Predecessors Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17
Mode S S M T W T F S S M T W T F S S M T W T F
0 Industrial shed 125 days Sun 9/11/16 Fri 1/13/17 Industrial shed
125 days
4 days
2 Excavation and 4 days Sun 9/11/16 Wed 9/14/16 Excavation and Dressing
Dressing 4 days
9 days
5 Laying and 3 days Sun 9/18/16 Tue 9/20/16 4 Laying and Compaction
Compaction 3 days
27 days
8 Reinforcement and 8 days Sat 9/24/16 Sat 10/1/16 6 Reinforcement and Shutterng
Shutterng 8 days
9 Casting of footing 2 days Mon 9/26/16 Tue 9/27/16 8SS+2 days Casting of footing
2 days
12 Cement Concrete 28 days Fri 10/21/16 Thu 11/17/16 11 Cement Concrete Flooring
Flooring
28 days
13 Shuttering 8 days Fri 10/21/16 Fri 10/28/16 11 Shuttering
8 days
14 Laying and Finishing 4 days Sun 10/23/16 Wed 10/26/16 13SS+2 days Laying and Finishing of cement concrete
of cement concrete 4 days
17 days
17 Erection of hollow 6 days Fri 11/18/16 Wed 11/23/16 15 Erection of hollow Steel Columns and Fixing
Steel Columns and 6 days
Fixing
19 Truss Erection 12 days Wed 11/23/16 Sun 12/4/16 18SS+3 days Truss Erection
12 days
20 Truss Erection and 5 days Wed 11/23/16 Sun 11/27/16 18SS+3 days Truss Erection and Bolting and Welding
Bolting and Welding 5 days
38 days
23 G.S Sheet 28 days Mon 12/5/16 Sun 1/1/17 21 G.S Sheet
28 days
25 Cleaning and Finishing 2 days Thu 1/12/17 Fri 1/13/17 24 Cleaning and Finishing
2 days
Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: Industrial shed
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress