 days Sat 9/24/16 Sat 10/1/16 6 Reinforcement and Shutterng
Shutterng 8 days

9 Casting of footing 2 days Mon 9/26/16 Tue 9/27/16 8SS+2 days Casting of footing
2 days

10 Curing 22 days Tue 9/27/16 Tue 10/18/16 9SS+1 day Curing


22 days

11 Back Filling 2 days Wed 10/19/16 Thu 10/20/16 10 Back Filling


2 days

12 Cement Concrete 28 days Fri 10/21/16 Thu 11/17/16 11 Cement Concrete Flooring
Flooring
28 days
13 Shuttering 8 days Fri 10/21/16 Fri 10/28/16 11 Shuttering
8 days

14 Laying and Finishing 4 days Sun 10/23/16 Wed 10/26/16 13SS+2 days Laying and Finishing of cement concrete
of cement concrete 4 days

15 Curing 25 days Mon 10/24/16 Thu 11/17/16 14SS+1 day Curing


25 days

16 Column Erection 17 days Fri 11/18/16 Sun 12/4/16 15 Column Erection

17 days

17 Erection of hollow 6 days Fri 11/18/16 Wed 11/23/16 15 Erection of hollow Steel Columns and Fixing
Steel Columns and 6 days
Fixing

18 Coating 15 days Sun 11/20/16 Sun 12/4/16 17SS+2 days Coating


15 days

19 Truss Erection 12 days Wed 11/23/16 Sun 12/4/16 18SS+3 days Truss Erection

12 days
20 Truss Erection and 5 days Wed 11/23/16 Sun 11/27/16 18SS+3 days Truss Erection and Bolting and Welding
Bolting and Welding 5 days

21 Coating 10 days Fri 11/25/16 Sun 12/4/16 20SS+2 days Coating


10 days

22 Roofing 38 days Mon 12/5/16 Wed 1/11/17 21 Roofing

38 days
23 G.S Sheet 28 days Mon 12/5/16 Sun 1/1/17 21 G.S Sheet
28 days

24 Coating of bolts 10 days Mon 1/2/17 Wed 1/11/17 23 Coating of bolts


10 days

25 Cleaning and Finishing 2 days Thu 1/12/17 Fri 1/13/17 24 Cleaning and Finishing
2 days

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: Industrial shed
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1

S-ar putea să vă placă și